Project progress management method and device, electronic equipment and storage medium

Through a project progress management method, project information is obtained and updated, and the problem that project managers find it difficult to intuitively display project progress is solved, achieving more efficient project management and improved project completion.

CN119539926APending Publication Date: 2025-02-28SHANGHAI ZHONGSHI CONSTRUCTION CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411621671.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-14
Publication Date
2025-02-28

AI Technical Summary

Technical Problem

In the prior art, when project managers manage multiple projects, it is difficult for project managers to intuitively and clearly display the progress, completion status and existing problems of the project, resulting in confusion in project progress records and affecting project completion.

Method used

Provide a project progress management method, by obtaining project construction information and updating project progress, including obtaining target supplier information based on the preset supplier registration system, determining winning suppliers and unsuccessful suppliers, sending deposit refund instructions, obtaining project results information and initiating project archiving process, unifying progress standards, and intuitively displaying project progress.

Benefits of technology

By unifying progress standards, we can more intuitively and clearly show the progress, completion status and existing problems of the project, helping project managers better manage projects and improve project completion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119539926A_ABST
    Figure CN119539926A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of evidence encryption, in particular to a project progress management method and device, electronic equipment and a storage medium. According to the scheme, the method comprises the steps of obtaining item building information; obtaining target supplier information based on a preset supplier registration system; determining bid-winning suppliers and non-bid-winning suppliers based on the target supplier information and the project bid evaluation result; based on the non-bid-winning suppliers, sending a non-bid-winning supplier deposit return instruction; obtaining project result data, and initiating a project archiving process; based on the project archiving process, the project corresponding to the project construction information is completed, after each step is completed, a 100% progress bar is updated in real time, the project progress can be visually displayed, the capability and efficiency of a project manager in project management and execution aspects can be reflected, the progress standard is unified, and the project management efficiency is improved. The progress, the completion condition and the existing problems of the project are displayed more visually and clearly, so that a project manager is helped to better manage the project, and the project completion degree is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of evidence encryption technology, and in particular to a project progress management method, management device, electronic device and storage medium. Background Art

[0002] As the bidding market continues to expand, the number of bidding projects in the market is also increasing. This means that project managers need to be responsible for and operate multiple projects at the same time. As the number of projects continues to increase, the requirements for the completion of each project are also gradually increasing. This is not only because the number of projects that need to be managed has increased, but also because completing multiple projects efficiently and with high quality has become a new challenge.

[0003] The degree of project completion will directly affect the company's operational efficiency and customer satisfaction, and therefore has become one of the important indicators for evaluating the performance of project managers. At present, the completion progress of the entire project from the project establishment stage to the archiving stage is still determined by the personal experience of each project manager, and when multiple projects are carried out at the same time, it is inevitable that the project progress records will be confused.

[0004] Therefore, how to more intuitively and clearly display the project progress, completion status and existing problems, so as to help project managers better manage projects and improve project completion, has become an issue that needs to be addressed urgently. Summary of the invention

[0005] The present application provides a project progress management method, management device, electronic device and storage medium, which can more intuitively and clearly display the progress, completion status and existing problems of the project, thereby helping project managers to better manage the project and improve the project completion rate.

[0006] In a first aspect, an embodiment of the present application provides a project progress management method, the method comprising: obtaining project construction information and updating the project progress, the project construction information comprising: project name, budget amount, procurement method, and project contact person; based on a preset supplier registration system, obtaining target supplier information and updating the project progress; based on the target supplier information and the project evaluation results, determining the winning supplier and the unsuccessful supplier, and updating the project progress; based on the unsuccessful supplier, sending a deposit refund instruction to the unsuccessful supplier, and updating the project progress; obtaining project achievement information, initiating a project archiving process, and updating the project progress; based on the project archiving process, completing the project corresponding to the project construction information.

[0007] In a possible implementation, obtaining target supplier information based on a preset supplier registration system and updating the project progress includes: obtaining bidding suppliers based on the preset supplier registration system; determining the target supplier information based on the bidding suppliers and information uploaded by the bidding suppliers; and updating the project progress when the number of target supplier information is greater than the preset number of suppliers.

[0008] In a possible implementation, determining the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and updating the project progress includes: based on the target supplier information, obtaining the bid document corresponding to the target supplier information; based on the bid document and the evaluation expert information, updating the project progress, and evaluating the bid document to determine the project evaluation results; based on the project evaluation results, determining the winning supplier and the unsuccessful supplier.

[0009] In a possible implementation, based on the unsuccessful supplier, sending a deposit refund instruction to the unsuccessful supplier and updating the project progress includes: updating the project progress after the deposit is fully refunded to the unsuccessful supplier; and sending an instruction to refund the deposit of the successful supplier after the successful supplier signs a contract with the project.

[0010] In a possible implementation, obtaining project achievement information, initiating a project archiving process, and updating project progress includes: obtaining project achievement information after the project is completed; initiating the project archiving process based on the project achievement information; and updating project progress based on the project archiving process.

[0011] In a possible implementation, based on the project archiving process, completing the project corresponding to the project establishment information includes: completing the project archiving process after the procurement documents, result notification, and the achievement data are uploaded; and determining that the project is completed based on the completed project archiving process.

[0012] In a possible implementation, updating the project progress based on the bidding document and the bid evaluation expert information includes: based on a preset model and the bidding document, capturing the bidding unit and bidding quotation in the bidding document; based on a preset model and the bid evaluation expert information, capturing the expert name, expert contact information, expert major and expert ID number in the bid evaluation expert information; updating the project progress based on the bidding unit, the bid quotation, the expert name, the expert contact information, the expert major and the expert ID number.

[0013] In the second aspect, an embodiment of the present application provides a project progress management device, which includes: an acquisition module, used to acquire project construction information and update the project progress, wherein the project construction information includes: project name, budget amount, procurement method, and project contact person; the acquisition module is also used to acquire target supplier information based on a preset supplier registration system and update the project progress; a determination module is used to determine the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and update the project progress; a sending module is used to send a deposit refund instruction to the unsuccessful supplier based on the unsuccessful supplier, and update the project progress; a processing module is used to acquire project achievement information, initiate a project archiving process, and update the project progress; the processing module is also used to complete the project corresponding to the project construction information based on the project archiving process.

[0014] In a third aspect, an embodiment of the present application provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the method described in the first aspect or any one of the implementation methods thereof is implemented.

[0015] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method described in the first aspect or any one of the implementation methods thereof is implemented.

[0016] The solution provided by the embodiment of the present application is as follows: obtaining project information and updating the project progress, the project information includes: project name, budget amount, procurement method, project contact person; based on the preset supplier registration system, obtaining target supplier information and updating the project progress; based on the target supplier information and the project evaluation results, determining the winning supplier and the unsuccessful supplier, and updating the project progress; based on the unsuccessful supplier, sending the unsuccessful supplier deposit refund instruction and updating the project progress; obtaining project achievement information, initiating the project archiving process, and updating the project progress; based on the project archiving process, completing the project corresponding to the project information. Different project managers in the prior art do not have a unified standard for project progress. This application can unify the progress standard according to the completion status of each stage of the project, and more intuitively and clearly display the project progress, completion status and existing problems, so as to help project managers better manage projects and improve project completion. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 A flowchart of a project progress management method provided in one embodiment of the present application;

[0019] Figure 2 A structural block diagram of a project progress management device provided in one embodiment of the present application;

[0020] Figure 3 A schematic diagram of the structure of an electronic device provided in one embodiment of the present application. DETAILED DESCRIPTION

[0021] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0022] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.

[0023] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0024] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.

[0025] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0026] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0027] For ease of understanding, the technical solution of the present application will be described in detail below with reference to the accompanying drawings.

[0028] Figure 1 This is a flowchart of a project progress management method provided by an embodiment of the present application. For the sake of convenience, only the part related to this embodiment is shown. The method provided by this embodiment includes the following steps:

[0029] S110, obtaining project information and updating project progress. The project information includes: project name, budget amount, procurement method, and project contact person.

[0030] For example, before obtaining project information, you must first establish the project, link to the entrusting unit pool, and associate the entrusting unit. After the process is approved, it can be archived. After the archiving is completed, the project can be confirmed.

[0031] Furthermore, when a project is established, it is necessary to obtain basic information about the project, such as project name, budget amount, procurement method, project contact person, etc. After obtaining this basic information, the system will update the project progress and automatically display the project progress as 16.67%.

[0032] S120, based on the preset supplier registration system, obtain target supplier information and update project progress.

[0033] For example, the preset supplier registration system includes the start time and end time of the project registration. During this period, the supplier uploads the registration related materials and supplier information according to the content of the procurement announcement.

[0034] In one possible implementation, based on a preset supplier registration system, target supplier information is obtained and the project progress is updated, including: based on the preset supplier registration system, bidding suppliers are obtained; based on the bidding suppliers and materials uploaded by the bidding suppliers, target supplier information is determined; when the number of target supplier information is greater than the preset number of suppliers, the project progress is updated.

[0035] Specifically, the registration materials uploaded by the bidding suppliers are reviewed. After the review is passed, the supplier pays the tender fee through the system to determine the target supplier information. During this period, if the number of suppliers reaches 3 or more, the system will update the project progress to 33.33%. If the number of suppliers is less than 3, the system progress will not reach 33.33%. At this time, there is a risk of the project failing to bid, and the staff needs to be vigilant.

[0036] S130, based on the target supplier information and the project evaluation results, determine the successful suppliers and unsuccessful suppliers, and update the project progress.

[0037] In one possible implementation, based on the target supplier information and the project evaluation results, the winning supplier and the unsuccessful supplier are determined, and the project progress is updated, including: based on the target supplier information, obtaining the bid documents corresponding to the target supplier information; based on the bid documents and the evaluation expert information, updating the project progress, evaluating the bid documents, and determining the project evaluation results; based on the project evaluation results, determining the winning supplier and the unsuccessful supplier.

[0038] In one possible implementation, updating the project progress based on the bidding documents and bid evaluation expert information includes: based on a preset model and the bidding documents, capturing the bidding unit and bid quotation in the bidding documents; based on the preset model and bid evaluation expert information, capturing the expert name, expert contact information, expert major and expert ID number in the bid evaluation expert information; updating the project progress based on the bidding unit, bid quotation, expert name, expert contact information, expert major and expert ID number.

[0039] Exemplarily, for the target supplier information, obtain the bidding documents corresponding to each target supplier information, and then extract the bidding units and bidding quotations in the bidding documents based on the preset model (which can be a natural language processing model (NLP) in this application); extract the expert name, expert contact information, expert major and expert ID number in the evaluation expert information based on the evaluation expert information and the NLP model; after the above information is extracted, the system will automatically update the project progress to 50%. If it does not reach 50%, it may mean that the project has not been reviewed or the system has failed to capture information. At this time, the staff can manually enter relevant information to achieve the same effect.

[0040] Furthermore, the bid evaluation experts evaluate the bids of each target supplier based on their information and bid documents, determine the project evaluation results, and determine the winning suppliers and unsuccessful suppliers based on the project evaluation results.

[0041] S140: Based on the unsuccessful suppliers, a deposit refund instruction is sent to the unsuccessful suppliers, and the project progress is updated.

[0042] In one possible implementation, based on the unsuccessful suppliers, a deposit refund instruction is sent to the unsuccessful suppliers, and the project progress is updated, including: when the deposit is fully refunded to the unsuccessful suppliers, the project progress is updated; when the successful supplier signs a contract with the project, an instruction to refund the deposit of the successful supplier is sent.

[0043] For example, after the winning supplier is determined, the NLP model further extracts the winning bidder's information, such as the company name, winning bid amount, agency service fee amount, etc. At the same time, the system will initiate a deposit instruction for the unsuccessful bidder and return the deposit with one click. After completing these operations, the system will automatically update the project progress to 66.67%. If this value is not reached, it may indicate that the deposit refund process for the unsuccessful bidder has not been initiated, and the deposit refund process for the winning bidder will be initiated after the project contract is signed.

[0044] S150, obtain project achievement information, initiate project archiving process, and update project progress.

[0045] In a possible implementation, obtaining project achievement information, initiating a project archiving process, and updating a project progress includes: obtaining project achievement information after the project is completed; initiating a project archiving process based on the project achievement information; and updating a project progress based on the project archiving process.

[0046] For example, after the project is completed and the results are uploaded to the system, the system will initiate the project archiving process. After the archiving process is completed, the project progress will be displayed as 83.33%.

[0047] S160, based on the project archiving process, complete the project corresponding to the project building information.

[0048] In a possible implementation, based on the project archiving process, completing the project corresponding to the project establishment information includes: completing the project archiving process after the procurement documents, result notification, and achievement data are uploaded; and determining that the project is completed based on the completed project archiving process.

[0049] For example, after the project is archived, that is, the procurement documents, result notice, achievement data and other related materials are uploaded, the project manager can make commissions. Only after the commission is completed, the project progress bar can show 100%, which means that the project has been completely completed.

[0050] The solution provided by the embodiment of the present application is: obtaining project information and updating the project progress, and the project information includes: project name, budget amount, procurement method, project contact person; based on the preset supplier registration system, obtaining the target supplier information and updating the project progress; based on the target supplier information and the project evaluation results, determining the winning supplier and the unsuccessful supplier, and updating the project progress; based on the unsuccessful supplier, sending the unsuccessful supplier deposit refund instruction and updating the project progress; obtaining the project achievement information, initiating the project archiving process, and updating the project progress; based on the project archiving process, completing the project corresponding to the project information. Different project managers in the prior art have no unified standard for project progress. This application can update the 100% progress bar at each stage according to the completion of each stage of the project, which can intuitively display the project progress, and can help staff and project managers better understand the progress of the project. At the same time, the progress bar is also one of the project manager assessment indicators, which can reflect the project manager's ability and efficiency in project management and execution. In addition, this application unifies the progress standard, more intuitively and clearly displays the progress, completion and existing problems of the project, thereby helping project managers to better manage the project and improve the project completion.

[0051] Figure 2 This is a structural block diagram of a project progress management device provided by an embodiment of the present application. For the sake of convenience, only the parts related to the embodiment of the present application are shown. Figure 2 The project progress management device 200 may include: an acquisition module 201 , a determination module 202 , a sending module 203 , and a processing module 204 .

[0052] The acquisition module 201 is used to acquire project information and update the project progress. The project information includes: project name, budget amount, procurement method, and project contact person;

[0053] The acquisition module 201 is also used to acquire target supplier information based on a preset supplier registration system and update the project progress;

[0054] A determination module 202 is used to determine the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and to update the project progress;

[0055] The sending module 203 is used to send a deposit refund instruction to the unsuccessful supplier based on the unsuccessful supplier, and update the project progress;

[0056] Processing module 204, used to obtain project achievement data, initiate project archiving process, and update project progress;

[0057] The processing module 204 is further used to complete the project corresponding to the project creation information based on the project archiving process.

[0058] The scheme provided by the project progress management device of this application is as follows: an acquisition module 201 is used to acquire project information and update the project progress, and the project information includes: project name, budget amount, procurement method, and project contact person; the acquisition module 201 is also used to acquire target supplier information based on the preset supplier registration system and update the project progress; the determination module 202 is used to determine the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and update the project progress; the sending module 203 is used to send the unsuccessful supplier deposit refund instruction based on the unsuccessful supplier, and update the project progress; the processing module 204 is used to acquire project achievement information, initiate the project archiving process, and update the project progress; the processing module 204 is also used to complete the project corresponding to the project information based on the project archiving process. This application can update the 100% progress bar at each stage according to the completion of each stage of the project, which can intuitively display the project progress and help staff and project managers better understand the progress of the project. At the same time, the progress bar is also one of the project manager assessment indicators, which can reflect the project manager's ability and efficiency in project management and execution. In addition, this application unifies the progress standards to more intuitively and clearly display the progress, completion status and existing problems of the project, thereby helping project managers to better manage projects and improve project completion.

[0059] It should be noted that the information interaction, execution process, etc. between the above-mentioned devices / units are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.

[0060] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0061] Figure 3 This is a schematic diagram of the structure of an electronic device provided by an embodiment of the present application. Figure 3As shown, the electronic device 3 of this embodiment includes: at least one processor 30 ( Figure 3 Only one is shown in the figure), a memory 31, and a computer program 32 stored in the memory 31 and executable on at least one processor 30, the processor 30 executes the computer program 32 to implement the above Figure 1 The steps in the method embodiment, or the implementation of the above Figure 2 Functions of each module / unit in the device embodiment.

[0062] The electronic device 3 may be a computing device such as a desktop computer, a notebook, a PDA, or a cloud server. The electronic device 3 may include but is not limited to a processor 30 and a memory 31. Those skilled in the art will appreciate that Figure 3 It is only an example of the electronic device 3 and does not constitute a limitation on the electronic device 3. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, it may also include input and output devices, network access devices, etc.

[0063] The processor 30 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0064] In some embodiments, the memory 31 may be an internal storage unit of the electronic device 3, such as a hard disk or memory of the electronic device 3. In other embodiments, the memory 31 may also be an external storage device of the electronic device 3, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the electronic device 3. Further, the memory 31 may also include both an internal storage unit and an external storage device of the electronic device 3. The memory 31 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as program codes of a computer program. The memory 31 may also be used to temporarily store data that has been output or is to be output.

[0065] The embodiment of the present application further provides a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.

[0066] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include at least: any entity or device capable of carrying the computer program code to an electronic device, a recording medium, a computer memory, a read-only memory (ROM, Read-Only Memory), a random access memory (RAM, Random Access Memory), an electric carrier signal, a telecommunication signal, and a software distribution medium. For example, a USB flash drive, a mobile hard disk, a disk or an optical disk.

[0067] A computer-readable storage medium provided in an embodiment of the present application has the same beneficial effects as the above-mentioned project progress management method.

[0068] An embodiment of the present application provides a computer program product, which includes a computer program. When the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.

[0069] A computer program product provided in an embodiment of the present application has the same beneficial effects as the above-mentioned project progress management method.

[0070] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0071] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0072] In the embodiments provided in the present application, it should be understood that the disclosed devices / electronic devices and methods can be implemented in other ways. For example, the device / electronic device embodiments described above are merely schematic. For example, the division of the modules or units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0073] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0074] The above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. A project progress management method, characterized in that: The method comprises: Obtain project information and update project progress. The project information includes: project name, budget amount, procurement method, and project contact person; Based on the preset supplier registration system, obtain target supplier information and update project progress; Based on the target supplier information and project evaluation results, determine the winning suppliers and unsuccessful suppliers, and update the project progress; Based on the unsuccessful suppliers, send a deposit refund instruction to the unsuccessful suppliers and update the project progress; Obtain project achievement information, initiate project archiving process, and update project progress; Based on the project archiving process, the project corresponding to the project creation information is completed.

2. The method according to claim 1, characterized in that The method of obtaining target supplier information and updating project progress based on the preset supplier registration system includes: Based on the preset supplier registration system, obtaining bidding suppliers; Determine the target supplier information based on the bidding supplier and the information uploaded by the bidding supplier; When the quantity of the target supplier information is greater than the preset quantity of suppliers, the project progress is updated.

3. The method according to claim 1, characterized in that Determining the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and updating the project progress includes: Based on the target supplier information, obtaining a bidding document corresponding to the target supplier information; Based on the bidding documents and bid evaluation expert information, update the project progress, evaluate the bidding documents, and determine the project evaluation results; Based on the project evaluation results, the successful supplier and unsuccessful suppliers are determined.

4. The method according to claim 1, characterized in that: Based on the unsuccessful supplier, sending a deposit refund instruction to the unsuccessful supplier and updating the project progress includes: updating the project progress after the deposit is fully refunded to the unsuccessful supplier; and sending a deposit refund instruction to the successful supplier after the successful supplier signs a contract with the project.

5. The method according to claim 1, characterized in that The acquisition of project achievement data, initiation of project archiving process, and updating of project progress include: When the project is completed, obtain project achievement information; Based on the project achievement data, initiate the project archiving process; Update the project progress based on the project archiving process.

6. The method according to claim 1, characterized in that Based on the project archiving process, the projects corresponding to the project building information include: When the procurement documents, result notification, and achievement data are uploaded, the project archiving process is completed; Based on the completed project archiving process, the project is determined to be completed.

7. The method according to claim 3, characterized in that Based on the bidding documents and bid evaluation expert information, update the project progress including: Based on the preset model and the bidding document, capture the bidding units and bidding quotations in the bidding document; Based on the preset model and the bid evaluation expert information, the expert name, expert contact information, expert major and expert ID number in the bid evaluation expert information are captured; Update the project progress based on the bidding unit, the bidding quotation, the expert's name, the expert's contact information, the expert's major and the expert's ID number.

8. A project progress management device, characterized in that: The device comprises: The acquisition module is used to obtain project information and update the project progress. The project information includes: project name, budget amount, procurement method, and project contact person; The acquisition module is also used to acquire target supplier information and update project progress based on a preset supplier registration system; A determination module, used to determine the winning supplier and the unsuccessful supplier based on the target supplier information and the project evaluation results, and update the project progress; A sending module, used for sending a deposit refund instruction to the unsuccessful supplier based on the unsuccessful supplier, and updating the project progress; The processing module is used to obtain project achievement data, initiate the project archiving process, and update the project progress; The processing module is further used to complete the project corresponding to the project creation information based on the project archiving process.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the method according to any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 7 is implemented.