Reconstruction and extension project old road pavement breaking device and construction method
By designing an adjustable breaking and suction mechanism, the problem of inconvenient operation and dust emission of the road breaking device is solved, and efficient road breaking and environmental improvement are achieved.
Patent Information
- Application Number
- CN202411126309.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-10-18
AI Technical Summary
The existing road breaking device is inconvenient to operate, requires multiple moves, and generates a large amount of dust during the breaking process, resulting in a harsh construction environment.
A pavement breaking device including an adjustable breaking mechanism and a suction mechanism is designed. The adjustable breaking component is used to realize the adjustment and fine crushing of the pavement crushing area, and the dust removal component and negative pressure suction machine are used to reduce dust and improve the construction environment.
It improves construction efficiency, reduces dust, improves the construction environment, reduces the difficulty of subsequent processing, and enhances the stability of the device.
Smart Images

Figure CN118792947A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of road surface demolition, in particular to a device and a construction method for demolition of an old road surface in a reconstruction and expansion project. Background Art
[0002] In the process of expanding and renovating old roads, it is often necessary to use a road surface breaking device to break the road surface. At present, the common road surface breaking devices in the prior art generally have only one crushing head, which needs to be moved many times during operation to complete the crushing of an area, which is inconvenient, and when finer crushing is required, the number of moves will be more, and more dust will be generated in the crushing process, resulting in a relatively poor construction environment. In the subsequent process of collecting the broken road surface, a large amount of dust will also be generated, making the construction environment poor. Therefore, it is of great significance to study a new road surface breaking device and construction method for old roads in renovation and expansion projects to solve the above problems. Summary of the invention
[0003] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.
[0004] In view of the above and / or existing problems in road surface demolition, the present invention is proposed.
[0005] Therefore, the technical problem to be solved by the present invention is that the common road breaking device in the prior art generally has only one crushing head, which needs to be moved many times during operation to complete the crushing of an area, which is inconvenient. Moreover, when finer crushing is required, more movements are required, and more dust will be generated in the crushing process, resulting in a relatively poor construction environment. In the subsequent process of collecting the crushed road surface, a large amount of dust will also be generated, resulting in a poor construction environment.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a device for breaking the pavement of an old road in a reconstruction and expansion project, comprising an adjustable breaking mechanism and a material suction mechanism;
[0007] The material suction mechanism includes a material removal assembly, one side of which is connected to a swing-type feeding assembly;
[0008] The adjustable breaking mechanism includes a dust removal component, which is arranged below the material removal component, and the swing-type feeding component extends downward to the bottom of the dust removal component. An elastic retaining component and a moving component are connected below the dust removal component, and a driving component is mounted on the elastic component. An adjustable breaking component is arranged below the driving component, and the adjustable breaking component is connected to the elastic retaining component. A turntable is connected below the elastic retaining component, and a plurality of oblique openings are provided on the turntable, and the adjustable breaking component slides in the plurality of oblique openings. The driving component cooperates with the elastic retaining component to drive the adjustable breaking component to realize the road surface breaking operation.
[0009] As a further solution of the present invention: the material removal assembly includes a material box, a negative pressure suction machine is installed above the material box, the negative pressure suction machine is connected to the material box, a box door is provided on the material box, a material box is fixedly connected to one side of the material box, and a handle is fixedly connected to one side of the material box.
[0010] As a further solution of the present invention: the swing-type feeding assembly includes a feeding hose, the feeding hose is connected to the negative pressure suction machine, the bottom end of the feeding hose is connected to a feeding head, and a plurality of paddles are fixedly connected below the feeding head;
[0011] Both sides of the feed head are fixedly connected with slide plates, and the slide plates are inserted and slidably arranged in the fixed plate;
[0012] An annular frame is fixedly connected above the feed head, a crankshaft is slidably connected in the annular frame, and one end of the crankshaft is fixedly connected to the output shaft of the first motor.
[0013] As a further solution of the present invention: the dust removal component includes a water tank, a water injection end is provided on one side of the water tank, the fixed plate and the first motor are fixedly connected to the bottom of the water tank, a water pump is installed on the water tank, the water inlet of the water pump extends to the interior of the water tank, the water outlet of the water pump is connected with a water outlet pipe, the water outlet pipe is connected with an annular nozzle, the annular nozzle is enclosed in the periphery of the water tank, the interior of the annular nozzle is fixedly connected with a fixing bar, and the fixing bar is fixedly connected to the outside of the water tank.
[0014] As a further solution of the present invention: the moving assembly includes an electric push rod, the electric push rod is fixedly connected to the bottom of the water tank, and the bottom end of the electric push rod is fixedly connected to a moving wheel.
[0015] As a further solution of the present invention: the elastic retaining assembly includes a fixed plate and two annular plates, the fixed plate is fixedly connected to the bottom of the water tank, a plurality of fixing openings are opened on the fixed plate, a fixing seat is fixedly connected to the upper annular plate, a fixing bolt is provided on the fixing seat, and the fixing bolt is adapted to the size of the fixing opening.
[0016] As a further solution of the present invention: two groups of sliding rods and three groups of guide sleeves are arranged between the two fixed plates, the number of each group of sliding rods is three, the number of each group of guide sleeves is two, wherein the two ends of the three sliding rods are fixedly connected to the two annular plates, and the other three sliding rods are fixedly connected to the two guide sleeves, the annular plates slide in the three guide sleeves, and the three guide sleeves on the top are fixedly connected to the bottom of the fixed plate;
[0017] The sliding rod is slidably connected in the sliding sleeve, and a spring is fixedly connected above the sliding sleeve, three of which are respectively fixedly connected to the three sliding sleeves above, and the remaining springs are fixedly connected below the annular plate above. Three of the sliding sleeves are installed on the turntable, and the other three sliding sleeves are respectively installed on three connecting plates. An annular bar is fixedly connected between the three connecting plates, and the annular bar is fixedly connected to the inner ring of the first bearing. The turntable is rotatably connected to the outer ring of the first bearing.
[0018] As a further solution of the present invention: the driving assembly includes a second motor, the upper part of the second motor is installed below the fixed disk through a support plate, the output shaft of the second motor is fixedly connected to a rotating shaft, the rotating shaft is rotatably connected to two vertical plates through two second bearings, the two vertical plates are fixedly connected to the bottom of the fixed disk, and a cam is fixedly connected to the rotating shaft.
[0019] As a further solution of the present invention: the adjustable breaking component includes a circular disk, a pulley is fixedly connected to the top of the circular disk, the pulley is in contact with the cam, the circular disk is fixedly connected to the annular bar through a plurality of guide plates, an adjusting sleeve is slidably connected to the guide plate, a first receiving disk is fixedly connected to the bottom of the adjusting sleeve, the first receiving disk slides in the oblique mouth, a first drill bit is installed below the first receiving disk, a second receiving disk is fixedly connected to the bottom of the circular disk, a second drill bit is installed below the second receiving disk, and the turntable is also rotatably connected to the second receiving disk through a third bearing.
[0020] A construction method for an old road pavement demolition device for a reconstruction and expansion project comprises the following steps:
[0021] S1. When performing a road surface breaking operation, first adjust the distance between the first drill bits, and by toggling the annular plate to rotate, the linkage part of the sliding rod drives the turntable to rotate, and the turntable squeezes the first receiving plate through the oblique opening to move, so that the first receiving plate drives the first drill bit to move, so that the spacing adjustment between the first drill bits is satisfied. After adjustment, the position of the annular plate is fixed by screwing the fixing bolt into the fixing opening, and the electric push rod is retracted to adjust the distance between the first drill bit and the second drill bit and the road surface;
[0022] S2, then control the second motor to drive the rotating shaft to rotate, the rotating shaft drives the cam to rotate, so that the cam squeezes the pulley to move downward, the circular plate drives the lower annular plate to move through the guide plate, so that the spring is deformed, and the cam cooperates with the spring to drive the rotating plate to achieve the purpose of vibration, so that the first drill bit and the second drill bit quickly vibrate to break the road surface;
[0023] S3. During the breaking process, the liquid inside the water tank is extracted by a water pump and enters the annular nozzle through the outlet pipe to spray out for dust reduction. Secondly, the negative pressure suction machine sucks the broken debris through the feed head, so that the debris enters the material box, and the crankshaft is driven to rotate by the first motor. The crankshaft drives the annular frame to reciprocate, so that the annular frame drives the feed head to reciprocate, and the feed head drives the paddle to poke the debris, thereby facilitating the recovery of the debris.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] 1. The old road pavement breaking device and construction method of the reconstruction and expansion project, by toggling the annular plate to rotate, the sliding rod of the annular plate linkage part drives the turntable to rotate, and the turntable squeezes the first receiving plate to move through the oblique mouth, so that the first receiving plate drives the first drill bit to move, and then the distance between the first drill bit and the second drill bit can be adjusted through the displacement of multiple first receiving plates, so that the first drill bit and the second drill bit can be expanded and retracted, so that the pavement breaking area can be adjusted, so that the retracted first drill bit can be concentratedly broken to achieve finer fragments, and the concentrated breaking can also increase the breaking diameter, which can meet the needs of directly destroying the area in the pavement damage area, thereby improving the construction efficiency. Secondly, by expanding the first drill bit, the breaking area is greatly increased, thereby accelerating the pavement construction process;
[0026] 2. The old road pavement demolition device and construction method of the reconstruction and expansion project uses a water pump to extract the liquid inside the water tank, so that the liquid enters the annular nozzle through the outlet pipe, and the annular nozzle sprays the liquid. Since the annular nozzle is located outside the water tank, the sprayed liquid can form a water wall in the demolition area, thereby preventing dust from being discharged, achieving the purpose of effective dust removal and improving the construction environment;
[0027] 3. The old road pavement demolition device and construction method of the reconstruction and expansion project can increase the overall weight by storing water inside the water tank, thereby increasing the overall weight of the device and improving the overall stability, so that the pavement demolition operation can be smoothly carried out, and the crushed materials are extracted by the negative pressure suction machine, so that the crushed materials enter through the feed head and are recycled into the material box. This method can greatly reduce the difficulty of subsequent processing, and the first motor drives the crankshaft to rotate, the crankshaft drives the annular frame to reciprocate, the annular frame drives the feed head to reciprocate, and the paddle plate reciprocates, and the reciprocating motion of the paddle plate can move the crushed materials. The material is scattered, which is more conducive to the recovery of the broken materials. Moreover, with the continuous progress of the dust removal operation, the amount of water in the water tank decreases, while the amount of broken materials in the material box increases, so that the weight of the device can be always maintained, so that the road surface breaking operation can proceed smoothly. Moreover, the purpose of dust suction can be achieved through the negative pressure suction machine, which reduces the flying dust and improves the construction environment. Secondly, after the road surface is humidified, it can not only make the road surface easier to break, but also play a certain lubricating role on the road surface material, reduce the friction between the materials, and make it easier for the first drill bit and the second drill bit to cut into and break the road surface. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:
[0029] Figure 1 A three-dimensional structural schematic diagram of an old road pavement removal device and a construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0030] Figure 2 A three-dimensional structural schematic diagram of an adjustable breaking mechanism in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0031] Figure 3 A structural schematic diagram of the connection between a material removal component and a dust removal component in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0032] Figure 4 A three-dimensional structural schematic diagram of a swing-type feeding assembly in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0033] Figure 5 A three-dimensional structural schematic diagram of a dust removal component in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0034] Figure 6A schematic structural diagram of a three-dimensional cross-section of an elastic retaining component in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0035] Figure 7 A schematic structural diagram of the connection between a driving component and an adjustable breaking component in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0036] Figure 8 A three-dimensional structural schematic diagram of a turntable in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0037] Fig. 9 A three-dimensional structural schematic diagram of an adjustable breaking component in an old road pavement breaking device and construction method for a reconstruction and expansion project described in an embodiment of the present invention.
[0038] In the figure: 100, suction mechanism; 101, material removal assembly; 1011, material box; 1012, negative pressure suction machine; 1013, material box; 1014, handle; 1015, box door; 102, swing feeding assembly; 1021, feeding hose; 1022, feeding head; 1023, paddle plate; 1024, annular frame; 1025, crankshaft; 1026, fixing plate; 1027, slide plate; 1028, first motor; 200, adjustable breaking mechanism; 201, elastic retaining assembly; 2011, annular plate; 2012, fixing seat; 2013, fixing bolt; 2014, guide sleeve; 2015, spring; 2016, slide rod; 2017, connecting plate; 2018, sliding sleeve; 2019, annular strip; 20110, first bearing; 20111, Fixed plate; 202, dust removal component; 2021, water pump; 2022, water outlet pipe; 2023, annular nozzle; 2024, fixed strip; 2025, water tank; 2026, water injection end; 203, moving component; 2031, moving wheel; 2032, electric push rod; 204, turntable; 205, driving component; 2051, second motor; 2052, support plate; 2053, vertical plate; 2054, cam; 2055, rotating shaft; 2056, second bearing; 206, adjustable breaking component; 2061, adjusting sleeve; 2062, guide plate; 2063, first receiving plate; 2064, first drill bit; 2065, second drill bit; 2066, second receiving plate; 2067, third bearing; 2068, pulley; 2069, circular plate; 207, bevel. DETAILED DESCRIPTION
[0039] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0040] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0041] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.
[0042] Furthermore, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.
[0043] Example 1
[0044] like Figure 1-3 and Figure 5-9 As shown, the present invention provides a technical solution: a device for breaking the pavement of an old road in a reconstruction and expansion project, comprising an adjustable breaking mechanism 200 and a suction mechanism 100;
[0045] The material suction mechanism 100 includes a material removal component 101, one side of which is connected to a swing-type feeding component 102;
[0046] The adjustable breaking mechanism 200 includes a dust removal component 202, which is arranged below the material removal component 101. The swing feeding component 102 extends downward to the bottom of the dust removal component 202. The bottom of the dust removal component 202 is connected with an elastic holding component 201 and a moving component 203. The moving component 203 includes an electric push rod 2032, which is fixedly connected to the bottom of the water tank 2025. The bottom end of the electric push rod 2032 is fixedly connected with a moving wheel 2031. By retracting the electric push rod 2032, the distance between the first drill bit 2064 and the second drill bit 2065 and the road surface can be adjusted, and the moving wheel 2031 can assist the device to move, making the moving operation more labor-saving. The elastic component is equipped with a driving Component 205, driving component 205 includes a second motor 2051, the upper part of the second motor 2051 is installed below the fixed disk 20111 through a support plate 2052, the second motor 2051 can be fixed by the support plate 2052 to ensure the stability of the second motor 2051, the output shaft of the second motor 2051 is fixedly connected with a rotating shaft 2055, the rotating shaft 2055 is rotatably connected to two vertical plates 2053 through two second bearings 2056, the second bearings 2056 can be supported by the vertical plates 2053, so that the second bearings 2056 can support the rotating shaft 2055, and the second bearings 2056 can also assist the rotating shaft 2055 to rotate stably, and the two vertical plates 2053 are fixedly connected to the fixed disk 20111. The cam 2054 is fixedly connected to the rotating shaft 2055, and an adjustable breaking component 206 is arranged below the driving component 205. The adjustable breaking component 206 includes a circular disk 2069, and a pulley 2068 is fixedly connected above the circular disk 2069. The pulley 2068 contacts the cam 2054. The pulley 2068 has rolling properties, so that the friction resistance between the cam 2054 and the pulley 2068 can be reduced when the cam 2054 rotates, thereby maintaining smooth operation and reducing wear. The circular disk 2069 is fixedly connected to the annular strip 2019 through a plurality of guide plates 2062, and an adjusting sleeve 2061 is slidably connected to the guide plate 2062. A first receiving plate 2063 is fixedly connected below the adjusting sleeve 2061. The first receiving plate 2063 is fixedly connected to the first receiving plate 2063. 63 slides in the oblique opening 207, the rotating disk 204 can rotate and squeeze the first receiving disk 2063 through the oblique opening 207 to translate, so that the first receiving disk 2063 can maintain stable movement through the adjusting sleeve 2061, so that the position of the first drill bit 2064 can be smoothly adjusted, the first receiving disk 2063 is installed with the first drill bit 2064 below, the circular disk 2069 is fixedly connected with the second receiving disk 2066 below, and the second drill bit 2065 is installed below the second receiving disk 2066, and the rotating disk 204 is also rotatably connected to the second receiving disk 2066 through the third bearing 2067, and the third bearing 2067 can assist the rotating disk 204 to rotate smoothly, and make the rotating disk 204 indirectly connected to the second receiving disk 2066, so that the position of the circular disk 2069 is fixed;
[0047] The adjustable breaking component 206 is connected to the elastic holding component 201, and a turntable 204 is connected below the elastic holding component 201. The turntable 204 is provided with a plurality of oblique openings 207, and the adjustable breaking component 206 slides in the plurality of oblique openings 207. The driving component 205 cooperates with the elastic holding component 201 to drive the adjustable breaking component 206 to achieve the road breaking operation. The elastic holding component 201 includes a fixed disk 20111 and two annular plates 2011. The fixed disk 20111 is fixedly connected below the water tank 2025. A plurality of fixed openings are provided on the fixed disk 20111. A fixing seat 20111 is fixedly connected to the upper annular plate 2011. 012, a fixing bolt 2013 is provided on the fixing seat 2012, and the position of the annular plate 2011 can be locked by screwing the fixing bolt 2013 into the fixing opening to prevent the position of the first drill bit 2064 from changing. The fixing bolt 2013 is adapted to the size of the fixing opening. Two groups of slide bars 2016 and three groups of guide sleeves 2014 are provided between the two fixing plates 20111, and the number of each group of slide bars 2016 is three, and the number of each group of guide sleeves 2014 is two, wherein the two ends of the three slide bars 2016 are fixedly connected to the two annular plates 2011, and the other three slide bars 2016 are fixedly connected to the two guide sleeves 2014, and the annular plate 2011 slides in the three guide sleeves 2014, and the guide sleeves 2014 can support the annular plate 2011 and make the annular plate 2011 rotate smoothly. The three guide sleeves 2014 on the top are fixedly connected to the bottom of the fixed plate 20111. The slide bar 2016 is slidably connected in the slide sleeve 2018, and the slide bar 2016 can move up and down smoothly through the guide of the slide sleeve 2018. The top of the slide sleeve 2018 is fixedly connected with a spring 2015, and the elastic reset force of the spring 2015 can drive the first drill bit 2064 to reset quickly, and then the spring 2015 cooperates with the cam 2054 to keep the first drill bit 2064 in position. Rapid vibration is performed to break the road surface, three of which are fixedly connected to the three upper sleeves 2018, and the remaining springs 2015 are fixedly connected to the bottom of the upper annular plate 2011, three of which are installed on the turntable 204, and the other three sleeves 2018 are installed on three connecting plates 2017, and an annular bar 2019 is fixedly connected between the three connecting plates 2017, and the annular bar 2019 is fixedly connected to the inner ring of the first bearing 20110. The turntable 204 is rotatably connected to the outer ring of the first bearing 20110, and the turntable 204 can be assisted to rotate smoothly through the first bearing 20110.
[0048] In this embodiment, by toggling the annular plate 2011 to rotate, the sliding rod 2016 of the linkage part of the annular plate 2011 drives the turntable 204 to rotate, and the turntable 204 squeezes the first receiving plate 2063 to move through the oblique mouth 207, so that the first receiving plate 2063 drives the first drill bit 2064 to move, and then the distance between the first drill bit 2064 and the second drill bit 2065 can be adjusted through the displacement of multiple first receiving plates 2063, so that the first drill bit 2064 and the second drill bit 2065 can be expanded and contracted, so that the road surface crushing area can be adjusted, so that the contracted first drill bit 2064 can be concentratedly crushed to achieve finer fragments, and the concentrated crushing can also increase the crushing diameter, which can meet the needs of directly destroying the area in the damaged area of the road surface and improve the construction efficiency. Secondly, by expanding the first drill bit 2064, the broken area is greatly increased, thereby speeding up the road surface construction process.
[0049] Example 2
[0050] Combined with Figure 5 , it is concluded that: the dust removal component 202 includes a water tank 2025, a water injection end 2026 is provided on one side of the water tank 2025, liquid can be stored through the water tank 2025, and the liquid can be guided to be injected into the water tank 2025 through the water injection end 2026, the fixing plate 1026 and the first motor 1028 are fixedly connected to the bottom of the water tank 2025, a water pump 2021 is installed on the water tank 2025, the water inlet of the water pump 2021 extends to the inside of the water tank 2025, and the water outlet of the water pump 2021 It is connected to the water outlet pipe 2022, through which the liquid can be guided to smoothly enter the annular nozzle 2023, and the annular nozzle 2023 is enclosed in the periphery of the water tank 2025, so that an annular water wall can be formed when the liquid is sprayed out. The water outlet pipe 2022 is connected to the annular nozzle 2023, and the annular nozzle 2023 is enclosed in the periphery of the water tank 2025. The interior of the annular nozzle 2023 is fixedly connected with a fixing strip 2024, and the fixing strip 2024 is fixedly connected to the outside of the water tank 2025.
[0051] In this embodiment: the liquid inside the water tank 2025 is extracted by the water pump 2021, and the liquid enters the annular nozzle 2023 through the outlet pipe 2022, and the annular nozzle 2023 sprays the liquid. Since the annular nozzle 2023 is located outside the water tank 2025, the sprayed liquid can form a water wall in the removal area, thereby preventing dust from being discharged, achieving the purpose of effective dust removal, and improving the construction environment.
[0052] Example 3
[0053] Combined with Figure 4, it is concluded that: the material removal component 101 includes a material box 1011, a negative pressure suction machine 1012 is installed above the material box 1011, the negative pressure suction machine 1012 can suck the crushed materials from the feed head 1022 through negative pressure, the negative pressure suction machine 1012 is connected to the material box 1011, a box door 1015 is arranged on the material box 1011, the crushed materials can be stored through the material box 1011, and then the material box 1011 is opened through the box door 1015, so as to facilitate the discharge of the crushed materials, a material box 1013 is fixedly connected to one side of the material box 1011, and a handle 1014 is fixedly connected to one side of the material box 1013, and the material box 1013 can be used to temporarily store construction tools, so that they can be taken out at any time;
[0054] The swing-type feeding assembly 102 includes a feeding hose 1021, which can smoothly convey the crushed materials upward, and the feeding hose 1021 is movable, so that the feeding head 1022 can smoothly perform reciprocating motion operation, the feeding hose 1021 is connected to the negative pressure suction machine 1012, and the bottom end of the feeding hose 1021 is connected to the feeding head 1022, and a plurality of paddles 1023 are fixedly connected below the feeding head 1022, and the paddles 1023 can paddle the flow of the crushed materials, thereby facilitating the negative pressure suction machine 1012 to recover the crushed materials, and both sides of the feeding head 1022 are fixedly connected. A slide plate 1027 is connected, and the slide plate 1027 is inserted and slid in the fixed plate 1026. The fixed plate 1026 keeps the slide plate 1027 sliding smoothly, so that the feed head 1022 can move smoothly. An annular frame 1024 is fixedly connected above the feed head 1022. The annular frame 1024 is provided with an annular opening, so that the crankshaft 1025 can slide and rotate in the annular opening, and the rotation of the crankshaft 1025 can also drive the annular frame 1024 to reciprocate. The crankshaft 1025 is slidably connected in the annular frame 1024, and one end of the crankshaft 1025 is fixedly connected to the output shaft of the first motor 1028.
[0055] In this embodiment: by storing water in the water tank 2025, the overall weight can be increased, thereby increasing the overall weight of the device and improving the overall stability, so that the road surface breaking operation can be smoothly performed, and the crushed materials are extracted by the negative pressure suction machine 1012, so that the crushed materials enter through the feed head 1022 and are recycled into the material box 1011. This method can greatly reduce the difficulty of subsequent processing, and the first motor 1028 drives the crankshaft 1025 to rotate, the crankshaft 1025 drives the annular frame 1024 to reciprocate, the annular frame 1024 drives the feed head 1022 to reciprocate, so that the paddle plate 1023 reciprocates, and the paddle plate 1023 moves back and forth. The repeated motion can disperse the broken materials, which is more conducive to the recovery of the broken materials. Moreover, as the dust removal operation continues, the amount of water inside the water tank 2025 decreases, while the amount of broken materials inside the material box 1011 increases, so that the weight of the device can be always maintained, so that the road breaking operation can proceed smoothly. Moreover, the purpose of dust collection can be achieved through the negative pressure suction machine 1012, thereby reducing dust flying and improving the construction environment. Secondly, after the road surface is humidified, it can not only make the road surface easier to break, but also play a certain lubricating role on the road surface material, reduce the friction between the materials, and make it easier for the first drill bit 2064 and the second drill bit 2065 to cut into and break the road surface.
[0056] A construction method for an old road pavement demolition device for a reconstruction and expansion project comprises the following steps:
[0057] S1. When performing a road surface breaking operation, first adjust the distance between the first drill bits 2064. By rotating the annular plate 2011, the linkage part slide bar 2016 drives the turntable 204 to rotate. The turntable 204 squeezes the first receiving plate 2063 through the oblique opening 207 to move, so that the first receiving plate 2063 drives the first drill bit 2064 to move, and the spacing between the first drill bits 2064 is adjusted. After adjustment, the fixing bolt 2013 is screwed into the fixing opening to fix the position of the annular plate 2011, and the electric push rod 2032 is retracted to adjust the distance between the first drill bit 2064 and the second drill bit 2065 and the road surface;
[0058] S2, then control the second motor 2051 to drive the rotating shaft 2055 to rotate, the rotating shaft 2055 drives the cam 2054 to rotate, so that the cam 2054 squeezes the pulley 2068 to move downward, and the circular plate 2069 drives the lower annular plate 2011 to move through the guide plate 2062, so that the spring 2015 is deformed, and the cam 2054 cooperates with the spring 2015 to drive the rotating disk 204 to achieve the purpose of vibration, so that the first drill bit 2064 and the second drill bit 2065 quickly vibrate to break the road surface;
[0059] S3. During the breaking process, the liquid inside the water tank 2025 is extracted by the water pump 2021, and enters the annular nozzle 2023 through the outlet pipe 2022 to be sprayed out for dust reduction. Secondly, the negative pressure suction machine 1012 sucks the broken debris through the feed head 1022, so that the debris enters the material box 1011, and the crankshaft 1025 is driven to rotate by the first motor 1028. The crankshaft 1025 drives the annular frame 1024 to reciprocate, so that the annular frame 1024 drives the feed head 1022 to reciprocate, and the feed head 1022 drives the paddle 1023 to pry the debris, thereby facilitating the recovery of the debris.
[0060] Importantly, it should be noted that the construction and arrangement of the present application shown in a number of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible, for example, the size, scale, structure, shape and proportion of various elements, and parameter values such as temperature, pressure, etc., mounting arrangements, use of materials, color, directional changes, etc., without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present invention. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of the execution function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other replacements, modifications, changes and omissions can be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the invention is not limited to a specific embodiment, but extends to numerous modifications still falling within the scope of the appended claims.
[0061] Furthermore, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment may not be described, i.e., those features that are not relevant to the best mode presently contemplated for carrying out the invention or those features that are not relevant to implementing the invention.
[0062] It should be understood that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but for those of ordinary skill having the benefit of this disclosure, the development effort will be a routine task of design, fabrication, and production without undue experimentation.
[0063] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.
Claims
1. A device for breaking up the pavement of an old road in a reconstruction and expansion project, characterized in that: It comprises an adjustable breaking mechanism (200) and a material suction mechanism (100); The material suction mechanism (100) comprises a material removal component (101), one side of which is connected to a swing-type feeding component (102); The adjustable breaking mechanism (200) comprises a dust removal component (202), the dust removal component (202) is arranged below the material removal component (101), the swing feeding component (102) extends downward to below the dust removal component (202), an elastic retaining component (201) and a moving component (203) are connected below the dust removal component (202), a driving component (205) is mounted on the elastic component, and an adjustable breaking mechanism (200) is arranged below the driving component (205). An adjustable breaking component (206) is connected to the elastic holding component (201), a rotating disk (204) is connected below the elastic holding component (201), a plurality of oblique openings (207) are provided on the rotating disk (204), and the adjustable breaking component (206) slides in the plurality of oblique openings (207), and the driving component (205) cooperates with the elastic holding component (201) to drive the adjustable breaking component (206) to realize a road surface breaking operation.
2. The device for removing the pavement of an old road for reconstruction and expansion engineering as claimed in claim 1, characterized in that: The material removal component (101) comprises a material box (1011), a negative pressure suction machine (1012) is installed above the material box (1011), the negative pressure suction machine (1012) is connected to the material box (1011), a box door (1015) is arranged on the material box (1011), a material box (1013) is fixedly connected to one side of the material box (1011), and a handle (1014) is fixedly connected to one side of the material box (1013).
3. The device for removing the pavement of an old road for reconstruction and expansion engineering as claimed in claim 2, characterized in that: The swing-type feeding assembly (102) comprises a feeding hose (1021), the feeding hose (1021) is connected to the negative pressure suction machine (1012), the bottom end of the feeding hose (1021) is connected to a feeding head (1022), and a plurality of paddles (1023) are fixedly connected below the feeding head (1022); Both sides of the feed head (1022) are fixedly connected with slide plates (1027), and the slide plates (1027) are inserted and slidably arranged in the fixed plate (1026); An annular frame (1024) is fixedly connected above the feed head (1022), a crankshaft (1025) is slidably connected in the annular frame (1024), and one end of the crankshaft (1025) is fixedly connected to the output shaft of the first motor (1028).
4. The device for removing the pavement of an old road for reconstruction and expansion engineering as claimed in claim 3, characterized in that: The dust removal component (202) comprises a water tank (2025), a water injection end (2026) is provided on one side of the water tank (2025), the fixing plate (1026) and the first motor (1028) are fixedly connected below the water tank (2025), a water pump (2021) is installed on the water tank (2025), the water inlet of the water pump (2021) extends into the interior of the water tank (2025), the water outlet of the water pump (2021) is connected to a water outlet pipe (2022), the water outlet pipe (2022) is connected to an annular nozzle (2023), the annular nozzle (2023) is enclosed around the periphery of the water tank (2025), the interior of the annular nozzle (2023) is fixedly connected to a fixing strip (2024), and the fixing strip (2024) is fixedly connected to the outside of the water tank (2025).
5. The device for removing the pavement of an old road in a reconstruction and expansion project as claimed in claim 4, characterized in that: The moving assembly (203) comprises an electric push rod (2032), wherein the electric push rod (2032) is fixedly connected below the water tank (2025), and a moving wheel (2031) is fixedly connected to the bottom end of the electric push rod (2032).
6. The device for removing the pavement of an old road in a reconstruction and expansion project as claimed in claim 4, characterized in that: The elastic retaining component (201) comprises a fixing disk (20111) and two annular plates (2011); the fixing disk (20111) is fixedly connected to the bottom of the water tank (2025); a plurality of fixing openings are provided on the fixing disk (20111); a fixing seat (2012) is fixedly connected to the upper annular plate (2011); a fixing bolt (2013) is provided on the fixing seat (2012); and the fixing bolt (2013) is adapted to the size of the fixing opening.
7. The device for removing the pavement of an old road in a reconstruction and expansion project as claimed in claim 6, characterized in that: Two groups of slide bars (2016) and three groups of guide sleeves (2014) are arranged between the two fixed plates (20111), each group of slide bars (2016) has three slide bars, and each group of guide sleeves (2014) has two slide bars, wherein the two ends of the three slide bars (2016) are fixedly connected to the two annular plates (2011), and the other three slide bars (2016) are fixedly connected to the two guide sleeves (2014), the annular plates (2011) slide in the three guide sleeves (2014), and the three guide sleeves (2014) on the top are fixedly connected to the bottom of the fixed plate (20111); The slide bar (2016) is slidably connected in the slide sleeve (2018), and a spring (2015) is fixedly connected above the slide sleeve (2018), wherein three springs (2015) are respectively fixedly connected to the three slide sleeves (2018) above, and the remaining springs (2015) are fixedly connected below the annular plate (2011) above, wherein three slide sleeves (2018) are installed on the turntable (204), and the other three slide sleeves (2018) are respectively installed on three connecting plates (2017), and an annular strip (2019) is fixedly connected between the three connecting plates (2017), and the annular strip (2019) is fixedly connected to the inner ring of the first bearing (20110), and the turntable (204) is rotatably connected to the outer ring of the first bearing (20110).
8. The device for removing the pavement of an old road in a reconstruction and expansion project as claimed in claim 7, characterized in that: The driving assembly (205) comprises a second motor (2051), the upper part of the second motor (2051) is installed below the fixed disk (20111) via a support plate (2052), the output shaft of the second motor (2051) is fixedly connected to a rotating shaft (2055), the rotating shaft (2055) is rotatably connected to two vertical plates (2053) via two second bearings (2056), the two vertical plates (2053) are fixedly connected below the fixed disk (20111), and the rotating shaft (2055) is fixedly connected to a cam (2054).
9. The device for removing the pavement of an old road in a reconstruction and expansion project as claimed in claim 8, characterized in that: The adjustable breaking assembly (206) comprises a circular disk (2069), a pulley (2068) is fixedly connected to the top of the circular disk (2069), the pulley (2068) is in contact with the cam (2054), the circular disk (2069) is fixedly connected to the annular strip (2019) via a plurality of guide plates (2062), an adjustment sleeve (2061) is slidably connected to the guide plate (2062), and a first adjustment sleeve (2061) is fixedly connected to the bottom of the adjustment sleeve (2061). A receiving plate (2063), wherein the first receiving plate (2063) slides in the oblique opening (207), a first drill bit (2064) is installed below the first receiving plate (2063), a second receiving plate (2066) is fixedly connected below the circular plate (2069), a second drill bit (2065) is installed below the second receiving plate (2066), and the rotating plate (204) is also rotatably connected to the second receiving plate (2066) via a third bearing (2067).
10. A construction method for a device for removing the pavement of an old road in a reconstruction and expansion project according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1. When performing a road surface breaking operation, first adjust the distance between the first drill bits (2064), and by toggling the annular plate (2011) to rotate, the linkage part slide bar (216) drives the rotating disk (204) to rotate, and the rotating disk (204) squeezes the first receiving plate (2063) through the oblique opening (207) to move, so that the first receiving plate (2063) drives the first drill bit (2064) to move, thereby satisfying the spacing adjustment between the first drill bits (2064). After adjustment, the position of the annular plate (2011) is fixed by screwing the fixing bolt (213) into the fixing opening, and the electric push rod (2032) is retracted to adjust the distance between the first drill bit (2064) and the second drill bit (2065) and the road surface; S2, then controlling the second motor (2051) to drive the rotating shaft (2055) to rotate, the rotating shaft (2055) drives the cam (2054) to rotate, so that the cam (2054) squeezes the pulley (2068) to move downward, the circular plate (2069) drives the lower annular plate (2011) to move through the guide plate (2062), so that the spring (2015) is deformed, and the cam (2054) cooperates with the spring (2015) to drive the rotating plate (204) to achieve the purpose of vibration, so that the first drill bit (2064) and the second drill bit (2065) quickly vibrate to break the road surface; S3. During the breaking process, the liquid in the water tank (2025) is extracted by the water pump (2021) and enters the annular nozzle (2023) through the water outlet pipe (2022) to be sprayed out for dust reduction. Then, the negative pressure suction machine (1012) sucks the crushed fragments through the feed head (1022), so that the fragments enter the material box (1011), and the crankshaft (1025) is driven to rotate by the first motor (1028). The crankshaft (1025) drives the annular frame (1024) to reciprocate, so that the annular frame (1024) drives the feed head (1022) to reciprocate, so that the feed head (1022) drives the paddle (1023) to pry the fragments, thereby facilitating the recovery of the fragments.