Dike structure giving consideration to load shedding of existing river-crossing building

By setting up interval embankments and empty box structures on the river embankment, the vertical load of the buildings crossing the river is reduced, the contradiction between the heightening and thickening of the embankments and the structural safety of the buildings crossing the river is solved, and the compatibility between the heightening of the embankments and the normal operation of the buildings is achieved safety, ensuring structural safety and saving of engineering investment.

CN118774070APending Publication Date: 2024-10-15BEIJING INST OF WATER
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410901134.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

When the flood control standards of river embankments are improved, the vertical load on existing river-crossing buildings increases, threatening structural safety. Important river-crossing lifeline projects that cannot be demolished and reconstructed cannot meet the needs of embankment heightening and thickening.

Method used

Design an embankment structure that takes into account the load reduction of existing buildings crossing the river. By setting up a first embankment and a second embankment at intervals above the buildings crossing the river, and placing an empty box between the two, a cavity is formed to reduce the load. Vertically load-bearing, and backfill soil in the empty box to enhance structural stability and avoid demolition and reconstruction.

Benefits of technology

Effectively control the gravity of the embankment itself, ensure that the load of the buildings crossing the river is within the allowable range, ensure structural safety, achieve compatibility between the heightening and thickening of the embankment and the normal operation of the buildings crossing the river, save engineering investment, and reduce environmental impact.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774070A_ABST
    Figure CN118774070A_ABST
Patent Text Reader

Abstract

The invention relates to the field of hydraulic engineering embankments, and discloses an embankment structure giving consideration to load shedding of an existing river-crossing building, comprising: an embankment comprising a first embankment and a second embankment which are arranged above the existing river-crossing building and are arranged at the upstream and downstream of the river-crossing building at intervals along the direction parallel to the water flow, the spacing distance between the two is the width of the existing river-crossing building along the water flow direction; the empty box is arranged on the top face of the existing river-crossing building, the two sides of the empty box are sequentially connected with the first dike and the second dike correspondingly, a containing cavity is formed in the empty box, vertical bearing on the upper portion of the existing river-crossing building is reduced, the load on the upper portion of the existing river-crossing building is within the allowable range, the existing river-crossing building does not need to be dismantled, and the cost is reduced. The contradiction between dike construction and the running of the existing river-crossing building is eliminated, and the compatibility and practicability of engineering are improved; and soil can be backfilled in the accommodating cavity, so that the anti-floating stability of the empty box structure is enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water conservancy engineering embankments, and in particular to an embankment structure that takes into account the load reduction of existing river-crossing buildings. Background Art

[0002] Dikes refer to water-retaining structures built along rivers, lakes or coasts to resist flooding. The main functions of dikes are to restrain water flow, improve the flood discharge and drainage capacity of rivers; limit flooding, protect industrial and agricultural production on both sides of the river and the safety of people's lives and property; resist wind and waves and tides, and prevent storm surges from invading land.

[0003] At present, more and more urban infrastructure projects need to cross and span rivers or river embankments. It is common for new embankments to intersect with existing river-crossing structures such as water tunnels, water pipelines, and natural gas pipelines that cross rivers. In addition, the existing embankments have been built, and the crossing projects need to verify their own structural stability before construction to resist the vertical load of the existing embankments. However, when the existing river embankments are required to improve flood control standards and the embankments need to be raised and thickened, the embankments themselves will have too much gravity, which will in turn increase the vertical load on the river-crossing structures that cross the embankments within the embankment overburden range, exceeding the allowable load of the embankment structures, threatening the structural safety of the river embankments and river-crossing structures. Among them, in the case of raising the flood control standards of river embankments and raising the embankments, most of the methods are to demolish the original embankments and demolish and rebuild the existing river-crossing structures to achieve a structure that can withstand the vertical load of the new embankments. However, some important river-crossing lifeline projects cannot be stopped or demolished and rebuilt. Therefore, faced with the contradiction between the normal and continuous operation of existing river-crossing structures and the need to raise and thicken the embankments, it is necessary to propose a solution based on the actual situation of the river. Summary of the invention

[0004] The purpose of the present invention is to overcome the contradiction between the need for normal and continuous operation of some important river-crossing lifeline projects in the prior art (which cannot be dismantled and rebuilt) and the need for heightening and thickening of embankments, and to provide an embankment structure that takes into account the load reduction of existing river-crossing buildings. Under the premise that the embankment project needs to be heightened and thickened to meet flood control standards, its own gravity is controlled so that the pressure load of the embankment project on the existing river-crossing buildings is within the allowable range of the existing river-crossing buildings, thereby ensuring the structural safety of the river embankment and the existing river-crossing buildings, meeting project needs, and saving project investment.

[0005] In order to achieve the above-mentioned purpose, the present invention provides a dike structure that takes into account the load reduction of existing river-penetrating structures, including: a dike, the dike including a first dike and a second dike that are arranged above the existing river-penetrating structure and are arranged upstream and downstream of the river-penetrating structure at intervals from each other in a direction parallel to the water flow, and the interval distance between the first dike and the second dike is the width of the existing river-penetrating structure along the water flow direction; an empty box, the empty box is arranged on the top surface of the existing river-penetrating structure and is connected to the first dike and the second dike on both sides, and a accommodating cavity is formed inside the empty box.

[0006] In some embodiments, the empty box includes two side walls respectively connected to the side walls of the first dike and the second dike, a flood wall connected to the side walls and located on the water-facing side, a backwater wall connected between the side walls and located on the backwater side, and a top plate connected to the tops of the side walls, the flood wall and the backwater wall, and the flood wall, the backwater wall and the top plate are all connected to the first dike and the second dike.

[0007] In some embodiments, the top plate is provided with a plurality of grooves spaced apart from each other along the width direction of the dike, the grooves are filled with a concrete layer, and the concrete layer is flush with the top surfaces of the first dike and the second dike.

[0008] In some embodiments, a corbel is provided at the top of the side wall, and the top surface of the corbel is connected to the top plate and the strapping plate provided on the top surface of the embankment.

[0009] In some embodiments, the water-facing surface of the flood wall is stepped from top to bottom, and the slope of the backwater wall is the same as the slope of the first dike and the second dike.

[0010] In some embodiments, the empty box further includes a middle partition wall which is arranged between the two side walls and is parallel to each other, and a through hole is opened in the middle partition wall.

[0011] In some embodiments, the middle partition wall includes a continuous beam connected to the top plate, and the continuous beam is arranged above the through hole.

[0012] Wherein, in some embodiments, reinforcement protrusions are respectively provided on both sides of the continuous beam facing the side wall.

[0013] In some embodiments, it further includes a barbed wall connected to the outer side of the side wall and extending toward the dike, and the barbed wall is arranged in the middle position of the side wall.

[0014] In some embodiments, it also includes a bottom plate connected to the bottom ends of the side walls, flood walls, and backwater walls, and the empty box is a cast-in-place concrete structure.

[0015] In the above technical scheme, the levee is set above the existing river-penetrating structure, and the levee is divided into a first levee and a second levee which are set at intervals upstream and downstream of the river-penetrating structure. The interval between the first levee and the second levee is consistent with the width of the existing river-penetrating structure. An empty box is set within the interval, and the empty box is connected to the first levee and the second levee on both sides, so that the empty box is fixedly set on the top surface of the existing river-penetrating structure. Since a receiving cavity is formed inside the empty box, the vertical load on the top of the existing river-penetrating structure is reduced, and soil can be backfilled in the receiving cavity according to actual conditions to enhance the anti-floating stability of the empty box structure. Therefore, when the flood control standard of the river channel is improved and the original levee needs to be heightened and thickened, the empty box structure can be set according to the heightening and thickening dimensions of the levee and the upper load limit of the existing river-penetrating structure, so that the upper load of the existing river-penetrating structure is within the allowable range, and there is no need to dismantle and rebuild the existing river-penetrating structure, ensuring that the construction is carried out in a normal operating state, eliminating the contradiction between the levee construction and the operation of the existing river-penetrating structure, and improving the compatibility and practicality of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural schematic diagram of a dike structure disclosed by the present invention that takes into account the load reduction of existing river-crossing buildings;

[0017] Figure 2 yes Figure 1 A cross-sectional view of a hollow box in a dike structure that takes into account the load reduction of an existing river-crossing structure and is installed on an existing river-crossing structure is disclosed;

[0018] Figure 3 yes Figure 1 A side view of the top plate of a dike structure that takes into account the load reduction of existing river-crossing structures;

[0019] Figure 4 yes Figure 1 A schematic structural diagram of a middle partition wall in a dike structure that takes into account the load reduction of existing river-crossing structures is disclosed in;

[0020] Figure 5 yes Figure 4 The front view of the middle partition wall disclosed in FIG.

[0021] Description of Reference Numerals

[0022] 1 dike 11 first dike

[0023] 12 Second dike 2 empty container

[0024] 21 side wall 211 corbel

[0025] 22 Flood wall 23 Backwater wall

[0026] 24 top plate 241 groove

[0027] 242 Concrete layer 25 Middle partition wall

[0028] 251 through hole 252 continuous beam

[0029] 253 Reinforced Protrusion 26 Thorn Wall

[0030] 27 Bottom plate 3 Accommodating cavity

[0031] 4. Planking 5. Existing river-crossing buildings DETAILED DESCRIPTION

[0032] The specific implementation of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the embodiments described herein are only a part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0033] In the present invention, unless otherwise specified, the directions or positional relationships indicated by the directional words such as "up" and "down" are based on the directions or positional relationships shown in the drawings and are only for the convenience of describing the present design and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present design.

[0034] In the description of this design, it should be noted that, unless otherwise clearly specified and limited, the terms "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this design can be understood according to specific circumstances.

[0035] Furthermore, the terms "first", "second", "third", etc. are used for descriptive purposes only and should not be construed as indicating or implying relative importance.

[0036] In order to overcome the contradiction between the need for normal and continuous operation of some important river-crossing lifeline projects in the existing technology (which cannot be dismantled and rebuilt) and the need for heightening and thickening of embankments, reference is made to Figures 1 to 5 As shown, the present invention provides a dike structure that takes into account the load reduction of existing river-crossing structures, including:

[0037] The dike 1 includes a first dike 11 and a second dike 12 which are arranged above the existing river-penetrating structure 5 and are arranged upstream and downstream of the river-penetrating structure 5 at intervals parallel to the water flow direction, and the interval between the first dike 11 and the second dike 12 is equal to the width of the existing river-penetrating structure 5 along the water flow direction;

[0038] The empty box 2 is arranged on the top surface of the existing river-crossing structure 5 and is connected to the first dike 11 and the second dike 12 on both sides respectively. A receiving cavity 3 is formed inside the empty box 2.

[0039] It is understandable that the original levee and the existing river-crossing structure 5 are arranged vertically in the axial direction. When the flood control standard of the river channel is improved and the original levee needs to be raised and thickened, the load on the upper part of the existing river-crossing structure 5 will increase, threatening the structural safety of the existing river-crossing structure 5. Therefore, an empty box structure can be set according to the heightening and thickening size of the levee and the upper load limit of the existing river-crossing structure 5 to meet the structural safety of the existing river-crossing structure when the levee is raised and thickened. Specifically, combined with Figures 1 to 5 As shown, the levee 1 is arranged above the existing river-penetrating structure 5, and the levee 1 is divided into a first levee 11 and a second levee 12 which are arranged at intervals upstream and downstream of the river-penetrating structure 5. The interval between the first levee 11 and the second levee 12 is consistent with the width of the existing river-penetrating structure 5. An empty box 2 is arranged within the interval, and the empty box 2 is connected with the first levee 11 and the second levee 12 on both sides, so that the empty box 2 is fixedly arranged on the top surface of the existing river-penetrating structure 5. Since a receiving cavity 3 is formed inside the empty box 2, the vertical bearing above the existing river-penetrating structure 5 is reduced, so that the load on the upper part of the existing river-penetrating structure 5 is within the allowable range, and there is no need to dismantle and rebuild the existing river-penetrating structure 5, ensuring that the construction is carried out in a normal operating state, eliminating the contradiction between the levee construction and the operation of the existing river-penetrating structure 5, and improving the compatibility and practicality of the project; and the soil can be backfilled in the receiving cavity 3 according to actual conditions, thereby enhancing the anti-floating stability of the empty box 2 structure.

[0040] Wherein, in some embodiments, Figure 1 As shown, the empty box 2 includes two side walls 21 connected to the side walls of the first dike 11 and the second dike 12 respectively, a flood wall 22 connected to the side walls 21 and located on the water-facing side, a backwater wall 23 connected between the side walls 21 and located on the backwater side, and a top plate 24 connected to the tops of the side walls 21, the flood wall 22 and the backwater wall 23. The flood wall 22, the backwater wall 23 and the top plate 24 are all connected to the first dike 11 and the second dike 12.

[0041] Specifically, Figure 1As shown, the top plate 24, side wall 21, flood wall 22 and back wall 23 are claimed to have the same structure as the first dike 11 and the second dike 12, forming an empty box 2 with a accommodating space 3. The empty box 2 is arranged on the top surface of the existing river-penetrating structure 5. The empty box 2 can be backfilled with soil to ensure the anti-floating stability of the empty box 2, and the internal load of the empty box 2 can be adjusted. When the dike needs to be raised and thickened, the load on the upper part of the existing river-penetrating structure 5 is also within the allowable range, and there is no need to demolish and rebuild, ensuring that the construction is carried out under normal operating conditions. This not only eliminates the contradiction between the dike construction and the operation of the existing river-penetrating structure 5, ensuring the long-term stability of the structure, but also meets the requirements of sustainable development and reduces the impact on the environment.

[0042] Further, refer to Figure 1 and Figure 3 As shown, the top plate 24 is provided with a plurality of grooves 241 spaced apart from each other along the width direction of the embankment 1 , and the grooves 241 are filled with a concrete layer 242 , which is flush with the top surfaces of the first embankment 11 and the second embankment 12 .

[0043] Specifically, combined Figure 1 and Figure 3 As shown, the multiple grooves 241 are parallel to each other, and a concrete layer 242 can be cast in place in the multiple grooves 241 and on the upper surface of the top plate 24 to enhance the bearing capacity of the top plate 24. The multiple grooves 241 are arranged at intervals on the top plate 24 to transmit force, effectively and evenly transmit the load borne on the top plate 24 to the surroundings, and avoid concentrated force causing damage to the top plate 24. Of course, in other implementations and methods, the top plate 24 and the concrete layer 242 can also be replaced by a cast-in-place reinforced concrete slab structure, as long as it can be evenly stressed, bear the upper load, effectively ensure the passage of vehicles and other transportation tools above, and avoid collapse.

[0044] Wherein, in some embodiments, reference Figure 2 As shown, a corbel 211 is provided at the top of the side wall 21 , and the top surface of the corbel 211 is connected to the top plate 24 and the butt plate 4 provided on the top surface of the embankment 1 .

[0045] Specifically, Figure 2 As shown, the top plate 24 can be welded to the top surface of the corbel 211, and the strap 4 provided on the top surface of the embankment 1 can be welded to the top surface of the corbel 211, so that the top plate 24 is smoothly connected to the embankment 1. And, it can be understood that by connecting the strap 4 to the top surface of the embankment 1 and the top surface of the corbel 211 at the same time, the misalignment between the empty box 2 and the embankment 1 is effectively avoided, and the top surface of the embankment structure is ensured to be flat.

[0046] Wherein, in some embodiments, Figure 1As shown, the water-facing surface of the flood wall 22 is stepped from top to bottom, and the slope of the backwater wall 23 is the same as that of the first dike 11 and the second dike 12 .

[0047] Specifically, Figure 1 As shown, the flood wall 22 and the water-facing surface of the dike 1 can be set in a step shape from top to bottom. The flood wall 22 is connected with the first dike 11 and the second dike 12, which effectively resists the impact of strong water flow in the river, making the dike structure more stable, avoiding the water flow directly overflowing the dike structure, reducing the risk of dike breach, and the slope of the steps can be 1:1.5, further enhancing the energy dissipation effect and avoiding damage to the dike structure due to excessive impact. Of course, in other embodiments, the water-facing surface of the flood wall 22 can also be set as a slope structure with the same slope as the slope of the dike 1, as long as it can effectively resist the water flow and avoid the water flow impact exceeding the dike structure.

[0048] Wherein, in some embodiments, combined Figure 1 , Figure 2 and Figure 4 As shown, the empty box 2 further includes a middle partition wall 25 which is arranged between the two side walls 21 and is parallel to each other. A through hole 251 is opened in the middle partition wall 25 .

[0049] Specifically, combined Figure 1 , Figure 2 and Figure 4 As shown, the middle partition wall 25 is arranged in the receiving cavity 3 and is parallel to the two side walls 21. The middle partition wall 25 can be arranged in the middle position between the two side walls 21, and supports the top plate 24 together with the two side walls 21 to enhance the supporting force. The middle partition wall 25 divides the receiving cavity 3 into two receiving spaces, and a through hole 251 is provided on the middle partition wall 25, so that the two receiving spaces can be connected, which is convenient for preventing some infrastructure according to actual conditions, reserving space, and flexibly using the receiving cavity 3 inside the empty box 2, thereby improving the versatility of the empty box 2 and avoiding space waste.

[0050] Further, refer to Figure 1 and Figure 4 As shown, the middle partition wall 25 includes a continuous beam 252 connected to the top plate 24, and the continuous beam 252 is arranged above the through hole 251. This arrangement is to further support the top plate 24 and prevent the top plate 24 from collapsing due to the heavy traffic load above the top plate 24.

[0051] And, combined with Figure 4 and Figure 5As shown, the continuous beam 252 is provided with reinforcement protrusions 253 on both sides facing the side wall 21. It can be understood that by providing the reinforcement protrusions 253 on both sides of the continuous beam 252 facing the side wall 21, the top surface of the reinforcement protrusion 253 is kept flush with the top surface of the continuous beam 252, increasing the bearing area, thereby enhancing the supporting effect, so that the top surface of the embankment structure can meet the effect of normal traffic.

[0052] Wherein, in some embodiments, reference Figure 1 As shown, it also includes a barbed wall 26 connected to the outer side of the side wall 21 and extending toward the dike 1 , and the barbed wall 26 is set in the middle position of the side wall 21 .

[0053] Specifically, Figure 1 As shown, a barbed wall 26 is added to the side where the side wall 21 is connected to the levee 1. The barbed wall 26 is perpendicular to the side wall 21 and extends into the first levee 11 and the second levee 12 on both sides, further increasing the seepage path length, which can effectively block seepage and enhance the anti-seepage effect of the levee structure.

[0054] Wherein, in some embodiments, reference Figure 1 and Figure 2 As shown, it also includes a bottom plate 27 connected to the bottom ends of the side wall 21, the flood wall 22, and the back wall 23, and the empty box 2 is a cast-in-place concrete structure.

[0055] Specifically, combined Figure 1 and Figure 2 As shown, the side wall 21, the flood wall 22, the back wall 23, the top plate 24 and the bottom plate 27 surround and form a accommodating cavity 3, so as to prevent the side wall 21, the flood wall 22 and the back wall 23 from being directly connected to the top surface of the existing river-crossing structure 5 and causing leakage. In addition, the empty box 2 can be a cast-in-place reinforced concrete structure with high overall strength, and can effectively prevent water from seeping into the empty box 2.

[0056] Of course, in other embodiments, the empty box 2 may also be an assembled or prefabricated structure, in which the side walls 21, flood walls 22, back walls 23, top plates 24 and bottom plates 27 are all connected by water-stopping connections (for example, by rubber water-stopping strips) to form an impermeable structure, thereby preventing water from entering the empty box 2 and causing damage, thereby ensuring the structural safety of the river embankment and existing river-crossing buildings 5.

[0057] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited thereto. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications. Including the combination of various specific technical features in any suitable manner. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations. However, these simple modifications and combinations should also be regarded as the contents disclosed by the present invention and belong to the protection scope of the present invention.

Claims

1. A dike structure that takes into account the load reduction of existing river-crossing structures, characterized in that: include: A dike (1), the dike (1) comprising a first dike (11) and a second dike (12) which are arranged above an existing river-penetrating structure (5) and are arranged upstream and downstream of the river-penetrating structure (5) at intervals parallel to a water flow direction, wherein the interval between the first dike (11) and the second dike (12) is equal to the width of the existing river-penetrating structure (5) along the water flow direction; An empty box (2), the empty box (2) is arranged on the top surface of the existing river-crossing structure (5) and is connected to the first dike (11) and the second dike (12) on both sides respectively, and a receiving cavity (3) is formed inside the empty box (2).

2. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 1 is characterized in that: The empty box (2) comprises two side walls (21) respectively connected to the side walls of the first dike (11) and the second dike (12), a flood wall (22) connected to the side walls (21) and located on the water-facing side, a backwater wall (23) connected between the side walls (21) and located on the backwater side, and a top plate (24) connected to the tops of the side walls (21), the flood wall (22) and the backwater wall (23); the flood wall (22), the backwater wall (23) and the top plate (24) are all connected to the first dike (11) and the second dike (12).

3. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: The top plate (24) is provided with a plurality of grooves (241) spaced apart from each other along the width direction of the levee (1); the grooves (241) are filled with a concrete layer (242); and the concrete layer (242) is flush with the top surfaces of the first levee (11) and the second levee (12).

4. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: A corbel (211) is provided at the top of the side wall (21), and the top surface of the corbel (211) is connected to the top plate (24) and the butt plate (4) provided on the top surface of the embankment (1).

5. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: The water-facing surface of the flood-proof wall (22) is stepped from top to bottom, and the slope of the backwater wall (23) is the same as the slopes of the first dike (11) and the second dike (12).

6. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: The empty box (2) further comprises a middle partition wall (25) which is arranged between the two side walls (21) and is parallel to each other, and a through hole (251) is provided on the middle partition wall (25).

7. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 6 is characterized in that: The middle partition wall (25) comprises a continuous beam (252) connected to the top plate (24), and the continuous beam (252) is arranged above the through hole (251).

8. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 7 is characterized in that: The continuous beam (252) is provided with reinforcement protrusions (253) on both sides facing the side wall (21).

9. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: It also comprises a barbed wall (26) connected to the outer side of the side wall (21) and extending in the direction of the dike (1), wherein the barbed wall (26) is arranged in the middle position of the side wall (21).

10. The embankment structure that takes into account the load reduction of existing river-crossing structures according to claim 2 is characterized in that: It also includes a bottom plate (27) connected to the bottom ends of the side wall (21), the flood wall (22) and the backwater wall (23); the empty box (2) is a cast-in-place concrete structure.

Citation Information

Cited By

  • Fabricated cavity concrete replacing and filling device crossing top of underground municipal pipe gallery and construction method

    CN119392744A

  • Fabricated cavity concrete backfill device and construction method across top of underground municipal pipe gallery

    CN119392744B