Engineering project intelligent management method and system

By arranging monitoring piles and intelligent mapping modules in the construction area, combined with the induction device on the safety helmet, the location and progress of the construction workers are monitored in real time, which solves the problem of dynamic management complexity during the construction phase and improves construction efficiency and safety.

CN118780759APending Publication Date: 2024-10-15CHINA ROAD & BRIDGE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410935209.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Dynamic management during the construction phase is complex, and it is difficult for traditional manual management to grasp the project progress and safety in real time, especially when the designs are different, the types of work are diverse, and the progress is different, making it difficult to improve construction efficiency and safety.

Method used

Adopting smart construction site management methods, by arranging monitoring piles and setting up sensing and alarm devices in the construction area, combined with intelligent mapping modules and sensing devices on safety helmets, the location and progress of construction workers can be monitored in real time, and a standardized construction route area can be generated, and Provide timely feedback on construction status.

Benefits of technology

It achieves precise management and safety supervision of the construction site, improves construction efficiency and safety, ensures that construction personnel work in appropriate areas, prevents unauthorized personnel from entering, and provides timely feedback on construction progress and status.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780759A_ABST
    Figure CN118780759A_ABST
Patent Text Reader

Abstract

The invention discloses an engineering project intelligent management method and system, and the method comprises the steps: drawing a construction region range, laying a monitoring pile, and enabling the monitoring pile to be provided with a first induction device and a first alarm device; the positions and the number of the monitoring piles are correspondingly supplemented and adjusted according to the current construction progress and the unit construction project; generating a standard construction route area range of all constructors of the unit construction project; a second sensing device, a positioning device and corresponding identification information are arranged on the safety helmet, and the positioning device sends out positioning information after the second sensing device is connected with the first sensing device; when the positioning information exceeds the standard construction route area range, a first alarm device is triggered; the construction state is fed back until the unit construction project is completed; and repeating until the whole project construction is completed. The system comprises an intelligent drawing module, a first sensing device, a communication interaction module and the like. The method has the advantages that constructors are supervised and prevented from entering non-safe areas, and construction efficiency and safety supervision capability are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of smart construction site engineering technology, and more specifically, to a smart management method and system for engineering projects. Background Art

[0002] Project management refers to the process of using specialized knowledge, skills, tools and methods in project activities to enable the project to achieve or exceed the set requirements and expectations under the conditions of limited resources. Project management is the overall monitoring and control of some activities related to the successful achievement of a series of goals. In the project management construction process, the construction stage has a particularly important position. The construction stage is the stage of converting the design into the project. The construction stage is the stage with the most investment and the most resources required. The construction stage takes the longest time, so it is necessary to face the changes brought by time, and the changes require dynamic management. Therefore, it is necessary to grasp the dynamics of the project construction stage in real time, but due to the complex situation on the construction site, the construction personnel are very different, and there are many types of construction work, traditional manual management is gradually at a disadvantage. Now the application of smart construction sites is born. Smart construction sites use information technology to accurately design and control construction projects through platforms, and establish the Internet of Things to improve the level of information technology in engineering management. Therefore, the present invention is aimed at different designs, different construction projects, different types of construction personnel, different construction progress and other multi-faceted factors for intelligent management to improve project construction efficiency and safety. Summary of the invention

[0003] An object of the present invention is to solve at least the above problems and to provide at least the advantages which will be described hereinafter.

[0004] In order to achieve these purposes and other advantages according to the present invention, a method for intelligent management of engineering projects is provided, comprising the following steps:

[0005] S1. Determine the construction area of ​​the entire project according to the project address and project design drawings, and deploy multiple monitoring piles within the construction area, each monitoring pile being a monitoring point. Then deploy monitoring piles at the construction site according to the construction area and the location of the monitoring piles, and set a first sensing device and a first alarm device on the monitoring piles.

[0006] S2. According to the construction plan, the current construction progress and one or more unit construction projects to be constructed are obtained, and the positions and quantities of monitoring piles are supplemented and adjusted accordingly on the project design drawings according to the current construction progress and the unit construction projects, and then monitoring piles are arranged at corresponding positions on the construction site, and a first sensing device and a first alarm device are set on the monitoring piles;

[0007] S3. Generate the standard construction route area of ​​all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles;

[0008] S4, assigning a safety helmet to each construction worker according to each unit construction project, wherein the safety helmet is provided with a second sensing device, a positioning device and identification information corresponding to the unit construction project and the construction worker. After being started, the second sensing device senses the first sensing device on the monitoring pile near it at a preset frequency, and the positioning device sends positioning information after the connection is established;

[0009] S5, drawing a dot-dash line diagram in chronological order according to the positioning information to form a trajectory route of the corresponding construction personnel; wherein, when the positioning information exceeds the standard construction route area generated in step S3, the first alarm device on the nearest monitoring pile is triggered to send out a first warning message;

[0010] S6. Feedback the construction status of each unit construction project according to the preset time node until the unit construction project is completed;

[0011] S7. Repeat steps S2 to S6 until the entire project is completed.

[0012] Preferably, the method further includes: dividing the standard construction route area in step S3 into multiple unit areas, and assigning a unit value to a unit area when a construction worker stays in the unit area for a unit time; and calculating the unit value of each unit area in the corresponding standard construction route area according to the dot-dash line diagram of each construction worker.

[0013] Preferably, a second alarm device is provided on the safety helmet, and the second sensing device senses the position of the construction worker's head at a preset frequency. When it senses that the safety helmet is separated from the construction worker's head, the second alarm device sends out a second warning message.

[0014] Preferably, the second sensing device comprises a radio frequency tag, and the radio frequency tag carries identification information corresponding to the unit construction project and the construction personnel;

[0015] The first sensing device includes a radio frequency tag identifier, and the radio frequency tag identifier can identify multiple radio frequency tags at the same time;

[0016] The positioning device is a GPS positioning module, which is communicatively connected with the first sensing device;

[0017] The first alarm device includes a voice announcer.

[0018] Preferably, the second sensing device includes a human infrared sensor, which is arranged on the inner wall of the safety helmet. The human infrared sensor detects at a preset frequency, and when no human body is detected, the second alarm device is triggered.

[0019] Preferably, a solar charging panel is provided on the rear outer side wall of the safety helmet, and the solar charging panel supplies power to the second sensing device, the positioning device and the second alarm device.

[0020] Provide an engineering project intelligent management system, including:

[0021] An intelligent mapping module, which is used to draw the construction area of ​​the entire project according to the project address and the project design drawings, and mark the positions of multiple monitoring piles within the construction area; wherein each monitoring pile is a monitoring point, and the monitoring pile is provided with a first sensing device and a first alarm device; and,

[0022] Used to obtain the current construction progress and one or more unit construction projects to be constructed according to the construction plan, and to supplement and adjust the position and quantity of monitoring piles on the project design drawings accordingly according to the current construction progress and unit construction projects; and,

[0023] It is used to generate the standard construction route area range for all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles, and mark it on the project design drawings;

[0024] A plurality of safety helmets, each of which is provided with a second sensing device, a positioning device, a second alarm device and identification information corresponding to a unit construction project and a construction worker. After being started, the second sensing device senses the first sensing device on a monitoring pile near it at a preset frequency, and the positioning device sends out positioning information after a connection is established; and the second sensing device senses the position of the construction worker's head at a preset frequency, and when it senses that the safety helmet is off the construction worker's head, the second alarm device sends out a second warning information;

[0025] The intelligent mapping module draws a dot-dash line diagram in chronological order according to the positioning information to form a corresponding trajectory route of the construction personnel; when the positioning information exceeds the scope of the standard construction route area, the first alarm device on the nearest monitoring pile is triggered to send out a first warning message;

[0026] A data processing module, which is used to determine whether the positioning information is within the corresponding standard construction route area according to the identification information, and if not, trigger the first alarm device;

[0027] A plurality of communication interaction modules, which are used for information interaction among the intelligent mapping module, the first sensing device, the first alarm device, the second sensing device, the positioning device, the second alarm device, and the storage module;

[0028] The communication interaction module feeds back the construction status of each unit construction project according to the preset time node until the unit construction project is completed;

[0029] A storage module is used to store the project address information, the project design drawings, the construction plan, the construction progress, the construction projects of each unit, the map drawn by the intelligent mapping module, the information processed by the data processing module and the interactive information of the communication interaction module.

[0030] Preferably, the intelligent mapping module divides the standard construction route area into multiple unit areas, and if a construction worker stays in a unit area for a unit time, a unit value is assigned to the unit area; the unit value of each unit area in the corresponding standard construction route area is calculated based on the dot-dash line diagram of each construction worker.

[0031] An electronic device is provided, comprising:

[0032] one or more processors;

[0033] Memory; and

[0034] One or more programs, wherein the one or more programs are stored in the memory and configured to be executed by the one or more processors, the programs including instructions for executing the above method.

[0035] A computer-readable storage medium is provided, characterized in that it stores a computer program used in combination with an electronic device, and the computer program can be executed by a processor to implement the above method.

[0036] The present invention has at least the following beneficial effects:

[0037] First, the intelligent mapping module is used to draw online based on the project address and project design drawings, and then the corresponding monitoring piles are set up at the construction site to synchronize the information between the site and the intelligent mapping module, which is convenient for accurate management and control. Since the design and implementation of the specific plan may be adjusted during the process from the preparation to the final completion of the project, and with the completion of each unit construction project, the layout within the construction area is constantly changing, and the movable area and key monitoring points are also constantly changing. Therefore, the monitoring piles are roughly set according to the overall project design drawings for overall supervision.

[0038] Second, the entire project is divided into multiple unit construction projects which are carried out in an orderly manner. After each unit construction project is completed or a node of a unit construction project is completed according to the construction plan, timely records and feedback are made to update the construction progress and project design drawings; and the construction plan is also matched and optimized according to the actual construction progress; thus, before construction, the construction progress and the specific conditions of the unit construction projects to be constructed are obtained according to the construction plan, and the construction area is more finely defined on the project design drawings (the project design drawings have been updated according to the construction progress), and monitoring piles are arranged within the construction area, so as to carry out targeted and precise supervision of the entry and exit activities of personnel of the corresponding project.

[0039] Third, each unit construction project has a corresponding standardized construction scope, such as the construction material storage area, machinery operation area, construction installation area, raw material transportation route, etc. According to the actual construction progress and unit construction project needs, a standardized construction route area needs to be planned, and this standardized construction route area is formed by the distribution of monitoring piles. At the same time, the construction personnel of the unit construction project are staffed and the access rights are set to include them in the supervision.

[0040] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 It is a flow chart of the intelligent management method of the present invention. DETAILED DESCRIPTION

[0042] The present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.

[0043] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the orientation or positional relationship indicated by the terms is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0044] like Figure 1 As shown, the present invention provides a method for intelligent management of engineering projects, comprising the following steps:

[0045] S1. According to the project address and project design drawings, the construction area of ​​the entire project is defined, and multiple monitoring piles are arranged within the construction area. Each monitoring pile is a monitoring point. Then, according to the construction area and the location of the monitoring pile, a physical monitoring pile is arranged at the corresponding position of the construction site, and a first sensing device and a first alarm device are set on the monitoring pile. Each monitoring pile is a base point, and the positions of all monitoring piles form a monitoring network, which can accurately mark and reflect the positions of the construction area. The construction area of ​​the entire project is a closed area, and non-project personnel are prohibited from entering. It can usually be closed by installing fences, leaving a dedicated entrance and exit. Through the intelligent mapping module, the project address and project design drawings are first drawn online, and then the corresponding monitoring piles are arranged at the construction site, so that the site and the intelligent mapping module information are synchronized, which is convenient for accurate management and control. Since the design and implementation of the specific plan may be adjusted during the process from the preparation to the final completion of the project, and with the completion of each unit construction project, the layout within the construction area is constantly changing, and the movable area and key monitoring points are also constantly changing. Therefore, the monitoring piles are roughly set according to the overall project design drawings for overall supervision. The supervision method relies on the first sensing device and the first alarm device. The first sensing device is used to identify the basic information of the construction personnel who are sensed to the monitoring range of the corresponding monitoring pile (basic information, for example, includes the personal information of the construction personnel, the name of the unit construction project currently in charge, the type of work in charge, the number of the construction personnel to whom they belong, etc.). The specific implementation method of the first sensing device can be a high-definition camera with an infrared capture function, which takes pictures of the construction personnel entering its monitoring range, and analyzes whether it matches the facial information stored in the system through the data processing module. If not, the first alarm device is triggered. The alarm method of the first alarm device can be sound and information, such as directly issuing a voice broadcast reminder, such as sending an information prompt to the corresponding management personnel, so that unauthorized personnel can be known in time to break into the construction site. Since the location of each monitoring pile is known, if the unauthorized personnel is an external personnel (not a construction personnel of this project), the specific location of the unauthorized personnel can be quickly and accurately determined, so that the management personnel can quickly and accurately drive them away. If the unauthorized person is an internal staff member (a construction worker of this project, but does not have the authority to enter this area), their communication information can also be obtained, and reminders such as phone or video can be made to let them leave quickly. The number, time, and specific location of the unauthorized person's illegal entry into other areas can also be recorded for later statistical management, and key supervision can be carried out on those who have violated the rules many times.

[0046] S2. According to the construction plan, the current construction progress and one or more unit construction projects to be constructed are obtained, and the position and number of monitoring piles are supplemented and adjusted accordingly on the project design drawings according to the current construction progress and unit construction projects, and then monitoring piles are arranged at corresponding positions on the construction site, and a first sensing device and a first alarm device are set on the monitoring piles; the entire project is divided into multiple unit construction projects and carried out in an orderly manner, and after each unit construction project is completed or a node of a unit construction project is completed according to the construction plan, records and feedback are made in a timely manner to update the construction progress and project design drawings; and the construction plan is also matched and optimized according to the actual construction progress; so that before construction, the construction progress and the specific conditions of the unit construction projects to be constructed are obtained according to the construction plan, and the construction area is more finely drawn on the project design drawings (the project design drawings that have been updated according to the construction progress), and monitoring piles are arranged within the construction area, so as to carry out targeted and precise supervision of the entry and exit activities of personnel of the corresponding project.

[0047] S3. Generate the standard construction route area for all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles; each unit construction project has a corresponding standard construction scope, such as construction material storage area, machinery operation area, construction installation area, raw material transportation route, etc. According to the actual construction progress and unit construction project, the standard construction route area needs to be planned, and this standard construction route area is formed by the monitoring pile layout. At the same time, the construction personnel of the unit construction project are staffed and the access rights are set to be included in the supervision. The reason for dividing the standard construction route area for each construction personnel separately is that there are some special projects that can only be implemented by personnel with technical qualifications, and when personnel without technical qualifications enter the corresponding area, it will cause safety hazards.

[0048] S4. Allocate a safety helmet to each construction worker according to each unit construction project. The safety helmet is provided with a second sensing device, a positioning device and identification information corresponding to the unit construction project and the construction worker. After startup, the second sensing device establishes a connection with the first sensing device on the monitoring pile near it according to a preset frequency, and after the connection is established, the positioning device is triggered to send positioning information; different unit construction projects are assigned different safety helmets (they can be distinguished by setting different colors and numbers on site, and distinguished by identification information online); the identification information includes the basic information of the construction workers and the scope of the standard construction route area, etc.; a second sensing device is set on the safety helmet, and the second sensing device is used to match with the first sensing device to generate interconnection, so that when the construction worker wearing the safety helmet enters the coverage area of ​​the monitoring pile, he can be quickly and accurately identified, and the corresponding identification information and the positioning information fed back by the positioning device are read and transmitted to the data processing module, and the data processing module determines whether the positioning information is within the corresponding standard construction route area based on the identification information (standard construction route area), and if not, the first alarm device is triggered.

[0049] A specific implementation method may be: the second sensing device includes a radio frequency tag, and the radio frequency tag carries identification information corresponding to the unit construction project and the construction personnel;

[0050] The first sensing device includes a radio frequency tag identifier, and the radio frequency tag identifier can identify multiple radio frequency tags at the same time;

[0051] The positioning device is a GPS positioning module, which is communicatively connected with the first sensing device;

[0052] The first alarm device includes a voice announcer and an information transmitter.

[0053] Because the high-definition cameras in the prior art are expensive, the project construction area is large, and the number required is too large, and more importantly, when the construction workers wear safety helmets, it will affect the recognition accuracy of the high-definition camera, and when multiple construction workers appear in the same area at the same time, the high-definition camera cannot quickly identify multiple construction workers at the same time, and when the construction workers face different directions or bow their heads, it is even more difficult for the high-definition camera to identify all the construction workers entering the area. Therefore, the present invention uses a second sensing device configured to include a radio frequency tag, and the first sensing device is configured to be a radio frequency tag identifier, so that all construction workers (radio frequency tags on safety helmets) within the area (radio frequency range) can be quickly and accurately identified, and supervision can be carried out based on the identification information.

[0054] S5. Draw a dot-dash line diagram in chronological order based on the positioning information to form the trajectory route of the corresponding construction personnel; it can more intuitively reflect the trajectory of each construction personnel during the construction process, and provide a data basis for the later analysis of construction efficiency. When the construction personnel are within the supervision range of multiple overlapping monitoring piles, the data processing module selects to trigger the first alarm device on the monitoring pile closest to the corresponding positioning device.

[0055] S6. Feedback the construction status of each unit construction project according to the preset time nodes until the unit construction project is completed; according to the specific unit construction project situation, such as the key construction nodes of the project, such as when the work is stopped due to weather reasons, such as when the construction task of the day is completed, timely and accurate feedback on the construction status is given, and dangerous areas are drawn in time to synchronize the online information of the construction site with the intelligent mapping module, so as to provide an accurate basis for subsequent construction plans, improve construction efficiency, and enhance safety supervision capabilities.

[0056] S7. Repeat steps S2 to S6 until the entire project is completed.

[0057] In the above technical scheme, the construction area of ​​the entire project is first defined according to the project address and design drawings to form a closed construction area, and then monitoring piles are marked on the design drawings according to the design drawings within the construction area, and monitoring piles are correspondingly laid out in the construction area to form a monitoring network; then, according to the construction progress and the construction plan, the corresponding construction areas of the unit construction projects are accurately defined and monitoring piles are accurately laid out; then, construction personnel are assigned to each unit project, and safety helmets are used for accurate distinction, and the standard construction route area of ​​each construction personnel is defined; then, according to the standard construction route area, the construction personnel entering the monitoring pile supervision range are identified and judged, and if they exceed the standard construction route area, the first alarm device is triggered. It can realize real-time supervision of the construction position of each construction personnel, prevent construction personnel from entering unsafe areas, etc., and improve construction efficiency and safety supervision capabilities.

[0058] In another technical solution, it also includes: dividing the standard construction route area in step S3 into multiple unit areas, and assigning a unit value to the unit area when the construction workers stay in the unit area for a unit time; and calculating the unit value of each unit area in the corresponding standard construction route area according to the dot-dash line diagram of each construction worker.

[0059] In the above technical solution, the main construction position of each construction worker can be intuitively reflected, thereby providing a basis for analyzing the construction efficiency of the construction workers.

[0060] In another technical solution, a second alarm device is also provided on the safety helmet. The second sensing device senses the position of the construction worker's head at a preset frequency. When it senses that the safety helmet is separated from the construction worker's head, the second alarm device sends out a second warning message.

[0061] In the above technical solution, for the sake of safety, it is ensured that the construction workers wear safety helmets as required after entering the construction area. At the same time, it is also prevented that the construction workers take off the safety helmets and put them in the area of ​​the standardized construction route to evade supervision, but the construction workers have actually left. Therefore, a second sensing device and a second alarm device are set on the safety helmet, which can identify whether the safety helmet is worn on the head of the construction worker. If not, the second alarm device is triggered. The alarm mode of the second alarm device can be set to send information or voice reminders to the direct superior of the construction worker, send information or voice reminders to the construction worker himself, etc. A specific implementation method can be: the second sensing device includes a human infrared sensor, which is set on the inner wall of the safety helmet. The human infrared sensor detects at a preset frequency. When no human body is detected, the second alarm device is triggered.

[0062] In another technical solution, a solar charging panel is provided on the rear outer side wall of the helmet, and the solar charging panel supplies power to the second sensing device, the positioning device and the second alarm device. Since the construction process is mostly outdoors, the solar charging panel can make full use of the advantages of outdoor work, obtain enough solar energy, reduce the extra charging time of the helmet, and improve the use efficiency of the helmet.

[0063] The present invention provides an engineering project intelligent management system, comprising:

[0064] An intelligent mapping module, which is used to draw the construction area of ​​the entire project according to the project address and the project design drawings, and mark the positions of multiple monitoring piles within the construction area; wherein each monitoring pile is a monitoring point, and the monitoring pile is provided with a first sensing device and a first alarm device; and,

[0065] Used to obtain the current construction progress and one or more unit construction projects to be constructed according to the construction plan, and to supplement and adjust the position and quantity of monitoring piles on the project design drawings accordingly according to the current construction progress and unit construction projects; and,

[0066] It is used to generate the standard construction route area range of all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles, and mark it on the project design drawings;

[0067] Among them, physical monitoring piles are arranged at corresponding positions on the construction site according to the scope of the construction area and the positions of monitoring piles, and a first sensing device and a first alarm device are set on the monitoring piles; each monitoring pile is a base point, and the positions of all monitoring piles form a monitoring network, which can accurately mark and reflect the positions within the scope of the construction area; through the intelligent mapping module, online drawing is first performed based on the project address and project design drawings, and then corresponding monitoring piles are arranged at the construction site, so that the site information is synchronized with the intelligent mapping module information, which is convenient for accurate management and control.

[0068] A plurality of safety helmets, each of which is provided with a second sensing device, a positioning device, a second alarm device and identification information corresponding to a unit construction project and a construction worker. After being started, the second sensing device senses the first sensing device on a monitoring pile near it at a preset frequency, and the positioning device sends out positioning information after a connection is established; and the second sensing device senses the position of the construction worker's head at a preset frequency, and when it senses that the safety helmet is off the construction worker's head, the second alarm device sends out a second warning information;

[0069] The intelligent mapping module draws a dot-dash line diagram in chronological order according to the positioning information to form a corresponding trajectory route of the construction personnel; when the positioning information exceeds the scope of the standard construction route area, the first alarm device on the nearest monitoring pile is triggered to send out a first warning message;

[0070] A data processing module, which is used to determine whether the positioning information is within the corresponding standard construction route area according to the identification information, and if not, trigger the first alarm device;

[0071] A plurality of communication interaction modules, which are used for information interaction between the intelligent mapping module, the first sensing device, the first alarm device, the second sensing device, the positioning device, the second alarm device, and the storage module; the communication interaction module feeds back the construction status of each unit construction project according to a preset time node until the unit construction project is completed;

[0072] A storage module is used to store the project address information, the project design drawings, the construction plan, the construction progress, the construction projects of each unit, the map drawn by the intelligent mapping module, the information processed by the data processing module and the interactive information of the communication interaction module.

[0073] In the above technical solution, by setting up an intelligent mapping module, the real-time status of the project construction and the supervision deployment status can be reflected in real time; the data processing module can process abnormal data in a timely manner and trigger early warnings so as to timely manage and control construction personnel; the communication interaction module can realize real-time information exchange between modules and facilitate the interaction between management and control personnel and construction personnel; the storage module is used to store various drawings, progress information, early warning information, etc., to provide a data basis for later construction improvements.

[0074] In another technical solution, the intelligent mapping module divides the standard construction route area into multiple unit areas. If a construction worker stays in a unit area for a unit time, a unit value is assigned to the unit area. The unit value of each unit area in the corresponding standard construction route area is calculated based on the dot-dash line diagram of each construction worker. The main construction position of each construction worker can be intuitively reflected, thereby providing a basis for analyzing the construction efficiency of the construction workers.

[0075] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims

1. The intelligent management method of engineering projects is characterized by: The following steps are involved: S1. Determine the construction area of ​​the entire project according to the project address and project design drawings, and deploy multiple monitoring piles within the construction area, each monitoring pile being a monitoring point. Then deploy monitoring piles at the construction site according to the construction area and the location of the monitoring piles, and set a first sensing device and a first alarm device on the monitoring piles. S2. According to the construction plan, the current construction progress and one or more unit construction projects to be constructed are obtained, and the positions and quantities of monitoring piles are supplemented and adjusted accordingly on the project design drawings according to the current construction progress and the unit construction projects, and then monitoring piles are arranged at corresponding positions on the construction site, and a first sensing device and a first alarm device are set on the monitoring piles; S3. Generate the standard construction route area range for all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles; S4, assigning a safety helmet to each construction worker according to each unit construction project, wherein the safety helmet is provided with a second sensing device, a positioning device and identification information corresponding to the unit construction project and the construction worker. After being started, the second sensing device senses the first sensing device on the monitoring pile near it at a preset frequency, and the positioning device sends positioning information after the connection is established; S5, drawing a dot-dash line diagram in chronological order according to the positioning information to form a trajectory route of the corresponding construction personnel; wherein, when the positioning information exceeds the standard construction route area generated in step S3, the first alarm device on the nearest monitoring pile is triggered to send out a first warning message; S6. Feedback the construction status of each unit construction project according to the preset time node until the unit construction project is completed; S7. Repeat steps S2 to S6 until the entire project is completed.

2. The engineering project intelligent management method according to claim 1, characterized in that: Also includes: The standard construction route area in step S3 is divided into multiple unit areas. If a construction worker stays in a unit area for a unit time, a unit value is assigned to the unit area. The unit value of each unit area in the corresponding standard construction route area is calculated based on the dot-dash line diagram of each construction worker.

3. The engineering project intelligent management method according to claim 1, characterized in that: It also includes a second alarm device arranged on the safety helmet, the second sensing device senses the position of the construction worker's head at a preset frequency, and when it senses that the safety helmet is separated from the construction worker's head, the second alarm device sends out a second warning message.

4. The engineering project intelligent management method according to claim 1, characterized in that: The second sensing device includes a radio frequency tag, on which identification information corresponding to the unit construction project and the construction personnel is loaded; The first sensing device includes a radio frequency tag identifier, and the radio frequency tag identifier can identify multiple radio frequency tags at the same time; The positioning device is a GPS positioning module, which is communicatively connected with the first sensing device; The first alarm device includes a voice announcer.

5. The engineering project intelligent management method according to claim 3, characterized in that: The second sensing device includes a human infrared sensor, which is arranged on the inner wall of the safety helmet. The human infrared sensor detects at a preset frequency, and when no human body is detected, the second alarm device is triggered.

6. The engineering project intelligent management method according to claim 5, characterized in that: A solar charging panel is provided on the rear outer side wall of the safety helmet, and the solar charging panel supplies power to the second sensing device, the positioning device and the second alarm device.

7. A system according to any one of claims 1 to 6, characterized in that: include: An intelligent mapping module, which is used to draw the construction area of ​​the entire project according to the project address and the project design drawings, and mark the positions of multiple monitoring piles within the construction area; wherein each monitoring pile is a monitoring point, and the monitoring pile is provided with a first sensing device and a first alarm device; and, Used to obtain the current construction progress and one or more unit construction projects to be constructed according to the construction plan, and to supplement and adjust the position and quantity of monitoring piles on the project design drawings accordingly according to the current construction progress and unit construction projects; and, It is used to generate the standard construction route area range of all construction personnel of each unit construction project according to the current construction progress, unit construction projects and monitoring piles, and mark it on the project design drawings; A plurality of safety helmets, each of which is provided with a second sensing device, a positioning device, a second alarm device and identification information corresponding to a unit construction project and a construction worker. After being started, the second sensing device senses the first sensing device on a monitoring pile near it at a preset frequency, and the positioning device sends out positioning information after a connection is established; and the second sensing device senses the position of the construction worker's head at a preset frequency, and when it senses that the safety helmet is off the construction worker's head, the second alarm device sends out a second warning information; The intelligent mapping module draws a dot-dash line diagram in chronological order according to the positioning information to form a corresponding trajectory route of the construction personnel; when the positioning information exceeds the scope of the standard construction route area, the first alarm device on the nearest monitoring pile is triggered to send out a first warning message; A data processing module, which is used to determine whether the positioning information is within the corresponding standard construction route area according to the identification information, and if not, trigger the first alarm device; A plurality of communication interaction modules, which are used for information interaction among the intelligent mapping module, the first sensing device, the first alarm device, the second sensing device, the positioning device, the second alarm device, and the storage module; The communication interaction module feeds back the construction status of each unit construction project according to the preset time node until the unit construction project is completed; A storage module is used to store the project address information, the project design drawings, the construction plan, the construction progress, the construction projects of each unit, the map drawn by the intelligent mapping module, the information processed by the data processing module and the interactive information of the communication interaction module.

8. The engineering project intelligent management system according to claim 7, characterized in that: The intelligent mapping module divides the standard construction route area into multiple unit areas. If a construction worker stays in a unit area for a unit time, a unit value is assigned to the unit area; the unit value of each unit area in the corresponding standard construction route area is calculated based on the dot-dash line diagram of each construction worker.

9. An electronic device, characterized in that include: one or more processors; Memory; as well as One or more programs, wherein the one or more programs are stored in the memory and configured to be executed by the one or more processors, the programs comprising instructions for executing the method according to any one of claims 1 to 6.

10. A computer-readable storage medium, characterized in that A computer program stored in an electronic device for use in combination, wherein the computer program can be executed by a processor to implement the method according to any one of claims 1 to 6.