Offshore wind power flexible DC transmission system sending end pre-charging control method and device
The pre-charging process of the offshore wind power flexible DC transmission system is optimized by using model predictive control strategy, which solves the problems of high control complexity and strong model dependence in the existing technology, and realizes precise control of charging current and voltage and improved dynamic response performance.
Patent Information
- Application Number
- CN202411253996.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-09-09
AI Technical Summary
In the pre-charging process of existing offshore wind power flexible DC transmission systems, closed-loop PI controllers suffer from high control complexity, difficulty in parameter adjustment, and poor dynamic response. Furthermore, the deadbeat control system is highly dependent on the accuracy of the model and has strict computational requirements.
A model predictive control strategy is adopted. By obtaining the voltage matrix of the bridge arm submodule, the charging current and energy at the next moment are predicted, the pre-charging process is optimized, and a cost function is added to balance the control objective, so as to ensure the safety and stability of the charging process.
It achieves precise control of DC charging current and submodule voltage, has good dynamic response performance, eliminates surge current interference, and ensures the balance and efficiency of submodule charging.
Smart Images

Figure CN118783516B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of offshore wind power high voltage direct current transmission control, and in particular to a sending end pre-charging control method and device for an offshore wind power flexible direct current transmission system. Background Art
[0002] The existing technology mainly uses a closed-loop PI controller for pre-charging. The charging current on the DC bus or the AC side can be adjusted to a constant value, so the charging speed is significantly improved. In addition, in order to improve the complexity of the closed-loop control system and the difficulty of parameter adjustment, the researchers proposed a deadbeat control system for pre-charging. Compared with the closed-loop PI controller, the deadbeat predictive control strategy has fast dynamic response and small current fluctuation.
[0003] The closed-loop PI controller has high control complexity, difficult parameter adjustment, and poor dynamic response. The PI controller mainly adjusts the system through proportional and integral links, and it is necessary to determine the optimal parameters through repeated experiments and experience, which increases the complexity and time cost of debugging. In addition, the PI controller may not be able to effectively compensate for the dynamic errors of the system.
[0004] The deadbeat control system predicts the system behavior in the next control cycle through a mathematical model based on the current state and future goals of the system, and calculates the control amount that should be applied accordingly. The key to this method is to establish an accurate system model and be able to quickly solve the required control instructions. The performance of deadbeat predictive control is highly dependent on the accuracy of the system model. If there is a deviation between the model and the actual system, the control effect may be affected. Since the deadbeat control system needs to perform accurate calculations and predictions in each control cycle, it has high requirements on the computing power and speed of the controller. Summary of the invention
[0005] In view of this, the present invention provides a sending-end pre-charging control method and device for an offshore wind power flexible direct current transmission system to solve the problem of how to optimize the pre-charging process.
[0006] In the first aspect, the present invention provides a pre-charging control method for the sending end of an offshore wind power flexible direct current transmission system, wherein the sending end of the transmission system includes a converter, and each bridge arm of the converter is composed of a plurality of sub-modules connected in series. The pre-charging control method includes: obtaining the voltage of each sub-module of the upper bridge arm and the voltage of each sub-module of the lower bridge arm of each bridge arm at the current moment, and establishing an upper bridge arm sub-module voltage matrix and a lower bridge arm sub-module voltage matrix of each bridge arm at the current moment; adopting a model prediction method, according to the upper bridge arm sub-module voltage matrix, the lower bridge arm sub-module voltage matrix and the bridge arm charging current of each bridge arm at the current moment, and the DC voltage reference value at the next moment, predicting the bridge arm charging current of each bridge arm at the next moment, and the bridge arm charging current of each bridge arm at the next moment. The arm charging current is determined by the number of upper arm submodules and lower arm submodules put into operation at the next moment; based on the upper arm voltage of each submodule of each bridge arm, the voltage of each submodule of the lower bridge arm, the arm charging current and the number of submodules put into operation at the current moment, the upper arm energy and the lower arm energy of each bridge arm at the next moment are predicted; according to multiple arm charging currents at the next moment, the arm charging current reference values at the next moment, the upper arm energy and the lower arm energy of each bridge arm at the next moment, multiple cost functions are calculated; the number of upper arm submodules and lower arm submodules put into operation of each bridge arm at the next moment corresponding to the minimum cost function among the multiple cost functions is used as the number of upper arm submodules and lower arm submodules put into operation of each bridge arm at the next moment.
[0007] The present invention adopts a model predictive control strategy to optimize the pre-charging process in the controllable charging process, and ensures the safety, stability and efficiency of the charging process by adding constraints to control targets such as DC charging current and submodule voltage; by introducing a cost function, the balance relationship between different control targets is quantified, thereby finding the optimal control strategy.
[0008] The present invention optimizes the charging process through model predictive control, can effectively control the charging current near the reference value, realizes the precise control of the DC charging current and the submodule voltage, and the control system can quickly and evenly complete the pre-charging of the submodule capacitor, and has good dynamic response performance.
[0009] The present invention adopts the strategy of model predictive control to optimize the pre-charging process, predicts future behavior based on the dynamic model of the system, and optimizes the current control decision accordingly. The core of the control is to ensure that the DC charging current of each bridge arm is a constant value, eliminate the interference of surge current on the system, and ensure that each submodule is charged evenly.
[0010] In an optional embodiment, the process of establishing an upper bridge arm submodule voltage matrix and a lower bridge arm submodule voltage matrix of each bridge arm at the current moment includes: numbering each submodule of the upper bridge arm of each bridge arm, and numbering each submodule of the lower bridge arm of each bridge arm; arranging the voltage of each submodule of the upper bridge arm of each bridge arm in ascending order to form an upper bridge arm submodule voltage matrix of each bridge arm, and placing each submodule serial number in a corresponding position in the voltage matrix; arranging the voltage of each submodule of the lower bridge arm of each bridge arm in ascending order to form a lower bridge arm submodule voltage matrix of each bridge arm, and placing each submodule serial number in a corresponding position in the voltage matrix.
[0011] In an optional embodiment, the process of predicting the bridge arm charging current of each bridge arm at multiple next moments includes: using a model prediction method to predict the sub-module voltage sum of each bridge arm at multiple next moments based on the upper bridge arm sub-module voltage matrix and the lower bridge arm sub-module voltage matrix of each bridge arm at the current moment; predicting the bridge arm charging current of each bridge arm at multiple next moments based on the sub-module voltage sum of each bridge arm at multiple next moments, the DC voltage reference value at the next moment, and the bridge arm charging current at the current moment.
[0012] In an optional implementation, the process of predicting the sum of the submodule voltages of each bridge arm at multiple next moments includes: calculating the sum of the upper bridge arm submodule voltage matrix of each bridge arm at the current moment. x The sum of the voltages of the submodules is taken as the first voltage sum; the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment is calculated. x The sum of the submodule voltages is used as the second sum of voltages; the sum of the first voltage and the sum of the second voltage are used as the submodule voltage of each bridge arm at the next moment; and the sum of the first voltage and the sum of the second voltage are used as the submodule voltage of each bridge arm at the next moment. x Increment between 1 and N to obtain the submodule voltage of each bridge arm at multiple next moments; wherein, the sum of the number of upper bridge arm submodules and the number of lower bridge arm submodules put into operation should be greater than N and less than 2N, where N is the number of upper bridge arm submodules and the number of lower bridge arm submodules.
[0013] In an optional embodiment, the process of predicting the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment includes: calculating the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the current moment based on the upper bridge arm voltage of each submodule and the lower bridge arm voltage of each submodule of each bridge arm at the current moment; predicting the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the next moment based on the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the current moment, the bridge arm charging current and the number of submodules put into use; calculating the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment based on the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the next moment.
[0014] In an optional embodiment, the process of calculating multiple cost functions includes: for each bridge arm, subtracting a bridge arm charging current reference value at the next moment from its bridge arm charging current at each next moment to obtain multiple current deviation values of each bridge arm at the next moment; for each bridge arm, subtracting an upper bridge arm energy from a lower bridge arm energy at the next moment to obtain an energy deviation value of each bridge arm; and obtaining multiple cost functions of each bridge arm based on the multiple current deviation values and energy deviation values of each bridge arm at the next moment.
[0015] In a second aspect, the present invention provides a pre-charging control device for a sending end of an offshore wind power flexible direct current transmission system, the device comprising: a voltage matrix establishment module, used to obtain the voltage of each submodule of an upper bridge arm and each submodule of a lower bridge arm of each bridge arm at a current moment, and establish the voltage matrix of the upper bridge arm submodule and the voltage matrix of the lower bridge arm submodule of each bridge arm at a current moment; a first prediction module, used to adopt a model prediction method, according to the voltage matrix of the upper bridge arm submodule, the voltage matrix of the lower bridge arm submodule and the bridge arm charging current of each bridge arm at a current moment, and the DC voltage reference value at a next moment, predict the bridge arm charging current of each bridge arm at a plurality of next moments, the bridge arm charging current of each bridge arm at a plurality of next moments is calculated by the upper bridge arm submodule and the lower bridge arm submodule at a next moment. The number of modules put into operation is determined; a second prediction module is used to predict the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment based on the upper bridge arm voltage of each submodule of each bridge arm at the current moment, the voltage of each submodule of the lower bridge arm, the bridge arm charging current and the number of submodules put into operation; a calculation module is used to calculate multiple cost functions according to multiple bridge arm charging currents at the next moment, the bridge arm charging current reference values at the next moment, and the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment; a cyclic iteration comparison module is used to use the number of upper bridge arm submodules and lower bridge arm submodules put into operation of each bridge arm at the next moment corresponding to the minimum cost function among the multiple cost functions as the number of upper bridge arm submodules and lower bridge arm submodules put into operation of each bridge arm at the next moment.
[0016] In a third aspect, the present invention provides a computer device, comprising: a memory and a processor, the memory and the processor being communicatively connected to each other, the memory storing computer instructions, and the processor executing the computer instructions to execute the sending-end pre-charging control method of the offshore wind power flexible direct current transmission system of the first aspect or any corresponding embodiment thereof.
[0017] In a fourth aspect, the present invention provides a computer-readable storage medium having computer instructions stored thereon, the computer instructions being used to enable a computer to execute the sending-end pre-charging control method for an offshore wind power flexible direct current transmission system of the first aspect or any corresponding embodiment thereof. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0019] Figure 1 is a single-phase equivalent circuit diagram of a pre-charging valve at the sending end according to an embodiment of the present invention;
[0020] Figure 2 It is a flow chart of a method for controlling pre-charging of a sending end of an offshore wind power flexible direct current transmission system according to an embodiment of the present invention;
[0021] Figure 3 It is a flow chart of another method for controlling pre-charging of a sending end of an offshore wind power flexible direct current transmission system according to an embodiment of the present invention;
[0022] Figure 4 It is a flow chart of another method for controlling pre-charging of a sending end of an offshore wind power flexible direct current transmission system according to an embodiment of the present invention;
[0023] Figure 5 It is a flow chart of another method for controlling pre-charging of a sending end of an offshore wind power flexible direct current transmission system according to an embodiment of the present invention;
[0024] Figure 6 is a pre-charging control block diagram according to an embodiment of the present invention;
[0025] Figure 7 It is a flow chart of another method for controlling pre-charging of a sending end of an offshore wind power flexible direct current transmission system according to an embodiment of the present invention;
[0026] Figure 8 It is a schematic diagram of the hardware structure of a computer device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0028] According to an embodiment of the present invention, an embodiment of a pre-charging control method for a sending end of an offshore wind power flexible direct current transmission system is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described may be executed in an order different from that shown here.
[0029] In the uncontrolled charging stage, the sending-end converter is connected to the receiving-end converter through the DC bus, and its submodule capacitor is first charged uncontrolled through the anti-parallel diode of the switching device. In this stage, similar to the receiving-end converter, the switching devices of each submodule are locked, and the upper and lower bridge arm submodules are connected to the DC bus through anti-parallel diodes. The DC bus provides charging current. After charging, the capacitor voltage of each submodule can be charged to Udc / 2N. This stage does not involve complex control strategies. Then it enters the controlled charging stage. In this stage, the number of submodules that need to be turned on needs to be less than 2N, and a certain control strategy is adopted to ensure that the submodule voltage is charged to the rated voltage. Based on the above, in this embodiment, a sending-end pre-charging control method for an offshore wind power flexible DC transmission system is provided, which is applied to the controllable charging stage.
[0030] The single-phase equivalent circuit of the pre-charging converter valve at the sending end is as follows Figure 1 As shown, the transmission system sending end includes a converter, each bridge arm of the converter is composed of multiple sub-modules connected in series. Figure 1 The equivalent circuit shown is Figure 2 As shown, the pre-charge control method includes:
[0031] Step S1: obtaining the voltage of each submodule of the upper bridge arm and each submodule of the lower bridge arm of each bridge arm at the current moment, and establishing the voltage matrix of the upper bridge arm submodule and the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment.
[0032] Specifically, by Figure 1 The equivalent circuit shown can be obtained as follows:
[0033] (1)
[0034] in, L =2 La , Udc is the DC voltage, Uaj is the voltage of the upper and lower bridge arms, Ipj is the bridge arm charging current, where j = phase A, B, C. Discretizing equation (1) using the backward Euler method yields:
[0035] (2)
[0036] in, ipj ( k +1) is the predicted value of the bridge arm charging current at the next moment; Udc *( k +1) is the DC voltage reference value at the next moment; Uaj ( k +1) is the predicted value of the sum of the submodule voltages of the bridge arm at the next moment; ipj ( k ) is the charging current of the bridge arm at the current moment.
[0037] Based on formula (2), the sum of the submodule voltages of the bridge arm at the current moment is used to predict the sum of the submodule voltages of the bridge arm at the next moment, thereby obtaining the predicted value of the bridge arm charging current at the next moment. The sum of the submodule voltages of the bridge arm at the current moment is related to the number of submodules. Therefore, in order to make the bridge arm charging current at the next moment follow the bridge arm current reference value at the next moment, a submodule voltage matrix is established to obtain multiple predicted values of the bridge arm charging current at the next moment, such as Figure 3 As shown, the process of establishing the upper bridge arm submodule voltage matrix and the lower bridge arm submodule voltage matrix of each bridge arm at the current moment includes:
[0038] Step S11: number each submodule of the upper bridge arm of each bridge arm, and number each submodule of the lower bridge arm of each bridge arm.
[0039] Exemplarily, when the upper bridge arm includes N sub-modules and the lower bridge arm includes N sub-modules, the sub-modules may be numbered from the 1st to the Nth sub-modules.
[0040] Step S12: Arrange the voltage of each submodule of the upper bridge arm of each bridge arm in ascending order to form a voltage matrix of the upper bridge arm submodules of each bridge arm, and put the serial number of each submodule into a corresponding position in the voltage matrix.
[0041] Step S13: Arrange the voltage of each submodule of the lower bridge arm of each bridge arm in ascending order to form a voltage matrix of the lower bridge arm submodules of each bridge arm, and put the serial number of each submodule into a corresponding position in the voltage matrix.
[0042] Specifically, the voltage of each submodule of the upper bridge arm U u1 … UU n is arranged in ascending order to form the upper bridge arm submodule voltage matrix U u , the voltage of each submodule of the lower bridge arm U l1 … U ln Arrange in ascending order to form the lower bridge arm submodule voltage matrix U l .
[0043] Step S2: adopting the model prediction method, according to the upper bridge arm submodule voltage matrix, the lower bridge arm submodule voltage matrix and the bridge arm charging current of each bridge arm at the current moment, and the DC voltage reference value at the next moment, predict the bridge arm charging current of each bridge arm at multiple next moments, and the bridge arm charging current of each bridge arm at multiple next moments is determined by the number of upper bridge arm submodules and lower bridge arm submodules put into use at the next moment.
[0044] Alternatively, if Figure 4 As shown, the process of predicting the bridge arm charging current of each bridge arm at multiple next moments includes:
[0045] Step S21: adopting a model prediction method, based on the upper bridge arm submodule voltage matrix and the lower bridge arm submodule voltage matrix of each bridge arm at the current moment, predict the sum of the submodule voltages of each bridge arm at the next moment.
[0046] Step S22: predicting the bridge arm charging current of each bridge arm at multiple next moments according to the sum of the submodule voltages of each bridge arm at multiple next moments, the DC voltage reference value at the next moment, and the bridge arm charging current at the current moment.
[0047] Specifically, since the upper bridge arm submodule voltage matrix and the lower bridge arm submodule voltage matrix of each bridge arm at the current moment are formed by sorting each submodule voltage in ascending order, the previous x The sum of the submodule voltages is calculated to obtain the predicted values of the sum of the submodule voltages of the bridge arms at the next moment, that is, multiple U aj ( k +1) value, thereby obtaining the bridge arm charging current of each bridge arm at multiple next moments.
[0048] Optionally, the process of predicting the sum of the submodule voltages of each bridge arm at multiple next moments includes:
[0049] (1) Calculate the voltage matrix of the upper bridge arm submodule of each bridge arm at the current moment. x The sum of the voltages of the submodules in the first bridge arm is taken as the first voltage sum; (2) the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment is calculated. x The sum of the submodule voltages is used as the second sum of voltages; (3) the sum of the first voltage and the sum of the second voltage are used as the submodule voltages of each bridge arm at the next moment; (4) by controlling the value x Increment between 1 and N to obtain the submodule voltage of each bridge arm at multiple next moments; wherein, the sum of the number of upper bridge arm submodules and the number of lower bridge arm submodules put into operation should be greater than N and less than 2N, where N is the number of upper bridge arm submodules and the number of lower bridge arm submodules.
[0050] For example, it is assumed that the upper bridge arm includes three submodules, and the voltages areU u1 , U u2 , U u3 , according to the boost sequence, the upper arm submodule voltage matrix is obtained U u =[ U u1 U u2 U u3 ], then the first voltage and value are U u1 , U u1 + U u2 , U u1 + U u2 + U u3 ; Assume that the lower bridge arm includes 3 submodules, and the voltages are U l1 , U l2 , U l3 , according to the boost sequence, the voltage matrix of the lower bridge arm submodule is obtained U l =[ U l1 U l2 U l3 ], then the second voltage and value is U l1 , U l1 + U l2 , U l1 + U l2 + U l3 The first voltage sum and the second voltage sum are added to obtain the submodule voltage of each bridge arm at the next moment. The submodule voltage of each bridge arm at the next moment is U u1 + U l1 , U u1 + U u2 + U l1 + U l2 , Uu1 + U u2 + U u3 + U l1 + U l2 + U l3 , substituting the submodule voltage of each bridge arm at the next three moments into formula (2), we can obtain the predicted value of the bridge arm charging current at the next moment when the number of submodules put into operation is 1, 2, and 3 respectively.
[0051] Step S3: Based on the upper bridge arm voltage of each submodule of each bridge arm, the lower bridge arm voltage of each submodule, the bridge arm charging current and the number of submodules put into use at the current moment, predict the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment.
[0052] Alternatively, if Figure 5 As shown, the process of predicting the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment includes:
[0053] Step S31: based on the upper bridge arm voltage of each submodule of each bridge arm and the lower bridge arm voltage of each submodule of each bridge arm at the current moment, calculate the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the current moment.
[0054] Step S32: predict the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the next moment based on the sum of the upper bridge arm submodule voltages, the sum of the lower bridge arm submodule voltages, the bridge arm charging current and the number of submodules put into operation at the current moment.
[0055] Step S33: calculating the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment based on the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the next moment.
[0056] Specifically, considering the energy balance between the upper and lower bridge arms during the charging process, the model prediction is performed at time k+1:
[0057] (3)
[0058] (4)
[0059] in, The predicted value of the sum of the voltages of the submodules in the upper bridge arm or lower bridge arm at the next moment; The number of submodules invested in the bridge arm; i ij ( k ), V cij (k ) is the bridge arm current obtained by sampling and the bridge arm input submodule voltage and; W ij ( k +1) is the energy of the upper bridge arm and the energy of the lower bridge arm.
[0060] Step S4: Calculate multiple cost functions according to multiple bridge arm charging currents at the next moment, bridge arm charging current reference values at the next moment, and upper bridge arm energy and lower bridge arm energy of each bridge arm at the next moment.
[0061] Optionally, for each bridge arm, the bridge arm charging current reference value at the next moment is subtracted from the bridge arm charging current at each next moment to obtain multiple current deviation values of each bridge arm at the next moment; for each bridge arm, the upper bridge arm energy and the lower bridge arm energy at the next moment are subtracted to obtain the energy deviation value of each bridge arm; based on the multiple current deviation values and energy deviation values of each bridge arm at the next moment, multiple cost functions of each bridge arm are obtained.
[0062] Considering the pre-charge current and the energy balance between bridge arms, the cost function can be established:
[0063] (5)
[0064] Where g is the cost function value; λ 1. λ 2 are prediction coefficients.
[0065] Step S5: taking the number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment corresponding to the minimum cost function among the multiple cost functions as the number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment.
[0066] Specifically, since equation (2) solves the predicted value of the bridge arm charging current when different numbers of sub-modules are put into operation at the next moment, that is, i pj ( k +1), so the cost function value of different numbers of sub-modules put into use at the next moment can be obtained, and the number of sub-modules put into use corresponding to the minimum cost function value is used as the number of upper bridge arm sub-modules and lower bridge arm sub-modules put into use for each bridge arm at the next moment.
[0067] Based on the above pre-charging control method, build a control block diagram as follows Figure 6 As shown, the control method flow chart is as follows Figure 7 As shown, the details are as follows:
[0068] (1) Obtained through voltage and current sensor sampling i u ( k ), il ( k ), U u1 ,... U un , U l1 ,... U ln ;
[0069] (2) Sort the sampled submodule voltages and arrange them in ascending order to form the upper and lower bridge arm submodule voltage matrix U u and U l , put the corresponding submodule numbers into the matrix in order N u and N l middle;
[0070] (3) Set the system initial value, enter the loop calculation and processing, and set the loop conditions as x Increment from N to 2N in steps of 1, where x is the number of submodules put into operation, that is, the sum of the number of submodules put into operation in the upper bridge arm and the number of submodules put into operation in the lower bridge arm;
[0071] (4) Calculate the voltage matrix of the upper and lower bridge arm submodules U u and U l Before i Voltage and U aj ( k +1);
[0072] (5) Read the DC bus voltage reference value U dc * ( k +1), and then bring it into the prediction model to calculate and , substitute into the cost function and calculate the cost function value;
[0073] (6) After cyclic processing and judgment, the number of upper and lower bridge arm submodules turned on when the cost function takes the minimum value is obtained. N au and N al ;
[0074] (7) Send corresponding control signals based on the calculation results to control the on and off of the corresponding modules.
[0075] In this embodiment, a pre-charging control device for the sending end of an offshore wind power flexible DC transmission system is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and will not be repeated hereafter. As used below, the term "module" can be a combination of software and / or hardware that implements a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0076] This embodiment provides a sending-end pre-charging control device for an offshore wind power flexible direct current transmission system, the device comprising:
[0077] A voltage matrix establishment module is used to obtain the voltage of each submodule of the upper bridge arm and each submodule of the lower bridge arm of each bridge arm at the current moment, and establish the voltage matrix of the upper bridge arm submodule and the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment;
[0078] The first prediction module is used to adopt a model prediction method to predict the bridge arm charging current of each bridge arm at multiple next moments according to the upper bridge arm submodule voltage matrix, the lower bridge arm submodule voltage matrix and the bridge arm charging current of each bridge arm at the current moment and the DC voltage reference value at the next moment, and the bridge arm charging current of each bridge arm at the multiple next moments is determined by the number of upper bridge arm submodules and lower bridge arm submodules put into use at the next moment;
[0079] The second prediction module is used to predict the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment based on the upper bridge arm voltage of each submodule of each bridge arm, the voltage of each submodule of the lower bridge arm, the bridge arm charging current and the number of submodules put into use at the current moment;
[0080] A calculation module, used for calculating multiple cost functions according to multiple bridge arm charging currents at the next moment, bridge arm charging current reference values at the next moment, and upper bridge arm energy and lower bridge arm energy of each bridge arm at the next moment;
[0081] The loop iteration comparison module is used to use the input quantity of the upper bridge arm submodule and the lower bridge arm submodule of each bridge arm at the next moment corresponding to the minimum cost function among multiple cost functions as the input quantity of the upper bridge arm submodule and the lower bridge arm submodule of each bridge arm at the next moment.
[0082] The sending-end pre-charging control device of the offshore wind power flexible direct current transmission system in this embodiment is presented in the form of a functional unit, where the unit refers to an ASIC circuit, a processor and memory that executes one or more software or fixed programs, and / or other devices that can provide the above functions.
[0083] The further functional description of each of the above modules and units is the same as that of the above corresponding embodiments and will not be repeated here.
[0084] An embodiment of the present invention further provides a computer device having the above-mentioned sending-end pre-charging control device of the offshore wind power flexible direct current transmission system.
[0085] See also Figure 8 , Figure 8 is a schematic diagram of the structure of a computer device provided by an optional embodiment of the present invention, such as Figure 8 As shown, the computer device includes: one or more processors 10, a memory 20, and interfaces for connecting various components, including high-speed interfaces and low-speed interfaces. Various components are connected to each other using different buses for communication, and can be installed on a common mainboard or installed in other ways as needed. The processor can process the instructions executed in the computer device, including instructions stored in or on the memory to display the graphical information of the GUI on an external input / output device (such as, a display device coupled to the interface). In some optional embodiments, if necessary, multiple processors and / or multiple buses can be used together with multiple memories and multiple memories. Similarly, multiple computer devices can be connected, and each device provides some necessary operations (for example, as a server array, a group of blade servers, or a multi-processor system). Figure 8 A processor 10 is taken as an example.
[0086] The processor 10 may be a central processing unit, a network processor or a combination thereof. The processor 10 may further include a hardware chip. The hardware chip may be a dedicated integrated circuit, a programmable logic device or a combination thereof. The programmable logic device may be a complex programmable logic device, a field programmable gate array, a general purpose array logic or any combination thereof.
[0087] The memory 20 stores instructions executable by at least one processor 10, so that at least one processor 10 executes the method shown in the above embodiment.
[0088] The memory 20 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created by the use of a computer device based on the presentation of a small program landing page, etc. In addition, the memory 20 may include a high-speed random access memory, and may also include a non-transient memory, such as at least one disk storage device, a flash memory device, or other non-transient solid-state storage device. In some optional embodiments, the memory 20 may optionally include a memory remotely arranged relative to the processor 10, and these remote memories may be connected to the computer device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0089] The memory 20 may include a volatile memory, such as a random access memory; the memory may also include a non-volatile memory, such as a flash memory, a hard disk or a solid state drive; the memory 20 may also include a combination of the above types of memory.
[0090] The computer device further comprises a communication interface 30 for the computer device to communicate with other devices or a communication network.
[0091] The embodiment of the present invention also provides a computer-readable storage medium. The method according to the embodiment of the present invention can be implemented in hardware, firmware, or can be implemented as a computer code that can be recorded in a storage medium, or can be implemented as a computer code that is originally stored in a remote storage medium or a non-temporary machine-readable storage medium and will be stored in a local storage medium through a network download, so that the method described herein can be stored in such software processing on a storage medium using a general-purpose computer, a dedicated processor, or programmable or dedicated hardware. Among them, the storage medium can be a magnetic disk, an optical disk, a read-only storage memory, a random access memory, a flash memory, a hard disk or a solid-state hard disk, etc.; further, the storage medium can also include a combination of the above types of memories. It can be understood that a computer, a processor, a microprocessor controller, or programmable hardware includes a storage component that can store or receive software or computer code. When the software or computer code is accessed and executed by a computer, a processor, or hardware, the method shown in the above embodiment is implemented.
[0092] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A method for controlling precharging at the sending end of an offshore wind power flexible direct current transmission system, characterized in that: The transmission system sending end includes a converter, each bridge arm of the converter is composed of a plurality of submodules connected in series, and the pre-charging control method includes: Obtain the voltage of each submodule of the upper bridge arm and each submodule of the lower bridge arm of each bridge arm at the current moment, and establish the voltage matrix of the upper bridge arm submodule and the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment; A model prediction method is adopted to predict the bridge arm charging current of each bridge arm at multiple next moments according to the upper bridge arm submodule voltage matrix, the lower bridge arm submodule voltage matrix and the bridge arm charging current of each bridge arm at the current moment and the DC voltage reference value at the next moment, wherein the bridge arm charging current of each bridge arm at the multiple next moments is determined by the number of upper bridge arm submodules and lower bridge arm submodules put into use at the next moment; Based on the upper bridge arm voltage of each submodule of each bridge arm at the current moment, the voltage of each submodule of the lower bridge arm, the bridge arm charging current, and the number of submodules put into use, the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment are predicted; Calculate multiple cost functions according to the multiple bridge arm charging currents at the next moment, the bridge arm charging current reference value at the next moment, and the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment; The number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment corresponding to the minimum cost function among the multiple cost functions is used as the number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment; The process of calculating multiple cost functions includes: for each bridge arm, subtracting a bridge arm charging current reference value at the next moment from the bridge arm charging current at each of the next moments to obtain multiple current deviation values of each bridge arm at the next moment; for each bridge arm, subtracting an upper bridge arm energy from a lower bridge arm energy at the next moment to obtain an energy deviation value of each bridge arm; and obtaining multiple cost functions of each bridge arm based on the multiple current deviation values and energy deviation values of each bridge arm at the next moment.
2. The method according to claim 1, characterized in that The process of establishing the upper bridge arm submodule voltage matrix and the lower bridge arm submodule voltage matrix of each bridge arm at the current moment includes: Number each submodule of the upper bridge arm of each bridge arm, and number each submodule of the lower bridge arm of each bridge arm; The voltage of each submodule of the upper bridge arm of each bridge arm is arranged in ascending order to form a voltage matrix of the upper bridge arm submodules of each bridge arm, and the serial number of each submodule is placed in a corresponding position in the voltage matrix; The voltage of each submodule of the lower bridge arm of each bridge arm is arranged in ascending order to form a voltage matrix of the lower bridge arm submodules of each bridge arm, and the serial number of each submodule is placed in a corresponding position in the voltage matrix.
3. The method according to claim 1, characterized in that The process of predicting the bridge arm charging current of each bridge arm at multiple next moments includes: Adopting a model prediction method, based on the upper bridge arm submodule voltage matrix and the lower bridge arm submodule voltage matrix of each bridge arm at the current moment, predicting the sum of the submodule voltages of each bridge arm at the next moment; The bridge arm charging current of each bridge arm at the multiple next moments is predicted according to the sum of the submodule voltages of each bridge arm at the multiple next moments, the DC voltage reference value at the next moment, and the bridge arm charging current at the current moment.
4. The method according to claim 3, characterized in that The process of predicting the sum of the submodule voltages of each bridge arm at multiple next moments includes: Calculate the voltage matrix of the upper bridge arm submodule of each bridge arm at the current moment. x The voltage and value of the submodule are used as the first voltage and value; Calculate the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment. x The voltage and value of the submodule are used as the second voltage and value; The first voltage sum and the second voltage sum are used as the submodule voltage of each bridge arm at the next moment; By controlling the value x Increment between 1 and N to obtain the submodule voltage of each bridge arm at multiple next moments; Among them, the sum of the number of upper bridge arm sub-modules and the number of lower bridge arm sub-modules should be greater than N and less than 2N, where N is the number of upper bridge arm sub-modules and the number of lower bridge arm sub-modules.
5. The method according to claim 1, characterized in that The process of predicting the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment includes: Based on the upper bridge arm voltage of each submodule of each bridge arm and the lower bridge arm voltage of each submodule of each bridge arm at the current moment, the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the current moment are calculated; According to the sum of the upper bridge arm submodule voltages, the sum of the lower bridge arm submodule voltages, the bridge arm charging current, and the number of submodules put into use of each bridge arm at the current moment, predict the sum of the upper bridge arm submodule voltages and the sum of the lower bridge arm submodule voltages of each bridge arm at the next moment; Based on the sum of the voltages of the upper bridge arm submodules and the sum of the voltages of the lower bridge arm submodules of each bridge arm at the next moment, the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment are calculated.
6. A pre-charging control device for a sending end of an offshore wind power flexible DC transmission system, characterized in that: The device comprises: A voltage matrix establishment module is used to obtain the voltage of each submodule of the upper bridge arm and each submodule of the lower bridge arm of each bridge arm at the current moment, and establish the voltage matrix of the upper bridge arm submodule and the voltage matrix of the lower bridge arm submodule of each bridge arm at the current moment; A first prediction module is used to adopt a model prediction method to predict the bridge arm charging current of each bridge arm at multiple next moments according to the upper bridge arm submodule voltage matrix, the lower bridge arm submodule voltage matrix and the bridge arm charging current of each bridge arm at the current moment and the DC voltage reference value at the next moment, wherein the bridge arm charging current of each bridge arm at the multiple next moments is determined by the number of upper bridge arm submodules and lower bridge arm submodules put into use at the next moment; The second prediction module is used to predict the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment based on the upper bridge arm voltage of each submodule of each bridge arm, the voltage of each submodule of the lower bridge arm, the bridge arm charging current and the number of submodules put into use at the current moment; A calculation module, used to calculate multiple cost functions according to the multiple bridge arm charging currents at the next moment, the bridge arm charging current reference value at the next moment, and the upper bridge arm energy and the lower bridge arm energy of each bridge arm at the next moment; A loop iteration comparison module, used for taking the number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment corresponding to the minimum cost function among the multiple cost functions as the number of upper bridge arm submodules and lower bridge arm submodules of each bridge arm at the next moment; The process of calculating multiple cost functions includes: for each bridge arm, subtracting a bridge arm charging current reference value at the next moment from the bridge arm charging current at each of the next moments to obtain multiple current deviation values of each bridge arm at the next moment; for each bridge arm, subtracting an upper bridge arm energy from a lower bridge arm energy at the next moment to obtain an energy deviation value of each bridge arm; and obtaining multiple cost functions of each bridge arm based on the multiple current deviation values and energy deviation values of each bridge arm at the next moment.
7. A computer device, characterized in that: include: A memory and a processor, wherein the memory and the processor are communicatively connected to each other, the memory stores computer instructions, and the processor executes the sending-end pre-charging control method of the offshore wind power flexible direct current transmission system according to any one of claims 1 to 5 by executing the computer instructions.
8. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a computer to execute the sending-end pre-charging control method of an offshore wind power flexible direct current transmission system according to any one of claims 1 to 5.