Greening structure of garbage heap body side slope in household garbage landfill and construction method

By setting up an anti-seepage layer, a drainage layer, a root-blocking layer and a greening layer on the slope of the garbage dump in the landfill, the problems of thin soil, easy drought and infiltration of pollutants are solved, and the greening of the slope of the garbage dump is realized. and ecological restoration, ensuring that water and soil are not lost and plant growth is ensured.

CN118765729AInactive Publication Date: 2024-10-15BEIJING GENERAL MUNICIPAL ENG DESIGN & RES INST
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411134946.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The slopes of garbage piles in domestic waste landfills have thin soil and are prone to drought and pollutant infiltration, leading to environmental pollution and soil erosion. The existing anti-seepage layer cannot effectively solve the problems of soil erosion and plant growth.

Method used

Adopt a structure including an anti-seepage layer, a drainage layer, a root-blocking layer and a greening layer. The anti-seepage layer uses a bentonite waterproof blanket, the drainage layer consists of a quick-drainage cage and a geocomposite drainage net, and the root-blocking layer is made of polypropylene or polyethylene. Complete, the green layer includes ecological vegetation blankets and planting holes to ensure that water does not penetrate and promote plant growth.

Benefits of technology

It effectively prevents leachate from entering the upper soil, prevents plant roots from damaging the underlying structure, ensures plant survival rate and slope stability, and achieves greening and ecological restoration of the slope of the garbage dump.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118765729A_ABST
    Figure CN118765729A_ABST
Patent Text Reader

Abstract

The invention provides a greening structure of a garbage heap side slope in a household garbage landfill and a construction method. The greening structure of the garbage heap side slope in the household garbage landfill comprises the garbage heap side slope (1), an impermeable layer, a root blocking layer (2) and a soil layer (3). According to the greening structure of the garbage heap side slope in the household garbage landfill, leachate in the garbage heap can be effectively prevented from entering the upper soil layer, plant root systems in soil can be prevented from penetrating through the impermeable layer and the root blocking layer, the structure of the lower garbage heap side slope is damaged, and the stability of the side slope is affected; the root systems of the plants do not make contact with the structure of the lower-layer side slope, the survival rate of the plants is also guaranteed, the greening effect of the garbage heap side slope is further guaranteed, and ecological restoration of the garbage heap side slope is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of greening of domestic waste landfills, and specifically to a greening structure and construction method for a garbage pile slope in a domestic waste landfill. Background Art

[0002] A municipal solid waste landfill is a facility used to treat municipal solid waste. In a municipal solid waste landfill, solid waste is piled up and buried in layers to form a waste pile. Sanitary landfill is a common waste disposal method in municipal solid waste landfills, but it also poses environmental and health risks, such as environmental pollution and soil erosion.

[0003] In order to reduce the landfill area, improve landfill efficiency and ensure safe operation, slopes are usually set on the garbage pile. The slopes of the garbage pile have problems such as large area, thin soil, easy drought and infiltration of pollutants. At present, an impermeable layer is often set on the slope to prevent the liquid generated by the garbage pile from polluting the soil layer on the slope, so as to achieve greening of the garbage pile and prevent soil erosion. Secondly, the soil covering the impermeable layer will also gradually be lost due to rainwater.

[0004] Therefore, it is necessary to propose a greening structure for the slope of the garbage pile in a domestic garbage landfill that can avoid soil erosion and is suitable for plant growth. Summary of the invention

[0005] In view of this, the present application proposes a greening structure and construction method for the slope of a garbage pile in a domestic waste landfill.

[0006] According to the first aspect of the present application, a greening structure for a garbage pile slope in a domestic waste landfill is proposed, wherein the greening structure for a garbage pile slope in a domestic waste landfill comprises: a garbage pile slope, an anti-seepage layer, a root barrier layer and a soil layer.

[0007] Specifically, the greening structure of the garbage pile slope in the domestic waste landfill includes a drainage layer, and the drainage layer is arranged between the anti-seepage layer and the root barrier layer.

[0008] Specifically, the drainage layer includes a fast-drainage cage and a geocomposite drainage net, and the geocomposite drainage net is arranged below the fast-drainage cage.

[0009] Specifically, the greening structure of the garbage pile slope in the domestic waste landfill includes a greening layer, and the greening layer is arranged above the soil layer.

[0010] Specifically, the greening layer includes: an ecological vegetation blanket, planting holes and a vegetation layer.

[0011] Specifically, plain soil is disposed below the anti-seepage layer and the root-blocking layer, respectively, to prevent the anti-seepage layer and the root-blocking layer from sliding downward.

[0012] Specifically, the thickness of the bare soil below the anti-seepage layer is 200mm-300mm, and the thickness of the bare soil below the root barrier layer is 3mm-5mm.

[0013] Specifically, the material of the root barrier layer is polypropylene or polyethylene.

[0014] According to the second aspect of the present application, a construction method for a greening structure on the slope of a garbage pile in a domestic waste landfill is proposed, the construction method comprising: constructing an anti-seepage layer, a drainage layer, a root barrier layer, a soil layer and a greening layer in sequence from bottom to top on the slope of the garbage pile.

[0015] The greening structure of the garbage pile slope in the domestic waste landfill proposed in the present application can effectively prevent the leachate in the garbage pile from entering the upper soil layer, and can also prevent the plant roots in the soil from penetrating the anti-seepage layer and the root barrier layer, destroying the structure of the lower slope and affecting the stability of the slope. Secondly, the plant roots do not contact the structure of the lower garbage pile slope, which also ensures the survival rate of the plants, thereby ensuring the greening effect of the garbage pile slope, which is beneficial to the ecological restoration of the garbage pile slope.

[0016] Other features and advantages of the present application will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings constituting a part of the present application are used to provide a further understanding of the present application, and the schematic implementation modes and descriptions of the present application are used to explain the present application. In the accompanying drawings:

[0018] Figure 1 This is a schematic diagram of the greening structure of the slope of the garbage pile in the domestic waste landfill according to this application.

[0019] Explanation of the numbers in the attached drawings: 1-slope of garbage pile; 2-root barrier layer; 3-soil layer; 4-speed drainage cage; 5-geocomposite drainage net; 6-ecological vegetation blanket; 7-vegetation layer; 8-bentonite waterproof blanket; 9-overlapping position. DETAILED DESCRIPTION

[0020] The technical solution of the present application will be described in detail below with reference to the accompanying drawings and in combination with the implementation modes.

[0021] In order to ensure the ecological environment restoration of the garbage pile in the domestic waste landfill, it is necessary to green the slopes of the garbage pile. However, due to the problems of thin soil, easy drought and infiltration of pollutants on the slopes of the garbage pile, the greening and ecological environment restoration of the garbage pile is very difficult.

[0022] Based on the above problems, according to the first aspect of the present application, a greening structure for the slope of a garbage pile in a domestic waste landfill is proposed. The greening structure for the slope of a garbage pile in a domestic waste landfill may include: a garbage pile slope 1, an anti-seepage layer, a root barrier layer 2 and a soil layer 3.

[0023] The above-mentioned anti-seepage layer adopts 4000g / ㎡-5000g / ㎡ bentonite waterproof blanket 8. Bentonite has the characteristics of water absorption and expansion, and can form a low-permeability waterproof barrier, which can effectively block water penetration; secondly, it can protect plant roots from being polluted by leachate from the garbage dump; at the same time, the bentonite waterproof blanket 8 also has good durability and stability, can adapt to harsh environmental conditions, and can effectively prevent soil erosion on the slopes of the garbage dump.

[0024] The root barrier layer 2 can effectively prevent the plant roots from growing downwards, and can protect the anti-seepage layer from being damaged by the plant roots.

[0025] The above-mentioned soil layer 3 is arranged above the root barrier layer 2. In order to provide nutrients for the plants on the slope of the garbage dump, the soil used can be loose and free of construction and domestic garbage, large plant branches, gravel with a diameter of more than 3 cm and other debris. The physical and chemical properties are pH value of 5.5-7.5, organic matter content greater than 17.6g / kg, and salt value EC of 0.16-0.60ms / cm.

[0026] The greening structure of the garbage pile slope in the domestic waste landfill proposed in the present application, on the one hand, prevents the leachate from seeping out and causing pollution of the soil above the slope, and on the other hand, prevents the roots of plants planted in the upper soil layer 3 from growing downward, causing damage to the lower slope structure, and the plant roots from being contaminated by leachate, resulting in poor plant growth, thereby failing to achieve the purpose of ecological environment restoration.

[0027] In order to achieve rapid drainage of the garbage pile slope and maintain the stability of the garbage pile slope, specifically, the greening structure of the garbage pile slope in the domestic waste landfill may include a drainage layer, and the drainage layer may be arranged between the anti-seepage layer and the root barrier layer 2. The drainage layer can quickly drain the rainwater that has infiltrated the soil layer 3 and accumulated on the upper part of the anti-seepage layer, prevent the rainwater from accumulating in the soil layer and causing soil landslides, and ensure its integrity. The root barrier layer 2 is arranged above the drainage layer, which can prevent the plant roots from penetrating the drainage layer, thereby ensuring the structure of the drainage layer and avoiding the potential damage of the roots to the lower anti-seepage layer; it can also avoid plant root diseases caused by excessive water.

[0028] In order to ensure the drainage effect of the slope of the garbage dump, specifically, the drainage layer may include a quick-drain cage 4 and a geocomposite drainage net 5, and the geocomposite drainage net 5 is arranged below the quick-drain cage 4. The quick-drain cage 4 is a three-dimensional mesh structure with a thickness of 5cm-15cm, which can orderly discharge the rainwater that has penetrated through the soil cover layer or the sewage discharged from the yard itself without forming clogging. The geocomposite drainage net 5 is composed of a three-dimensional plastic net with a double-sided bonded geotextile, and has a thickness of 6.0mm. The quick-drain cage 4 has a large pore size and can quickly collect and guide water. The geocomposite drainage net 5 has high drainage and maintains the stability of the drainage channel. Combining the quick-drain cage 4 with the geocomposite drainage net 5 can effectively improve the drainage efficiency and structural stability of the drainage layer.

[0029] In order to realize the ecological restoration of the garbage pile, specifically, the greening structure of the garbage pile slope in the domestic waste landfill may include a greening layer, and the greening layer is arranged above the soil layer 3. Providing a greening layer on the garbage pile slope can restore the ecological environment of the slope and improve the surrounding environmental quality. Secondly, the plant roots penetrate deep into the soil layer 3, which can also prevent soil erosion on the garbage pile slope, maintain the stability of the garbage pile slope, and prevent the occurrence of landslides.

[0030] In order to further ensure the stability of the slope of the garbage dump and prevent the problem of soil erosion on the slope, specifically, the greening layer may include: an ecological vegetation blanket 6, planting holes and a vegetation layer 7. The above-mentioned ecological vegetation blanket 6 is a structure made of plant fiber material and containing shrub and grass seeds in the middle. Covering it on the soil layer 3 of the garbage dump slope can reduce the direct erosion of rainwater on the soil layer 3 and effectively prevent soil erosion. The shrub and grass seeds in the ecological vegetation blanket 6 can germinate and grow, which is conducive to the ecological restoration of the garbage dump slope. Secondly, the ecological vegetation blanket 6 can maintain soil moisture and reduce water evaporation; in order to further ensure the germination of shrub and grass seeds, covering soil needs to be laid on the top of the ecological vegetation blanket 6. The planting holes are formed by breaking holes in the ecological vegetation blanket 6, and shrubs can be planted in the planting holes; the ecological vegetation blanket 6 can provide preliminary vegetation restoration, and the shrubs can provide deeper vegetation coverage, which helps to form a more stable and diverse ecosystem. Combining the ecological vegetation blanket 6 with the planting holes can reduce the erosion of the garbage dump slope by rainwater and reduce the risk of soil erosion. On the other hand, shrubs can be planted to quickly form a vegetation layer. The plants in the ecological vegetation blanket 6 and the planting holes grow to form a vegetation layer 7 covering the garbage dump slope.

[0031] In order to ensure the greening effect, the planting holes are naturally distributed with a density of no less than 1 plant / m 2In order to ensure the success rate of planting, the planting holes can be set as PVC pipe planting holes with a diameter of 100mm for planting shrubs. Planting shrubs on the slope of the garbage dump can provide a higher density of coverage. The shrubs have a higher ability to adapt to the environment and grow faster, and can quickly form a vegetation layer 7 on the slope of the garbage dump.

[0032] In order to ensure the stability of the slope of the garbage dump, specifically, soil can be provided below the anti-seepage layer and the root barrier layer 2, respectively, to prevent the anti-seepage layer and the root barrier layer 2 from sliding downward. The thickness of the soil layer can be adjusted according to different geological conditions. In the present application, the thickness of the soil below the anti-seepage layer is 200mm-300mm, and the thickness of the soil below the root barrier layer 2 is 3mm-5mm.

[0033] In order to ensure the root barrier effect of the root barrier layer 2, specifically, the material of the root barrier layer 2 can be one of polypropylene or polyethylene, preferably a polyethylene root barrier board. The root barrier board made of polyethylene has good chemical corrosion resistance and root penetration resistance, and can maintain the continuity and sealing of the root barrier layer 2 for a long time. The root barrier board 2 can be in an appropriate form to effectively prevent plant roots from penetrating, and has a water permeable function.

[0034] According to the second aspect of the present application, a construction method for a greening structure of a garbage pile slope in a domestic waste landfill is proposed, the construction method comprising: constructing an anti-seepage layer, a drainage layer, a root barrier layer 2, a soil layer 3 and a greening layer in sequence from bottom to top on the garbage pile slope 1.

[0035] In order to ensure a better greening effect, the slope 1 of the garbage pile to be greened should be less than 1:3, the pH value of acidic pollutants should not be less than 2.5, and the pH value of alkaline pollutants should not be greater than 10.5. During construction, the slope of the garbage pile should be cleaned and leveled, and the slope of the garbage pile should be covered with plain soil, bentonite waterproof blanket 8, geocomposite drainage net 5, quick-drainage cage 4, plain soil, root barrier layer 2, soil layer 3 and ecological vegetation blanket 6 in sequence, and planting holes should be dug to plant shrubs. Adjacent bentonite waterproof blanket 8, geocomposite drainage net 5, quick-drainage cage 4 and ecological vegetation blanket 6 are all overlapped along the direction of water flow. Taking the ecological vegetation blanket 6 as an example, refer to Figure 1 The overlapping position 9, that is, the overlapping position of the ecological vegetation blanket 6 above the slope covers the upper part of the ecological vegetation blanket 6 below the slope, and the width of the overlapping position 9 is 30 cm.

[0036] In order to fix the greening structure of the slope of the garbage dump, the bentonite waterproof blanket 8, the geocomposite drainage net 5, the quick-drainage cage 4 and the ecological vegetation blanket 6 are fixed respectively. The fixing parts can be pins. The shape of the pins can be one or more of the U-shaped, T-shaped, I-shaped and other types, and the length is not less than 300mm, and the insertion depth of the pins is not less than 150mm.

[0037] The greening structure of the garbage pile slope in the domestic waste landfill proposed in the present application can effectively prevent the leachate in the garbage pile from entering the upper soil layer, and can also prevent the plant roots in the soil from penetrating the anti-seepage layer and the root barrier layer, destroying the structure of the garbage pile slope and affecting the stability of the slope. Secondly, the plant roots do not contact the structure of the lower slope, which also ensures the survival rate of the plants, thereby ensuring the greening effect of the garbage pile slope, which is beneficial to the ecological restoration of the garbage pile slope.

[0038] The preferred embodiments of the present application are described in detail above; however, the present application is not limited to the specific details in the above embodiments. Within the technical concept of the present application, a variety of simple modifications can be made to the technical solution of the present application, and these simple modifications all fall within the protection scope of the present application.

[0039] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, this application will not further describe various possible combinations.

[0040] In addition, the various implementation modes of the present application may be arbitrarily combined, and as long as they do not violate the concept of the present application, they should also be regarded as the contents disclosed by the present invention.

Claims

1. The greening structure of the garbage pile slope in the domestic garbage landfill is characterized by: The greening structure of the garbage pile slope in the domestic garbage landfill comprises: a garbage pile slope (1), an anti-seepage layer, a root barrier layer (2) and a soil layer (3).

2. The greening structure of the garbage pile slope in the domestic waste landfill according to claim 1 is characterized in that: The greening structure of the garbage pile slope in the domestic garbage landfill comprises a drainage layer, and the drainage layer is arranged between the anti-seepage layer and the root barrier layer (2).

3. The greening structure of the garbage pile slope in the domestic waste landfill according to claim 2 is characterized in that: The drainage layer comprises a fast-drainage cage (4) and a geocomposite drainage net (5), and the geocomposite drainage net (5) is arranged below the fast-drainage cage (4).

4. The greening structure for the slope of a garbage pile in a domestic waste landfill according to any one of claims 1 to 3, characterized in that: The greening structure of the garbage pile slope in the domestic garbage landfill comprises a greening layer, and the greening layer is arranged above the soil layer (3).

5. The greening structure of the garbage pile slope in the domestic waste landfill according to claim 4 is characterized in that: The greening layer comprises: an ecological vegetation blanket (6), planting holes and a vegetation layer (7).

6. The greening structure of the garbage pile in the domestic waste landfill according to claim 1 is characterized in that: Plain soil is provided below the anti-seepage layer and the root-blocking layer (2), respectively, to prevent the anti-seepage layer and the root-blocking layer (2) from sliding downward.

7. The greening structure of the garbage pile in the domestic waste landfill according to claim 6, characterized in that: The thickness of the plain soil below the anti-seepage layer is 200mm-300mm, and the thickness of the plain soil below the root barrier layer (2) is 3mm-5mm.

8. The greening structure of the garbage pile slope in the domestic waste landfill according to claim 1 is characterized in that: The material of the root barrier layer (2) is polypropylene or polyethylene.

9. A construction method for a greening structure on the side slope of a garbage dump in a domestic garbage landfill, characterized in that: The construction method comprises: constructing an anti-seepage layer, a drainage layer, a root barrier layer (2), a soil layer (3) and a greening layer in sequence from bottom to top on a garbage dump slope (1).

Citation Information

Patent Citations

  • Ecological restoration planting material for landfill closure and regreening method

    CN107691166A

  • Emergent flood discharge formula road landscape escape canal

    CN208309751U