A continuous smelting system for crude copper in two continuous furnaces
By using a two-continuous furnace system and a commutation gas-reversing unit in crude copper smelting, the problems of high fuel consumption rate and large heat loss in the prior art are solved, and a more efficient copper smelting process is achieved, reducing fuel consumption and heat Losses improve output grade.
Patent Information
- Application Number
- CN202411237580.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2044-09-05
AI Technical Summary
The existing crude copper smelting process has high fuel consumption rate and large heat loss, which is mainly due to the need for multiple kilns and high-heat flue gas to take away heat, resulting in low copper smelting efficiency.
The two-continuous furnace system is adopted, combining oxygen-rich double-sided blowing smelting furnace and top blowing smelting furnace, and cancel the double-sided blowing slag-making furnace. The gas supply method is changed through the reversing gas modification unit, so that oxygen and materials are fully mixed, and the process flow is shortened. And reduce the amount of water jacket and heat loss.
It effectively reduces fuel consumption and heat loss, speeds up the reaction speed, improves copper smelting efficiency, and improves output grade.
Smart Images

Figure CN118776317B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a two-furnace continuous blister copper smelting system, and in particular to a two-furnace continuous blister copper smelting system applied to the technical field related to copper smelting. Background Art
[0002] In the prior art, crude copper smelting generally adopts a three-furnace process, in which a smelting furnace first produces low-grade matte containing about 57% copper, which enters a slag-making furnace through a chute and is then blown into white matte containing about 75% copper. This process has the following defects:
[0003] 1. Two kilns are needed for smelting and slagging. Both kilns are double-side blowing type, and the total amount of water jacket used is large. Therefore, the heat taken away by the circulating water is also large, resulting in a high fuel consumption rate.
[0004] 2. The smelting furnace produces low-grade matte (containing 57% copper), which needs to be re-slaged in the double-sided slag-making furnace. The slag-making furnace uses low oxygen-rich concentration blasting, which results in a large amount of flue gas, a large amount of heat carried away by the flue gas, and a large heat loss.
[0005] 3. The lower grade of matte produced by the smelting furnace means that the oxidation and removal ability of iron and sulfur in the copper concentrate during the smelting process is relatively low, and the heat released and directly acting on the melt is also relatively low, which is also one of the reasons for the high fuel consumption. Summary of the invention
[0006] In view of the above-mentioned prior art, the technical problem to be solved by the present invention is that the prior art generally adopts a three-continuous furnace process for crude copper smelting, which has defects such as high fuel consumption rate and large heat loss.
[0007] In order to solve the above problems, the present invention provides a two-furnace continuous blister copper smelting system, comprising a bottom plate, an oxygen-enriched double-side blowing smelting furnace fixedly installed on the bottom plate, and a top-blowing converting furnace located on the discharge side of the oxygen-enriched double-side blowing smelting furnace, and the top-blowing converting furnace and the bottom plate are in contact with each other at one end close to each other, a white matte copper chute is installed at the upper end of the bottom plate between the two, the white matte copper chute is connected to the oxygen-enriched double-side blowing smelting furnace and the top-blowing converting furnace, and a left exhaust pipe and a plurality of inlet pipes are fixedly connected to the top of the upper end of the oxygen-enriched double-side blowing smelting furnace. The feed inlet, the front and rear sides of the oxygen-enriched double-side blowing smelting furnace are provided with a plurality of evenly distributed tuyeres, a smelting slag chute is installed at one end of the oxygen-enriched double-side blowing smelting furnace away from the top-blowing converting furnace, a flux feed inlet, a plurality of main oxygen lances, and a right smoke exhaust pipe are sequentially connected to the upper end of the top-blowing converting furnace in a direction away from the bottom plate, and the flux feed inlet, the main oxygen lance and the right smoke exhaust pipe are all in communication with the inside of the top-blowing converting furnace, a crude copper chute is installed at one end of the top-blowing converting furnace away from the oxygen-enriched double-side blowing smelting furnace, and the lower end of the main oxygen lance extends into the top-blowing converting furnace;
[0008] A reversing gas-changing unit is arranged outside the multiple main oxygen guns, and the reversing gas-changing unit includes a convex ring fixedly connected to the top-blowing refining furnace, an auxiliary oxygen gun fixedly connected to the upper end of the convex ring, and multiple change-of-direction nozzles fixedly connected to the lower end of the convex ring. The auxiliary oxygen gun, the convex ring and the multiple change-of-direction nozzles are connected in sequence. The outer end of the main oxygen gun located below the top-blowing refining furnace is fixedly connected to a special-shaped angle-changing ring, and the outer end of the main oxygen gun located above the top-blowing refining furnace is fixedly connected to a driven wheel. A reversing assembly is installed on the top of the top-blowing refining furnace. The reversing assembly includes a double-sided rack meshing with multiple driven wheels at the same time and a forward and reverse motor for driving the double-sided rack. The double-sided rack is slidably connected to the top of the top-blowing refining furnace, and the outer end of the output shaft of the forward and reverse motor is fixedly connected to a driving wheel meshing with the double-sided rack.
[0009] In the above-mentioned two-furnace continuous blister copper smelting system, a two-furnace process combining an oxygen-enriched double-side blowing smelting furnace and a top-blowing blowing furnace is adopted for continuous blister copper smelting, and the double-side blowing slag making furnace is eliminated, shortening the process flow, and improving the three-step blister copper smelting process to a two-step blister copper smelting process, thereby reducing the water jacket usage, thereby effectively reducing fuel consumption, and also reducing heat loss.
[0010] As a further improvement of the present application, the white matte chute, the smelting slag chute and the blister copper chute are all inclined, and the white matte chute and the blister copper chute are gradually lowered in the direction away from the oxygen-enriched double-side blowing smelting furnace, and the smelting slag chute is gradually raised in the direction away from the oxygen-enriched double-side blowing smelting furnace.
[0011] As a further improvement of the present application, the unidirectional rotation angle of the main oxygen lance is not less than 180° and not greater than 360°, and the forward and reverse motors are located on the side of the main oxygen lance away from the auxiliary oxygen lance.
[0012] As a further improvement of the present application, the changing direction nozzle includes a fixed pipe fixedly connected to the convex ring, a moving pipe located below the fixed pipe, and a changing joint fixedly connected between the two. The special-shaped angle-changing ring is lower than the changing joint and higher than the center line of the moving pipe. The changing joint includes two changing plates fixedly connected to the fixed pipe and the moving pipe at one end close to each other, and a metal hose connected between the two changing plates.
[0013] As a further improvement of the present application, a center hole is drilled at the center of the upper deflection plate, and a plurality of outer holes distributed in a circular array are drilled on the lower deflection plate; when the deflection nozzle is in a vertical state, the two deflection plates contact each other, and the center hole is completely misaligned with the plurality of outer holes.
[0014] As a further improvement of the present application, inner ring grooves are formed on the edges of the two deflection plates that are close to each other, and the upper and lower ends of the metal hose are respectively fixedly connected between the two inner ring grooves.
[0015] As a further improvement of the present application, the special-shaped variable angle ring includes two variable distance segments distributed in a centrally symmetrical manner and two transition segments respectively connecting the two variable distance segments at their ends. The outer edge of the variable distance segment is a cylindrical structure, the center of the cross section of the outer edges of the two variable distance segments and the center of the cross section of the main oxygen gun are located on the same straight line, and the three do not overlap, and the outer surface of the transition segment is an arc structure.
[0016] As another improvement of the present application, a loss reduction platform is provided on the bottom plate between the top-blown refining furnace and the upper end of the oxygen-enriched double-side-blown smelting furnace. An air inlet pipe and an air return pipe are fixedly connected between the loss reduction platform and the right smoke exhaust pipe. A strip cover groove is opened in the middle of the lower end of the loss reduction platform, and an insulation cavity is opened inside the loss reduction platform. The air inlet pipe and the air return pipe are fixedly passed through the loss reduction platform and are respectively connected to the left and right ends of the insulation cavity.
[0017] As another improved supplement of the present application, part of the loss reduction platform located between the strip cover groove and the heat preservation cavity is made of high thermal conductivity material, and the rest of the loss reduction platform is made of high thermal insulation material.
[0018] In summary, the double-furnace process of an oxygen-enriched double-side blowing smelting furnace and a top-blowing converting furnace is adopted for continuous smelting of crude copper, the double-side blowing slag-making furnace is cancelled, the process flow is shortened, and the three-step crude copper smelting process is improved to a two-step crude copper smelting process, which reduces the amount of water jacket, thereby effectively reducing the fuel consumption, and also reduces the heat loss; in addition, in the top-blowing converting furnace, through the setting of a reversing gas conversion unit, the traditional direct blowing method can be changed during the gas supply process, so that the air intake direction is radiated outward, and the overall gas injection direction is not fixed, so that the airflow in the top-blowing converting furnace is turbulent. Compared with the existing technology, the full oxidation mixing of oxygen and the materials in the top-blowing converting furnace can be greatly improved, thereby effectively accelerating the reaction speed, and can also reduce the gas supply time, so that the heat loss is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a three-dimensional diagram of the first embodiment of the present application;
[0020] Figure 2 This is a front view of the first embodiment of the present application;
[0021] Figure 3 This is a partial schematic diagram of a main oxygen lance and an auxiliary oxygen lance according to a first embodiment of the present application;
[0022] Figure 4 A schematic top view of a switching component portion of a first embodiment of the present application;
[0023] Figure 5 A cross-sectional view of the upper end portion of the first embodiment of the present application when the nozzle of the reversing nozzle faces downward;
[0024] Figure 6A cross-sectional view of the upper end portion of the first embodiment of the present application when the mouth of the change-of-direction nozzle is tilted outward;
[0025] Figure 7 This is a schematic top view of a deflection plate according to a first embodiment of the present application;
[0026] Figure 8 A schematic top view of a plurality of redirecting nozzle parts according to a first embodiment of the present application;
[0027] Fig. 9 A top view of the special-shaped angle-changing ring according to the first embodiment of the present application;
[0028] Fig.10 This is a perspective view of a second embodiment of the present application;
[0029] Fig.11 A three-dimensional diagram of a loss reduction platform according to a second embodiment of the present application;
[0030] Fig.12 This is a cross-sectional view of the loss reduction platform portion of the second embodiment of the present application.
[0031] Description of the numbers in the figure:
[0032] 1 oxygen-enriched double-side blowing smelting furnace, 101 wind eye, 102 white matte chute, 103 smelting slag chute, 11 feed port, 12 left smoke exhaust pipe, 2 top blowing refining furnace, 201 crude copper chute, 21 flux feed port, 22 main oxygen gun, 23 right smoke exhaust pipe, 3 bottom plate, 41 auxiliary oxygen gun, 42 convex ring, 43 driven wheel, 44 double-sided rack, 45 forward and reverse motor, 5 reversing nozzle, 51 fixed pipe, 52 moving pipe, 53 metal hose, 6 reversing plate, 601 center hole, 602 inner retreat ring groove, 603 outer chute, 7 special-shaped angle ring, 71 variable pitch section, 72 transition section, 8 loss reduction table, 801 strip cover groove, 802 insulation chamber, 91 air inlet pipe, 92 air return pipe. DETAILED DESCRIPTION
[0033] Two implementation modes of the present application are described in detail below with reference to the accompanying drawings.
[0034] The first implementation method:
[0035] Figure 1-2It is shown that a two-furnace continuous blister copper smelting system comprises a bottom plate 3, an oxygen-enriched double-side blowing smelting furnace 1 fixedly mounted on the bottom plate 3, and a top-blowing converting furnace 2 located on the discharge side of the oxygen-enriched double-side blowing smelting furnace 1, and the top-blowing converting furnace 2 is in contact with one end of the bottom plate 3 that is close to each other, a white matte copper chute 102 is installed at the upper end of the bottom plate 3 between the two, the white matte copper chute 102 connects the oxygen-enriched double-side blowing smelting furnace 1 and the top-blowing converting furnace 2, a left smoke exhaust pipe 12 and a plurality of feed ports 11 are fixedly connected to the top of the upper end of the oxygen-enriched double-side blowing smelting furnace 1, a plurality of evenly distributed wind eyes 101 are arranged on the front and rear sides of the oxygen-enriched double-side blowing smelting furnace 1, and a smelting slag chute is installed at the end of the oxygen-enriched double-side blowing smelting furnace 1 that is away from the top-blowing converting furnace 2 103, the white matte chute 102, the smelting slag chute 103 and the blister copper chute 201 are all inclined, and the white matte chute 102 and the blister copper chute 201 are gradually lowered in the direction away from the oxygen-enriched double-side blowing smelting furnace 1, the smelting slag chute 103 is gradually raised in the direction away from the oxygen-enriched double-side blowing smelting furnace 1, the upper end of the top-blowing converting furnace 2 is connected with a flux feed port 21, a plurality of main oxygen lances 22, and a right smoke exhaust pipe 23 in sequence in the direction away from the bottom plate 3, and the flux feed port 21, the main oxygen lance 22 and the right smoke exhaust pipe 23 are all connected with the inside of the top-blowing converting furnace 2, the blister copper chute 201 is installed at one end of the top-blowing converting furnace 2 away from the oxygen-enriched double-side blowing smelting furnace 1, and the lower end of the main oxygen lance 22 extends into the top-blowing converting furnace 2;
[0036] Among them, the tuyere 101 has an air inlet made of a composite material of stainless steel and copper and is installed in the copper water jacket furnace wall. It is resistant to high temperature corrosion and can be smelted with a high oxygen enrichment concentration. A matte siphon outlet is provided at the lower part of one end of the oxygen-enriched double-side blowing smelting furnace 1, and an observation port is provided at the upper part. The siphon technology can guide the white matte produced by the oxygen-enriched double-side blowing smelting furnace 1 to the white matte chute 102 and slide along it into the top-blowing converting furnace 2. The masonry of the oxygen-enriched double-side blowing smelting furnace 1 is built by a mixture of copper water jacket and chrome-magnesia bricks. The key parts of the furnace wall adopt water-cooled copper water jacket slag protection technology, which makes the furnace wall resistant to high temperature and erosion, has good operating performance and a long furnace life, and reduces the requirements for the performance of refractory materials and reduces the consumption of refractory materials.
[0037] Among them, a white matte inlet is provided at the position corresponding to the white matte chute 102 of the top-blown converting furnace 2, and a blister copper siphon discharge port is provided at the other end. The siphon technology can guide the generated blister copper melt to the blister copper chute 201, and flow into the slag bag along the blister copper chute 201. A two-furnace process combining an oxygen-enriched double-side blowing smelting furnace 1 and a top-blown converting furnace 2 is adopted for continuous blister copper smelting, and the double-side blowing slag-making furnace is eliminated, shortening the process flow, and improving the three-step blister copper smelting process into a two-step blister copper smelting process, thereby reducing the water jacket usage, thereby effectively reducing fuel consumption, and also reducing heat loss.
[0038] like Figure 3-4, a plurality of main oxygen guns 22 are each provided with a reversing gas-changing unit, the reversing gas-changing unit comprises a convex ring 42 fixedly connected to the top-blowing refining furnace 2, an auxiliary oxygen gun 41 fixedly connected to the upper end of the convex ring 42, and a plurality of reversing nozzles 5 fixedly connected to the lower end of the convex ring 42, the auxiliary oxygen gun 41, the convex ring 42 and the plurality of reversing nozzles 5 are sequentially connected, the outer end of the main oxygen gun 22 located below the top-blowing refining furnace 2 is fixedly connected to a special-shaped angle-changing ring 7, the outer end of the main oxygen gun 22 located above the top-blowing refining furnace 2 is fixedly connected to a driven wheel 43, a reversing assembly is installed on the top of the top-blowing refining furnace 2, the reversing assembly comprises a double-sided rack 44 meshed with a plurality of driven wheels 43 at the same time and a forward and reverse motor 45 for driving the double-sided rack 44, the double-sided rack 44 is slidably connected to the top of the top-blowing refining furnace 2, the outer end of the output shaft of the forward and reverse motor 45 is fixedly connected to a driving wheel meshed with the double-sided rack 44, when smelting, the main oxygen gun 22 and the auxiliary oxygen gun 41 are both connected to the external oxygen source. When the high-pressure oxygen flow is introduced into the top-blowing refining furnace 2 through the main oxygen gun 22, the forward and reverse motor 45 can be synchronously controlled to continuously rotate forward and reverse, thereby driving the double-sided rack 44 to continuously move back and forth horizontally, thereby synchronously driving multiple main oxygen guns 22 to continuously rotate forward and reverse. When the main oxygen gun 22 rotates, due to the action of the special-shaped angle ring 7, it will continuously push multiple moving pipes 52, so that it repeatedly moves away from the main oxygen gun 22 and approaches the main oxygen gun 22, thereby causing the direction of the mouth of the moving pipe 52 to continuously change, so that the oxygen sprayed from the mouth has a wider radiation range, and the contact reaction effect with the material in the top-blowing refining furnace 2 is faster and better. Compared with the direct blowing method in the prior art, the oxidation reaction speed is greatly improved, thereby reducing the time required for the reaction, shortening the gas supply time, thereby reducing the air volume consumed to reduce the wall temperature of the main oxygen gun 22, and achieving the effect of reducing heat loss.
[0039] like Figure 5 The change-of-direction nozzle 5 includes a fixed pipe 51 fixedly connected to the convex ring 42, a moving pipe 52 located below the fixed pipe 51, and a change-of-direction joint fixedly connected between the two. The special-shaped angle-changing ring 7 is lower than the change-of-direction joint and higher than the center line of the moving pipe 52. The change-of-direction joint includes two change-of-direction plates 6 fixedly connected to the fixed pipe 51 and the moving pipe 52 at one end close to each other, and a metal hose 53 connected between the two change-of-direction plates 6. Through the arrangement of the metal hose 53, the overall angle of the change-of-direction nozzle 5 can be changed.
[0040] The materials of the fixed pipe 51, the moving pipe 52, the metal hose 53, the deflection plate 6, the auxiliary oxygen gun 41 and the convex ring 42 are consistent with the materials of the top of the top blowing furnace 2, so that they can withstand high temperatures and are not easily damaged by high temperatures.
[0041] A central hole 601 is bored at the center of the upper deflection plate 6, and a plurality of outer holes 603 distributed in a circular array are bored on the lower deflection plate 6; when the deflection nozzle 5 is in a vertical state, Figure 7The two deflection plates 6 are in contact with each other, and the central hole 601 is completely misaligned with the multiple outer holes 603. The edges of the two deflection plates 6 close to each other are both provided with inner ring grooves 602. The upper and lower ends of the metal hose 53 are respectively fixedly connected between the two inner ring grooves 602. Figure 5 When the fixed pipe 51 and the moving pipe 52 are in a vertical state, the two deflection plates 6 collide with each other. At this time, the center hole 601 and the outer hole 603 are misaligned, so that the two ends of the deflection nozzle 5 are blocked. Figure 6 When the main oxygen lance 22 rotates, the special-shaped angle ring 7 pushes the moving tube 52, which causes the moving tube 52 to rotate, so that the two deflection plates 6 are separated from each other. At this time, the central hole 601 and the outer slot 603 are connected, and the high-pressure oxygen flow can enter the deflection nozzle 5 and be ejected into the oxygen-enriched double-side blowing smelting furnace 1.
[0042] like Fig. 9 The special-shaped variable angle ring 7 includes two variable pitch segments 71 which are symmetrically distributed in the center and two transition segments 72 which respectively connect the two variable pitch segments 71 at the head and tail. The outer edge of the variable pitch segment 71 is a cylindrical structure. The center of the cross section of the outer edge of the two variable pitch segments 71 and the center of the cross section of the main oxygen lance 22 are located on the same straight line, and the three do not overlap, so that the distances between the two ends of the variable pitch segment 71 and the main oxygen lance 22 are different, so that when the main oxygen lance 22 rotates and drives the special-shaped variable angle ring 7 to rotate accordingly, the special-shaped variable angle ring 7 has different pushing amplitudes on the same direction-changing nozzle 5, and as it changes The outward bending angle of the nozzle 5 will change from large to small or from small to large, so that the oxygen injection range of the single change-direction nozzle 5 will change dynamically, so that the airflow in the oxygen-enriched double-side blowing smelting furnace 1 will be turbulent, and the contact oxidation effect with the material will be better and the speed will be faster. The outer surface of the transition section 72 is an arc structure, so that the two variable distance sections 71 are in an arc transition. When the main oxygen gun 22 rotates forward and reverse, the special-shaped angle ring 7 and the moving tube 52 can move relative to each other, and it is not easy for the moving tube 52 and the special-shaped angle ring 7 to conflict and get stuck.
[0043] It is worth noting that the unidirectional rotation angle of the main oxygen lance 22 is not less than 180°. Figure 8 , so that each time the main oxygen gun 22 rotates, it can drive the variable pitch section 71 to produce a minimum to maximum angle change on the fixed pipe 51, effectively ensuring that when the high-pressure oxygen flow is introduced, the effective range of the ejected oxygen flow is effectively guaranteed, and at the same time it is not greater than 360°, effectively avoiding continuous rotation in the same direction, making it difficult for the main oxygen gun 22 or the auxiliary oxygen gun 41 to be wrapped around the pipe or the wire, effectively ensuring the stable introduction of the oxygen flow, and the forward and reverse motor 45 is located on the side of the main oxygen gun 22 away from the auxiliary oxygen gun 41, so that the auxiliary oxygen gun 41 and the forward and reverse motor 45 are not easy to affect each other.
[0044] In the process of improving the three-continuous furnace to a two-continuous furnace, experimental tests were carried out. The specific test process is as follows:
[0045] Copper concentrate powder and flux are directly added to the slag-making furnace using a feeding system. At the same time, the blast oxygen enrichment concentration of the slag-making furnace is increased from the original 45% to 70%. After smelting the copper concentrate, 75% grade white matte is directly produced. During the experiment, it was found that adding a certain amount of copper concentrate powder during the slag-making and blowing process is more stable than simply slag-making and blowing the matte.
[0046] Based on the above experiments, it can be known that the smelting of crude copper in two continuous furnaces is feasible. When the crude copper smelting in two continuous furnaces is implemented, the grade of matte produced by the smelting furnace is increased from about 57% to about 72%. While the slag-making furnace further improves the grade of matte produced by the smelting furnace through slag making, about 20 tons of copper concentrate is added per hour, and the grade of white matte produced by the slag-making furnace still reaches about 75%.
[0047] In summary, a two-furnace process in which an oxygen-enriched double-side-blowing smelting furnace 1 and a top-blowing converting furnace 2 are used to continuously smelt crude copper, and the double-side-blowing slag-making furnace is eliminated, thereby shortening the process flow and improving the three-step crude copper smelting process to a two-step crude copper smelting process, thereby reducing the amount of water jacket used, thereby effectively reducing fuel consumption, and also reducing heat loss; in addition, in the top-blowing converting furnace 2, by setting a reversing gas conversion unit, the traditional direct blowing method can be changed during the gas supply process, so that the air intake direction is radiated outward, and the overall gas injection direction is not fixed, so that the airflow in the top-blowing converting furnace 2 is turbulent. Compared with the prior art, the sufficient oxidation mixing of oxygen and the materials in the top-blowing converting furnace 2 can be greatly improved, thereby effectively accelerating the reaction speed, thereby reducing the gas supply time and reducing heat loss.
[0048] The second implementation method:
[0049] Based on the first embodiment, this embodiment adds a loss reduction platform 8 and related structures, and the rest of the parts are consistent with the first embodiment.
[0050] Figure 10-11 As shown, a loss reduction platform 8 is also provided at the bottom plate 3 between the top-blown refining furnace 2 and the upper end of the oxygen-enriched double-side-blown smelting furnace 1. An air inlet pipe 91 and an air return pipe 92 are fixedly connected between the loss reduction platform 8 and the right smoke exhaust pipe 23. A strip cover groove 801 is opened in the middle of the lower end of the loss reduction platform 8. The strip cover groove 801 is just set above the white matte chute 102, which can effectively reduce the heat loss of the white matte produced by smelting in the oxygen-enriched double-side-blown smelting furnace 1 when it flows into the top-blown refining furnace 2 through the white matte chute 102, thereby reducing the overall fuel consumption of the system. An insulation cavity 802 is opened inside the loss reduction platform 8. The air inlet pipe 91 and the air return pipe 92 are fixedly passed through the loss reduction platform 8 and are respectively connected to the left and right ends of the insulation cavity 802. The part of the loss reduction platform 8 located between the strip cover groove 801 and the insulation cavity 802 is made of high thermal conductivity material, and the rest of the loss reduction platform 8 is made of high thermal insulation material. Fig.12When smelting blister copper, part of the flue gas can be guided into the insulation chamber 802 through the air inlet pipe 91, and this part of the flue gas can flow back into the right exhaust pipe 23 through the return air pipe 92, so that part of the exhausted high-temperature flue gas can circulate in the insulation chamber 802. The heat it carries can make the part of the loss reduction platform 8 facing the white matte chute 102 always in a high-temperature state, so that when the white matte passes through, the temperature difference between the outside and the white matte can be effectively reduced, thereby realizing low heat loss transfer of the products between the two furnaces, thereby greatly reducing the overall fuel consumption of this system during blister copper smelting.
[0051] In addition, an air pump may be installed on the air inlet pipe 91 or the air return pipe 92 to assist the circulation of smoke in the heat preservation chamber 802 .
[0052] In view of current practical needs, the above-mentioned implementation mode adopted in this application is not limited to the scope of protection. Various changes made within the knowledge scope of technical personnel in this field without departing from the concept of this application still fall within the scope of protection of the present invention.
Claims
1. A two-furnace continuous smelting system for crude copper. Features: The invention comprises a bottom plate (3), an oxygen-enriched double-side blowing smelting furnace (1) fixedly mounted on the bottom plate (3), and a top-blowing converting furnace (2) located on the discharge side of the oxygen-enriched double-side blowing smelting furnace (1), wherein the top-blowing converting furnace (2) and the bottom plate (3) are in contact with each other at one end close to each other, a white matte chute (102) is installed at the upper end of the bottom plate (3) located between the two, and the white matte chute (102) is connected to the oxygen-enriched double-side blowing smelting furnace (1) and the top-blowing converting furnace (2), a left exhaust pipe (12) and a plurality of feed ports (11) are fixedly connected to the top of the upper end of the oxygen-enriched double-side blowing smelting furnace (1), and a plurality of Evenly distributed wind eyes (101), a smelting slag chute (103) is installed at one end of the oxygen-enriched double-side-blowing smelting furnace (1) away from the top-blowing converting furnace (2), a flux feed port (21), a plurality of main oxygen lances (22), and a right smoke exhaust pipe (23) are sequentially connected to the upper end of the top-blowing converting furnace (2) in a direction away from the bottom plate (3), and the flux feed port (21), the main oxygen lance (22) and the right smoke exhaust pipe (23) are all in communication with the inside of the top-blowing converting furnace (2), a blister copper chute (201) is installed at one end of the top-blowing converting furnace (2) away from the oxygen-enriched double-side-blowing smelting furnace (1), and the lower end of the main oxygen lance (22) extends into the top-blowing converting furnace (2); A reversing gas-changing unit is disposed outside the plurality of main oxygen lances (22), the reversing gas-changing unit comprising a convex ring (42) fixedly connected to the top-blowing refining furnace (2), an auxiliary oxygen lance (41) fixedly connected to the upper end of the convex ring (42), and a plurality of reversing nozzles (5) fixedly connected to the lower end of the convex ring (42), the auxiliary oxygen lance (41), the convex ring (42), and the plurality of reversing nozzles (5) being connected in sequence, the outer end of the main oxygen lance (22) located below the top-blowing refining furnace (2) being fixedly connected to a special-shaped angle-changing ring (7), The main oxygen lance (22) is located above the top-blowing refining furnace (2), and its outer end is fixedly connected to a driven wheel (43). A reversing assembly is installed on the top of the top-blowing refining furnace (2). The reversing assembly includes a double-sided rack (44) that meshes with a plurality of driven wheels (43) at the same time, and a forward and reverse motor (45) for driving the double-sided rack (44). The double-sided rack (44) is slidably connected to the top of the top-blowing refining furnace (2), and the outer end of the output shaft of the forward and reverse motor (45) is fixedly connected to a driving wheel that meshes with the double-sided rack (44).
2. A two-furnace continuous blister copper smelting system according to claim 1, Features: The white matte chute (102), the smelting slag chute (103) and the blister copper chute (201) are all inclined, and the white matte chute (102) and the blister copper chute (201) are gradually lowered in a direction away from the oxygen-enriched double-side blowing smelting furnace (1), and the smelting slag chute (103) is gradually raised in a direction away from the oxygen-enriched double-side blowing smelting furnace (1).
3. A two-furnace continuous blister copper smelting system according to claim 1, Features: The unidirectional rotation angle of the main oxygen lance (22) is not less than 180° and not more than 360°, and the forward and reverse motor (45) is located on a side of the main oxygen lance (22) away from the auxiliary oxygen lance (41).
4. A two-furnace continuous blister copper smelting system according to claim 1, Features: The direction-changing nozzle (5) comprises a fixed pipe (51) fixedly connected to the convex ring (42), a movable pipe (52) located below the fixed pipe (51), and a direction-changing joint fixedly connected between the two, the special-shaped angle-changing ring (7) is lower than the direction-changing joint and higher than the center line of the movable pipe (52), and the direction-changing joint comprises two direction-changing plates (6) respectively fixedly connected to the fixed pipe (51) and the movable pipe (52) at one end close to each other, and a metal hose (53) connected between the two direction-changing plates (6).
5. A two-furnace continuous blister copper smelting system according to claim 4, Features: A central hole (601) is bored at the center of the deflection plate (6) located at the top, and a plurality of outer holes (603) distributed in a circular array are bored on the deflection plate (6) located at the bottom; when the deflection nozzle (5) is in a vertical state, the two deflection plates (6) are in contact with each other, and the central hole (601) and the plurality of outer holes (603) are completely misaligned.
6. A two-furnace continuous blister copper smelting system according to claim 5, Features: The edges of the two deflection plates (6) that are close to each other are both provided with inner ring grooves (602), and the upper and lower ends of the metal hose (53) are respectively fixedly connected between the two inner ring grooves (602).
7. A two-furnace continuous blister copper smelting system according to claim 1, Features: The special-shaped variable angle ring (7) comprises two variable pitch segments (71) distributed symmetrically with respect to the center, and two transition segments (72) respectively connecting the two variable pitch segments (71) at their ends, the outer edges of the variable pitch segments (71) being cylindrical structures, the center of the cross section of the outer edges of the two variable pitch segments (71) and the center of the cross section of the main oxygen lance (22) being located on the same straight line, and the three do not overlap, and the outer surface of the transition segment (72) being an arc structure.
8. The two-furnace continuous blister copper smelting system according to claim 1, Features: A loss reduction platform (8) is also provided at the bottom plate (3) between the upper ends of the top-blown refining furnace (2) and the oxygen-enriched double-side-blown smelting furnace (1); an air intake pipe (91) and an air return pipe (92) are fixedly connected between the loss reduction platform (8) and the right smoke exhaust pipe (23); a strip-shaped cover groove (801) is bored in the middle of the lower end of the loss reduction platform (8); a heat preservation chamber (802) is bored inside the loss reduction platform (8); the air intake pipe (91) and the air return pipe (92) are both fixedly passed through the loss reduction platform (8) and are respectively connected to the left and right ends of the heat preservation chamber (802).
9. A two-furnace continuous blister copper smelting system according to claim 8, Features: The portion of the loss reduction platform (8) located between the strip-shaped cover groove (801) and the heat preservation cavity (802) is made of a high heat conductive material, and the rest of the loss reduction platform (8) is made of a high heat insulating material.