Intelligent steel bar sample turning and blanking system and method based on digital twinning

Through the intelligent rebar cutting and cutting system based on digital twins, a digital twin model of building components and steel bars is created, and a steel rebar cutting and cutting plan is generated, which solves the problems of low material usage and high learning cost in the traditional rebar cutting method. Automated production and high-efficiency steel processing are realized.

CN118779972AInactive Publication Date: 2024-10-15SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD

Patent Information

Application Number
CN202411259831.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-10-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The traditional steel bar sample-turning method has problems such as low material usage, high waste, low processing efficiency, and high learning costs during the construction process. Moreover, the BIM-based method cannot comprehensively consider the construction plan of the entire project and the actual site conditions, resulting in a degree of intelligence. Not enough, the operation is complicated.

Method used

An intelligent steel bar cutting and cutting system based on digital twins is used to create a digital twin model of building components and steel bars, extract the steel bar design quantity required for the construction plan, generate a steel bar cutting and cutting plan, and conduct data collection, processing, and simulation analysis. , residual material utilization and production execution modules realize automated production, reduce manual data entry and errors, and improve efficiency.

Benefits of technology

It achieves the reduction of manual data entry throughout the project cycle, reduces repeated operation errors, facilitates construction personnel to monitor and adjust the construction plan, improves the accuracy and efficiency of steel bar processing, reduces the waste of remaining materials, and improves production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118779972A_ABST
    Figure CN118779972A_ABST
Patent Text Reader

Abstract

The invention relates to the field of steel bar sample turning, and discloses an intelligent steel bar sample turning and blanking system and method based on digital twinning, and the method comprises the steps: building a digital twinning model of a building component and a steel bar according to a divided and itemized construction plan; extracting a steel bar design quantity required by a construction plan from the digital twin model; the reinforcing steel bar design quantity comprises reinforcing steel bar types required for forming the building component and the number of reinforcing steel bars corresponding to the reinforcing steel bar types; the steel bar type comprises a steel bar shape and a steel bar size; according to the steel bar design quantity and the steel bar stock quantity, a steel bar sample turning and blanking scheme is generated; according to the steel bar design quantity and the steel bar stock quantity, a steel bar sample turning and blanking scheme is generated, and machining production is conducted according to the steel bar sample turning and blanking scheme. By creating the digital twinborn model, the steel bar sample turning scheme is automatically produced, manpower is saved, production efficiency is improved, excess materials can be fully utilized according to the steel bar sample turning scheme, and waste of the excess materials is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of steel bar pattern making, and in particular relates to a steel bar intelligent pattern making and blanking system and method based on digital twin. Background Art

[0002] Rebar sample making refers to the calculation and analysis of the material list of the steel bar components according to the specifications and quantity of the steel bars required for each component in the design drawings during the construction process. The processing site processes the steel bars by welding, bundling or mechanical connection according to the instructions on the material list, so as to produce the steel bars that meet the requirements of the current components.

[0003] In traditional construction, due to the decentralized management, the steel bar processing process is difficult to control, and the use of materials in the processing is relatively random, so the utilization rate of materials is generally low, resulting in a large waste. Usually, only the production capacity of steel bars for a certain component can be planned and controlled. For the steel bar production of multiple components or all components of the entire project, it is impossible to achieve scientific processing and coordinated production management, and it is impossible to ensure that the equipment is produced at saturated capacity, resulting in large steel bar losses, low processing efficiency, and inability to maximize the utilization of steel bars and maximize the efficiency of steel bar production scheduling.

[0004] Even if a BIM-based steel bar optimization method is used to solve the above problems, there are still problems such as too many tools, software, and plug-ins, high learning costs, and it is not suitable for front-line personnel to use. The plan cannot be considered as a whole according to any component or construction plan for any time period; it does not take into account surplus materials and actual on-site conditions; it cannot compare multiple plans; manual operation of models and calculations is complex, error-prone, and inefficient; there is no real-time display of progress, and it cannot be implemented in actual applications. Summary of the invention

[0005] The purpose of the present invention is to overcome the problems in the prior art that the method of steel bar cutting and material making is not intelligent enough and does not comprehensively consider the construction plan of the entire project and the high learning cost caused by the complex operation, and to provide a steel bar intelligent cutting and material making system and method based on digital twins.

[0006] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions: A method for intelligent cutting and blanking of steel bars based on digital twins comprises the following steps: Create digital twin models of building components and reinforcements based on the construction plan for each part; Extracting the steel bar design quantity required for the construction plan from the digital twin model; the steel bar design quantity includes the steel bar type required to form the building component and the number of steel bars corresponding to the steel bar type; the steel bar type includes the steel bar shape and steel bar size; A steel bar cutting plan is generated according to the steel bar design quantity and the steel bar inventory, and processing and production are carried out according to the steel bar cutting plan.

[0007] As a preferred embodiment of the present invention, the steps of constructing the digital twin model include: generating a BIM model of a building component and a BIM model of a steel bar respectively, and binding the construction plan of each part with the BIM model of the building component required for the construction plan, and then binding the BIM model of the building component with the BIM model of the steel bar required to constitute the building component to construct the digital twin model.

[0008] As a preferred solution of the present invention, by creating a sub-item construction plan table, a building component table and a component attribute table in a database, the binding of the building component BIM model and the steel bar BIM model, and the binding of the construction plan and the building component BIM model are achieved.

[0009] As a preferred solution of the present invention, the sub-item construction schedule includes a plan ID, a project ID, a component ID, a construction team, a cumulative completion amount, and actual concrete consumption.

[0010] As a preferred solution of the present invention, the building component table includes the component ID, the project ID, the component code, the component name and the parent component ID.

[0011] As a preferred solution of the present invention, the component attribute table includes a component attribute ID, the parent component ID, the component code and a component specific value.

[0012] As a preferred embodiment of the present invention, the step of generating the steel bar cutting plan comprises: Generate a steel bar sample plan according to the steel bar design quantity, so as to analyze the required steel bar cutting type; The steel bar inventory and the steel bar cutting type are calculated and compared by using a cutting optimization algorithm to obtain the steel bar cutting plan; The indices for calculation and comparison include the amount of residual material and the residual material output rate.

[0013] As a preferred solution of the present invention, when the construction plan of any sub-item is completed, the digital twin model is updated according to the steel bar usage of the construction plan of the sub-item, and the steel bar design quantity is updated synchronously.

[0014] Based on the same concept, the present invention also proposes a steel bar intelligent cutting and blanking system based on digital twin, comprising: The data acquisition and processing module obtains the drawing data of the project building and its steel bars, and parses, classifies and stores the drawing data; A model building module is used to build a building component BIM model and a steel bar BIM model according to the information stored in the data acquisition and processing module, thereby building the digital twin model; A simulation analysis module performs simulation analysis on the digital twin model and outputs the steel bar cutting plan; A surplus material utilization module is used to design a surplus material utilization plan according to the steel bar cutting plan; The production execution module converts the steel bar cutting plan and the surplus material utilization plan into production execution instructions, and sends them to the automated steel bar processing equipment for production; The material management module stores and manages the steel bar materials used in each of the building components during the entire construction process.

[0015] Compared with the prior art, the present invention has the following beneficial effects: The present invention provides a method and system for intelligent steel bar cutting and blanking based on digital twin, which creates digital twin models of building components and steel bars according to the construction plan, automatically generates steel bar cutting plans, and reduces frequent manual data entry throughout the project cycle, thus saving manpower and reducing errors caused by repeated operations, making it convenient for construction personnel to monitor and adjust the construction plan in a timely manner. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 A schematic flow chart of a method for intelligent rebar cutting and blanking based on digital twins according to Example 1; Figure 2 This is a functional analysis diagram of the digital twin platform of Example 2; Figure 3 This is a schematic diagram of the use process of the digital twin platform of Example 2; Figure 4 This is a schematic diagram of the process of steel bar cutting and blanking on the digital twin platform of Example 2; Figure 5 This is a schematic diagram of the interface of the steel bar sample drawing results of the digital twin platform of Example 2. DETAILED DESCRIPTION

[0017] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.

[0018] Example 1 like Figure 1 As shown, a method for intelligent cutting and blanking of steel bars based on digital twins includes: Create digital twin models of building components and reinforcements based on the construction plan for each part; Extracting the steel bar design quantity required for the construction plan from the digital twin model; the steel bar design quantity includes the steel bar type required to form the building component and the number of steel bars corresponding to the steel bar type; the steel bar type includes the steel bar shape and steel bar size; Generate a steel bar cutting plan based on the steel bar design quantity and steel bar inventory; A steel bar cutting plan is generated according to the steel bar design quantity and the steel bar inventory, and processing and production are carried out according to the steel bar cutting plan.

[0019] As a preferred embodiment of the present invention, the steps of constructing the digital twin model include: generating a BIM model of a building component and a BIM model of a steel bar respectively, and binding the construction plan of each part with the BIM model of the building component required for the construction plan, and then binding the BIM model of the building component with the BIM model of the steel bar required to constitute the building component to construct the digital twin model.

[0020] As a preferred solution of the present invention, by creating a sub-item construction plan table, a building component table and a component attribute table in a database, the binding of the building component BIM model and the steel bar BIM model, and the binding of the construction plan and the building component BIM model are achieved.

[0021] Specifically, as shown in Table 1, the sub-item construction schedule includes the plan ID, project ID, component ID, construction team, cumulative completion volume, and actual concrete consumption.

[0022] Table 1 Construction schedule for each part As shown in Table 2, the building component table includes the component ID, the project ID, the component code, the component name and the parent component ID.

[0023] Table 2 Building components As shown in Table 3, the component attribute table includes a component attribute ID, the parent component ID, the component code and a component specific value.

[0024] Table 3 Component attribute table When establishing a BIM model of a building component, a GUID is randomly generated by a computer and assigned to the BIM model of the building component, and the GUID is stored in the building component table as a component ID. In the building component table, each building component will also store its parent component ID, so that the tree structure of the entire project can be established. Then a component attribute table is created to store the attribute content of the component. The parent component ID in the component attribute table indicates the component ID in the component table corresponding to the component attribute, so that the component attribute table is matched with the building component table, so that the corresponding relationship between the component and all its attributes and the building component table can be established. The specific attributes of a component attribute table are determined by the component code, which adopts the standards issued by the Department of Transportation and is constantly improved in practice. For example, the component code "41-05.12.05.00" can be known as "rebar diameter" by looking up the table. Different attributes are determined by different component codes. In this way, the component attribute table can store any number of component attributes. Even if a component adds a new attribute, only one more piece of data needs to be stored without modifying the table design and adding a column. At the same time, a sub-item construction schedule is created. When the sub-item construction schedule is created, the plan ID and project ID are randomly generated. The sub-item construction schedule contains the component ID, which indicates the building component required in the sub-item construction plan. The component and its properties can be found by combining the three tables. Taking a pile foundation as an example, the time period is set in the system and the established model is viewed, as shown in Table 4. Table 4 fills in the corresponding data in the table according to the data content of the sub-item construction schedule defined in Table 1, and then the pile foundation ID can be found in the sub-item construction schedule.

[0025] Table 4 Data of a pile foundation in the sub-item construction plan According to the pile foundation ID, the tree structure of the project where the pile foundation is located can be found in the building component table, as shown in Table 4. Table 5 fills in the corresponding data in the table according to the data content of the building component table defined in Table 2 to form the content filled in Table 5, as shown in Table 5, that is, the ID of the pile foundation is the PID of all the steel bars belonging to the pile foundation, the ID of the substructure is the PID of the pile foundation, the ID of the bridge is the PID of the substructure, and the ID of the project is the PID of the bridge. Based on this association, all the steel bars belonging to the pile foundation and even the components of any granularity of the project can be found in this table.

[0026] Table 5 Data of a pile foundation in the building component table According to the ID of all the steel bars belonging to the pile foundation, all the properties of the required steel bars can be found in the component attribute table. Table 6 fills in the corresponding data in the table according to the data content of the component attribute table defined in Table 3 to form the content filled in Table 6. As shown in Table 6, the PID of the required steel bar attribute is the ID of the steel bar component, and then the specific attributes and values ​​corresponding to the data are obtained according to the values ​​of Code and Value. The system has built-in standard corresponding relationship of component coding. The Code value "41-05.12.05.00" in the table represents the diameter of the steel bar, "41-05.02.32.00" represents the length of the steel bar, "41-06.01.05.00" represents the number of roots, and "41-08.01.01.00" represents the weight, that is, the diameter of the No. 1 main bar is 32mm, the length is 38584mm, the number of roots is 46, and the weight is 11159kg. The diameter of the No. 2 main bar is 32mm, the length is 24724mm, the number of roots is 92, and the weight is 14360kg.

[0027] It should be noted that the ID numbers in Tables 4, 5, and 6 are GUIDs randomly generated by computers and assigned to building components. Each ID is randomly generated from numbers and letters, is different, and is used to refer to a unique component.

[0028] Table 6 Data of main reinforcement of a pile foundation in the component attribute table As a preferred embodiment of the present invention, the step of generating the steel bar cutting plan comprises: Generate a steel bar sample plan according to the steel bar design quantity, so as to analyze the required steel bar cutting type; The steel bar inventory and the steel bar cutting type are calculated and compared by using a cutting optimization algorithm to obtain the steel bar cutting plan; The indicators for calculation and comparison include the amount of excess material and the excess material yield rate. When producing the steel bar re-sample plan, the use of excess material is also considered, which can not only improve the accuracy and efficiency of steel bar processing, but also reduce the waste of excess material and improve production efficiency; and can generate a real-time comparative analysis report based on the actual amount of steel bars used in processing and production and the digital twin model.

[0029] As a specific embodiment, Figure 5 To explain, according to Figure 5As shown in the figure, the steel bar design quantity of the model is imported into the system to automatically generate this steel bar re-sample scheme. The method is the mainstream cutting method currently used in construction, that is, the steel bar design quantity is 21000mm for the single length of the No. 1 main bar and 15000mm for the single length of the No. 2 main bar, and the number of bars is 8. The steel bar re-sample scheme generated by the system's cutting algorithm is: 8 bars of each of the four types of steel bars with lengths of 12000mm, 9000mm, 10880mm, and 4120mm. The system's cutting algorithm is calculated in the following four steps: 1. First, the commonly used steel bar cutting length is calculated based on the length of the original steel bar and the staggered distance of the commonly used joints. If the arrangement scheme cannot be calculated in the end, it will be calculated again based on the minimum joint staggered distance. 2. Then loop through the length of each steel bar and traverse the length of each steel bar cutting, and divide it into sections many times until the remaining length is less than the minimum length, that is, find a reasonable solution, then go back to the previous section until the steel bar is traversed, and then go back to the previous section until the length of each steel bar is traversed. At this point, each steel bar has an arrangement scheme. 3. Then use depth-first search to arrange the plans by group, and you can arrange all the cutting plans. When arranging, the influence area of ​​steel bar bending, joint rate, etc. will be calculated according to the specifications and settings, and a reasonable plan will be traversed. After the traversal is completed, all steel bar re-sampling plans can be found. 4. According to the actual situation on site, the first arrangement plan with the highest priority is generally directly output, that is, the above-mentioned steel bar re-sampling plan. With this steel bar re-sampling plan, you can know the so-called steel bar cutting type, that is, the specific details of each steel bar.

[0030] Although the types of steel bar cutting are already known, there are still various steel bar cutting and cutting schemes. The system supports generating schemes based on different rules. The traditional scheme is sorting optimization, which is simple to operate on site but may result in waste. The system also has three built-in rules for optimal yield rate, guaranteed surplus yield rate, or optimal surplus usage. The so-called yield rate refers to the design amount of steel bars divided by the amount of steel bars used. The yield rate of the traditional sorting optimization scheme is approximately 90%. The optimal yield rate of the system uses a genetic algorithm, and the yield rate can generally be increased to about 95%. The two rules of guaranteed surplus yield rate and optimal surplus usage are generally used in the later stages of the project. Use as much surplus as possible and ensure the yield rate, so that the final steel bars can be just used up or not wasted too much.

[0031] As a preferred embodiment of the present invention, when the construction plan of any sub-item is completed, the digital twin model is updated according to the steel bar usage in the construction plan of the sub-item, and the steel bar design quantity is also updated accordingly.

[0032] Based on the same concept, the present invention also proposes a steel bar intelligent pattern-turning and cutting system based on digital twin, which is used to implement any of the above-mentioned steel bar intelligent pattern-turning and cutting methods based on digital twin, and is characterized by comprising: The data acquisition and processing module obtains the drawing data of the project building and its steel bars, and parses, classifies and stores the drawing data; A model building module is used to build a building component BIM model and a steel bar BIM model according to the information stored in the data acquisition and processing module, thereby building the digital twin model; A simulation analysis module performs simulation analysis on the digital twin model and outputs the steel bar cutting plan; A surplus material utilization module is used to design a surplus material utilization plan according to the steel bar cutting plan; The production execution module converts the steel bar cutting plan and the surplus material utilization plan into production execution instructions, and sends them to the automated steel bar processing equipment for production; The material management module stores and manages the steel bar materials used in each of the building components during the entire construction process.

[0033] Example 2 like Figure 2 As shown, according to an intelligent steel bar cutting and blanking system and method based on digital twins in Example 1, a digital twin platform for project management is designed, and the digital twin platform has the function of importing BIM models of building components and steel bars; after the BIM models of building components and steel bars are imported, the information on the BIM models is stored in a database, and in the database, the building components are bound to the corresponding steel bar information required, thereby establishing a digital twin model.

[0034] In addition, an interactive function between the digital twin model and the construction plan of each sub-item is developed in the digital twin platform. After the interaction, the detailed information of the building components and steel bars under each sub-item can be viewed and operated, such as which building components are included in a certain sub-item, and the type, size, material and quantity of steel bars required for these building components.

[0035] Then, the digital twin model is developed in the digital twin platform to interact with the digital steel bar processing equipment, and data is sent or received through the hardware interface. Finally, a report generation function is developed to compare the steel bar processing in multiple dimensions.

[0036] At the same time, the digital twin platform adopts functional modularization and also supports the expansion of other functions.

[0037] Specifically, Figure 3 As shown in the figure, the specific steps to build a digital twin platform include: (A) 3D modeling is performed based on traditional design drawings. The steel bar design quantities in the drawings are then stored in a database according to the sub-items of each building component. The building components and their corresponding steel bar model information are dynamically bound in the database to create a digital twin model, which is convenient for the display and modification of building component and steel bar model information. The steel bar model information includes the steel bar diameter, size and design quantity.

[0038] (B) After creating the digital twin model, the digital twin platform can display the construction progress and the dynamic display of the steel bar design quantity and actual processing usage according to the input construction plan and actual construction percentage, and provides interactive functions to enable manual input or modification of data. The model quantity is completely consistent with the design quantity of the drawing. All places where quantity statistics are used in the entire project production process can be exported from the digital twin model. When the steel bar is re-sampled later, the key data such as the amount, size, shape, etc. of the steel bars required for each part of the time period can be directly extracted from the digital twin model, reducing the errors and manpower waste of manual statistics and improving efficiency.

[0039] (C) If Figure 4 As shown, the digital twin platform supports engineering personnel to input construction plans for sub-items or components. Based on the input construction plans, the sub-item construction plans in the building are obtained. The digital twin platform matches the digital twin model of the steel bars of the corresponding components to obtain the steel bar composition required for the sub-items of the planned construction. For example, the construction plan shows which building components are to be built, such as bridge piers or pile foundations, and then calculates the amount of steel bars required for the building components. The required amount of steel bars is extracted from the digital twin model. The amount of steel bars includes the type of steel bars, the size of the steel bars and the corresponding amount of steel bars used. After the amount is extracted, the remaining amount of steel bars is calculated, so that the feeding and cutting can be selected according to the remaining amount of steel bars, which is convenient for processing and production.

[0040] (D) If Figure 5 As shown in the figure, after the rebar cutting plan is generated, the rebar cutting plan is imported into the material list management subsystem. The material list management subsystem includes multiple sub-functions such as material list scheduling, review, and surplus material management. The material list management subsystem parses the required rebar cutting type, size, and quantity data according to the rebar cutting plan, then reads the surplus material inventory in the database, sets the raw material constraints and surplus material usage, calculates through the material cutting optimization algorithm, compares the material yield and surplus material usage, and selects the most suitable cutting plan for the project.

[0041] The digital twin platform displays different functions according to the permissions of the staff; staff with ordinary permissions can review the calculated material list after logging into the digital twin platform, and then add it to the review list. Managers with management permissions can review the material list added to the order list after logging into the digital twin platform. The reviewed material cutting plan will be added to the material order list. After production is completed, the steel bar inventory will be updated according to the returned data, and the steel bar digital twin model of the project management system will be refreshed. The complete material list approval and material cutting optimization mechanism can save surplus materials and improve production efficiency. According to the order list, the staff can place orders for the steel bars required by the steel bar processing plant.

[0042] (E) After data sorting, the sample plan completed in step D is used to obtain the number of steel bars, steel bar size, and steel bar shape that the current equipment needs to process; and it is sent directly to the digital mechanical processing equipment of the steel bar processing plant through the serial port, such as sending the number of steel bars to be processed to the steel bar CNC steel bar automatic feeder, and sending the steel bar cage that needs to be processed for the pile foundation to the fully automatic rolling cage welding workstation. After receiving the processing instructions, the processing equipment starts the steel bar processing and production. At the same time, the digital twin platform can send requests through the serial port to obtain the timed, daily or total steel bar processing data of the equipment, and store it as the actual amount of steel bar processing. For the surplus materials generated by production, on-site engineering personnel need to register them in time and enter the surplus materials on the digital twin platform.

[0043] The project management digital twin software platform of this embodiment, as a general platform for overall steel bar pattern making, material list generation, plan filling, progress control, and image display, can replace traditional manual solutions and output the optimal steel bar processing solution through real-time analysis of digital twin technology and data.

[0044] The platform can also send requests through the serial port to obtain the amount of steel bar processing on time, by day, or in total history. The platform can generate a comprehensive comparative analysis report on steel bar planning, processing, and surplus materials based on the digital twin steel bar model. First, the project management system uses digital twin technology to intuitively display all models of the project department. By clicking on the steel bar processing plant, the information introduction of the steel bar processing plant can be popped up, including the introduction of the steel bar processing plant, the capacity of the steel bar processing plant, the equipment composition of the steel bar processing plant, and the basic information such as steel bar in and out of the warehouse.

[0045] At the same time, by switching the perspective to jump to the inside of the steel bar processing plant, when you need to obtain the corresponding information, if it is the interaction with the steel bar processing equipment, you can quickly access the physical equipment through the serial port to know whether the equipment is currently running, the equipment's current day, the current day, and the historical processing status. Second, you can access the database corresponding to the model. The database is kept updated in real time, and the steel bar processing equipment is traversed through the serial port every day to extract and save data.

[0046] For the theoretical consumption and actual consumption that have been stored in the warehouse. For example, for a bridge, the comparison between the theoretical steel bar consumption and the actual steel bar consumption can be used to analyze the difference in steel bar construction, which can be used to trace the time and components that caused the deviation during the construction process and find out the reason for the difference. At the same time, the steel bar cost can be calculated based on the steel bar consumption, and a comprehensive cost analysis and settlement can be conducted with the budget to facilitate related financial analysis and report generation.

[0047] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for intelligent cutting and cutting of steel bars based on digital twins. It is characterized in that The following steps are involved: Create digital twin models of building components and reinforcements based on the construction plan for each part; Extracting the steel bar design quantity required for the construction plan from the digital twin model; the steel bar design quantity includes the steel bar type required to form the building component and the number of steel bars corresponding to the steel bar type; the steel bar type includes the steel bar shape and steel bar size; A steel bar cutting plan is generated according to the steel bar design quantity and the steel bar inventory, and processing and production are carried out according to the steel bar cutting plan.

2. According to the method of intelligent steel bar cutting and blanking based on digital twinning according to claim 1, It is characterized in that The steps of constructing the digital twin model include: generating a BIM model of a building component and a BIM model of a steel bar respectively, and binding the construction plan of each part with the BIM model of the building component required by the construction plan, and then binding the BIM model of the building component with the BIM model of the steel bar required to constitute the building component to construct the digital twin model.

3. According to claim 2, a method for intelligent cutting and blanking of steel bars based on digital twins, It is characterized in that By creating a sub-item construction plan table, a building component table and a component attribute table in a database, the binding of the building component BIM model and the steel bar BIM model, and the binding of the construction plan and the building component BIM model are achieved.

4. According to the method of intelligent cutting and blanking of steel bars based on digital twinning according to claim 3, It is characterized in that The detailed construction schedule includes the plan ID, project ID, component ID, construction team, cumulative completion volume, and actual concrete consumption.

5. According to claim 4, a method for intelligent cutting and blanking of steel bars based on digital twins, It is characterized in that The building component table includes the component ID, the project ID, the component code, the component name and the parent component ID.

6. According to claim 5, a method for intelligent cutting and blanking of steel bars based on digital twins, It is characterized in that The component attribute table includes a component attribute ID, the parent component ID, the component code and a component specific value.

7. According to claim 6, a method for intelligent cutting and blanking of steel bars based on digital twins, It is characterized in that The steps of generating the steel bar cutting plan include: Generate a steel bar sample drawing plan according to the steel bar design quantity, so as to analyze the required steel bar cutting type; The steel bar inventory and the steel bar cutting type are calculated and compared by using a cutting optimization algorithm to obtain the steel bar cutting plan; The indices for calculation and comparison include the amount of residual material and the residual material output rate.

8. According to claim 7, a method for intelligent cutting and blanking of steel bars based on digital twins, It is characterized in that When the construction plan of any sub-item is completed, the digital twin model is updated according to the steel bar usage in the construction plan of the sub-item, and the steel bar design quantity is updated synchronously.

9. A digital twin-based intelligent steel bar cutting system. It is characterized in that include: The data acquisition and processing module obtains the drawing data of the project building and its steel bars, and parses, classifies and stores the drawing data; A model building module is used to build a building component BIM model and a steel bar BIM model according to the information stored in the data acquisition and processing module, thereby building the digital twin model; A simulation analysis module performs simulation analysis on the digital twin model and outputs the steel bar cutting plan; A surplus material utilization module is used to design a surplus material utilization plan according to the steel bar cutting plan; The production execution module converts the steel bar cutting plan and the surplus material utilization plan into production execution instructions, and sends them to the automated steel bar processing equipment for production; The material management module stores and manages the steel bar materials used in each of the building components during the entire construction process.

Citation Information

Patent Citations

  • Reinforcement baiting matching method based on BIM technology

    CN107729662A

  • Method for editing and updating three-dimensional rebars

    CN107844677A

  • BIM-based prefabricated component rebar data processing method and device

    CN108427818A

  • A steel bar construction management method based on a BIM technology

    CN109726499A

  • Steel bar information full life cycle management method based on BIM technology

    CN109785436A

Cited By

  • Building pile structure calculation and analysis method and computer equipment

    CN121009722A