Workload management and control method for nuclear power station overhaul worker in charge
By calculating the workload and adjustment of the person in charge of the nuclear power plant overhaul work, the problem of opaque workload of the person in charge is solved and the overhaul plan is ensured to be rational and completed on schedule.
Patent Information
- Application Number
- CN202411003149.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-10-15
AI Technical Summary
During the overhaul of a nuclear power plant, the workload of the person in charge is not transparent, resulting in the failure to complete the overhaul plan on schedule and affecting overall performance.
Provide a workload control method for the person in charge of nuclear power plant overhaul work, including calculating the current overhaul professional coefficient, single-day workload and single-day total workload, and evaluating whether adjustments are needed to ensure reasonable manpower allocation and plan execution.
It realizes the transparency and adjustment of the workload of the person in charge of the work, ensuring the rationality and on-schedule completion of the overhaul plan.
Smart Images

Figure CN118780780A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of workload control for persons in charge of nuclear power plant overhaul work, and in particular to a workload control method, device, computer equipment and computer-readable storage medium for persons in charge of nuclear power plant overhaul work. Background Art
[0002] During the current nuclear power plant overhaul, the execution of on-site work needs to rely on the work leader to lead the maintenance personnel to implement. The work arrangement of the work leader is directly related to whether the planned work can be completed on schedule. Usually, the overhaul planner arranges work without considering the staffing of the on-site construction unit, and only requires the on-site construction unit to allocate sufficient manpower in principle. About one month before the overhaul begins, the on-site construction unit allocates manpower according to the plan of the overhaul work order and performs the overhaul work. This operation method has the following problems:
[0003] 1. The configuration of the person in charge of the work is not strongly related to the overhaul plan. The overhaul plan will continuously adjust the planned start and completion time of the work order in advance according to the current work progress. The configuration of the person in charge of the work of the on-site construction unit is often adjusted after problems occur in the execution, which lags behind the plan.
[0004] 2. The workload of the work supervisor is not transparent. Managers and even the work supervisors themselves are not clear about the workload of the work orders they hold during the execution period, and therefore cannot evaluate whether all the work can be completed on time.
[0005] These problems can easily result in the overhaul work not being completed as planned, ultimately affecting the entire overhaul performance. Summary of the invention
[0006] Based on this, it is necessary to provide a workload control method, device, computer equipment and computer-readable storage medium for the person in charge of nuclear power plant overhaul work to address the above problems, so as to realize the calculation and adjustment of the workload of the person in charge of nuclear power plant overhaul work.
[0007] In order to solve the above problems, the present invention provides a method for controlling the workload of a person in charge of nuclear power plant overhaul work, comprising the following steps:
[0008] Calculate the current overhaul specialty coefficient;
[0009] Calculate the daily workload of the current overhaul professional work leader holding a single work order;
[0010] Calculate the total daily workload of the current overhaul professional work leader in executing all work orders;
[0011] Evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders.
[0012] As one of the feasible ways, the calculation of the current overhaul professional coefficient includes the following steps:
[0013] Obtain all historical overhaul data of all nuclear power units in a nuclear power plant; calculate all single historical overhaul professional coefficients of the nuclear power plant based on all historical overhaul data of all nuclear power units in a nuclear power plant;
[0014] According to the professional coefficients of all single historical overhauls of the nuclear power plant, choose one of the following four methods to calculate the professional coefficient of the current overhaul;
[0015] The first method is to take the average of the professional coefficients of the most recent historical overhauls from all the professional coefficients of all nuclear power units of the same reactor type as the current overhaul in the nuclear power plant as the professional coefficient of the current overhaul;
[0016] The second method is to take the weighted average of the most recent historical overhaul professional coefficients from all the single historical overhaul professional coefficients of all nuclear power units of the same reactor type as the current overhaul as the current overhaul professional coefficient. The closer the single historical overhaul time is to the current overhaul, the greater the weight of the professional coefficient.
[0017] The third method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, take the average of the professional coefficients of the most recent historical overhauls as the current overhaul professional coefficient;
[0018] The fourth method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, the weighted average of the professional coefficients of the most recent historical overhauls is taken as the current overhaul professional coefficient. The closer the single historical overhaul time is to the current overhaul time, the greater the weight of the professional coefficient.
[0019] When there is sufficient data on the professional coefficients of all single historical overhauls of nuclear power plants, the second method is the best and the third method is the worst.
[0020] As one of the feasible methods, the calculation of the professional coefficient of a single historical overhaul includes the following steps:
[0021] Calculate the converted working hours for a single work order of a single historical overhaul specialty;
[0022] According to the converted working hours of a single work order of a single historical overhaul specialty, calculate the sum of the converted working hours of all work orders of a single historical overhaul specialty;
[0023] Obtain the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders, and calculate the coefficient of a single historical overhaul specialty based on the sum of the converted working hours of all the work orders of a single historical overhaul specialty and the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders;
[0024] Single historical overhaul specialty coefficient = the sum of converted working hours of all work orders of a single historical overhaul specialty / the total number of days on site for all work persons in charge of a single historical overhaul specialty to execute all work orders;
[0025] Among them, a single work order for a single historical overhaul specialty includes a single standard working time work order for a single historical overhaul specialty and a single non-standard working time work order for a single historical overhaul specialty.
[0026] As one of the feasible methods, the calculation of the converted working hours of a single standard working time work order of a single historical overhaul specialty includes the following steps:
[0027] Get the standard labor time quota entry of a single standard labor time work order of a single historical overhaul specialty;
[0028] Calculate the converted working hours of a single historical overhaul professional single standard working hour work order based on the standard working hour quota items of a single historical overhaul professional single standard working hour work order.
[0029] As one of the feasible ways, there is one or more types of maintenance work in a single standard working time work order of a single historical overhaul specialty, matching one or more standard working time quota entries in the standard working time quota manual; a standard working time quota entry includes the on-site working hours for the maintenance of a single equipment in a type of maintenance work, and the on-site working hours for the maintenance of a single equipment in a type of maintenance work = the number of maintenance personnel for the maintenance of a single equipment in this type of maintenance work × the maintenance working days for the maintenance of a single equipment in this type of maintenance work; the converted working hours of a single standard working time work order of a single historical overhaul specialty is the sum of the on-site working hours for the maintenance of a single equipment in all types of maintenance work in a single standard working time work order of a single historical overhaul specialty.
[0030] As one of the feasible methods, the calculation of the converted working hours of a single non-standard working hours work order of a single historical overhaul specialty includes the following steps:
[0031] Get the contract hours of a single non-standard work order for a single historical overhaul specialty;
[0032] Calculate the number of people converted for a single non-standard work order for a single historical overhaul specialty based on the contracted work hours for a single non-standard work order for a single historical overhaul specialty;
[0033] Calculate the converted working days of a single non-standard working hours work order for a single historical overhaul specialty based on the contract working hours and converted number of people for the single non-standard working hours work order for a single historical overhaul specialty;
[0034] Calculate the converted working hours of a single non-standard working hours work order of a single historical overhaul specialty based on the converted number of people and converted working days of a single non-standard working hours work order of a single historical overhaul specialty;
[0035] The converted number of employees for a single non-standard work order for a single historical overhaul specialty is the square of the contract hours for a single non-standard work order for a single historical overhaul specialty and the converted number of employees for a single non-standard work order for a single historical overhaul specialty is ≥ 2;
[0036] The calculation formula for the converted working days of a single non-standard working time work order for a single historical overhaul specialty is as follows:
[0037]
[0038] The calculation formula for the converted working hours of a single non-standard working hours work order for a single historical overhaul specialty is as follows:
[0039] H 历史大修 =M 历史大修 ×D 历史大修
[0040] Among them, H 历史大修 The converted working hours for a single non-standard working hours work order for a single historical overhaul, M 历史大修 The converted working days for a single non-standard working time work order of a single historical overhaul specialty, D 历史大修 The converted number of people for a single non-standard working time work order for a single historical overhaul.
[0041] As one of the feasible ways, the daily workload of the current overhaul professional work leader holding a single work order is calculated, including the following steps:
[0042] Calculate the converted man-days for the current person in charge of the overhaul professional work to execute a single work order;
[0043] Obtain the planning window for the current person in charge of overhaul professional work to execute a single work order, and calculate the single-day workload of the current person in charge of overhaul professional work to execute a single work order based on the converted working days and planning window of the current person in charge of overhaul professional work to execute a single work order;
[0044] The daily workload of the current person in charge of overhaul professional work who holds a single work order = the converted working days of the current person in charge of overhaul professional work who holds a single work order / the planning window of the current person in charge of overhaul professional work who holds a single work order;
[0045] Among them, the single work order held by the current person in charge of the overhaul professional work includes a single standard working time work order held by the current person in charge of the overhaul professional work and a single non-standard working time work order held by the current person in charge of the overhaul professional work.
[0046] As one of the feasible ways, the daily workload of the current overhaul professional work leader who executes a single standard working time work order is calculated, including the following steps:
[0047] Calculate the converted working days for the current overhaul professional work leader to execute a single standard working time work order;
[0048] Obtain the planning window for the current overhaul professional work leader to execute a single standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single standard working time work order;
[0049] The calculation formula for the daily workload of the current overhaul professional work leader holding a single standard working time work order is as follows:
[0050]
[0051] Among them, Ks is the daily workload of the current overhaul professional work leader who executes a single standard working time work order, T is the planning window for the current overhaul professional work leader who executes a single standard working time work order, and D 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single standard working time work order.
[0052] As one of the feasible ways, the daily workload of the current overhaul professional work leader who holds a single non-standard working time work order is calculated, including the following steps:
[0053] Calculate the converted working days for the current overhaul professional work leader to execute a single non-standard working time work order;
[0054] Obtain the planning window for the current overhaul professional work leader to execute a single non-standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single non-standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single non-standard working time work order;
[0055] The current calculation formula for the daily workload of the person in charge of the overhaul professional work who holds a single non-standard working time work order is as follows:
[0056]
[0057] Among them, Ks , The current overhaul professional work leader performs a single-day workload of holding a single non-standard working time work order, T , The planning window for the current overhaul professional work leader to hold a single non-standard working time work order, D , 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single non-standard working time work order.
[0058] As one of the feasible ways, the calculation of the converted working days of the current overhaul professional work leader who executes a single standard working time work order includes the following steps:
[0059] Get the standard working hours quota entry of the current overhaul professional work leader who holds a single standard working hours work order;
[0060] According to the standard working hours quota entry of the current overhaul professional work person in charge who executes the single standard working hours work order, calculate the converted working hours and converted number of people for the current overhaul professional work person in charge who executes the single standard working hours work order;
[0061] Calculate the converted working days of the current overhaul professional work leader who executes a single standard working hours work order based on the converted working hours and converted number of people who execute the single standard working hours work order;
[0062] The current calculation formula for converting working days for the person in charge of overhaul professional work who holds a single standard working time work order is as follows:
[0063]
[0064] Among them, D 当前大修 The person in charge of the current overhaul professional work shall execute the converted working days for the person who holds a single standard working time work order. 当前大修 The current person in charge of the overhaul professional work performs the converted working hours for the single standard working hours work order, M 当前大修 The number of people who hold a single standard working time work order is calculated for the current overhaul professional work leader.
[0065] As one of the feasible ways, the current person in charge of overhaul professional work holds one or more types of maintenance work in a single standard working time work order, which matches one or more standard working time quota entries; a standard working time quota entry includes the on-site working hours for the maintenance of a single equipment in a type of maintenance work, and the on-site working hours for the maintenance of a single equipment in a type of maintenance work = the number of maintenance personnel for the maintenance of a single equipment in this type of maintenance work × the maintenance working days for the maintenance of a single equipment in this type of maintenance work; the converted working hours for the current person in charge of overhaul professional work to execute a single standard working time work order is the sum of the on-site working hours for the maintenance of a single equipment in all types of maintenance work executed by the current person in charge of overhaul professional work holding a single standard working time work order; the converted number of people for the current person in charge of overhaul professional work to execute a single standard working time work order is the maximum number of maintenance and overhaul personnel for a single equipment in all types of maintenance work executed by the current person in charge of overhaul professional work holding a single standard working time work order.
[0066] As one of the feasible methods, the calculation of the converted working days of the current overhaul professional work leader who holds a single non-standard working time work order includes the following steps:
[0067] Get the contract hours of the current overhaul professional work leader who holds a single non-standard work hour work order;
[0068] According to the contract working hours of the current overhaul professional work leader who holds a single non-standard working hours work order, calculate the converted number of people who are currently in charge of the overhaul professional work and hold a single non-standard working hours work order;
[0069] Calculate the converted working days of the current overhaul professional work leader who holds a single non-standard working hours work order based on the contract working hours and converted number of people who hold a single non-standard working hours work order held by the current overhaul professional work leader;
[0070] The converted working days of the current overhaul professional work leader who holds a single non-standard working time work order = the contract working hours of the current overhaul professional work leader who holds a single non-standard working time work order / the converted number of people who hold a single non-standard working time work order;
[0071] The converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is the square of the contract working hours of the current overhaul professional work leader holding a single non-standard working time work order, and the converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is ≥2.
[0072] As one of the feasible ways, the total daily workload of the current overhaul professional work leader in executing all work orders is calculated, including the following steps:
[0073] According to the daily workload of the current person in charge of the overhaul professional work who holds a single work order, the sum of the daily workload of the current person in charge of the overhaul professional work who holds all the work orders is calculated;
[0074] The total daily workload of the current person in charge of overhaul professional work who holds all work orders is calculated based on the sum of the daily workload of the current person in charge of overhaul professional work who holds all work orders and the current overhaul professional coefficient;
[0075] The total daily workload of the current person in charge of overhaul professional work in executing all work orders held = the sum of the daily workload of the current person in charge of overhaul professional work in executing all work orders held / current overhaul professional coefficient.
[0076] As one of the feasible ways, it is necessary to evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders, including the following steps:
[0077] If the total daily workload of the current overhaul professional work leader who executes all the work orders he holds is less than 1, it is determined that the total daily workload of the current overhaul professional work leader who executes all the work orders he holds is normal, and there is no need to adjust the total daily workload of the current overhaul professional work leader who executes all the work orders he holds;
[0078] 1≤The total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds<2, then the current person in charge of overhaul professional work is judged to be under heavy pressure, and the current person in charge of overhaul professional work can barely complete the work of the day, and the total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds is appropriately adjusted;
[0079] If the total daily workload of the current person in charge of overhaul professional work executing all work orders is ≥ 2, it is determined that the total daily workload of the current person in charge of overhaul professional work is overloaded, and the total daily workload of the current person in charge of overhaul professional work needs to be adjusted.
[0080] In order to solve the above problems, the present invention also provides a workload control device for a person in charge of nuclear power plant overhaul work, comprising:
[0081] The first calculation module is used to calculate the current overhaul professional coefficient;
[0082] The second calculation module is used to calculate the daily workload of the current overhaul professional work leader who holds a single work order;
[0083] The third calculation module is used to calculate the total daily workload of the current overhaul professional work leader who executes all work orders;
[0084] The evaluation module is used to evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders.
[0085] In order to solve the above technical problems, the present invention provides a computer device including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the workload control method for the person in charge of the nuclear power plant overhaul work are implemented.
[0086] In order to solve the above technical problems, the present invention provides a computer-readable storage medium, on which computer-readable instructions are stored. When the computer-readable instructions are executed, the steps of the workload control method for the person in charge of the above-mentioned nuclear power plant overhaul work are implemented.
[0087] Beneficial technical effects of the present invention:
[0088] The method, device, computer equipment and storage medium for controlling the workload of a nuclear power plant overhaul worker of the present invention realize the calculation of the workload of a nuclear power plant overhaul worker. After all work orders have been scheduled in the overhaul plan, the workload of the person in charge of the work every day during the overhaul period can be intuitively seen before the overhaul, which is convenient for reasonable manpower allocation. During the overhaul, combined with the actual arrangement of the overhaul plan, the on-site construction unit is assisted in adjusting the workload of the person in charge of the work to ensure the rationality of the execution of the overhaul plan. BRIEF DESCRIPTION OF THE DRAWINGS
[0089] Figure 1 A flowchart of an embodiment of a method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to the present invention;
[0090] Figure 2 It is a schematic structural view of an embodiment of a workload control device for a nuclear power plant overhaul worker of the present invention.
[0091] Figure 3 The figure is a schematic structural view of an embodiment of a computer device of the present invention. DETAILED DESCRIPTION
[0092] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by technicians in the technical field of this application; the terms used in the specification of the application are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned drawings are intended to cover non-exclusive inclusions. The terms "first", "second", etc. in the specification and claims of this application or the above-mentioned drawings are used to distinguish different objects, not to describe a specific order.
[0093] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0094] The technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings and specific embodiments.
[0095] refer to Figure 1 , shows a flow chart of an embodiment of a method for controlling the workload of a person in charge of nuclear power plant overhaul work, the method for controlling the workload of a person in charge of nuclear power plant overhaul work comprises the following steps:
[0096] S101. Calculate the current overhaul professional coefficient;
[0097] S102, calculating the daily workload of the current person in charge of the overhaul professional work who holds a single work order;
[0098] S103, calculating the total daily workload of the current overhaul professional work leader in executing all work orders;
[0099] S104. Evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders.
[0100] As one of the feasible ways, the calculation of the current overhaul professional coefficient includes the following steps:
[0101] Obtain all historical overhaul data of all nuclear power units in a nuclear power plant; calculate all single historical overhaul professional coefficients of the nuclear power plant based on all historical overhaul data of all nuclear power units in a nuclear power plant;
[0102] According to the professional coefficients of all single historical overhauls of the nuclear power plant, choose one of the following four methods to calculate the professional coefficient of the current overhaul;
[0103] The first method is to take the average of the five most recent historical overhaul professional coefficients of all nuclear power units of the same reactor type as the current overhaul as the current overhaul professional coefficient;
[0104] The second method is to take the weighted average of the professional coefficients of the five most recent historical overhauls from all the professional coefficients of all nuclear power units of the same reactor type as the current overhaul in the nuclear power plant as the current overhaul professional coefficient. The closer the time of the single historical overhaul is to the current overhaul, the greater the weight of the professional coefficient.
[0105] The third method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, take the average of the professional coefficients of the most recent five historical overhauls as the current overhaul professional coefficient;
[0106] The fourth method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, the weighted average of the professional coefficients of the five most recent historical overhauls is taken as the current overhaul professional coefficient. The closer the single historical overhaul time is to the current overhaul, the greater the weight of the professional coefficient.
[0107] When there is sufficient data on the professional coefficients of all single historical overhauls of nuclear power plants, the second method is the best and the third method is the worst.
[0108] Due to the continuous improvement of maintenance management, maintenance equipment, and maintenance technology, the professional coefficients of each overhaul will be slightly different. In theory, the later the overhaul is performed, the more reasonable the professional coefficients. In addition, the differences in the reactor types of each nuclear power unit will also lead to differences in the professional coefficients of the overhaul of nuclear power units of each reactor type. The professional coefficients of overhauls of nuclear power units of the same reactor type are closer. Based on this principle, when there is sufficient data on the professional system of all single historical overhauls of nuclear power plants, it is best to choose the second method to calculate the current overhaul professional coefficient, and it is worst to choose the third method to calculate the current overhaul professional coefficient.
[0109] In this embodiment, as one of the feasible ways, the weights of the professional coefficients of the five most recent historical overhauls sorted in order from the nearest to the current overhaul time are 30%, 25%, 20%, 15% and 10% respectively.
[0110] In this embodiment, as one of the achievable methods, calculating the professional coefficient of a single historical overhaul includes the following steps:
[0111] Calculate the converted working hours for a single work order of a single historical overhaul specialty;
[0112] According to the converted working hours of a single work order of a single historical overhaul specialty, calculate the sum of the converted working hours of all work orders of a single historical overhaul specialty;
[0113] Obtain the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders, and calculate the coefficient of a single historical overhaul specialty based on the sum of the converted working hours of all the work orders of a single historical overhaul specialty and the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders;
[0114] Single historical overhaul specialty coefficient = the sum of converted working hours of all work orders of a single historical overhaul specialty / the total number of days on site for all work persons in charge of a single historical overhaul specialty to execute all work orders;
[0115] Among them, a single work order for a single historical overhaul specialty includes a single standard working time work order for a single historical overhaul specialty and a single non-standard working time work order for a single historical overhaul specialty.
[0116] In this embodiment, as one of the achievable methods, the converted working hours of a single standard working hours work order of a single historical overhaul specialty is calculated, including the following steps:
[0117] Get the standard labor time quota entry of a single standard labor time work order of a single historical overhaul specialty;
[0118] Calculate the converted working hours of a single historical overhaul professional single standard working hour work order based on the standard working hour quota items of a single historical overhaul professional single standard working hour work order.
[0119] In this embodiment, as one of the feasible ways, there is one or more types of maintenance work in a single standard working time work order of a single historical overhaul specialty, which matches one or more standard working time quota entries in the standard working time quota manual; a standard working time quota entry includes the on-site working hours for the maintenance of a single equipment in a type of maintenance work, and the on-site working hours for the maintenance of a single equipment in a type of maintenance work = the number of maintenance personnel for the maintenance of a single equipment in this type of maintenance work × the maintenance working days for the maintenance of a single equipment in this type of maintenance work; the converted working hours of a single standard working time work order of a single historical overhaul specialty is the sum of the on-site working hours for the maintenance of a single equipment in all types of maintenance work in a single standard working time work order of a single historical overhaul specialty.
[0120] In this embodiment, as one of the achievable methods, the converted working hours of a single non-standard working hours work order of a single historical overhaul specialty is calculated, including the following steps:
[0121] Get the contract hours of a single non-standard work order for a single historical overhaul specialty. The contract hours of a single non-standard work order for a single historical overhaul specialty is the hours recommended by the client of the single non-standard work order for a single historical overhaul specialty.
[0122] Calculate the number of people converted for a single non-standard work order for a single historical overhaul specialty based on the contracted work hours for a single non-standard work order for a single historical overhaul specialty;
[0123] Calculate the converted working days of a single non-standard working hours work order for a single historical overhaul specialty based on the contract working hours and converted number of people for the single non-standard working hours work order for a single historical overhaul specialty;
[0124] Calculate the converted working hours of a single non-standard working hours work order of a single historical overhaul specialty based on the converted number of people and converted working days of a single non-standard working hours work order of a single historical overhaul specialty;
[0125] The converted number of employees for a single non-standard work order for a single historical overhaul specialty is the square of the contract hours for a single non-standard work order for a single historical overhaul specialty and the converted number of employees for a single non-standard work order for a single historical overhaul specialty is ≥ 2;
[0126] The calculation formula for the converted working days of a single non-standard working time work order for a single historical overhaul specialty is as follows:
[0127]
[0128] The calculation formula for the converted working hours of a single non-standard working hours work order for a single historical overhaul specialty is as follows:
[0129] H 历史大修 =M 历史大修 ×D 历史大修
[0130] Among them, H 历史大修The converted working hours for a single non-standard working hours work order for a single historical overhaul, D 历史大修 The converted working days of a single non-standard working time work order for a single historical overhaul specialty, M 历史大修 The converted number of people for a single non-standard working time work order for a single historical overhaul.
[0131] In this embodiment, as one of the achievable methods, calculating the daily workload of the current overhaul professional work leader who holds a single work order includes the following steps:
[0132] Calculate the converted man-days for the current person in charge of the overhaul professional work to execute a single work order;
[0133] Obtain the planning window for the current person in charge of overhaul professional work to execute a single work order, and calculate the single-day workload of the current person in charge of overhaul professional work to execute a single work order based on the converted working days and planning window of the current person in charge of overhaul professional work to execute a single work order;
[0134] The daily workload of the current person in charge of overhaul professional work who holds a single work order = the converted working days of the current person in charge of overhaul professional work who holds a single work order / the planning window of the current person in charge of overhaul professional work who holds a single work order;
[0135] Among them, the single work order held by the current person in charge of the overhaul professional work includes a single standard working time work order held by the current person in charge of the overhaul professional work and a single non-standard working time work order held by the current person in charge of the overhaul professional work.
[0136] In this embodiment, as one of the achievable methods, calculating the single-day workload of the current overhaul professional work leader who holds a single standard working time work order includes the following steps:
[0137] Calculate the converted working days for the current overhaul professional work leader to execute a single standard working time work order;
[0138] Obtain the planning window for the current overhaul professional work leader to execute a single standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single standard working time work order;
[0139] The calculation formula for the daily workload of the current overhaul professional work leader holding a single standard working time work order is as follows:
[0140]
[0141] Among them, Ks is the daily workload of the current overhaul professional work leader who executes a single standard working time work order; T is the planning window for the current overhaul professional work leader who executes a single standard working time work order, which is equal to the planned completion time of the current overhaul professional work leader who executes a single standard working time work order minus the planned start time of the current overhaul professional work leader who executes a single standard working time work order; D 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single standard working time work order.
[0142] In this embodiment, as one of the achievable methods, calculating the single-day workload of the current overhaul professional work leader who holds a single non-standard working time work order includes the following steps:
[0143] Calculate the converted working days for the current overhaul professional work leader to execute a single non-standard working time work order;
[0144] Obtain the planning window for the current overhaul professional work leader to execute a single non-standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single non-standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single non-standard working time work order;
[0145] The current calculation formula for the daily workload of the person in charge of the overhaul professional work who holds a single non-standard working time work order is as follows:
[0146]
[0147] Among them, Ks , Execute the single-day workload of holding a single non-standard working time work order for the current overhaul professional work leader; T , The planning window for the current overhaul professional work leader to execute a single non-standard work order, which is equal to the planned completion time of the current overhaul professional work leader to execute a single non-standard work order minus the planned start time of the current overhaul professional work leader to execute a single non-standard work order; D , 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single non-standard working time work order.
[0148] In this embodiment, as one of the achievable methods, calculating the converted working days of the current overhaul professional work leader who executes a single standard working time work order includes the following steps:
[0149] Get the standard working hours quota entry of the current overhaul professional work leader who holds a single standard working hours work order;
[0150] According to the standard working hours quota entry of the current overhaul professional work person in charge who executes the single standard working hours work order, calculate the converted working hours and converted number of people for the current overhaul professional work person in charge who executes the single standard working hours work order;
[0151] Calculate the converted working days of the current overhaul professional work leader who executes a single standard working hours work order based on the converted working hours and converted number of people who execute the single standard working hours work order;
[0152] The current calculation formula for converting working days for the person in charge of overhaul professional work who holds a single standard working time work order is as follows:
[0153]
[0154] Among them, D 当前大修 Execute the conversion of working days for the current overhaul professional work leader who holds a single standard working time work order; 当前大修 Execute the converted working hours for the current overhaul professional work leader who holds a single standard working hours work order; M 当前大修 The number of people who hold a single standard working time work order is calculated for the current overhaul professional work leader.
[0155] In this embodiment, as one of the achievable methods, the current person in charge of the overhaul professional work holds a single standard work time work order with one or more types of maintenance work, matching one or more standard work time quota entries; a standard work time quota entry includes the on-site working hours for the maintenance of a single device in a type of maintenance work, and the on-site working hours for the maintenance of a single device in a type of maintenance work = the number of maintenance personnel for the maintenance of a single device in this type of maintenance work × the maintenance man-days for the maintenance of a single device in this type of maintenance work;
[0156] The converted working hours for the current person in charge of overhaul professional work to execute a single standard working hours work order is the sum of the on-site working hours for single equipment maintenance in all types of maintenance work executed by the current person in charge of overhaul professional work holding a single standard working hours work order;
[0157] The converted number of people who are currently in charge of overhaul professional work and are holding a single standard working time work order is the maximum number of people who are currently in charge of overhaul professional work and are responsible for the maintenance and inspection of a single piece of equipment in all types of maintenance work that are held by the single standard working time work order.
[0158] In this embodiment, as one of the achievable methods, a standard labor quota item includes a contract labor calculation formula for a type of maintenance work, and the contract labor calculation formula for a type of maintenance work is:
[0159] S=(w×m)×c×n1×η+n2×(p×r)
[0160] Where S is the contractual working hours for this type of maintenance work, in units of man-days per person;
[0161] w is the number of maintenance personnel for a single piece of equipment under this type of maintenance work, m is the maintenance man-days for a single piece of equipment under this type of maintenance work, and w×m is the on-site man-hours for a single piece of equipment under this type of maintenance work;
[0162] p is the preparation time for the maintenance of a single piece of equipment in this type of maintenance work, r is the reporting time for the maintenance of a single piece of equipment in this type of maintenance work, and p×r is the auxiliary time for the maintenance of a single piece of equipment in this type of maintenance work;
[0163] c is the coefficient of on-site maintenance hours for a single piece of equipment in this type of maintenance work;
[0164] n1 is the number of equipment in this type of maintenance work; n2 is the auxiliary coefficient, which is used to adjust the auxiliary working hours of single equipment maintenance in this type of maintenance work under different numbers of equipment;
[0165] η is the multiple-unit coefficient, which is used to adjust the on-site working hours for this type of maintenance work under different numbers of equipment.
[0166] In this embodiment, as one of the achievable methods, the calculation of the converted working days of the current overhaul professional work leader who holds a single non-standard working time work order includes the following steps:
[0167] Get the contract working hours of the current overhaul professional work leader who performs a single non-standard working hours work order. The contract working hours of the current overhaul professional work leader who performs a single non-standard working hours work order are the working hours recommended by the client who performs the single non-standard working hours work order;
[0168] According to the contract working hours of the current overhaul professional work leader who holds a single non-standard working hours work order, calculate the converted number of people who are currently in charge of the overhaul professional work and hold a single non-standard working hours work order;
[0169] Calculate the converted working days of the current overhaul professional work leader who holds a single non-standard working hours work order based on the contract working hours and converted number of people who hold a single non-standard working hours work order held by the current overhaul professional work leader;
[0170] The converted working days of the current overhaul professional work leader who holds a single non-standard working time work order = the contract working hours of the current overhaul professional work leader who holds a single non-standard working time work order / the converted number of people who hold a single non-standard working time work order;
[0171] The converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is the square of the contract working hours of the current overhaul professional work leader holding a single non-standard working time work order, and the converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is ≥2.
[0172] In this embodiment, as one of the achievable methods, the total daily workload of the current overhaul professional work leader in executing all work orders held by him is calculated, including the following steps:
[0173] According to the daily workload of the current person in charge of overhaul professional work who holds a single work order, the sum of the daily workload of the current person in charge of overhaul professional work who holds all work orders is calculated;
[0174] The total daily workload of the current person in charge of overhaul professional work who holds all work orders is calculated based on the sum of the daily workload of the current person in charge of overhaul professional work who holds all work orders and the current overhaul professional coefficient;
[0175] The total daily workload of the current person in charge of overhaul professional work in executing all work orders held = the sum of the daily workload of the current person in charge of overhaul professional work in executing all work orders held / current overhaul professional coefficient.
[0176] In this embodiment, as one of the achievable methods, evaluating whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders includes the following steps:
[0177] If the total daily workload of the current overhaul professional work leader who holds all the work orders is less than 1, it is determined that the total daily workload of the current overhaul professional work leader is normal, and the current overhaul professional work leader can complete the work of the day normally, and there is no need to adjust the total daily workload of the current overhaul professional work leader who holds all the work orders;
[0178] 1≤The total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds<2, then the current person in charge of overhaul professional work is judged to be under heavy pressure, and the current person in charge of overhaul professional work can barely complete the work of the day, and the total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds is appropriately adjusted;
[0179] If the total daily workload of the current overhaul professional work leader executing all work orders is ≥ 2, the current overhaul professional work leader’s total daily workload is judged to be overloaded, and the current overhaul professional work leader cannot complete the work for the day, and the current overhaul professional work leader’s total daily workload needs to be adjusted.
[0180] refer to Figure 2 As an implementation of the above method, the present invention provides an embodiment of a workload control device for a person in charge of nuclear power plant overhaul work. The embodiment of the device corresponds to the embodiment of the workload control method for a person in charge of nuclear power plant overhaul work, and the device can be specifically applied to various electronic devices.
[0181] The workload control device for the person in charge of nuclear power plant overhaul work described in this embodiment includes:
[0182] The first calculation module 201 is used to calculate the current overhaul professional coefficient;
[0183] The second calculation module 202 is used to calculate the daily workload of the current overhaul professional work person in charge who holds a single work order;
[0184] The third calculation module 203 is used to calculate the total daily workload of the current overhaul professional work leader who executes all work orders;
[0185] Evaluation module 204, used to evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders;
[0186] The first calculation module 201 , the second calculation module 202 , the third calculation module 203 and the evaluation module 204 are data connected.
[0187] As an implementation of the above method, the present invention provides an embodiment of a computer device, and the embodiment of the computer device corresponds to the embodiment of the workload control method for the person in charge of the nuclear power plant overhaul work.
[0188] The computer device described in this embodiment includes a memory 301, a processor 302 and a network interface 303 that are interconnected and communicated through a system bus. It should be noted that the figure only shows a computer device with components 301-303, but it should be understood that it is not required to implement all the components shown, and more or fewer components can be implemented instead. Among them, those skilled in the art can understand that the computer device here is a device that can automatically perform numerical calculations and / or information processing according to pre-set or stored instructions, and its hardware includes but is not limited to microprocessors, application-specific integrated circuits, programmable gate arrays, digital processors, embedded devices, etc.
[0189] The computer device may be a computing device such as a desktop computer, a notebook, a PDA, a cloud server, etc. The computer device may interact with a user through a keyboard, a mouse, a remote controller, a touch pad, or a voice control device.
[0190] The memory 301 includes at least one type of readable storage medium, and the readable storage medium includes flash memory, hard disk, multimedia card, card-type memory, random access memory, static random access memory, read-only memory, electrically erasable programmable read-only memory, programmable read-only memory, magnetic memory, disk, optical disk, etc. In some embodiments, the memory 301 can be an internal storage unit of the computer device, such as a hard disk or memory of the computer device. In other embodiments, the memory 301 can also be an external storage device of the computer device, such as a plug-in hard disk, smart memory card, secure digital card, flash memory card, etc. equipped on the computer device. Of course, the memory 301 can also include both the internal storage unit of the computer device and its external storage device. In this embodiment, the memory 301 is generally used to store the operating system and various application software installed on the computer device, such as the computer-readable instructions of the workload control method of the person in charge of the overhaul of the nuclear power plant mentioned above. In addition, the memory 301 can also be used to temporarily store various types of data that have been output or are to be output.
[0191] The processor 302 may be a central processing unit, a controller, a microcontroller, a microprocessor, or other data processing chip in some embodiments. The processor 302 is generally used to control the overall operation of the computer device. In this embodiment, the processor 302 is used to run the computer-readable instructions or process data stored in the memory 301, such as running the computer-readable instructions of the workload control method for the person in charge of the nuclear power plant overhaul work.
[0192] The network interface 303 may include a wireless network interface or a wired network interface. The network interface 303 is generally used to establish a communication connection between the computer device and other electronic devices.
[0193] As an implementation of the above method, the present invention provides an embodiment of a computer-readable storage medium, and the embodiment of the computer-readable storage medium corresponds to the embodiment of the workload control method for the person in charge of the above nuclear power plant overhaul work.
[0194] The computer-readable storage medium described in this embodiment stores computer-readable instructions, and the computer-readable instructions can be executed by at least one processor to enable the at least one processor to perform the steps of the workload control method for the person in charge of the nuclear power plant overhaul work as described above.
[0195] The workload control method, device, computer equipment and storage medium of the nuclear power plant overhaul work supervisor of this embodiment realizes the workload calculation of the nuclear power plant overhaul work supervisor. After the overhaul plan has completed the arrangement of all work order plans, the workload of the work supervisor every day during the overhaul period can be intuitively seen before the overhaul, which is convenient for reasonable manpower allocation; during the overhaul, combined with the actual arrangement of the overhaul plan, the on-site construction unit is assisted in adjusting the workload of the work supervisor to ensure the rationality of the execution of the overhaul plan.
[0196] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for controlling the workload of a person in charge of nuclear power plant overhaul work, characterized in that: The following steps are involved: S101. Calculate the current overhaul professional coefficient; S102, calculating the daily workload of the current overhaul professional work leader who holds a single work order; S103, calculating the total daily workload of the current overhaul professional work leader in executing all work orders; S104. Evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders.
2. The method for controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 1, characterized in that: Calculation of the current overhaul specialty coefficient includes the following steps: Obtain all historical overhaul data of all nuclear power units in a nuclear power plant; calculate all single historical overhaul professional coefficients of the nuclear power plant based on all historical overhaul data of all nuclear power units in a nuclear power plant; According to the professional coefficients of all single historical overhauls of the nuclear power plant, choose one of the following four methods to calculate the professional coefficient of the current overhaul; The first method is to take the average of the professional coefficients of the most recent historical overhauls from all the professional coefficients of all nuclear power units of the same reactor type as the current overhaul in the nuclear power plant as the professional coefficient of the current overhaul; The second method is to take the weighted average of the most recent historical overhaul professional coefficients from all the single historical overhaul professional coefficients of all nuclear power units of the same reactor type as the current overhaul as the current overhaul professional coefficient. The closer the single historical overhaul time is to the current overhaul, the greater the weight of the professional coefficient. The third method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, take the average of the professional coefficients of the most recent historical overhauls as the current overhaul professional coefficient; The fourth method: among all the single historical overhaul professional coefficients of all nuclear power units in the nuclear power plant, the weighted average of the professional coefficients of the most recent historical overhauls is taken as the current overhaul professional coefficient. The closer the single historical overhaul time is to the current overhaul time, the greater the weight of the professional coefficient. When there is sufficient data on the professional coefficients of all single historical overhauls of nuclear power plants, the second method is the best and the third method is the worst.
3. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 2, characterized in that: Calculating the professional coefficient of a single historical overhaul includes the following steps: Calculate the converted working hours for a single work order of a single historical overhaul specialty; According to the converted working hours of a single work order of a single historical overhaul specialty, calculate the sum of the converted working hours of all work orders of a single historical overhaul specialty; Obtain the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders, and calculate the coefficient of a single historical overhaul specialty based on the sum of the converted working hours of all the work orders of a single historical overhaul specialty and the total number of days on site that all the persons in charge of a single historical overhaul specialty perform all the work orders; Single historical overhaul specialty coefficient = the sum of converted working hours of all work orders of a single historical overhaul specialty / the total number of days on site for all work persons in charge of a single historical overhaul specialty to execute all work orders; Among them, a single work order for a single historical overhaul specialty includes a single standard working time work order for a single historical overhaul specialty and a single non-standard working time work order for a single historical overhaul specialty.
4. The method for controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 3, characterized in that: Calculating the converted working hours for a single standard working hours work order for a single historical overhaul specialty includes the following steps: Get the standard labor time quota entry of a single standard labor time work order of a single historical overhaul specialty; Calculate the converted working hours of a single historical overhaul professional single standard working hour work order based on the standard working hour quota items of a single historical overhaul professional single standard working hour work order.
5. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 4, characterized in that: There is one or more types of maintenance work in a single standard working time work order for a single historical overhaul, matching one or more standard working time quota entries in the standard working time quota manual; a standard working time quota entry includes the on-site working hours for the maintenance of a single equipment in a type of maintenance work, and the on-site working hours for the maintenance of a single equipment in a type of maintenance work = the number of maintenance personnel for the maintenance of a single equipment in this type of maintenance work × the maintenance working days for the maintenance of a single equipment in this type of maintenance work; the converted working hours of a single standard working time work order for a single historical overhaul is the sum of the on-site working hours for the maintenance of a single equipment in all types of maintenance work in a single standard working time work order for a single historical overhaul.
6. The method for managing and controlling the workload of a nuclear power plant overhaul supervisor according to claim 3, characterized in that: Calculating the converted working hours for a single non-standard working hours work order for a single historical overhaul specialty includes the following steps: Get the contract hours of a single non-standard work order for a single historical overhaul specialty; Calculate the number of people converted for a single non-standard work order for a single historical overhaul specialty based on the contracted work hours for a single non-standard work order for a single historical overhaul specialty; Calculate the converted working days of a single non-standard working hours work order for a single historical overhaul specialty based on the contract working hours and converted number of people for the single non-standard working hours work order for a single historical overhaul specialty; Calculate the converted working hours of a single non-standard working hours work order of a single historical overhaul specialty based on the converted number of people and converted working days of a single non-standard working hours work order of a single historical overhaul specialty; The converted number of employees for a single non-standard work order for a single historical overhaul specialty is the square of the contract hours for a single non-standard work order for a single historical overhaul specialty and the converted number of employees for a single non-standard work order for a single historical overhaul specialty is ≥ 2; The calculation formula for the converted working days of a single non-standard working time work order for a single historical overhaul specialty is as follows: The calculation formula for the converted working hours of a single non-standard working hours work order for a single historical overhaul specialty is as follows: H 历史大修 =M 历史大修 ×D 历史大修 Among them, H 历史大修 The converted working hours for a single non-standard working hours work order for a single historical overhaul, M 历史大修 The converted working days for a single non-standard working time work order of a single historical overhaul specialty, D 历史大修 The converted number of people for a single non-standard working time work order for a single historical overhaul.
7. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 1, characterized in that: Calculating the daily workload of the current overhaul professional work leader holding a single work order includes the following steps: Calculate the converted man-days for the current person in charge of the overhaul professional work to execute a single work order; Obtain the planning window for the current person in charge of overhaul professional work to execute a single work order, and calculate the single-day workload of the current person in charge of overhaul professional work to execute a single work order based on the converted working days and planning window of the current person in charge of overhaul professional work to execute a single work order; The daily workload of the current person in charge of overhaul professional work who holds a single work order = the converted working days of the current person in charge of overhaul professional work who holds a single work order / the planning window of the current person in charge of overhaul professional work who holds a single work order; Among them, the single work order held by the current person in charge of the overhaul professional work includes a single standard working time work order held by the current person in charge of the overhaul professional work and a single non-standard working time work order held by the current person in charge of the overhaul professional work.
8. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 7, characterized in that: Calculating the daily workload of the current overhaul professional work leader who holds a single standard working time work order includes the following steps: Calculate the converted working days for the current overhaul professional work leader to execute a single standard working time work order; Obtain the planning window for the current overhaul professional work leader to execute a single standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single standard working time work order; The calculation formula for the daily workload of the current overhaul professional work leader holding a single standard working time work order is as follows: Among them, Ks is the daily workload of the current overhaul professional work leader who executes a single standard working time work order, T is the planning window for the current overhaul professional work leader who executes a single standard working time work order, and D 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single standard working time work order.
9. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 8, characterized in that: Calculating the converted working days of the current overhaul professional work leader who holds a single standard working time work order includes the following steps: Get the standard working hours quota entry of the current overhaul professional work leader who holds a single standard working hours work order; According to the standard working hours quota entry of the current overhaul professional work person in charge who executes the single standard working hours work order, calculate the converted working hours and converted number of people for the current overhaul professional work person in charge who executes the single standard working hours work order; Calculate the converted working days of the current overhaul professional work leader who executes a single standard working hours work order based on the converted working hours and converted number of people who execute the single standard working hours work order; The current calculation formula for converting working days for the person in charge of overhaul professional work who holds a single standard working time work order is as follows: Among them, D 当前大修 The person in charge of the current overhaul professional work shall execute the converted working days for the person who holds a single standard working time work order. 当前大修 The current person in charge of the overhaul professional work performs the converted working hours for the single standard working hours work order, M 当前大修 The number of people who hold a single standard working time work order is calculated for the current overhaul professional work leader.
10. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 9, characterized in that: The current person in charge of overhaul professional work holds a single standard working time work order in which there is one or more types of maintenance work, matching one or more standard working time quota entries; a standard working time quota entry includes the on-site working hours for the maintenance of a single equipment in a type of maintenance work, and the on-site working hours for the maintenance of a single equipment in a type of maintenance work = the number of maintenance personnel for the maintenance of a single equipment in this type of maintenance work × the maintenance working days for the maintenance of a single equipment in this type of maintenance work; the converted working hours for the current person in charge of overhaul professional work to execute a single standard working time work order is the sum of the on-site working hours for the maintenance of a single equipment in all types of maintenance work executed by the current person in charge of overhaul professional work holding a single standard working time work order; the converted number of people for the current person in charge of overhaul professional work to execute a single standard working time work order is the maximum number of maintenance and overhaul personnel for a single equipment in all types of maintenance work executed by the current person in charge of overhaul professional work holding a single standard working time work order.
11. The method for managing and controlling the workload of a nuclear power plant overhaul supervisor according to claim 7, characterized in that: Calculating the daily workload of the current overhaul professional work leader who holds a single non-standard working time work order includes the following steps: Calculate the converted working days for the current overhaul professional work leader to execute a single non-standard working time work order; Obtain the planning window for the current overhaul professional work leader to execute a single non-standard working time work order, and calculate the single-day workload of the current overhaul professional work leader to execute a single non-standard working time work order based on the converted working days and planning window of the current overhaul professional work leader to execute a single non-standard working time work order; The current calculation formula for the daily workload of the person in charge of the overhaul professional work who holds a single non-standard working time work order is as follows: Among them, Ks' is the daily workload of the current overhaul professional work leader who holds a single non-standard working time work order, T' is the planning window for the current overhaul professional work leader to hold a single non-standard working time work order, and D' 当前大修 Execute the conversion of working days for the current person in charge of overhaul professional work who holds a single non-standard working time work order.
12. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 11, characterized in that: Calculating the converted working days of the current overhaul professional work leader who holds a single non-standard working time work order includes the following steps: Get the contract hours of the current overhaul professional work leader who holds a single non-standard work hour work order; According to the contract working hours of the current overhaul professional work leader who holds a single non-standard working hours work order, calculate the converted number of people who are currently in charge of the overhaul professional work and hold a single non-standard working hours work order; Calculate the converted working days of the current overhaul professional work leader who holds a single non-standard working hours work order based on the contract working hours and converted number of people who hold a single non-standard working hours work order held by the current overhaul professional work leader; The converted working days of the current overhaul professional work leader who holds a single non-standard working time work order = the contract working hours of the current overhaul professional work leader who holds a single non-standard working time work order / the converted number of people who hold a single non-standard working time work order; The converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is the square of the contract working hours of the current overhaul professional work leader holding a single non-standard working time work order, and the converted number of people who are currently in charge of overhaul professional work and hold a single non-standard working time work order is ≥2.
13. The method for managing and controlling the workload of a person in charge of nuclear power plant overhaul work according to claim 1, characterized in that: Calculating the total daily workload of the current overhaul professional work leader in executing all work orders includes the following steps: According to the daily workload of the current person in charge of overhaul professional work who holds a single work order, the sum of the daily workload of the current person in charge of overhaul professional work who holds all work orders is calculated; The total daily workload of the current person in charge of overhaul professional work who holds all work orders is calculated based on the sum of the daily workload of the current person in charge of overhaul professional work who holds all work orders and the current overhaul professional coefficient; The total daily workload of the current person in charge of overhaul professional work in executing all work orders held = the sum of the daily workload of the current person in charge of overhaul professional work in executing all work orders held / current overhaul professional coefficient.
14. The method for managing and controlling the workload of a nuclear power plant overhaul supervisor according to claim 1, characterized in that: Evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders, including the following steps: If the total daily workload of the current overhaul professional work leader who executes all the work orders he holds is less than 1, it is determined that the total daily workload of the current overhaul professional work leader who executes all the work orders he holds is normal, and there is no need to adjust the total daily workload of the current overhaul professional work leader who executes all the work orders he holds; 1≤The total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds<2, then the current person in charge of overhaul professional work is judged to be under heavy pressure, and the current person in charge of overhaul professional work can barely complete the work of the day, and the total daily workload of the current person in charge of overhaul professional work in executing all the work orders he holds is appropriately adjusted; If the total daily workload of the current person in charge of overhaul professional work executing all work orders is ≥ 2, it is determined that the total daily workload of the current person in charge of overhaul professional work is overloaded, and the total daily workload of the current person in charge of overhaul professional work needs to be adjusted.
15. A workload control device for a nuclear power plant overhaul supervisor, characterized in that: include: A first calculation module (201) is used to calculate the current overhaul professional coefficient; The second calculation module (202) is used to calculate the daily workload of the current overhaul professional work leader who holds a single work order; The third calculation module (203) is used to calculate the total daily workload of the current overhaul professional work leader in executing all work orders; The evaluation module (204) is used to evaluate whether it is necessary to adjust the total daily workload of the current overhaul professional work leader who holds all work orders.
16. A computer device comprising a memory and a processor, wherein the memory stores computer-readable instructions, characterized in that: When the processor executes the computer-readable instructions, the steps of the workload control method for the person in charge of nuclear power plant overhaul work are implemented as described in any one of claims 1-14.
17. A computer-readable storage medium having computer-readable instructions stored thereon, characterized in that: When the computer-readable instructions are executed, the steps of the workload control method for the person in charge of nuclear power plant overhaul work are implemented as described in any one of claims 1-14.