Nuclear power station overhaul early meeting management method and device, computer equipment and storage medium

By automatically capturing and displaying data, and performing visual display according to the nuclear power plant overhaul morning meeting process, it solves the problems of low efficiency and poor effect in the existing technology of nuclear power plant overhaul morning meeting, realizes intelligent and standardized morning meeting management, and significantly shortens the time Reduce meeting preparation time and improve efficiency.

CN118780773APending Publication Date: 2024-10-15CNNC NUCLEAR POWER OPERATION MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310358032.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-04-06
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing technology for nuclear power plant overhaul morning meetings has problems such as unintelligent, non-standard, unintuitive, low efficiency, and poor effectiveness. It lacks user-oriented unified data architecture design and visual meeting methods, resulting in long meeting preparation time and low efficiency.

Method used

Provide a nuclear power plant overhaul morning meeting management method, including parsing meeting requests, obtaining target meeting information, completing each meeting process step according to the nuclear power plant overhaul morning meeting process, automatically capturing and displaying data, sending pre-meeting reminders through text messages or emails, and using The database displays safety information, unit overhaul progress and quality management data, generates visual reports, and shortens meeting preparation time.

Benefits of technology

It has realized the intelligent, standardized and intuitive morning meeting of nuclear power plant overhaul, shortened the meeting preparation time from 30-50 minutes to 2 minutes, improved the efficiency and effect of the meeting, and ensured the full coverage of meeting elements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780773A_ABST
    Figure CN118780773A_ABST
Patent Text Reader

Abstract

The invention particularly relates to a nuclear power station overhaul early meeting management method, which comprises the following steps: when a conference establishment request of a nuclear power station overhaul early meeting is received, analyzing the conference establishment request to obtain target conference information corresponding to the conference establishment request; and when the target conference information is received, completing the target conference process according to the nuclear power station overhaul early conference process. The invention further relates to a nuclear power station overhaul morning meeting management device, computer equipment and a storage medium. Intelligent, standardized and visualized nuclear power plant overhaul early meeting is realized, the nuclear power plant overhaul early meeting efficiency is improved, and the nuclear power plant overhaul early meeting effect is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of conference management, and in particular to a method, device, computer equipment and storage medium for managing a nuclear power plant overhaul morning meeting. Background Art

[0002] The nuclear power plant overhaul morning meeting is an important activity that undertakes the information collection, exchange and planning of the nuclear power plant overhaul. The accuracy, timeliness and comprehensiveness of the daily overhaul morning meeting information collection and information work plan exchange play a vital role in the implementation safety, quality and progress of the entire overhaul. The content of the nuclear power plant overhaul morning meeting includes pre-meeting reminders, safety learning, an introduction to the unit overhaul, a review of the progress of the unit overhaul yesterday's key path, the unit overhaul today's key path operations and important work deployment, an introduction to the unit overhaul plan execution, a notification reminder of the unit overhaul today's concerns, the unit overhaul morning meeting action item record feedback and the compilation and distribution of the unit overhaul morning meeting information report.

[0003] At present, the morning meeting of nuclear power plant overhaul still adopts the conventional meeting mode. The planning manager arrives at work early every day to retrieve relevant meeting materials from multiple production management systems and complete the compilation of morning meeting information and printing of materials, and communicates orally to all on-site participants. The preparation time for a meeting ranges from 30 minutes to 50 minutes. The meeting process is mostly one person reading to many people listening. There is a lack of unified data architecture design and visual meeting methods for users. The effectiveness of the meeting needs to be strengthened and the efficiency needs to be improved. Summary of the invention

[0004] Based on this, it is necessary to provide a nuclear power plant overhaul morning meeting management method, device, computer equipment and storage medium to address the problems of the existing nuclear power plant overhaul morning meeting model, such as being unintelligent, non-standard, non-intuitive, inefficient and ineffective, so as to realize the intelligence, standardization and intuition of the nuclear power plant overhaul morning meeting, improve the efficiency of the nuclear power plant overhaul morning meeting, and enhance the effectiveness of the nuclear power plant overhaul morning meeting.

[0005] In order to solve the above technical problems, the present invention provides a nuclear power plant overhaul morning meeting management method, comprising the following steps:

[0006] S101, when receiving a meeting establishment request for a nuclear power plant overhaul morning meeting, parsing the meeting establishment request to obtain target meeting information corresponding to the meeting establishment request;

[0007] S102. When receiving the target meeting information, complete the target meeting process according to the nuclear power plant overhaul morning meeting process.

[0008] Furthermore, the target conference information includes target conference personnel information and target conference feature information; the target conference personnel information is target conference participant information; the target conference feature information is target conference corresponding unit and overhaul frequency information.

[0009] Furthermore, the nuclear power plant overhaul morning meeting process is divided into multiple meeting process steps, wherein the first meeting process step of the nuclear power plant overhaul morning meeting process is a pre-meeting reminder;

[0010] According to the first meeting process step of the nuclear power plant overhaul morning meeting process, the first meeting process step of the target meeting process is completed, including the following steps:

[0011] The pre-meeting reminder field information of the target conference is obtained, the pre-meeting reminder data of the target conference is generated and sent to the target conference participants via SMS or email, and the pre-meeting reminder data of the target conference is displayed to the target conference participants.

[0012] Furthermore, the second meeting process step of the nuclear power plant overhaul morning meeting process is safety learning;

[0013] According to the second meeting process step of the nuclear power plant overhaul morning meeting process, the second meeting process step of the target meeting process is completed, including the following steps:

[0014] The security information is extracted from the security information database and displayed to the target conference participants.

[0015] Furthermore, the third meeting process step of the nuclear power plant overhaul morning meeting process is the unit overhaul overview introduction;

[0016] According to the third meeting process step of the nuclear power plant overhaul morning meeting process, the third meeting process step of the target meeting process is completed, including the following steps:

[0017] Obtaining the unit operation status field information corresponding to the target meeting and displaying it to the participants of the target meeting;

[0018] Acquire the unit overhaul progress field information corresponding to the target meeting, generate the unit overhaul progress data corresponding to the target meeting and display it to the participants of the target meeting;

[0019] Obtain the industrial safety data of the unit overhaul corresponding to the target meeting, classify and count the industrial safety index data of the unit overhaul corresponding to the target meeting and display them to the participants of the target meeting; click on the industrial safety index data of the unit overhaul corresponding to the target meeting to display the detailed content of the industrial safety data of the unit overhaul corresponding to the target meeting to the participants of the target meeting, so as to facilitate the publicity and implementation in the morning meeting of the unit overhaul and improve the awareness of industrial safety prevention of the unit overhaul;

[0020] Acquire the unit overhaul quality management data corresponding to the target meeting, classify and count the unit overhaul quality management quantity corresponding to the target meeting and display it to the participants of the target meeting; click on the unit overhaul quality management quantity corresponding to the target meeting to display the detailed content of the unit overhaul quality management data corresponding to the target meeting to the participants of the target meeting;

[0021] Obtain the safety hazard data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting and show it to the participants of the target meeting, so as to supervise the listed implementing units so as to make them pay more attention to safety hazard;

[0022] Obtain the quality fact data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting and display them to the participants of the target meeting, so as to supervise the listed implementing units so as to increase their attention to quality facts;

[0023] The high-risk operation data of the unit overhaul corresponding to the target meeting are obtained, the high-risk operation data of the unit overhaul corresponding to the target meeting are classified and counted, and displayed to the participants of the target meeting; the numerical value in the high-risk operation data of the unit overhaul corresponding to the target meeting is clicked, and the detailed content of the high-risk operation data of the unit overhaul corresponding to the target meeting is displayed to the participants of the target meeting.

[0024] Furthermore, the fourth meeting process step of the nuclear power plant overhaul morning meeting process is the review of the critical path of yesterday's overhaul of the unit overhaul;

[0025] According to the fourth meeting process step of the nuclear power plant overhaul morning meeting process, the fourth meeting process step of the target meeting process is completed, including the following steps:

[0026] Obtaining the work progress data of the critical path of the unit overhaul corresponding to the target meeting, calculating the deviation value of the unit overhaul duration corresponding to the target meeting and displaying it to the participants of the target meeting;

[0027] Acquire planned critical path water level diagram data and executed critical path water level diagram data of the unit overhaul corresponding to the target meeting, and display the planned critical path water level diagram and the actual critical path water level diagram to the participants of the target meeting;

[0028] The critical path operation field information of the unit overhaul corresponding to the target meeting in the past 24 hours is obtained, and the critical path operation data of the unit overhaul corresponding to the target meeting in the past 24 hours is generated and displayed to the participants of the target meeting.

[0029] Furthermore, the fifth meeting process step of the nuclear power plant overhaul morning meeting process is today's overhaul key path operations and important work deployment;

[0030] According to the fifth meeting process step of the nuclear power plant overhaul morning meeting process, the fifth meeting process step of the target meeting process is completed, including the following steps:

[0031] Obtain the key path operation data of the unit overhaul plan for the next 24 hours corresponding to the target meeting and display them one by one to the participants of the target meeting;

[0032] The planning manager manually inputs the critical path operations and important work deployment data for the next 24 hours of the unit overhaul corresponding to the target meeting and displays it to the participants of the target meeting.

[0033] Furthermore, the sixth meeting process step of the nuclear power plant overhaul morning meeting process is the introduction of the unit overhaul plan implementation status;

[0034] According to the sixth meeting process step of the nuclear power plant overhaul morning meeting process, the sixth meeting process step of the target meeting process is completed, including the following steps:

[0035] Obtain the work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting, classify and count the number of work orders of yesterday's planned execution of the unit overhaul corresponding to the target meeting, and display them to the participants of the target meeting through bar charts respectively;

[0036] Obtain the work order data of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, classify and count the number of work orders of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, and display them to the participants of the target meeting;

[0037] Obtaining the data of delayed work orders for overhaul of the units corresponding to the target meeting, classifying and counting the number of delayed work orders for overhaul of the units corresponding to the target meeting, and presenting them to the participants of the target meeting through pie charts;

[0038] Obtaining unit overhaul special data corresponding to the target meeting, classifying and counting the number of unit overhaul special data corresponding to the target meeting, and presenting it to the participants of the target meeting through a pie chart;

[0039] Obtaining the work order data of the unit overhaul plan for today corresponding to the target meeting, classifying and counting the number of work orders of the unit overhaul plan for today corresponding to the target meeting, and displaying them to the participants of the target meeting through bar charts;

[0040] Obtain the work order data of the unit overhaul defect corresponding to the target meeting, classify and count the number of the work orders of the unit overhaul defect corresponding to the target meeting, and display them to the participants of the target meeting through a pie chart;

[0041] The target meeting participants click on the number of work orders that were not executed as planned yesterday, the number of delayed work orders, or the number of work orders scheduled today for the overhaul of the unit corresponding to the target meeting, and display the detailed content of the corresponding work order to the target meeting participants, urging the relevant departments to advance the on-site work in a timely manner;

[0042] The target meeting participant clicks on the number of the unit overhaul project corresponding to the target meeting, and the detailed content of the corresponding project is displayed to the target meeting participant.

[0043] Furthermore, the seventh meeting process step of the nuclear power plant overhaul morning meeting process is the notification reminder of the unit overhaul today's focus items, the record feedback of the unit overhaul morning meeting action items, and the preparation and issuance of the unit overhaul morning meeting information report;

[0044] According to the seventh meeting process step of the nuclear power plant overhaul morning meeting process, the seventh meeting process step of the target meeting process is completed, including the following steps:

[0045] Obtain today's focus items information of the unit overhaul corresponding to the target meeting and display them item by item to the participants of the target meeting, so that the planning manager can be notified of today's focus items information from the overall plan notification of the unit overhaul corresponding to the target meeting;

[0046] Displaying the action item information of the target meeting to the participants of the target meeting in the form of data strips, supporting the planning manager to add new action item information of the target meeting, delete existing action item information of the target meeting, or close existing action item information of the target meeting;

[0047] The data displayed in each meeting process step is obtained under triggering, and filled into the unit overhaul morning meeting information report template, and the unit overhaul morning meeting information report corresponding to the target meeting is generated and sent to the participants of the target meeting.

[0048] In order to solve the above technical problems, the present invention provides a nuclear power plant overhaul morning meeting management device, comprising:

[0049] A parsing module, used for parsing the meeting establishment request for the nuclear power plant overhaul morning meeting when receiving the meeting establishment request, obtaining the target meeting information corresponding to the meeting establishment request and sending the meeting module;

[0050] The conference module is used to complete the target conference process according to the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0051] In order to solve the above technical problems, the present invention provides a computer device, including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the above-mentioned nuclear power plant overhaul morning meeting management method are implemented.

[0052] In order to solve the above technical problems, the present invention provides a computer-readable storage medium, on which computer-readable instructions are stored. When the computer-readable instructions are executed, the steps of the above-mentioned nuclear power plant overhaul morning meeting management method are implemented.

[0053] Beneficial technical effects of the present invention:

[0054] The nuclear power plant overhaul morning meeting management method, device, computer equipment and storage medium of the present invention realize the automatic capture of data information required for display at the nuclear power plant overhaul morning meeting and automatically generate the data required for display at the nuclear power plant overhaul morning meeting, and perform visual display to the participants of the nuclear power plant overhaul morning meeting according to the nuclear power plant overhaul morning meeting process, shortening the planning manager's overhaul morning meeting preparation time from 30-50 minutes to less than 2 minutes, shortening the overhaul morning meeting time from 40 minutes to less than 20 minutes, and achieving full coverage of overhaul morning meeting elements and sending of SMS summaries of important information before the meeting, which greatly improves the efficiency of the overhaul morning meeting and enhances the effect of the overhaul morning meeting. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] Figure 1 A flowchart of an embodiment of the nuclear power plant overhaul morning meeting management method of the present invention;

[0056] Figure 2 A schematic structural view of an embodiment of a nuclear power plant overhaul morning meeting management device of the present invention;

[0057] Figure 3 The figure is a schematic structural view of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0058] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by technicians in the technical field of the present application; the terms used in the specification of the application herein are only for the purpose of describing specific embodiments and are not intended to limit the present application; the terms "including" and "having" and any variations thereof in the specification and claims of the present application and the above-mentioned drawings are intended to cover non-exclusive inclusions. The terms "first", "second", etc. in the specification and claims of the present application or the above-mentioned drawings are used to distinguish different objects, not to describe a specific order.

[0059] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0060] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.

[0061] refer to Figure 1 , shows a flow chart of an embodiment of a method for managing a nuclear power plant overhaul morning meeting according to the present invention, the method for managing a nuclear power plant overhaul morning meeting comprises the following steps:

[0062] S101, when receiving a meeting establishment request for a nuclear power plant overhaul morning meeting, parsing the meeting establishment request to obtain target meeting information corresponding to the meeting establishment request;

[0063] S102. When receiving the target meeting information, complete the target meeting process according to the nuclear power plant overhaul morning meeting process.

[0064] In this embodiment, the target meeting information includes target meeting personnel information and target meeting characteristic information; the target meeting personnel information is the target meeting participant information, for example, the planning manager, industrial safety manager, radiation safety manager and fire safety manager; the target meeting characteristic information is the target meeting corresponding unit and its overhaul number information, for example, the target meeting is a morning meeting of an overhaul of a certain unit.

[0065] In this embodiment, the nuclear power plant overhaul morning meeting process is divided into multiple meeting process steps, wherein the first meeting process step of the nuclear power plant overhaul morning meeting process is a pre-meeting reminder;

[0066] According to the first meeting process step of the nuclear power plant overhaul morning meeting process, the first meeting process step of the target meeting process is completed, including the following steps:

[0067] The pre-meeting reminder field information of the target conference is obtained, the pre-meeting reminder data of the target conference is generated and sent to the target conference participants via SMS or email, and the pre-meeting reminder data of the target conference is displayed to the target conference participants.

[0068] The target meeting pre-meeting reminder field information includes the number of unit overhauls, the start date of the unit overhaul and the unit overhaul status, wherein the "unit overhaul status" field information is "in progress" or "completed".

[0069] The target meeting pre-meeting reminder data includes the following field information: the nth overhaul morning meeting of the unit, the current date and the progress of the unit overhaul.

[0070] When the "Unit Overhaul Status" field information is "In Progress", the "Unit Overhaul Progress" field information is the actual start days of the unit overhaul; when the "Unit Overhaul Status" field information is "Completed", the "Unit Overhaul Progress" field information is that the unit overhaul has been completed; the "Actual Start Days of Unit Overhaul" field information is the number of days obtained by subtracting the unit overhaul start date from the previous date.

[0071] In this embodiment, the second meeting process step of the nuclear power plant overhaul morning meeting process is safety learning;

[0072] According to the second meeting process step of the nuclear power plant overhaul morning meeting process, the second meeting process step of the target meeting process is completed, including the following steps:

[0073] The security information is extracted from the security information database and displayed to the target conference participants.

[0074] In this embodiment, the third meeting process step of the nuclear power plant overhaul morning meeting process is the unit overhaul overview introduction;

[0075] According to the third meeting process step of the nuclear power plant overhaul morning meeting process, the third meeting process step of the target meeting process is completed, including the following steps:

[0076] Obtaining the unit operation status field information corresponding to the target meeting and displaying it to the participants of the target meeting;

[0077] Acquire the unit overhaul progress field information corresponding to the target meeting, generate the unit overhaul progress data corresponding to the target meeting and display it to the participants of the target meeting;

[0078] Obtain the industrial safety data of the unit overhaul corresponding to the target meeting, classify and count the industrial safety index data of the unit overhaul corresponding to the target meeting and display them to the participants of the target meeting; click on the industrial safety index data of the unit overhaul corresponding to the target meeting to display the detailed content of the industrial safety data of the unit overhaul corresponding to the target meeting to the participants of the target meeting, so as to facilitate the publicity and implementation in the morning meeting of the unit overhaul and improve the awareness of industrial safety prevention of the unit overhaul;

[0079] Acquire the unit overhaul quality management data corresponding to the target meeting, classify and count the unit overhaul quality management quantity corresponding to the target meeting and display it to the participants of the target meeting; click on the unit overhaul quality management quantity corresponding to the target meeting to display the detailed content of the unit overhaul quality management data corresponding to the target meeting to the participants of the target meeting;

[0080] Obtain the safety hazard data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting and show it to the participants of the target meeting, so as to supervise the listed implementing units so as to make them pay more attention to safety hazard;

[0081] Obtain the quality fact data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting and display them to the participants of the target meeting, so as to supervise the listed implementing units so as to increase their attention to quality facts;

[0082] The high-risk operation data of the unit overhaul corresponding to the target meeting are obtained, the high-risk operation data of the unit overhaul corresponding to the target meeting are classified and counted, and displayed to the participants of the target meeting; the numerical value in the high-risk operation data of the unit overhaul corresponding to the target meeting is clicked, and the detailed content of the high-risk operation data of the unit overhaul corresponding to the target meeting is displayed to the participants of the target meeting.

[0083] The field information of the unit overhaul progress corresponding to the target meeting includes: unit overhaul status, unit overhaul start date and unit overhaul target duration days.

[0084] The unit overhaul progress data corresponding to the target meeting includes the following field information: actual start days of the unit overhaul and target duration days of the unit overhaul; the "actual start days of the unit overhaul" field information is displayed to the participants of the target meeting in the form of a progress bar.

[0085] When the "Unit Overhaul Status" field information is "In Progress", the "Actual Start Days for Unit Overhaul" field information is the number of days obtained by subtracting the start date of the unit overhaul corresponding to the target meeting from the current date; when the "Unit Overhaul Status" field information is "Ended", the "Actual Start Days for Unit Overhaul" field information remains at the current value, which is the number of days for the execution period of the unit overhaul corresponding to the target meeting.

[0086] The industrial safety data for unit overhaul corresponding to the target meeting include external hidden danger inspection data, yesterday's external hidden danger inspection data, self-inspection data for hidden dangers, yesterday's self-inspection data for hidden dangers, deviation data and violation data; the industrial safety quantities for unit overhaul corresponding to the target meeting include the number of external hidden danger inspections, yesterday's external hidden danger inspections, the number of self-inspections for hidden dangers, yesterday's self-inspections for hidden dangers, the number of deviations and the number of violations.

[0087] The data of external hidden danger inspection, yesterday's external hidden danger inspection data, hidden danger self-inspection data, yesterday's hidden danger self-inspection data, deviation data and violation data are counted separately to obtain the number of external hidden danger inspections, yesterday's external hidden danger inspections, the number of self-inspections of hidden dangers, yesterday's self-inspections of hidden dangers, the number of deviations and the number of violations.

[0088] Click on the number of external hidden danger inspections, the number of external hidden danger inspections yesterday, the number of hidden danger self-inspections, the number of hidden danger self-inspections yesterday, the number of deviations or the number of violations to display the detailed contents of the industrial safety data of the overhaul of the units corresponding to the target meeting to the participants of the target meeting.

[0089] The number of safety hazard data of each unit overhaul implementation unit corresponding to the target meeting is obtained by counting the number of safety hazard data of each unit overhaul implementation unit corresponding to the target meeting.

[0090] The number of quality facts of each unit overhaul implementation unit corresponding to the target meeting is obtained by counting the number of quality facts of each unit overhaul implementation unit corresponding to the target meeting.

[0091] The target meeting corresponds to the high-risk operation data of the unit overhaul, including the following field information: operation status, planned start time, actual start time, planned completion time, actual completion time, safety classification, risk classification, operation area and responsible department, among which the "operation status" field information includes "in progress" and "completed", and the "safety classification" field information includes "industrial safety", "radiation safety" and "fire safety".

[0092] Count the high-risk operation data whose "Safety Classification" field information is "Industrial Safety", "Radiation Safety" and "Fire Safety" respectively, the number of high-risk operation data whose "Operation Status" field information is "In Progress", the number of high-risk operation data whose "Planned Start Time", "Actual Start Time", "Planned Completion Time" or "Actual Completion Time" field information is today's time period, the "Risk Classification" field information, the "Main Working Area" field information, and the "Responsible Department" field information, and obtain the following field information of the high-risk operation data of industrial safety, radiation safety and fire safety, and display it to the target meeting participants in the form of data strips: the number of ongoing high-risk operations, the number of new high-risk operations today, risk classification, main working area and responsible department.

[0093] Click on "Number of ongoing medium- and high-risk operations" or "Number of new high-risk operations today" in the high-risk operation data of industrial safety, radiation safety or fire safety to display the detailed content of the corresponding high-risk operation data to the participants of the target meeting, so that the planning manager can explain the various risks, so that the industrial safety manager, radiation safety manager and fire safety manager can conduct on-site supervision and control of the corresponding high-risk operations to reduce and eliminate the occurrence of safety risk events of unit overhaul.

[0094] In this embodiment, the fourth meeting process step of the nuclear power plant overhaul morning meeting process is the review of the critical path of yesterday's overhaul of the unit overhaul;

[0095] According to the fourth meeting process step of the nuclear power plant overhaul morning meeting process, the fourth meeting process step of the target meeting process is completed, including the following steps:

[0096] Obtaining the work progress data of the critical path of the unit overhaul corresponding to the target meeting, calculating the deviation value of the unit overhaul duration corresponding to the target meeting and displaying it to the participants of the target meeting;

[0097] Acquire planned critical path water level diagram data and executed critical path water level diagram data of the unit overhaul corresponding to the target meeting, and display the planned critical path water level diagram and the actual critical path water level diagram to the participants of the target meeting;

[0098] The critical path operation field information of the unit overhaul corresponding to the target meeting in the past 24 hours is obtained, and the critical path operation data of the unit overhaul corresponding to the target meeting in the past 24 hours is generated and displayed to the participants of the target meeting.

[0099] The target meeting corresponding to the unit overhaul critical path work progress data includes the following field information: the critical path target duration hours of the unit overhaul, the actual unexecuted critical path hours and the actual executed critical path time-consuming hours;

[0100] Unit overhaul duration deviation = actual number of hours of critical path executed + actual number of hours of critical path not executed - target number of hours of unit overhaul critical path.

[0101] The critical path water level diagram data includes the following field information: water level change inflection point and water level holding time.

[0102] In order to facilitate the comparison between the planned critical path water level chart and the actual critical path water level chart of the unit overhaul corresponding to the target meeting, the planned critical path water level chart and the actual critical path water level chart of the unit overhaul corresponding to the target meeting can be displayed as lines of different specifications. For example, in the actual critical path water level chart of the unit overhaul corresponding to the target meeting, the executed critical path water level chart is displayed as a solid red line, and the unexecuted critical path water level chart is displayed as a dotted red line; the planned critical path water level chart is displayed as a solid blue line.

[0103] In addition, an indicator mark may be set in the actual critical path water level diagram of the unit overhaul corresponding to the target meeting to indicate the progress position of the current unit overhaul corresponding to the target meeting. The indicator mark may be an arrow following the unexecuted critical path water level diagram.

[0104] The critical path water level diagram of the unit overhaul plan corresponding to the target meeting remains unchanged during the implementation of the unit overhaul corresponding to the target meeting, and the actual critical path water level diagram of the unit overhaul corresponding to the target meeting is dynamically adjusted in real time according to the actual progress of the unit overhaul corresponding to the target meeting.

[0105] By comparing the planned critical path water level chart and the actual critical path water level chart of the unit overhaul corresponding to the target meeting and the current progress indication of the unit overhaul corresponding to the target meeting, the overall progress and progress control of the unit overhaul corresponding to the target meeting can be intuitively understood.

[0106] The critical path operation data of the unit overhaul corresponding to the target meeting in the past 24 hours are displayed, so that the content of each critical path operation of the unit overhaul corresponding to the target meeting in the past 24 hours is clear at a glance, which is convenient for timely review and feedback of the critical path operation of the unit overhaul corresponding to the target meeting in the past 24 hours, and timely exchange and summarize experience to promote subsequent overhaul optimization and improvement.

[0107] The field information of the key path operations of the unit overhaul in the past 24 hours corresponding to the target meeting includes work content, responsible department, responsible person, actual duration and planned duration; the key path operation data of the unit overhaul in the past 24 hours corresponding to the target meeting includes the following field information: work content, responsible department, responsible person and duration deviation; the "duration deviation" field information is obtained by subtracting the planned duration from the actual duration, and the content of each key path operation is displayed by a key path operation data.

[0108] In this embodiment, the fifth meeting process step of the nuclear power plant overhaul morning meeting process is today's overhaul path operation and important work deployment;

[0109] According to the fifth meeting process step of the nuclear power plant overhaul morning meeting process, the fifth meeting process step of the target meeting process is completed, including the following steps:

[0110] Obtain the key path operation data of the unit overhaul plan for the next 24 hours corresponding to the target meeting and display them one by one to the participants of the target meeting;

[0111] The planning manager manually inputs the critical path operations and important work deployment data for the next 24 hours of the unit overhaul corresponding to the target meeting and displays it to the participants of the target meeting.

[0112] The target meeting will display the key path operation data of the unit overhaul scheduled for the next 24 hours one by one, which will be used for the unit overhaul morning meeting to confirm with the implementation unit whether each key path operation can be implemented as planned, and urge the implementation unit to understand the implementation window time of the key path operation and the content of the preceding and subsequent operations, and make preparations in advance according to the plan and connect the key path negative interface work.

[0113] The planning manager manually inputs the sub-critical path operation data for the next 24 hours of the unit overhaul and displays it item by item to the participants of the unit overhaul morning meeting, so as to facilitate full explanation of the sub-critical path operations for the next 24 hours of the unit overhaul and promote the progress control of the unit overhaul.

[0114] The target meeting corresponds to the key path data of the unit overhaul plan for the next 24 hours, including the following field information: key path operation name, planned start time, responsible department and responsible person.

[0115] Further, in this embodiment, the sixth meeting process step of the nuclear power plant overhaul morning meeting process is the introduction of the unit overhaul plan execution status;

[0116] According to the sixth meeting process step of the nuclear power plant overhaul morning meeting process, the sixth meeting process step of the target meeting process is completed, including the following steps:

[0117] Obtain the work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting, classify and count the number of work orders of yesterday's planned execution of the unit overhaul corresponding to the target meeting, and display them to the participants of the target meeting through bar charts respectively;

[0118] Obtain the work order data of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, classify and count the number of work orders of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, and display them to the participants of the target meeting;

[0119] Obtaining the data of delayed work orders for overhaul of the units corresponding to the target meeting, classifying and counting the number of delayed work orders for overhaul of the units corresponding to the target meeting, and presenting them to the participants of the target meeting through pie charts;

[0120] Obtaining unit overhaul special data corresponding to the target meeting, classifying and counting the number of unit overhaul special data corresponding to the target meeting, and presenting it to the participants of the target meeting through a pie chart;

[0121] Obtaining the work order data of the unit overhaul plan for today corresponding to the target meeting, classifying and counting the number of work orders of the unit overhaul plan for today corresponding to the target meeting, and displaying them to the participants of the target meeting through bar charts;

[0122] Obtain the work order data of the unit overhaul defect corresponding to the target meeting, classify and count the number of the work orders of the unit overhaul defect corresponding to the target meeting, and display them to the participants of the target meeting through a pie chart;

[0123] The target meeting participants click on the number of work orders that were not executed as planned yesterday, the number of delayed work orders, or the number of work orders scheduled today for the overhaul of the unit corresponding to the target meeting, and display the detailed content of the corresponding work order to the target meeting participants, urging the relevant departments to advance the on-site work in a timely manner;

[0124] The target meeting participant clicks on the number of the unit overhaul project corresponding to the target meeting, and the detailed content of the corresponding project is displayed to the target meeting participant.

[0125] The target meeting corresponding unit overhaul work order data includes the following field information: overhaul number, work order task status, planned start time, planned completion time, operation permission start time, work order task number, work content, responsible team, responsible person, actual start time, actual completion time, equipment classification, maintenance classification and work order type.

[0126] The number of work orders for the overhaul of the unit corresponding to the target meeting includes the total number of work orders for the overhaul of the unit corresponding to the target meeting, the number of ongoing work orders, the number of unstarted work orders, and the number of completed work orders.

[0127] By counting the number of work order data whose "overhaul number" field information is the overhaul number of the unit corresponding to the target meeting, the total number of work orders for the overhaul of the unit corresponding to the target meeting is obtained.

[0128] By counting the number of work order data of the unit overhaul corresponding to the target meeting whose "work order task status" field information is "in progress", the number of in-progress work orders for the unit overhaul corresponding to the target meeting is obtained.

[0129] By counting the number of work order data of the unit overhaul corresponding to the target meeting whose "work order task status" field information is "not started", the number of unstarted work orders for the unit overhaul corresponding to the target meeting is obtained.

[0130] By counting the number of work order data of the unit overhaul corresponding to the target meeting whose "work order task status" field information is "completed", the number of completed work orders for the unit overhaul corresponding to the target meeting is obtained.

[0131] By extracting any field information of "planned start time", "planned completion time", "actual start time" or "actual completion time" for the target meeting corresponding to the unit overhaul work order data of yesterday's time period, the yesterday's planned execution work order data of the unit overhaul corresponding to the target meeting is obtained.

[0132] The number of work orders planned to be executed yesterday for the unit overhaul corresponding to the target meeting includes the number of work orders planned to be started yesterday, the number of work orders actually started yesterday, the number of work orders planned to be completed yesterday, and the number of work orders actually completed yesterday for the unit overhaul corresponding to the target meeting.

[0133] By counting the number of work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting whose "Planned Start Time" field information is yesterday's time period, the number of yesterday's planned start work orders of the unit overhaul corresponding to the target meeting is obtained.

[0134] By counting the number of work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting in the yesterday time period whose "planned completion time" field information is yesterday, the number of yesterday's planned completion work orders of the unit overhaul corresponding to the target meeting is obtained.

[0135] By counting the number of work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting in the yesterday time period with the "actual start time" field information, the number of work orders actually started yesterday for the unit overhaul corresponding to the target meeting is obtained.

[0136] By counting the number of work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting in the yesterday time period whose "actual completion time" field information is yesterday, the number of yesterday's actually completed work orders of the unit overhaul corresponding to the target meeting is obtained.

[0137] The data of work orders that were not executed as planned yesterday for the overhaul of the unit corresponding to the target meeting include the data of work orders that were not started as planned yesterday and the data of work orders that were not completed as planned yesterday for the overhaul of the unit corresponding to the target meeting; the number of work orders that were not executed as planned yesterday for the overhaul of the unit corresponding to the target meeting includes the number of work orders that were not started as planned yesterday and the number of work orders that were not completed as planned yesterday for the overhaul of the unit corresponding to the target meeting.

[0138] By extracting the overhaul work order data of the unit corresponding to the target meeting whose later time period in the "Planned Start Time" and "Operation Permit Start Time" field information is delayed by more than 12 hours and whose "Work Order Task Status" field information is "Complete Preparation", the overhaul work order data of the unit corresponding to the target meeting that did not start as planned yesterday is obtained.

[0139] By extracting the unit overhaul work order data corresponding to the target meeting whose "planned completion time" field information is yesterday's time period and whose "work order task status" field information is "in progress", the unit overhaul work order data corresponding to the target meeting that was not completed as planned yesterday is obtained.

[0140] The number of work orders for the overhaul of the unit corresponding to the target meeting that were not started as planned yesterday is obtained by counting the number of work orders for the overhaul of the unit corresponding to the target meeting that were not started as planned yesterday.

[0141] The number of work orders for the overhaul of the unit corresponding to the target meeting that were not completed as planned yesterday is obtained by counting the number of work orders for the overhaul of the unit corresponding to the target meeting that were not completed as planned yesterday.

[0142] The target meeting participant clicks on the number of work orders for the overhaul of the unit corresponding to the target meeting that were not started as planned yesterday, and the detailed contents of the work orders for the overhaul of the unit corresponding to the target meeting that were not started as planned yesterday are displayed to the target meeting participant.

[0143] The target meeting participant clicks on the number of work orders for the overhaul of the unit corresponding to the target meeting that were not completed as planned yesterday, and the detailed contents of the work orders for the overhaul of the unit corresponding to the target meeting that were not completed as planned yesterday are displayed to the target meeting participant.

[0144] Display yesterday's planned execution data of the unit overhaul corresponding to the target meeting, so as to facilitate coordination and communication with the implementation team in the morning meeting of the unit overhaul corresponding to the target meeting on the day of the target meeting, explain the work orders that were not started as planned yesterday and start or adjust the plan in time, explain the work orders that were not completed as planned yesterday or handle the extension procedures, and accurately advance the progress of the unit overhaul corresponding to the target meeting.

[0145] By extracting the unit overhaul work order data corresponding to the target meeting whose time period in the "actual completion time" field information is greater than the time period in the "planned completion time" field information, the unit overhaul extension work order data corresponding to the target meeting is obtained.

[0146] The number of deferred work orders for the unit overhaul corresponding to the target meeting includes the total number of deferred work orders for the unit overhaul corresponding to the target meeting, the number of ongoing deferred work orders, and the number of completed deferred work orders.

[0147] It is determined that the delayed work order data for the overhaul of the unit corresponding to the target meeting whose “work order task status” field information is “completed” is the completed delayed work order data for the overhaul of the unit corresponding to the target meeting.

[0148] It is determined that the target meeting corresponding unit overhaul postponed work order data whose “work order task status” field information is “in progress” is the target meeting corresponding unit overhaul postponed work order data in progress.

[0149] By counting the number of work order data for delayed overhaul of the unit corresponding to the target meeting, the total number of work orders for delayed overhaul of the unit corresponding to the target meeting is obtained.

[0150] The number of completed and deferred work orders for the overhaul of the unit corresponding to the target meeting is obtained by counting the number of completed and deferred work orders for the overhaul of the unit corresponding to the target meeting.

[0151] The number of work orders for the unit overhaul in progress that are deferred at the target meeting is obtained by counting the number of work orders for the unit overhaul in progress that are deferred at the target meeting.

[0152] The target meeting participant clicks on the total number of delayed overhaul work orders for the units corresponding to the target meeting, and the detailed contents of the delayed overhaul work orders for the units corresponding to the target meeting are displayed to the target meeting participant.

[0153] The target meeting participant clicks on the number of delayed work orders for the overhaul of the unit corresponding to the target meeting, and displays the detailed contents of the delayed work orders for the overhaul of the unit corresponding to the target meeting to the target meeting participants.

[0154] The target meeting participant clicks on the number of completed and deferred work orders for the overhaul of the unit corresponding to the target meeting, and the detailed contents of the completed and deferred work orders for the overhaul of the unit corresponding to the target meeting are displayed to the target meeting participant.

[0155] The overhaul postponement work order data of the unit corresponding to the target meeting is displayed to the participants of the target meeting, so as to analyze the reasons for the overhaul postponement of the unit corresponding to the target meeting and adjust the overhaul resources or plans of the unit corresponding to the target meeting in time.

[0156] The target meeting corresponding unit overhaul special data includes the following field information: special project name and special project status; the target meeting corresponding unit overhaul special project quantity includes the total number of unit overhaul special projects, the number of ongoing special projects, the number of completed special projects and the number of unstarted special projects.

[0157] By counting the number of unit overhaul special data corresponding to the target meeting, the total number of unit overhaul special data corresponding to the target meeting is obtained.

[0158] By counting the number of unit overhaul special data corresponding to the target meeting whose "special status" field information is "in progress", the number of unit overhaul in progress special projects corresponding to the target meeting is obtained.

[0159] By counting the number of unit overhaul special data corresponding to the target meeting whose "special status" field information is "completed", the number of completed unit overhaul special data corresponding to the target meeting is obtained.

[0160] By counting the number of unit overhaul special data corresponding to the target meeting whose "special status" field information is "not started", the number of unstarted special projects for unit overhaul corresponding to the target meeting is obtained.

[0161] The target meeting participants click on the total number of special items for the unit overhaul corresponding to the target meeting, and the target meeting participants are shown detailed information on the special items for the unit overhaul corresponding to the target meeting, so that they can intuitively understand the overall situation of the special items for the unit overhaul corresponding to the target meeting.

[0162] The target meeting participants click on the number of ongoing special projects of the unit overhaul corresponding to the target meeting, and the target meeting participants are shown detailed information of the ongoing special projects of the unit overhaul corresponding to the target meeting, so that they can intuitively understand the status of the ongoing special projects of the unit overhaul corresponding to the target meeting.

[0163] The target meeting participants click on the number of completed special projects of the unit overhaul corresponding to the target meeting, and the target meeting participants are shown detailed information of the completed special projects of the unit overhaul corresponding to the target meeting, so that they can intuitively understand the status of the completed special projects of the unit overhaul corresponding to the target meeting.

[0164] The target meeting participants click on the number of unstarted special projects of the unit overhaul corresponding to the target meeting, and the detailed information of the unstarted special projects of the unit overhaul corresponding to the target meeting is displayed to the target meeting participants, so that they can intuitively understand the situation of the unstarted special projects of the unit overhaul corresponding to the target meeting.

[0165] By extracting the unit overhaul work order data corresponding to the target meeting in today's time period whose field information is "planned start time", "planned completion time", "actual start time" or "actual completion time", the today's planned work order data for the unit overhaul corresponding to the target meeting is obtained.

[0166] The number of work orders scheduled today for the overhaul of the unit corresponding to the target meeting includes the number of work orders planned to be started today, the number of work orders planned to be completed today, the number of work orders planned to be scheduled today with the "equipment classification" field information being "SPV", the number of work orders planned to be scheduled today with the "maintenance classification" field information being "M1 level", and the number of work orders planned to be scheduled today with the "maintenance classification" field information being "M2 level".

[0167] By counting the number of work order data for today's planned overhaul of the unit corresponding to the target meeting whose "planned start time" field information is today's time period, the number of today's planned start work orders for the unit overhaul corresponding to the target meeting is obtained.

[0168] By counting the number of work order data of the unit overhaul planned for today corresponding to the target meeting whose "planned completion time" field information is today's time period, the number of work orders planned to be completed today for the unit overhaul corresponding to the target meeting is obtained.

[0169] By counting the number of work order data for today's planned overhaul of the unit corresponding to the target meeting whose "equipment classification" field information is "SPV", the number of work orders for today's planned overhaul of the unit corresponding to the target meeting whose "equipment classification" field information is "SPV" is obtained.

[0170] By counting the number of work order data for today's planned unit overhaul corresponding to the target meeting whose "Maintenance Classification" field information is "M1 level", the number of work orders for today's planned unit overhaul corresponding to the target meeting whose "Maintenance Classification" field information is "M1 level" is obtained.

[0171] By counting the number of work order data for today's planned unit overhaul corresponding to the target meeting whose "Maintenance Classification" field information is "M2 Level", the number of work orders for today's planned unit overhaul corresponding to the target meeting whose "Maintenance Classification" field information is "M2 Level" is obtained.

[0172] The target meeting participants click on the number of work orders for the overhaul of the unit corresponding to the target meeting that are planned to be started today, and the details of the work orders for the overhaul of the unit corresponding to the target meeting that are planned to be started today are displayed to the target meeting participants, so that each department can grasp the work orders they are responsible for in real time, make preparations for the start of work in a timely manner, and start work on time.

[0173] The target meeting participants click on the number of work orders for the overhaul of the unit corresponding to the target meeting that are planned to be completed today, and the detailed content of the work orders for the overhaul of the unit corresponding to the target meeting that are planned to be completed today is displayed to the target meeting participants, so that each department can grasp the completed work orders for which they are responsible in real time, promptly promote the corresponding work on site and complete it on time.

[0174] The target meeting participant clicks on the number of work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Equipment Classification" field information is "SPV", and displays the detailed content of the work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Equipment Classification" field information is "SPV" to the target meeting participants, focusing on the maintenance quality of SPV equipment.

[0175] The target meeting participant clicks on the number of work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Maintenance Classification" field information is "M1 Level", and displays the detailed content of the work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Maintenance Classification" field information is "M1 Level" to the target meeting participants.

[0176] The target meeting participant clicks on the number of work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Maintenance Classification" field information is "M2 Level" to display the detailed content of the work orders for today's planned overhaul of the unit corresponding to the target meeting whose "Maintenance Classification" field information is "M2 Level" to the target meeting participants.

[0177] By extracting the unit overhaul work order data corresponding to the target meeting whose “work order type” field information is “CM” or “DM”, the unit overhaul defect work order data corresponding to the target meeting is obtained.

[0178] The number of defect work orders for the unit overhaul corresponding to the target meeting includes the total number of defect work orders for the unit overhaul corresponding to the target meeting, the number of completed defect work orders, and the number of uncompleted defect work orders.

[0179] By counting the number of unit overhaul defect work order data corresponding to the target meeting, the total number of unit overhaul defect work orders corresponding to the target meeting is obtained.

[0180] By counting the number of defect work order data of the unit overhaul corresponding to the target meeting whose "work order task status" field information is "completed", the number of defect work orders of the unit overhaul corresponding to the target meeting that have been completed is obtained.

[0181] By counting the number of defect work orders corresponding to the target meeting whose "work order task status" field information is "in progress" and "not started", the number of unfinished defect work orders corresponding to the target meeting is obtained. Furthermore, in this embodiment, the seventh meeting process step of the nuclear power plant overhaul morning meeting process is the notification reminder of the unit overhaul today's concerns, the record feedback of the unit overhaul morning meeting action items, and the compilation and issuance of the unit overhaul morning meeting information report;

[0182] According to the seventh meeting process step of the nuclear power plant overhaul morning meeting process, the seventh meeting process step of the target meeting process is completed, including the following steps:

[0183] Obtain today's focus items information of the unit overhaul corresponding to the target meeting and display them item by item to the participants of the target meeting, so that the planning manager can be notified of today's focus items information from the overall plan notification of the unit overhaul corresponding to the target meeting;

[0184] Displaying the action item information of the target meeting to the participants of the target meeting in the form of data strips, supporting the planning manager to add new action item information of the target meeting, delete existing action item information of the target meeting, or close existing action item information of the target meeting;

[0185] The data displayed in each meeting process step is obtained under triggering, and filled into the unit overhaul morning meeting information report template, and the unit overhaul morning meeting information report corresponding to the target meeting is generated and sent to the participants of the target meeting.

[0186] The action item information of the target meeting includes the following field information: sequence number, generation date, content, responsible person, status, progress and completion deadline.

[0187] Click the "New" button, enter the new action item information of the target meeting in the pop-up page and save it, and generate and display the new action item information of the target meeting.

[0188] Check the existing action item information of the target meeting, and click the "Delete" button to delete the checked action item information of the target meeting.

[0189] Check the existing action item information of the target meeting, and click the "Close" button to close the checked action item information of the target meeting.

[0190] Track the morning meeting action items generated during the nuclear power plant overhaul until they are closed, so as to implement closed-loop management of the morning meeting action items and promote the efficiency of unit overhaul implementation.

[0191] The nuclear power plant overhaul morning meeting management method proposed in this embodiment realizes the automatic capture of data information required for display at the nuclear power plant overhaul morning meeting and automatically generates data required for display at the nuclear power plant overhaul morning meeting, and performs visual display to the participants of the nuclear power plant overhaul morning meeting according to the nuclear power plant overhaul morning meeting process, shortening the planning manager's overhaul morning meeting preparation time from 30-50 minutes to less than 2 minutes, shortening the overhaul morning meeting time from 40 minutes to less than 20 minutes, and achieving full coverage of overhaul morning meeting elements and sending SMS summaries of important information before the meeting, which greatly improves the efficiency of the overhaul morning meeting and enhances the effect of the overhaul morning meeting.

[0192] refer to Figure 2 As an implementation of the above method, the present invention provides an embodiment of a nuclear power plant overhaul morning meeting management device. The device embodiment corresponds to the embodiment of the above method, and the device can be specifically applied to various electronic devices.

[0193] The nuclear power plant overhaul morning meeting management device described in this embodiment includes:

[0194] The parsing module 201 is used to parse the meeting establishment request for the nuclear power plant overhaul morning meeting when receiving the meeting establishment request, obtain the target meeting information corresponding to the meeting establishment request and send it to the meeting module;

[0195] The meeting module 202 is used to complete the target meeting process according to the nuclear power plant overhaul morning meeting process when receiving the target meeting information.

[0196] In this embodiment, the target meeting information includes target meeting personnel information and target meeting characteristic information; the target meeting personnel information is the target meeting participant information, that is, target user information, such as planning manager, industrial safety manager, radiation safety manager and fire safety manager; the target meeting characteristic information is the target meeting corresponding unit and overhaul number information, for example, the target meeting is a morning meeting of an overhaul of a certain unit.

[0197] In this embodiment, the conference module 202 includes a first conference module, which is used to complete the first conference process step of the target conference process according to the first conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0198] The first meeting module completes the first meeting process step of the target meeting process according to the first meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0199] When receiving the target conference information, the target conference pre-meeting reminder field information is obtained, the target conference pre-meeting reminder data is generated and sent to the target user via SMS or email, and the target conference pre-meeting reminder data is displayed to the target user.

[0200] In this embodiment, a "next" operation button is provided on the display page of the first conference module. The target user clicks the "next" operation button of the first conference to enter the display page of the second conference module.

[0201] In this embodiment, the conference module also includes a second conference module, which is used to complete the second conference process step of the target conference process according to the second conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0202] The second conference module completes the second conference process step of the target conference process according to the second conference process step of the nuclear power plant overhaul morning meeting process, including the following steps: extracting safety information from the safety information database and displaying it to the target user.

[0203] In this embodiment, the second conference module display page is provided with a "Next" operation button and a "Return" operation button. The target user clicks the "Next" operation button of the second conference to enter the display page of the third conference module. The target user clicks the "Return" operation button of the second conference to return to the display page of the first conference module.

[0204] In this embodiment, the conference module 202 also includes a third conference module, which is used to complete the third conference process step of the target conference process according to the third conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0205] The third meeting module completes the third meeting process step of the target meeting process according to the third meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0206] Obtaining the unit operation status field information corresponding to the target conference and displaying it to the target user;

[0207] Acquire the unit overhaul progress field information corresponding to the target meeting, generate the unit overhaul progress data corresponding to the target meeting and display it to the target user;

[0208] Obtain the industrial safety data of the unit overhaul corresponding to the target meeting, classify and count the industrial safety data of the unit overhaul corresponding to the target meeting and display them to the target user; click on the industrial safety data of the unit overhaul corresponding to the target meeting to display the detailed content of the industrial safety data of the unit overhaul corresponding to the target meeting to the target user, so as to facilitate the publicity and implementation in the morning meeting of the unit overhaul and improve the awareness of industrial safety prevention of the unit overhaul;

[0209] Obtain the unit overhaul quality management data corresponding to the target meeting, classify and count the unit overhaul quality management quantity corresponding to the target meeting and display it to the target user; click on the unit overhaul quality management quantity corresponding to the target meeting to display the detailed content of the unit overhaul quality management data corresponding to the target meeting to the target user;

[0210] Obtain the safety hazard data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of safety hazard of each implementing unit of the unit overhaul corresponding to the target meeting and display it to the target user, so as to supervise the listed implementing units so as to make them pay more attention to safety hazard;

[0211] Obtain the quality fact data of each implementing unit of the unit overhaul corresponding to the target meeting, count the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting, rank the number of quality facts of each implementing unit of the unit overhaul corresponding to the target meeting and display them to the target user, so as to supervise the listed implementing units so as to increase their attention to quality facts;

[0212] The high-risk operation data of the unit overhaul corresponding to the target meeting is obtained, and the high-risk operation data of the unit overhaul corresponding to the target meeting is classified and counted, and displayed to the target user; the numerical value in the high-risk operation data of the unit overhaul corresponding to the target meeting is clicked, and the detailed content of the high-risk operation data of the unit overhaul corresponding to the target meeting is displayed to the target user.

[0213] In this embodiment, the third conference module display page is provided with a "Next" operation button and a "Return" operation button. The target user clicks the "Next" operation button of the third conference to enter the display page of the fourth conference module. The target user clicks the "Return" operation button of the third conference to return to the display page of the second conference module.

[0214] In this embodiment, the conference module 202 also includes a fourth conference module, which is used to complete the fourth conference process step of the target conference process according to the fourth conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0215] The fourth meeting module completes the fourth meeting process step of the target meeting process according to the fourth meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0216] Acquire the work progress data of the key path of the unit overhaul corresponding to the target meeting, calculate the deviation value of the unit overhaul duration corresponding to the target meeting and display it to the target user;

[0217] Acquire planned critical path water level diagram data and executed critical path water level diagram data of the unit overhaul corresponding to the target meeting, and display the planned critical path water level diagram and the actual critical path water level diagram to the target user;

[0218] The key path operation field information of the unit overhaul corresponding to the target meeting in the past 24 hours is obtained, and the key path operation data of the unit overhaul corresponding to the target meeting in the past 24 hours is generated and displayed to the target user.

[0219] In this embodiment, the fourth conference module display page is provided with a "Next" operation button and a "Return" operation button. The target user clicks the "Next" operation button of the fourth conference to enter the display page of the fourth conference module. The target user clicks the "Return" operation button of the fourth conference to return to the display page of the third conference module.

[0220] In this embodiment, the conference module 202 also includes a fifth conference module, which is used to complete the fifth conference process step of the target conference process according to the fifth conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0221] The fifth meeting module completes the fifth meeting process step of the target meeting process according to the fifth meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0222] Obtain the key path operation data of the unit overhaul plan for the next 24 hours corresponding to the target meeting and display them to the target user one by one;

[0223] The planning manager manually inputs the critical path operation data of the unit overhaul in the next 24 hours corresponding to the target meeting and displays it to the target user.

[0224] In this embodiment, the fifth conference module display page is provided with a "Next" operation button and a "Return" operation button. The target user clicks the "Next" operation button of the fifth conference to enter the display page of the sixth conference module. The target user clicks the "Return" operation button of the fifth conference to return to the display page of the fourth conference module.

[0225] In this embodiment, the conference module 202 also includes a sixth conference module, which is used to complete the sixth conference process step of the target conference process according to the sixth conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0226] The sixth meeting module completes the sixth meeting process step of the target meeting process according to the sixth meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0227] Obtain the work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting, classify and count the number of work orders of yesterday's planned execution of the unit overhaul corresponding to the target meeting, and display them to the target user through bar charts respectively;

[0228] Obtain the work order data of the overhaul of the unit corresponding to the target meeting that was not executed as planned yesterday, classify and count the number of work orders of the overhaul of the unit corresponding to the target meeting that was not executed as planned yesterday, and display them to the target user;

[0229] Obtaining the data of delayed work orders for overhaul of the units corresponding to the target meeting, classifying and counting the number of delayed work orders for overhaul of the units corresponding to the target meeting, and presenting them to the target users through pie charts respectively;

[0230] Obtaining data on unit overhaul projects corresponding to the target meeting, classifying and counting the number of unit overhaul projects corresponding to the target meeting, and displaying the data to the target user through a pie chart;

[0231] Obtaining the work order data of the unit overhaul plan for today corresponding to the target meeting, classifying and counting the number of work orders of the unit overhaul plan for today corresponding to the target meeting, and displaying them to the target user through bar charts respectively;

[0232] Obtain the work order data of the unit overhaul defect corresponding to the target meeting, classify and count the number of the work orders of the unit overhaul defect corresponding to the target meeting, and display them to the target user through a pie chart;

[0233] Click the number of work orders that were not executed as planned yesterday, the number of delayed work orders, or the number of work orders scheduled today for the unit overhaul corresponding to the target meeting to display the corresponding work order details to the target user;

[0234] Click on the unit overhaul special item quantity corresponding to the target meeting to display the corresponding special item details to the target user.

[0235] In this embodiment, the display page of the sixth conference module is provided with a "Next" operation button and a "Return" operation button. The target user clicks the "Next" operation button of the sixth conference to enter the display page of the seventh conference module. The target user clicks the "Return" operation button of the sixth conference to return to the display page of the fifth conference module.

[0236] In this embodiment, the conference module 202 also includes a seventh conference module, which is used to complete the seventh conference process step of the target conference process according to the seventh conference process step of the nuclear power plant overhaul morning meeting process when receiving the target conference information.

[0237] The seventh meeting module completes the seventh meeting process step of the target meeting process according to the seventh meeting process step of the nuclear power plant overhaul morning meeting process, including the following steps:

[0238] Acquire today's focus items information of the unit overhaul corresponding to the target meeting and display them one by one to the target user, so that the plan manager can be prompted with today's focus items information from the overall plan notification of the unit overhaul corresponding to the target meeting;

[0239] Displaying the action item information of the target meeting to the target user in the form of data strips, supporting the plan manager to add new action item information of the target meeting, delete the existing action item information of the target meeting, or close the existing action item information of the target meeting;

[0240] The data displayed in each meeting process step is obtained under triggering, filled into the unit overhaul morning meeting information report template, and the unit overhaul morning meeting information report corresponding to the target meeting is generated and sent to the target user.

[0241] In this embodiment, the nuclear power plant overhaul morning meeting management device sets user role permissions, and the target users include ordinary users and administrator users. Ordinary users and administrator users can log in to view the display page of each meeting module, and administrator users can also log in to edit the display page of each meeting module. Administrator users are generally planning managers.

[0242] The nuclear power plant overhaul morning meeting management device proposed in this embodiment realizes the automatic capture of data information required for display at the nuclear power plant overhaul morning meeting and automatically generates data required for display at the nuclear power plant overhaul morning meeting, and performs visual display to the participants of the nuclear power plant overhaul morning meeting according to the nuclear power plant overhaul morning meeting process, shortening the planning manager's overhaul morning meeting preparation time from 30-50 minutes to less than 2 minutes, shortening the overhaul morning meeting time from 40 minutes to less than 20 minutes, and achieving full coverage of overhaul morning meeting elements and sending of SMS summaries of important information before the meeting, which greatly improves the efficiency of overhaul morning meetings and enhances the effectiveness of overhaul morning meetings.

[0243] See also Figure 3 As an implementation of the above method, the present invention provides an embodiment of a computer device, and the computer device embodiment corresponds to the embodiment of the above method.

[0244] The computer device described in this embodiment includes a memory 301, a processor 302 and a network interface 303 that are interconnected and communicated through a system bus. It should be noted that the figure only shows a computer device with components 301-303, but it should be understood that it is not required to implement all the components shown, and more or fewer components can be implemented instead. Among them, those skilled in the art can understand that the computer device here is a device that can automatically perform numerical calculations and / or information processing according to pre-set or stored instructions, and its hardware includes but is not limited to microprocessors, application-specific integrated circuits, programmable gate arrays, digital processors, embedded devices, etc.

[0245] The computer device may be a computing device such as a desktop computer, a notebook, a PDA, a cloud server, etc. The computer device may interact with a user through a keyboard, a mouse, a remote controller, a touch pad, or a voice control device.

[0246] The memory 301 includes at least one type of readable storage medium, and the readable storage medium includes flash memory, hard disk, multimedia card, card-type memory, random access memory, static random access memory, read-only memory, electrically erasable programmable read-only memory, programmable read-only memory, magnetic memory, disk, optical disk, etc. In some embodiments, the memory 301 can be an internal storage unit of the computer device, such as a hard disk or memory of the computer device. In other embodiments, the memory 301 can also be an external storage device of the computer device, such as a plug-in hard disk, smart memory card, secure digital card, flash memory card, etc. equipped on the computer device. Of course, the memory 301 can also include both the internal storage unit of the computer device and its external storage device. In this embodiment, the memory 301 is generally used to store the operating system and various application software installed on the computer device, such as computer-readable instructions of the nuclear power plant overhaul morning meeting management method, etc. In addition, the memory 301 can also be used to temporarily store various types of data that have been output or are to be output.

[0247] The processor 302 may be a central processing unit, a controller, a microcontroller, a microprocessor, or other data processing chip in some embodiments. The processor 302 is generally used to control the overall operation of the computer device. In this embodiment, the processor 302 is used to run the computer-readable instructions or process data stored in the memory 301, such as running the computer-readable instructions of the nuclear power plant overhaul morning meeting management method.

[0248] The network interface 303 may include a wireless network interface or a wired network interface. The network interface 303 is generally used to establish a communication connection between the computer device and other electronic devices.

[0249] The computer device proposed in this embodiment realizes the automatic capture of data information required for display at the nuclear power plant overhaul morning meeting and automatically generates data required for display at the nuclear power plant overhaul morning meeting, and performs visual display to the participants of the nuclear power plant overhaul morning meeting according to the nuclear power plant overhaul morning meeting process, shortening the planning manager's overhaul morning meeting preparation time from 30-50 minutes to less than 2 minutes, shortening the overhaul morning meeting time from 40 minutes to less than 20 minutes, and achieving full coverage of overhaul morning meeting elements and sending SMS summaries of important information before the meeting, which greatly improves the efficiency of the overhaul morning meeting and enhances the effect of the overhaul morning meeting.

[0250] As an implementation of the above method, the present invention provides an embodiment of a computer-readable storage medium, and the embodiment of the computer-readable storage medium corresponds to the embodiment of the above method.

[0251] The computer-readable storage medium described in this embodiment stores computer-readable instructions, and the computer-readable instructions can be executed by at least one processor to enable the at least one processor to perform the steps of the nuclear power plant overhaul morning meeting management method as described above.

[0252] The computer-readable storage medium proposed in this embodiment realizes the automatic capture of data information required for display at the nuclear power plant overhaul morning meeting and automatically generates data required for display at the nuclear power plant overhaul morning meeting, and performs visual display to the participants of the nuclear power plant overhaul morning meeting according to the nuclear power plant overhaul morning meeting process, thereby shortening the planning manager's overhaul morning meeting preparation time from 30-50 minutes to less than 2 minutes, shortening the overhaul morning meeting time from 40 minutes to less than 20 minutes, and achieving full coverage of overhaul morning meeting elements and sending SMS summaries of important information before the meeting, which greatly improves the efficiency of the overhaul morning meeting and enhances the effectiveness of the overhaul morning meeting.

[0253] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.

Claims

1. A nuclear power plant overhaul morning meeting management method, characterized in that: The following steps are involved: S101, when receiving a meeting establishment request for a nuclear power plant overhaul morning meeting, parsing the meeting establishment request to obtain target meeting information corresponding to the meeting establishment request; S102. When receiving the target meeting information, complete the target meeting process according to the nuclear power plant overhaul morning meeting process.

2. The nuclear power plant overhaul morning meeting management method according to claim 1 is characterized in that: The target conference information includes target conference personnel information and target conference feature information; the target conference personnel information is target conference participant information; the target conference feature information is target conference corresponding unit and overhaul frequency information.

3. The nuclear power plant overhaul morning meeting management method according to claim 2 is characterized in that: The process of the nuclear power plant overhaul morning meeting is divided into multiple meeting process steps, among which the first meeting process step of the nuclear power plant overhaul morning meeting is the pre-meeting reminder; According to the first meeting process step of the nuclear power plant overhaul morning meeting process, the first meeting process step of the target meeting process is completed, including the following steps: The pre-meeting reminder field information of the target conference is obtained, the pre-meeting reminder data of the target conference is generated and sent to the target conference participants, and the pre-meeting reminder data of the target conference is displayed to the target conference participants.

4. The nuclear power plant overhaul morning meeting management method according to claim 3 is characterized in that: The second meeting process step of the nuclear power plant overhaul morning meeting process is safety learning; According to the second meeting process step of the nuclear power plant overhaul morning meeting process, the second meeting process step of the target meeting process is completed, including the following steps: The security information is extracted from the security information database and displayed to the target conference participants.

5. The nuclear power plant overhaul morning meeting management method according to claim 4 is characterized in that: The third meeting process step of the nuclear power plant overhaul morning meeting process is the unit overhaul overview introduction; According to the third meeting process step of the nuclear power plant overhaul morning meeting process, the third meeting process step of the target meeting process is completed, including the following steps: Obtaining the unit operation status field information corresponding to the target meeting and displaying it to the participants of the target meeting; Acquire the unit overhaul progress field information corresponding to the target meeting, generate the unit overhaul progress data corresponding to the target meeting and display it to the participants of the target meeting; Obtain the industrial safety data of the unit overhaul corresponding to the target meeting, classify and count the industrial safety index data of the unit overhaul corresponding to the target meeting and display them to the participants of the target meeting; click on the industrial safety index data of the unit overhaul corresponding to the target meeting to display the detailed content of the industrial safety data of the unit overhaul corresponding to the target meeting to the participants of the target meeting; Acquire the unit overhaul quality management data corresponding to the target meeting, classify and count the unit overhaul quality management quantity corresponding to the target meeting and display it to the participants of the target meeting; click on the unit overhaul quality management quantity corresponding to the target meeting to display the detailed content of the unit overhaul quality management data corresponding to the target meeting to the participants of the target meeting; Obtaining safety hazard data of each unit overhaul implementation unit corresponding to the target meeting, counting the number of safety hazard of each unit overhaul implementation unit corresponding to the target meeting, ranking the number of safety hazard of each unit overhaul implementation unit corresponding to the target meeting and displaying it to the participants of the target meeting; Acquire quality fact data of each unit overhaul implementation unit corresponding to the target meeting, count the number of quality facts of each unit overhaul implementation unit corresponding to the target meeting, rank the number of quality facts of each unit overhaul implementation unit corresponding to the target meeting and display them to the participants of the target meeting; The high-risk operation data of the unit overhaul corresponding to the target meeting are obtained, the high-risk operation data of the unit overhaul corresponding to the target meeting are classified and counted, and displayed to the participants of the target meeting; the numerical value in the high-risk operation data of the unit overhaul corresponding to the target meeting is clicked, and the detailed content of the high-risk operation data of the unit overhaul corresponding to the target meeting is displayed to the participants of the target meeting.

6. The nuclear power plant overhaul morning meeting management method according to claim 5 is characterized in that: The fourth meeting process step of the nuclear power plant overhaul morning meeting process is the review of the critical path of the unit overhaul yesterday; According to the fourth meeting process step of the nuclear power plant overhaul morning meeting process, the fourth meeting process step of the target meeting process is completed, including the following steps: Obtaining the work progress data of the critical path of the unit overhaul corresponding to the target meeting, calculating the deviation value of the unit overhaul duration corresponding to the target meeting and displaying it to the participants of the target meeting; Acquire planned critical path water level diagram data and executed critical path water level diagram data of the unit overhaul corresponding to the target meeting, and display the planned critical path water level diagram and the actual critical path water level diagram to the participants of the target meeting; The critical path operation field information of the unit overhaul corresponding to the target meeting in the past 24 hours is obtained, and the critical path operation data of the unit overhaul corresponding to the target meeting in the past 24 hours is generated and displayed to the participants of the target meeting.

7. The nuclear power plant overhaul morning meeting management method according to claim 6 is characterized in that: The fifth meeting process step of the nuclear power plant overhaul morning meeting process is today's overhaul key path operations and important work deployment; According to the fifth meeting process step of the nuclear power plant overhaul morning meeting process, the fifth meeting process step of the target meeting process is completed, including the following steps: Obtain the key path operation data of the unit overhaul plan for the next 24 hours corresponding to the target meeting and display them one by one to the participants of the target meeting; The planning manager manually inputs the critical path operations and important work deployment data for the next 24 hours of the unit overhaul corresponding to the target meeting and displays it to the participants of the target meeting.

8. The nuclear power plant overhaul morning meeting management method according to claim 7 is characterized in that: The sixth meeting process step of the nuclear power plant overhaul morning meeting process is the introduction of the unit overhaul plan implementation status; According to the sixth meeting process step of the nuclear power plant overhaul morning meeting process, the sixth meeting process step of the target meeting process is completed, including the following steps: Obtain the work order data of yesterday's planned execution of the unit overhaul corresponding to the target meeting, classify and count the number of work orders of yesterday's planned execution of the unit overhaul corresponding to the target meeting, and display them to the participants of the target meeting through bar charts respectively; Obtain the work order data of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, classify and count the number of work orders of the unit overhaul corresponding to the target meeting that was not executed as planned yesterday, and display them to the participants of the target meeting; Obtaining the data of delayed work orders for overhaul of the units corresponding to the target meeting, classifying and counting the number of delayed work orders for overhaul of the units corresponding to the target meeting, and presenting them to the participants of the target meeting through pie charts; Obtaining unit overhaul special data corresponding to the target meeting, classifying and counting the number of unit overhaul special data corresponding to the target meeting, and presenting it to the participants of the target meeting through a pie chart; Obtaining the work order data of the unit overhaul plan for today corresponding to the target meeting, classifying and counting the number of work orders of the unit overhaul plan for today corresponding to the target meeting, and displaying them to the participants of the target meeting through bar charts; Obtain the work order data of the unit overhaul defect corresponding to the target meeting, classify and count the number of the work orders of the unit overhaul defect corresponding to the target meeting, and display them to the participants of the target meeting through a pie chart; The target meeting participants click on the number of work orders that were not executed as planned yesterday, the number of delayed work orders, or the number of work orders scheduled today for the overhaul of the unit corresponding to the target meeting, and display the detailed content of the corresponding work order to the target meeting participants, urging the relevant departments to advance the on-site work in a timely manner; The target meeting participant clicks on the number of the unit overhaul project corresponding to the target meeting, and the detailed content of the corresponding project is displayed to the target meeting participant.

9. The nuclear power plant overhaul morning meeting management method according to claim 8, characterized in that: The seventh meeting process step of the nuclear power plant overhaul morning meeting process is to notify the unit overhaul today's focus items, record and feedback the unit overhaul morning meeting action items, and compile and issue the unit overhaul morning meeting information report; According to the seventh meeting process step of the nuclear power plant overhaul morning meeting process, the seventh meeting process step of the target meeting process is completed, including the following steps: Obtain today's focus items information of the unit overhaul corresponding to the target meeting and display them item by item to the participants of the target meeting, so that the planning manager can be notified of today's focus items information from the overall plan notification of the unit overhaul corresponding to the target meeting; Displaying the action item information of the target meeting to the participants of the target meeting in the form of data strips, supporting the planning manager to add new action item information of the target meeting, delete existing action item information of the target meeting, or close existing action item information of the target meeting; The data displayed in each meeting process step is obtained under triggering, and filled into the unit overhaul morning meeting information report template, and the unit overhaul morning meeting information report corresponding to the target meeting is generated and sent to the participants of the target meeting.

10. A nuclear power plant overhaul morning meeting management device, characterized in that: include: A parsing module, used for parsing the meeting establishment request for the nuclear power plant overhaul morning meeting when receiving the meeting establishment request, obtaining the target meeting information corresponding to the meeting establishment request and sending the meeting module; The conference module is used to complete the target conference process according to the nuclear power plant overhaul morning meeting process when receiving the target conference information.

11. A computer device comprising a memory and a processor, wherein the memory stores computer-readable instructions, characterized in that: When the processor executes the computer-readable instructions, the steps of the nuclear power plant overhaul morning meeting management method as described in any one of claims 1-9 are implemented.

12. A computer-readable storage medium having computer-readable instructions stored thereon, characterized in that: When the computer-readable instructions are executed, the steps of the nuclear power plant overhaul morning meeting management method as described in any one of claims 1-9 are implemented.