Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

100 results about "Framing (construction)" patented technology

Framing, in construction, is the fitting together of pieces to give a structure support and shape. Framing materials are usually wood, engineered wood, or structural steel. The alternative to framed construction is generally called mass wall construction, where horizontal layers of stacked materials such as log building, masonry, rammed earth, adobe, etc. are used without framing.

Self-anchorage type suspension bridge design and construction method adopting first cable later beam dynasty

The invention discloses a self-anchorage type suspension bridge design and construction method adopting a first cable later beam dynasty. The method includes the steps that (1), bridge towers and piers are constructed, and main beam anchoring sections are constructed; (2), temporary anchors are constructed, and temporary pintle cables are mounted; (3), main cables are erected, and the temporary pintle cables are tensioned synchronously; (4), main beam sections are hoisted, main cable saddles on the tops of the bridge towers are pushed, and the temporary pintle cables are tensioned; and (5), the main beams are formed into a whole, the temporary pintle cables are detached, and system conversion is completed. The method has the beneficial effects that force bearing is clear, monitoring is facilitated, and navigation below a bridge is not interrupted, the construction method is simple and convenient, and design and monitoring are facilitated. Compared with a construction method adopting afirst beam later cable construction method, the requirements of navigation below the bridge can be guaranteed, the temporary measures that full framing and temporary piers are erected in a riverway with a deep riverbed are avoided, the construction problems of a self-anchorage type suspension bridge which has high requirements on navigation below the bridge and is located at the deep position of the riverbed can be solved, and the competitiveness of the large-span self-anchorage type suspension bridge is further improved.
Owner:ZHEJIANG PROVINCIAL INST OF COMM PLANNING DESIGN & RES CO LTD

Framing demounting supporting structure of spandrelless arch bridge of over crossing operation highway and construction method

The invention relates to a framing demounting supporting structure of a spandrelless arch bridge of an over crossing operation highway. The supporting structure is characterized by being mainly composed of an intermediate support, a bowl-button full support, a full support spiral steel pipe support and a frame support; the intermediate support comprises two spiral steel pipes, a transverse rod and a shearing force support are welded between the spiral steel pipes, the bottoms of the spiral steel pipes and a strip foundation are anchored, and the tops of the spiral steel pipes and a bridge body are anchored through a U-shaped screw; the bowl-button full support is provided with a shearing force support, a top support and a small wood wedge block, and the small wood wedge block is plugged between the top support and the bridge body; the spiral steel pipe support is additionally arranged at the bowl-button full support; and the frame support is formed by box iron in a welded manner, a shearing force support is arranged inside the frame support, an arc-shaped top support is arranged at the top of the frame support, and a shearing force key of the arc-shaped top support is inserted into an arch bridge arch ring. The supporting structure has the beneficial effects of being safe and reliable in construction and high in stability, having no influences on normal traffic, and having the good economic and technological benefits.
Owner:西安市市政建设(集团)有限公司

Thermal and acoustic insulating and sealing system for a safing slot in a curtain wall

Described is a construction and parts of the construction for effectively thermally and acoustically insulating and sealing of a safing slot (1) between a floor (6) of a building and an exterior wall construction wherein the exterior wall construction comprises a curtain wall configuration (2) utilizing an interior panel module design. In particular, the thermal insulating and sealing system comprises a first element (7) comprising a top framing component (8) having an interior wall surface (13) and an opening, positioned substantially in the height of the floor (6), wherein the top framing component (8) is located on top of the interior wall surface (3) of the spandrel panel (7), and a second element (9) comprised of a thermally resistant and/or air tight material for insulating, positioned at least partially in the top framing component (8) of the first element (7), wherein the second element (9) includes an inner end surface (10) positionable in abutment with respect to the outer edge (11) of the floor (6) for sealing thereadjacent, outer end surface (12) positionable in abutment with respect the interior wall surface (13) of the top framing component (8), a lower facing surface (14) extending between the inner end surface (10) and the outer end surface (12) and facing downwardly therebetween, and an upper facing surface (15) extending between the inner end surface (10) and the outer end surface (12) and facing upwardly therebetween.
Owner:HILTI AG

Construction method applied to template supporting frame body based on BIM template integral installation technology

The invention discloses a construction method applied to a template supporting frame body based on a BIM template integral installation technology. The construction method comprises the following steps: S1, creating a BIM model; s2, outputting an automatic safety calculation book; s3, optimizing the BIM model; s4, performing one-key output on the construction drawing; s5, accurately calculating the quantity and generating a template matching list; s6, centralized processing and template numbering; s7, performing positioning and paying off; s8, erecting a full framing; s9, the formwork is hoisted; s10, carrying out vertical component steel bar installation and template supporting; s11, carrying out vertical component concrete pouring; s12, carrying out full framing inspection and acceptance; s13, installing a beam plate template; s14, binding beam steel bars; s15, carrying out checking and accepting; s16, carrying out horizontal component pouring; s17, carrying out concrete curing; and S18, removing the template. According to the method, BIM software is combined with related specifications to establish a template supporting frame body BIM model, mechanical calculation is conducted on a template supporting frame body, a template supporting frame body erecting plane graph, a large sample graph and the steel pipe and template material amount are output, a perfect template engineering planning scheme is compiled accordingly, and the management level and construction quality of template engineering are improved.
Owner:贵州建工集团第四建筑工程有限责任公司

Cast-in-place box girder construction system and construction method for excavation section of existing in-service line modified bridge

The invention provides a cast-in-place box girder construction system and construction method for an excavation section of an existing in-service line modified bridge. Stand columns of a stand columnpre-isolation structure are pre-buried in backfill soil of a foundation; a foam light soil pipe is positioned and sleeved on each stand column; tie beam side dies and tie beam bottom dies of a tie beam supporting structure are positioned on the outer side of a tie beam; the tie beam side dies are arranged between the stand columns, and two ends are respectively connected with the stand columns; the tie beam bottom dies are positioned and supported through low brackets and are used for realizing the positioning arrangement of tie beams; the lower portion of a box girder outer side die of a boxgirder formwork structure is located on a box girder bottom die through a supporting frame, and the upper portion is located through a pull rod assembly; and a box girder inner side die is positionedin the box girder outer side die. By arranging the stand column pre-isolation structure, the tie beam supporting structure and the box girder formwork structure, full framing and corresponding construction support formwork dismounting are not needed, more time and labor are saved, the construction period is greatly shortened, and the system is economical, practical and suitable for wide popularization.
Owner:ANHUI ROAD & BRIDGE GRP

Lining supporting system for tunnel framing reconstruction tunnel bottom structure and construction method thereof

The invention discloses a lining supporting system for a tunnel framing reconstruction tunnel bottom structure and a construction method thereof. The supporting system comprises an inverted arch lining, a primary support, steel flower tube lock feet, a blocking isolation wall and a pre-reinforcing pile, wherein the inverted arch lining and the primary support are arranged at the tunnel bottom, thesteel flower tube lock feet are driven into surrounding rock from side walls on the two sides, and the blocking isolation wall and the pre-reinforcing pile are positioned above and below a central ditch correspondingly; the inverted arch lining comprises two half-range inverted arch linings which are symmetrically arranged in the transverse direction of a tunnel; the primary support comprises twohalf-range primary supports which are symmetrically arranged in the transverse direction of the tunnel; and the pre-reinforcing pile is fixedly connected with the two half-range inverted arch liningsand the two half-range primary supports. According to the lining supporting system for the tunnel framing reconstruction tunnel bottom structure and the construction method thereof, the risk of framing reconstruction of the tunnel bottom structure in the operating state of the tunnel is reduced in the form of framing excavation and framing support, the operation time of reconstruction of the tunnel bottom structure can be not limited, the overhead reinforcing procedure of a steel cushion beam is omitted, interference to a track structure is reduced, and the construction progress in the operating state can be greatly improved on the premise of ensuring safety.
Owner:CHINA RAILWAY ERYUAN ENG GRP CO LTD

Overload small-clear-distance beam adjustable disc buckle formwork supporting frame and construction method thereof

The invention discloses a super-load small-distance beam adjustable ring buckle formwork supporting frame and a construction method thereof.The super-load small-distance beam adjustable ring buckle formwork supporting frame comprises a ring buckle type scaffold, a full framing arranged on the ring buckle type scaffold, a full framing adjustable jacking and a wooden box, and the full framing adjustable jacking and the wooden box are arranged on the full framing and used for supporting a beam body; the concrete pouring bodies are poured between the adjacent beam bodies, and the bottoms of the concrete pouring bodies abut against the full framing. The construction method comprises the steps of erecting the ring-lock type scaffold, erecting the full framing and erecting the overload small-clear-distance inter-beam supporting structure. The technical problems that the erecting working condition of a beam body supporting frame cannot meet the modular space requirement of the ring-lock type scaffold, and the formwork mounting quality is affected due to insufficient side formwork reinforcing operation space caused by complex main body structures or large-density beam body distribution of a transfer layer are mainly solved.
Owner:CHINA MCC5 GROUP CORP

Structure beam plate back-to-top reinforcing method

PendingCN113482394ASolving Temporary Reinforcement IssuesSimple structureBuilding repairsBasementArchitectural engineering
The invention relates to the field of buildings, and provides a structural beam plate back-to-top reinforcing method. The structural beam plate back-to-top reinforcing method comprises the following steps that a to-be-reinforced floor arranged in a back-to-top zone area and a corresponding position on the to-be-reinforced floor are preliminarily determined according to a load on a structural beam plate, and a back-to-top supporting assembly is arranged below the back-to-top zone area; a back-to-top overall model is established; the bearing capacity of the structural beam plate is judged according to a model calculation result; if the bearing capacity is insufficient, the setting number of the back-to-top zone areas is continuously increased on the same floor and/or the setting number of the back-to-top zone areas is increased on the next floor, and then re-modeling is carried out until the bearing capacity meets the preset requirement; and setting of the final back-to-top zone area is determined, and construction of the back-to-top supporting assembly of the corresponding area is completed. A basement top plate is divided into a plurality of span plates by providing the back-to-top zone, the plate span of the basement top plate is reduced, the bearing capacity of the basement top plate is improved, a large number of full framing does not need to be erected, and therefore the construction cost is reduced, and the construction efficiency is improved.
Owner:中建三局集团(深圳)有限公司

Large-gradient special-shaped sloping roof concrete construction system and construction method thereof

The invention provides a construction method of a large-gradient special-shaped sloping roof concrete construction system. The construction method of the large-gradient special-shaped sloping roof concrete construction system comprises the following steps that a full framing system is built firstly, then a bottom formwork and an outer formwork are erected, and the outer formwork is reinforced; a double-formwork structure is adopted, a vibration space facilitating vibration of a direct inserted type vibration rod is formed in a steel bar system, an inclined roof panel formed after casting is clamped between the bottom formwork and the outer formwork, the bottom formwork and the outer formwork can enable the surface flatness of the inclined roof panel to be good, the honeycomb and pitted surface phenomena do not exist, and the inclined roof panel is well connected with a connecting position. According to the large-gradient special-shaped sloping roof concrete construction system, the arrangement of pre-embedded supporting pieces particularly facilitates the arrangement of the steel bar system and the placement and fine adjustment of a whole top formwork; meanwhile, in order to ensure the vibration effect of the inserted type vibration rod, radians are intermittently arranged on transverse steel bars in the steel bar system.
Owner:THE FIRST COMPARY OF CHINA EIGHTH ENG BUREAU LTD

Combined cast-in-place box girder support structure and construction method thereof

The invention provides a combined cast-in-place box girder support structure. The combined cast-in-place box girder support structure comprises a prestressed pipe pile foundation, a steel pipe column, a formwork and a roadbed, wherein multiple sets of prestressed pipe pile foundations are distributed in a soft foundation in an array mode, lower ends of the prestressed pipe pile foundations penetrate into a fully-weathered granite layer, and a concrete bearing platform is arranged at an upper end of each set of prestressed pipe pile foundation; each steel pipe column is fixed on one concrete bearing platform, and a bearing beam is fixed on each row of steel pipe columns; a plurality of bailey trusses are lapped on the bearing beams, and a plurality of distribution beams are transversely carried on the bailey trusses; the formwork comprises a bottom plate and side plates, a plurality of square timbers are arranged between the bottom plate and the distribution beams in the bridge direction, and side formwork supporting frames are arranged between the side plates and the distribution beams; the roadbed is located on the hard ground, a bowl-buckle-type full framing is built on the roadbed, a jacking plate is arranged on the upper portion of the bowl-buckle-type full framing, and a plurality of square timbers are arranged between the jacking plate and a bottom plate and a side plate of the formwork in the bridge direction. The invention further provides a construction method of the combined cast-in-place box girder support.
Owner:中交二公局第六工程有限公司

Thermal and acoustic insulating and sealing system for a safing slot in a curtain wall

Described is a construction and parts of the construction for effectively thermally and acoustically insulating and sealing of a safing slot (1) between a floor (6) of a building and an exterior wall construction wherein the exterior wall construction comprises a curtain wall configuration (2) utilizing an interior panel module design. In particular, the thermal insulating and sealing system comprises a first element (7) comprising a top framing component (8) having an interior wall surface (13) and an opening, positioned substantially in the height of the floor (6), wherein the top framing component (8) is located on top of the interior wall surface (3) of the spandrel panel (7), and a second element (9) comprised of a thermally resistant and / or air tight material for insulating, positioned at least partially in the top framing component (8) of the first element (7), wherein the second element (9) includes an inner end surface (10) positionable in abutment with respect to the outer edge (11) of the floor (6) for sealing thereadjacent, outer end surface (12) positionable in abutment with respect the interior wall surface (13) of the top framing component (8), a lower facing surface (14) extending between the inner end surface (10) and the outer end surface (12) and facing downwardly therebetween, and an upper facing surface (15) extending between the inner end surface (10) and the outer end surface (12) and facing upwardly therebetween.
Owner:HILTI AG

Cast-in-place box girder spanning cavern method for karst tunnel

The invention belongs to the technical field of box girder spanning cavern construction, and discloses a cast-in-place box girder spanning cavern method for a karst tunnel, which comprises the following steps of treating a foundation; erecting a bracket; mounting an outer side mold; binding bottom and web steel bars; threading the steel strands; mounting an inner mold; binding top plate reinforcing steel bars; pouring concrete; carrying out surface finishing and maintenance; conducting pre-tensioning and initial tensioning; removing the template and the bracket; performing final tensioning andmud jacking; adopting a full framing method for construction; the bottom die, the outer die and the inner die are all wood dies, the inner supports are pulled outwards, and tie bars are arranged at the beam bottom and the beam top for reinforcement; concrete pouring adopts centralized stirring of a mixing station, a tank truck transports the concrete to a construction site, and a delivery pump truck pours the concrete; the full framing foundation is locally filled with tunnel hole slag, a water passing channel is reserved, and the foundation is hardened by C20 concrete by 30 cm. The method isconvenient to construct, durable, convenient to maintain, small in investment scale, good in universality and high in economic benefit; obvious stress concentration cannot be generated at the periphery, and a new fatigue risk source is prevented from being introduced.
Owner:中铁二十局集团第三工程有限公司

Solid-web arch bridge system spliced by UHPC prefabricated corrugated plate sections and construction method

PendingCN112813794AGive full play to high-strength tensile and compressive propertiesEven by forceBridge erection/assemblyArch-type bridgeEpoxyArchitectural engineering
The invention discloses a solid-web arch bridge system spliced by UHPC prefabricated corrugated plate sections and a construction method. The arch bridge system comprises a strip-shaped concrete foundation arranged on foundation soil, two arch seats provided with reinforced ultra-high performance concrete (RUHPC) tie bars, segment assembled UHPC corrugated plate arch rings arranged on the arch seats, side wall foundations, side walls built by concrete precast blocks, arch filler and concrete side wall coping. The UHPC corrugated plate arch ring is prefabricated in a segmented mode through UHPC, and all the prefabricated segments are spliced into a whole through finish rolling twisted steel and epoxy resin mortar. The UHPC corrugated plate main arch ring is firstly pre-assembled, hoisting construction is adopted after pre-assembly is qualified, and after the main arch ring is hoisted in place, main arch ring folding and on-arch building construction are conducted on the full framing. The prefabricated RUHPC tie bars and the strip-shaped concrete foundation are adopted, the arch foot thrust can be balanced, the work amount of the lower structure can be remarkably reduced, the damage of excavation to the environment is reduced, and the adaptability to the fragile ecological environment area is enhanced.
Owner:CHANGAN UNIV

Underground excavation station arch bridge type arc-shaped middle plate construction method

The invention provides an underground excavation station arch bridge type arc-shaped middle plate construction method. According to the method, arch bridge type arc-shaped middle plate construction isdivided into a plurality of construction sections, and for each construction section, the following steps of S1), completing arch excavation of a station and lining construction of an arch cover; S2), completing excavation construction of the lower cross section of a station main body by adopting a step method, and completing structural construction of an inverted arch and parts of the side wallsin side walls; S3), erecting formworks of the remaining parts of the side walls, and binding steel bars in the formworks of the remaining parts of the side walls; S4), erecting formwork supports of an arc-shaped middle plate by adopting a full framing, erecting a formwork of the arc-shaped middle plate on the top surfaces of the formwork supports, and binding steel bars in the formwork of the arc-shaped middle plate; S5), sequentially pouring the formworks of the remaining parts of the side walls and the formwork of the arc-shaped middle plate; S6), erecting formworks of straight section axillary angle supports of rail top air duct parts of the arc-shaped middle plate on the top face of the arc-shaped middle plate and the top faces of the remaining side walls; and S7), pouring the formworks of the straight section axillary angle supports to form straight section axillary angle supports are included.
Owner:CHINA RAILWAY 12TH BUREAU GRP +1

Box culvert construction assembly, application thereof and box culvert construction method

The invention discloses a box culvert construction assembly, application of the box culvert construction assembly and a box culvert construction method, and belongs to the technical field of buildings. The assembly comprises a full framing, a supporting beam, a plurality of steel formworks, pulleys and sliding rails. The plurality of steel formworks are used for being assembled into a box culvert inner formwork frame matched with a preset box culvert in shape, and the full framing is erected in the box culvert inner formwork frame and connected with the inner walls of the steel formworks; the supporting beam is longitudinally connected to the top of the full framing and connected with the steel formwork at the same time, the sliding rail is laid at the bottom of the full framing in the length direction of the preset box culvert, and the pulley is connected with the supporting beam and used for sliding along the sliding rail. By adopting the box culvert construction assembly to conduct box culvert construction, the problems that in the prior art, an inner mold needs to be disassembled and assembled multiple times, consequently, carrying and installation are not changed, a steel formwork deforms, and a wood formwork is broken can be effectively solved, and the construction cost is reduced and the construction efficiency is improved while the construction quality is guaranteed.
Owner:新疆路桥建设集团有限公司

Single-arch-rib framing swivel construction steel box arch bridge and construction method thereof

The invention belongs to the technical field of arch bridge construction, and relates to a single-arch-rib framing swivel construction steel box arch bridge and a construction method thereof. The archbridge comprises a lower rotating disc located on a foundation, a horizontal rotating system fixedly installed on the lower rotating disc, an upper rotating disc installed on the horizontal rotatingsystem in a rotating mode, two sets of bridge deck longitudinal beams fixed to the upper rotating disc, and a vertical rotating hinge installed on the inner side of the upper rotating disc and used for fixing an arch rib to be constructed. The upper rotating disc, the lower rotating disc and arch ribs are arranged in a left-right framing manner, transverse supports and inter-rib cross beams are arranged between the left framing arch rib and the right framing arch rib, a suspender cross beam is fixedly mounted between the bridge deck longitudinal beams, suspenders are arranged at equal intervals along the longitudinal direction of each arch rib, the upper ends of the suspenders are anchored to the arch ribs, the lower ends of the suspenders are anchored to the suspender cross beams, a plurality of secondary cross beams are arranged between the suspender cross beams, and the suspenders, the suspender cross beams, the secondary cross beams and the bridge deck longitudinal beams are connected to form a lattice system in order to construct a bridge deck framework. The construction method guarantees the construction quality of the arch bridge, reduces safety risks and construction cost,and achieves convenient construction.
Owner:重庆高速工程顾问有限公司 +2
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products