Cable-stayed bridge dismantling construction method
By adding temporary piers and partially cutting the main beam during the dismantling process of the cable-stayed bridge, and using a truck crane for lifting, the technical difficulties and high costs of dismantling the cable-stayed bridge were solved, and a fast and low-cost construction effect was achieved.
Patent Information
- Application Number
- CN202411084726.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-10-18
AI Technical Summary
The technical difficulty of dismantling cable-stayed bridges is high, especially when the sea-crossing section increases the cost and construction period. Existing methods such as blasting and reverse process demolition methods have problems with noise, dust and high transportation costs, and the floating crane construction speed is slow and inaccurate. Difficult to control.
Add temporary piers on the side of the bank span, partially cut the main beam, gradually dismantle the old cables and the main beam of the bridge deck, and use a truck crane for hoisting to reduce the weight of the cantilever end and improve the speed and stability of the demolition.
There is no need to build cross-sea pile foundations, which significantly saves time and cost, reduces construction complexity, increases hoisting speed through pre-cutting, and reduces project costs.
Smart Images

Figure CN118792980A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge demolition, and in particular to a cable-stayed bridge demolition construction method. Background Art
[0002] A cable-stayed bridge, also known as a cable-stayed bridge, is a structural system composed of pressure-bearing bridge towers, tension-bearing cable-stayed cables and bending main beams. Its core components include bridge piers, cable towers, main beams and multiple cable-stayed cables.
[0003] With the rapid development of my country's transportation infrastructure, some existing bridges are unable to meet the navigation needs due to limited clearance under the bridges, or the traffic capacity is insufficient to cope with the growing traffic flow. Their demolition and reconstruction work is urgent. At present, the demolition of cable-stayed bridges mainly adopts blasting and reverse process demolition methods. In view of the noise and dust associated with blasting and the impact on surrounding residents, non-blasting demolition methods are more popular in the demolition of urban areas, densely populated areas and cross-river bridges.
[0004] Compared with continuous beam bridges, the technical difficulty of dismantling cable-stayed bridges is significantly higher. Especially when the bridge crosses a wide area of water, the cost of setting up temporary supports to ensure the stability of the structure is high, while floating crane operations have strict technical requirements. In addition, offshore construction is limited by transportation efficiency, construction period and high transportation costs, and the overall difficulty and cost are significantly increased.
[0005] Existing technologies, such as patent documents CN116289669 A and CN114382023 A, improve the stability of demolition by adding supports under the main beams on both sides of the tower. However, the construction of the cross-sea section support not only greatly increases the project volume and construction period, but also raises the technical threshold and cost.
[0006] Another existing patent document CN110552296 B uses a combination of stiffening beams and temporary cables to perform demolition through a combination of a truck crane and a floating crane. Although this ensures demolition stability and a single lifting weight, the floating crane has a slow construction speed, is difficult to control precision, and the use of dual equipment increases the workload. Summary of the invention
[0007] The purpose of the present invention is to provide a method for dismantling a cable-stayed bridge, the core of which is to add temporary piers on the shore span side, partially cut the main beam, and then symmetrically release the cable force on both sides of the cable tower, in this way gradually dismantle the old cables and the bridge deck main beam.
[0008] To achieve the above purpose, the technical solution of the present application is: a cable-stayed bridge dismantling construction method, comprising:
[0009] Inspect the main beam and cable towers of the bridge, including the upper and lower tower columns;
[0010] Temporary piers are set under the side span main beam connected to the abutment;
[0011] Consolidate the main beam and upper tower to increase the overall stiffness of the bridge and improve the stability during the bridge demolition process;
[0012] First, the cable-free area is removed to form independent and symmetrical first and second cable-stayed bridge structures;
[0013] When dismantling the first cable-stayed bridge structure, first dismantle the middle span beam, then the upper tower column, then the side span beam, and finally the lower tower column, temporary piers and abutments;
[0014] When dismantling the second cable-stayed bridge structure, the middle span beam is dismantled first, followed by the upper tower column, then the side span beam, and finally the lower tower column, temporary piers and abutments.
[0015] In one of the embodiments, the specific method of dismantling the cable-free area is: first mill the pavement layer on the bridge surface, then cut and remove the concrete guardrails on both sides, and then longitudinally cut the middle part of the bridge deck with the center line of the main beam cross section as the symmetry axis, symmetrically retain the non-middle part of the bridge deck, and finally transversely cut and completely dismantle the cable-free area.
[0016] In one embodiment, the specific method of removing the mid-span beam is:
[0017] Cutting off longitudinally the middle part of the main girder deck between the mid-span side cable and the mid-span secondary side cable;
[0018] The cable forces of the middle span side cables and the side span side cables are symmetrically released with the cable tower as the center, so that the beam body between the middle span side cables and the middle span secondary side cables forms a cantilever end;
[0019] On the bridge deck, use a truck crane to completely remove the main beam between the middle span side cables and the middle span secondary side cables;
[0020] Then longitudinally cut off the middle part of the bridge deck of the main beam between the secondary side cables of the middle span and the third group of inclined cables of the middle span, and then release the cable tension of the secondary side cables of the middle span and the secondary side cables of the side spans, so that the beam body between the secondary side cables of the middle span and the third group of inclined cables of the middle span forms a cantilever end, and remove the beam body between the secondary side cables of the middle span and the third group of inclined cables of the middle span, and repeat this step until the entire beam body of the middle span is removed.
[0021] In one of the embodiments, the specific method of longitudinally cutting the middle part of the main beam bridge deck between the middle span side cables and the middle span secondary side cables is: first milling the bridge surface pavement layer, then cutting and removing the concrete guardrails on both sides, and then longitudinally cutting the middle part of the bridge deck with the center line of the main beam cross section as the symmetry axis, and symmetrically retaining the non-middle part of the bridge deck.
[0022] In one embodiment, the specific method of removing the side span beam is:
[0023] Cut the main beam horizontally above the temporary pier to change the main beam structure from continuous to simply supported;
[0024] The cut beams are removed in sequence from the cable tower to the abutment.
[0025] In one embodiment, the number of temporary piers is set according to the bearing capacity requirements of truck cranes and transport vehicles when passing through.
[0026] In one of the embodiments, the specific method of longitudinally cutting the middle part of the bridge deck with the center line of the main beam cross section as the symmetry axis is: first, the middle part of the bridge deck is divided into unit structures along the longitudinal and transverse directions of the bridge, and the shape of the unit structure is a quadrilateral. Each unit structure is provided with lifting holes on all sides and the lifting device is connected. After the unit structure is cut with a rope saw, it is lifted by a car crane and lifted onto a transport vehicle for transportation to the crushing site.
[0027] In one of the embodiments, the specific method of dismantling the upper tower column is: draw transverse cutting lines at certain intervals in the direction perpendicular to the upper tower column, wherein the transverse cutting lines are parallel to the horizontal plane, and then use a rope saw to cut transversely along the transverse cutting lines section by section. After the upper tower column is cut into multiple sections, it is lifted away from the site with a car crane.
[0028] In one of the embodiments, the side span beams are used as transportation channels when the middle span beams are removed.
[0029] Due to the adoption of the above technical solution, the present invention can achieve the following technical effects: the method is specially designed for a double-tower cable-stayed bridge that spans both the shore and the sea, and there is no need to build a pile foundation for the sea-crossing section. This measure greatly saves time, reduces engineering costs, and effectively reduces construction complexity. The bridge deck is used as a transportation channel, and the lifting operation can be completed only by relying on a truck crane. At the same time, by pre-cutting the beam body, the weight of the cantilever end is effectively reduced, thereby achieving a significant increase in the lifting speed, a significant shortening of the construction period, and a further reduction in engineering costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0031] Figure 1 A schematic diagram of a double-tower cable-stayed bridge targeted by the construction method of the present invention;
[0032] Figure 2 This is a schematic diagram of the bridge deck with a longitudinal cutout of part of the main beam cross section near the center line;
[0033] Explanation of the serial numbers in the figure: 1—abutment, 2—upper tower, 3—stayed cable, 31—middle span side cable, 32—middle span secondary side cable, 33—side span side cable, 34—side span secondary side cable, 4—main beam, 41—middle part of bridge deck, 42—non-middle part of bridge deck, 5—lower tower, 6—temporary pier, 7—cable-free area. DETAILED DESCRIPTION
[0034] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0035] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0036] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, "multiple" means two or more, unless otherwise clearly and specifically defined. "Several" means one or more, unless otherwise clearly and specifically defined.
[0037] In the description of the present application, it should be understood that the terms "center", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0038] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0039] See also Figure 1 This embodiment provides a cable-stayed bridge dismantling construction method, which specifically includes:
[0040] S1. Inspect the main beam and cable tower of the bridge, including the upper tower column and the lower tower column;
[0041] Specifically, since the bridge has been in operation for a long time and its current load-bearing condition is unknown, in order to ensure safety during the bridge demolition process, the bridge must be inspected, including: inspecting the concrete strength of the main beam 4, the lower tower column 5 and the upper tower column 2; inspecting the actual cable force of the inclined cable 3, and inspecting the corrosion of the anchorage and tensioning ends of the inclined cable 3 at both ends; inspecting the integrity of the structure such as the tower-beam consolidation point, the tensioning anchorage of the inclined cable 3 on the tower, and the anchorage end of the inclined cable 3 in the beam body. If the strength is too low, the corrosion is too serious, and the structural integrity is very poor, appropriate reinforcement is required.
[0042] In addition, various pipelines within the scope of the bridge demolition construction will be checked in detail, and temporary rerouting or reinforcement and protection measures will be taken in a timely manner if they affect the construction.
[0043] S2. Set up temporary piers under the side span main beam connected to the abutment;
[0044] Specifically, the number of temporary piers is reasonably determined under the conditions that truck cranes and transport vehicles can pass through, and the temporary piers are made of reinforced concrete structures. When the side span cable tension is released, the temporary piers can effectively support the side span beam and maintain the stability of the side span main beam. When the middle span beam is dismantled, the side span beam can be used as a transportation channel.
[0045] S3. Consolidate the main beam and upper tower to increase the overall stiffness of the bridge and improve the stability of the bridge during demolition;
[0046] The main beam and upper tower column were hinged before demolition construction and became fixed during demolition.
[0047] S4. Firstly, the cable-free area is removed to form an independent and symmetrical first cable-stayed bridge structure and a second cable-stayed bridge structure;
[0048] Specifically, the pavement layer of the bridge surface in the cable-free area 7 is first milled, and then the concrete guardrails on both sides of the main beam of this section are cut and removed with a diamond wire saw. When cutting, the guardrails are first cut vertically to divide the longitudinal bridge into unit structures, and then the connection part between each unit structure and the bridge deck is horizontally cut. Then, the middle part of the bridge deck is longitudinally cut with the center line of the main beam cross section as the symmetry axis, and the non-middle part of the bridge deck is symmetrically retained. Finally, the cable-free area 7 is cut horizontally and completely removed to form an independent and symmetrical first cable-stayed bridge structure and a second cable-stayed bridge structure.
[0049] S5. When dismantling the first cable-stayed bridge structure, first dismantle the middle span beam, then dismantle the upper tower column, then dismantle the side span beam, and finally dismantle the lower tower column, temporary piers and abutments; specifically include:
[0050] S5.1. Longitudinally cut the middle part 41 of the bridge deck of the main beam 8 between the middle span side cable 31 and the middle span secondary side cable 32. Specifically, first mill the bridge deck pavement layer of the main beam 8, and then cut and remove the concrete guardrails on both sides of the section, such as Figure 2 Then, the middle part 41 of the bridge deck is longitudinally cut off with the center line of the cross section of the main beam as the symmetry axis, and the non-middle part 42 of the bridge deck is retained.
[0051] It should be noted that the longitudinal cutting of the middle part 41 of the bridge deck with the center line of the main beam cross section as the symmetry axis is specifically as follows: first, the middle part 41 of the bridge deck is divided into small unit structures along the longitudinal and transverse directions of the bridge, and the shape of the small unit structures is a quadrilateral. Each unit structure is provided with lifting holes on all sides and the lifting device is connected. After the unit structure is cut with a rope saw, it is lifted by a car crane onto a transport vehicle and transported to the crushing site.
[0052] S5.2. The cable forces of the middle span side cables 31 and the side span side cables 33 are symmetrically released with the cable tower as the center, so that the beam body 8 between the middle span side cables 31 and the middle span secondary side cables 32 forms a cantilever end. At this time, the temporary piers set up in the side span begin to play a role in maintaining the stability of the side span structure. After the cable force of the middle span side cables 31 is released, the beam body 8 between adjacent cables becomes a cantilever structure, but because the middle part of the bridge deck has been removed, the deadweight is reduced, and the rib plate is retained to still maintain stability;
[0053] S5.3. Use a truck crane to completely dismantle the main beam between the middle span side cable and the middle span secondary side cable on the bridge deck, using four-corner lifting;
[0054] S5.4. Then longitudinally cut off the middle part of the bridge deck of the main beam between the secondary side cable 32 of the middle span and the third group of the middle span inclined cables, and then release the cable force of the secondary side cable 32 of the middle span and the secondary side cable 34 of the side span, so that the beam body between the secondary side cable 32 of the middle span and the third group of the middle span inclined cables forms a cantilever end, and remove the beam body between the secondary side cable 32 of the middle span and the third group of the middle span inclined cables, and repeat this step until the beam body of the middle span is completely removed. At this time, the inclined cables are completely removed, there is no cable force on the cable tower, and it can maintain stability, and the side span main beam is supported by temporary piers and becomes a continuous structure;
[0055] S5.5. When dismantling the upper tower column 2, draw transverse cutting lines at certain intervals in its vertical direction, wherein the transverse cutting lines are parallel to the horizontal plane, and then use a rope saw to cut transversely section by section along the transverse cutting lines. After the upper tower column 2 is cut into multiple sections, it is lifted away from the site with a car crane.
[0056] S5.6. When dismantling the side span beam, first cut the main beam 4 above the temporary pier horizontally to change the side span main beam structure from continuous to simply supported, and then cut and dismantle the side span beam in sections from the cable tower to the abutment.
[0057] S5.7. Remove the lower tower column 5 and temporary pier 6, and finally remove the abutment 1.
[0058] S6. When dismantling the second cable-stayed bridge structure, first dismantle the middle span beam, then the upper tower column, then the side span beam, and finally the lower tower column, temporary piers and abutments. For details, refer to S5.1-S5.7.
[0059] In this embodiment, the purpose of first milling the bridge deck pavement layer, cutting off the guardrail and cutting off part of the main beam panel is to reduce the weight of the part to be removed, which is conducive to the lifting construction of the truck crane on the bridge deck. The method of the present invention is unique and novel, with convenient and efficient construction, low cost, and meets the requirements of modern construction.
[0060] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A cable-stayed bridge dismantling construction method, characterized in that: include: Inspect the main beam and cable towers of the bridge, including the upper and lower tower columns; Temporary piers are set under the side span main beam connected to the abutment; Consolidate the main beam and upper tower to increase the overall stiffness of the bridge; First, the cable-free area is removed to form independent and symmetrical first and second cable-stayed bridge structures; When dismantling the first cable-stayed bridge structure, first dismantle the middle span beam, then the upper tower column, then the side span beam, and finally the lower tower column, temporary piers and abutments; When dismantling the second cable-stayed bridge structure, the middle span beam is dismantled first, followed by the upper tower column, then the side span beam, and finally the lower tower column, temporary piers and abutments.
2. A cable-stayed bridge dismantling construction method according to claim 1, characterized in that: The specific method of dismantling the cable-free area is: first mill the pavement layer on the bridge surface, then cut and remove the concrete guardrails on both sides, and then cut off the middle part of the bridge deck longitudinally with the center line of the main beam cross section as the symmetry axis, symmetrically retain the non-middle part of the bridge deck, and finally cut horizontally and completely dismantle the cable-free area.
3. The method for dismantling a cable-stayed bridge according to claim 1, characterized in that: The specific method of dismantling the mid-span beam is: Cutting off longitudinally the middle part of the main girder deck between the mid-span side cable and the mid-span secondary side cable; The cable forces of the middle span side cables and the side span side cables are symmetrically released with the cable tower as the center, so that the beam body between the middle span side cables and the middle span secondary side cables forms a cantilever end; On the bridge deck, use a truck crane to completely remove the main beam between the middle span side cables and the middle span secondary side cables; Then longitudinally cut off the middle part of the bridge deck of the main beam between the secondary side cables of the middle span and the third group of inclined cables of the middle span, and then release the cable tension of the secondary side cables of the middle span and the secondary side cables of the side spans, so that the beam body between the secondary side cables of the middle span and the third group of inclined cables of the middle span forms a cantilever end, and remove the beam body between the secondary side cables of the middle span and the third group of inclined cables of the middle span, and repeat this step until the entire beam body of the middle span is removed.
4. A cable-stayed bridge dismantling construction method according to claim 3, characterized in that: The specific method of longitudinally cutting the middle part of the main beam bridge deck between the middle span side cables and the middle span secondary side cables is: first mill the bridge surface pavement layer, then cut and remove the concrete guardrails on both sides, and then longitudinally cut the middle part of the bridge deck with the center line of the main beam cross section as the symmetry axis, and symmetrically retain the non-middle part of the bridge deck.
5. The cable-stayed bridge dismantling construction method according to claim 1, characterized in that: The specific method of dismantling the side span beam is: Cut the main beam horizontally above the temporary pier to change the main beam structure from continuous to simply supported; The cut beams are removed in sequence from the cable tower to the abutment.
6. A cable-stayed bridge dismantling construction method according to claim 1, characterized in that: The number of temporary piers is set according to the bearing capacity requirements of truck cranes and transport vehicles passing through.
7. A cable-stayed bridge dismantling construction method according to claim 2 or 4, characterized in that: The specific method of longitudinally cutting the middle part of the bridge deck with the center line of the main beam cross section as the symmetry axis is: first, divide the middle part of the bridge deck into unit structures along the longitudinal and transverse directions of the bridge, and the shape of the unit structure is a quadrilateral. Each unit structure is provided with lifting holes on all sides and the lifting device is connected. After the unit structure is cut with a rope saw, it is lifted by a car crane onto a transport vehicle and transported to the crushing site.
8. The cable-stayed bridge dismantling construction method according to claim 1, characterized in that: The specific method of dismantling the upper tower column is: draw transverse cutting lines at certain intervals in the vertical direction of the upper tower column, and the transverse cutting lines are parallel to the horizontal plane. Then use a rope saw to cut transversely along the transverse cutting lines section by section. After cutting the upper tower column into multiple sections, use a car crane to lift it away from the site.
9. A cable-stayed bridge dismantling construction method according to claim 1, characterized in that: When dismantling the middle span beam, the side span beam is used as a transportation channel.