Shallow layer curing monitoring system and monitoring method
By introducing an intelligent monitoring system in shallow curing construction to collect and control construction data in real time, the problem of uneven construction quality and difficulty in controlling the dosage of cured materials has been solved, achieving precise control of construction units and improving construction efficiency.
Patent Information
- Application Number
- CN202411047520.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing shallow solidification construction technology lacks intelligent monitoring and control, resulting in uneven construction quality, difficulty in controlling the dosage of solidified materials, and safety issues such as insufficient bearing capacity and excessive settlement.
Design a shallow solidification construction monitoring system, including human-computer interaction module, construction design information module, central control platform, mixing equipment operation module, feeding equipment operation module, construction data collection module, control module, background server and data storage evaluation The module divides construction units through a three-dimensional coordinate system, collects and monitors construction data in real time, and achieves precise control and compensation adjustment.
The construction quality control of construction units is realized, ensuring that the amount of solidified materials and mixing times of each unit meet the design requirements, improving construction efficiency and material utilization, and reducing construction risks and costs.
Smart Images

Figure CN118793029A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of soft soil foundation construction monitoring, and in particular to a shallow layer solidification monitoring system and a monitoring method. Background Art
[0002] Soft soil has high organic matter content, low strength and high compressibility, and cannot meet the normal use requirements of foundation engineering. Common soft soil foundation treatment methods include composite foundation method, drainage consolidation method, compaction method and solidification material stabilization method. For shallow soft soil, the replacement method is usually regarded as the preferred option, but it has problems such as in-situ soft soil disposal and large replacement volume. In order to achieve the goals of green construction, energy conservation and environmental protection, and economic efficiency, shallow in-situ solidification technology has been widely used in the treatment of shallow soft soil foundations.
[0003] Shallow solidification technology uses cement, solidification materials and other solidification materials to modify the in-situ soft soil foundation to form a soft foundation treatment method that meets certain strength requirements. The basic principle is that the solidification material reacts with the chemical components and water in the soft soil to produce gelling substances, forming a "hard shell layer" with certain rigidity and strength, thereby improving the bearing capacity of the foundation. This "hard shell layer" of soil helps to evenly spread the upper load and improve the surface bearing capacity of the soft soil foundation. Shallow soft soil in-situ solidification technology has the advantages of high construction efficiency, economy and environmental protection, ability to meet different bearing capacity requirements, and can be combined with other soft soil roadbed treatment methods.
[0004] The results of the engineering application of shallow solidification technology in treating shallow soft soil over the years show that the quality of the project depends on whether the quality of deep mixing pile construction can be controlled and whether the solidification material can be fully and evenly mixed with the soft soil. In the shallow solidification engineering construction, the existing shallow solidification engineering technology relies on the workers' sense of responsibility and experience, and usually cannot effectively control the construction quality of shallow solidification. There are often serious engineering quality problems such as uneven mixing of solidification materials and soft soil, uneven strength distribution, omission of some construction areas, and the amount of solidification materials not meeting the design requirements. It will also lead to engineering safety problems such as the bearing capacity of the treated soft soil foundation not meeting the design requirements and the settlement exceeding the standard.
[0005] At present, shallow layer solidification construction machinery is all realized by manual operation of pile drivers by machine operators. Since there is no intelligent monitoring and control equipment on shallow layer solidification construction machinery, the machine operators cannot perceive the changes in the strata and the real-time amount of solidifying materials during construction, nor can they accurately control the posture and speed of the mixing head, let alone the amount of ash mixed in the soft soil at different depths. All manual control actions cannot be implemented quantitatively. This is the fundamental reason for a large number of construction quality accidents and safety accidents caused by shallow layer solidification. Summary of the invention
[0006] The technical problem to be solved by the present invention is how to solve the construction quality problem of shallow layer solidification. In order to overcome the defects of the above prior art, the present invention provides a shallow layer solidification monitoring system and a monitoring method.
[0007] The present invention provides a shallow layer solidification construction monitoring system, which is used to control a mixing device and a feeding device to perform shallow layer solidification treatment on a construction site of a soft soil foundation, and includes a human-computer interaction module, a construction design information module, a central control platform, a mixing device operation module, a feeding device operation module, a construction data acquisition module, a control module, a background server, a feedback control module and a data storage evaluation module;
[0008] The human-computer interaction module is used to input preset execution parameter information including construction unit division information and display construction progress. The human-computer interaction module is connected to the central control platform through the construction design information module and is used to transmit the input preset execution parameter information to the central control platform. The construction design information module calculates the vertex coordinates and center coordinates of each construction unit according to the preset execution parameter information. The central control platform controls the mixing equipment operation module and the feeding equipment operation module through the control module to perform curing material injection and mixing processing on each construction unit in turn; the mixing equipment operation module is connected to the mixing equipment, and the feeding equipment operation module is connected to the feeding equipment;
[0009] The construction data acquisition module is used to collect construction data information of the mixing equipment and the feeding equipment, and the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the rotation speed of the mixing head, the working temperature of the mixing head, the torque of the mixing head, the pressure of the feeding pipe on the feeding equipment, and the flow rate of the solidified material in the feeding pipe; the construction data acquisition module feeds back the collected data information to the central control platform, and the central control platform compares the data with the preset information, calculates the soil strength of each construction unit, corrects the preset execution parameter information, and compensates the operation of the mixing equipment operation module and the feeding equipment operation module through the feedback control module, and obtains the compensation control data information;
[0010] The construction data acquisition module is connected to the background server via the wireless communication module, and the background server is connected to the data storage and evaluation module and the construction design information module, and is used to store preset execution parameter information, construction unit division information, construction data information and compensation control data information, and evaluate the construction quality of the construction site.
[0011] Compared with the prior art, the shallow solidification construction monitoring system of the present application has the following advantages: by dividing the entire area to be constructed into many smaller three-dimensional construction units on a three-dimensional coordinate system, the actual construction parameters of each construction unit are monitored and controlled during the construction process to meet the design requirements, and the construction quality of each unit is controlled by breaking the whole into parts, and then the construction quality of the entire construction area is controlled. The system can collect the output torque of the mixing head in real time and continuously judge the soft and hard properties of the soil layer, so as to reasonably control the drilling and mixing action of the construction drill, realize the construction of variable speed and variable dosage during the construction process, optimize the formation of variable strength foundation, and achieve the purpose of saving man-hours and solidifying materials. The present invention can determine the dosage and mixing times of the solidifying material of each construction unit according to the properties of the foundation soil layer, and can also maintain constant preset parameters during the construction process to meet the mixing uniformity and design strength of the shallow solidification, and ensure the construction quality of each construction unit to ensure the construction quality of the entire construction site.
[0012] In a possible implementation, the preset execution parameter information includes construction area coordinates, construction depth, construction unit plane side length, construction unit depth, required curing material dosage of the construction unit, required stirring times of the construction unit, required stirring energy of the construction unit and required feeding pressure of the construction unit.
[0013] In one possible implementation, the construction data acquisition module includes a satellite positioning sensor for the mixing equipment itself, a satellite positioning sensor for the center point of the mixing head of the mixing equipment, an inclination sensor for the mixing equipment, a torque sensor for the mixing head, a speed sensor for the mixing head, a temperature sensor for the mixing head, a pressure sensor for the ash conveying pipe, a flow sensor for the ash conveying pipe, and a background weighing sensor.
[0014] In a possible implementation, the stirring device operation module includes:
[0015] The mixing equipment moving unit obtains the center coordinates of the unit to be constructed through the central control platform, and is used to compare the center coordinates of the unit to be constructed with the center coordinates of the mixing equipment to control the mixing equipment to move to the unit to be constructed;
[0016] A mixing head positioning unit, used to control the mixing head to move to the top of the unit to be constructed according to the center coordinates of the mixing head and the center coordinates of the unit to be constructed;
[0017] A stirring control unit, used to control the rotation speed of the stirring head, the rotation direction of the stirring head and the moving speed of the stirring head in the depth direction according to preset execution parameter information;
[0018] The resistance feedback control unit is used to monitor and feedback the soil strength of the construction unit according to the torque of the mixing head, and to correct the preset execution parameter information through the feedback control module.
[0019] Compared with the existing technology, the above technical solution can control the precise positioning of the mixing head and the construction unit, and monitor the changes in the soil strength of the construction unit in real time to ensure the construction quality of each construction unit.
[0020] In a possible implementation, the feeding equipment operation module includes:
[0021] A material supply amount calculation unit is used to calculate the injection amount of the solidifying material per unit time interval on the construction unit;
[0022] The feeding unit is used to control the feeding device to deliver the solidified material to the mixing device according to the injection amount per unit time interval.
[0023] Compared with the prior art, the above technical solution can control the feeding equipment to feed materials according to the amount of solidifying material required by the construction unit, thereby ensuring the construction quality.
[0024] A monitoring method based on any of the above shallow layer solidification construction monitoring systems, comprising:
[0025] S1. Establish a three-dimensional coordinate system for the construction site according to the exploration results of the construction site, and preset execution parameter information, wherein the preset execution parameter information includes the coordinates of the construction area, the construction depth H, the side length j of the construction unit plane, the depth k of the construction unit, the amount of solidified material required by the construction unit, the number of stirring times required by the construction unit, the stirring energy required by the construction unit, and the feeding pressure required by the construction unit; divide the construction site into multiple construction areas on the three-dimensional coordinate system, and divide each construction area into m×n×h construction units with a volume of j×j×k, and number each construction unit in the form of (i, p, o), where i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; and calculate the coordinates of each vertex of each construction unit and the coordinates of the center point of the construction unit;
[0026] S2. Control the mixing equipment and the feeding equipment to reach the plane coordinates of the unit to be constructed (i, p, o), so that the unit to be constructed enters the construction range of the mixing equipment; then perform the curing material injection and mixing work on the unit to be constructed according to the preset execution parameters;
[0027] S3. Real-time collection of construction data information of the mixing equipment and the feeding equipment, the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the mixing head speed, the mixing head working temperature, the mixing head torque, the pressure of the feed pipe on the feeding equipment, the flow rate of the solidified material in the feed pipe, the current construction unit cumulative solidified material dosage, the current construction unit cumulative stirring times and the current construction unit cumulative stirring energy;
[0028] S4. Calculate the soil strength at the current position according to the torque of the mixing head, and correct the preset execution parameter information according to the soil strength;
[0029] S5. Calculate the displacement speed of the mixing head according to the change of the center coordinate of the mixing head, calculate the injection amount of the solidifying material per unit time interval according to the amount of solidifying material required by the current construction unit, the actual amount of solidifying material injected and the displacement speed of the mixing head, and supply the slurry according to the feeding pressure required by the construction unit; and control the stirring of the mixing head according to the updated stirring times and stirring energy;
[0030] S6. Determine whether the current position of the mixing head reaches the depth k of the current construction unit. If so, mark the completion of the construction of the current construction unit and proceed to S7. If not, return to S5;
[0031] S7.o=o+1, determine whether o≤h is satisfied. If so, return to S2; if not, enter S8;
[0032] S8.o is reset to zero, i=i+1, and it is determined whether i≤m is satisfied. If so, p takes values from the set {0, 1, 2, ..., n) in sequence and returns to S2; if not, the shallow solidification construction in the current construction area is completed.
[0033] Compared with the prior art, the shallow solidification construction monitoring method of the present application has the following advantages: by dividing the construction site into j×j×k three-dimensional construction units in combination with the construction plane and the construction depth direction, the amount of solidification material and the number of mixing times of each construction unit are controlled based on the soil strength of the construction unit, so as to ensure the construction quality of each construction unit, thereby ensuring the construction quality of the entire construction site.
[0034] In a possible implementation manner, the S2 specifically includes:
[0035] S21. According to the vertex coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing device, the mixing device and the feeding device are moved to the plane coordinates of the unit to be constructed (i, p, o) on the construction surface, so that the unit to be constructed enters the construction range of the mixing device;
[0036] S22. According to the center coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing head, the mixing head is moved to the top of the unit to be constructed (i, p, o);
[0037] S23. Control the feeding equipment and the mixing equipment to inject and mix the solidified material to the construction unit (i, p, o) according to the preset execution parameters.
[0038] In a possible implementation manner, the expression for calculating the soil strength at the current position according to the mixing head torque in step S4 is:
[0039]
[0040] C u It represents soil strength; k represents the correction coefficient of mixing head size; M represents the torque of mixing head; D represents the blade diameter of mixing head; H represents the blade height of mixing head. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 A structural diagram of a shallow solidification monitoring system provided in a specific embodiment 1 of the present invention;
[0042] Figure 2 The feeding device provided for the specific embodiment 1 of the present invention is a mechanical structure diagram of wet spray feeding;
[0043] Figure 3 The feeding device provided in the specific embodiment 1 of the present invention is a mechanical structure diagram of dry spray feeding;
[0044] Figure 4 The present invention specifically implements the flowchart of the shallow solidification monitoring method provided in 2.
[0045] Description of reference numerals:
[0046] 1-mixing machinery, 2-mixing head, 6-dry spraying feeding module, 61-dry spraying ash conveying pipe, 62-dry spraying air supply pipe, 71-wet spraying feeding module, 72-wet spraying slurry supply pump, 73-wet spraying flow meter and pressure sensor, 74-wet spraying slurry supply pipe. DETAILED DESCRIPTION
[0047] First, those skilled in the art should understand that these implementations are only used to explain the technical principles of the embodiments of the present application, and are not intended to limit the protection scope of the embodiments of the present application. Those skilled in the art can make adjustments to them as needed to adapt to specific application scenarios.
[0048] In the description of the embodiments of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.
[0049] In the embodiments of the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0050] The present application is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0051] See also Figure 1 As shown, the embodiment of the present application discloses a shallow layer solidification construction monitoring system, which is used to control the mixing equipment and the feeding equipment to perform shallow layer solidification treatment on the construction site of the soft soil foundation. The system includes a human-computer interaction module, a construction design information module, a central control platform, a mixing equipment operation module, a feeding equipment operation module, a construction data acquisition module, a control module, a background server, a feedback control module and a data storage evaluation module;
[0052] The human-computer interaction module is used to input preset execution parameter information including construction unit division information. This specific embodiment manually inputs the information through the human-computer interaction module or performs cloud input through the background server. It is also used to display the construction progress and construction status of each construction unit on the entire construction site. The preset execution parameter information includes the construction area coordinates, construction depth, plane side length of the construction unit, construction unit depth, the amount of solidified material required by the construction unit, the number of stirring times required by the construction unit, the stirring energy required by the construction unit, and the feeding pressure required by the construction unit; the human-computer interaction module of this specific embodiment is a human-computer interaction screen display, and the human-computer interaction module is connected to the construction design information module, and is used to calculate the vertex coordinates and center coordinates of each construction unit according to the preset execution parameter information; the construction design information module is connected to the central control platform, and is used to control the mixing equipment operation module and the feeding equipment operation module through the control module according to the preset execution parameters and the calculation results of the construction unit to perform solidified material injection and stirring processing on each construction unit in turn;
[0053] The construction data acquisition module is used to collect construction data information of the mixing equipment and the feeding equipment. The construction data acquisition module of this specific embodiment includes a satellite positioning sensor for the mixing equipment itself, a satellite positioning sensor for the center point of the mixing head of the mixing equipment, an inclination sensor for the mixing equipment, a torque sensor for the mixing head, a speed sensor for the mixing head, a temperature sensor for the mixing head, an ash conveying pipe pressure sensor, an ash conveying pipe flow sensor and a background weighing sensor; the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the speed of the mixing head, the working temperature of the mixing head, the torque of the mixing head, the pressure of the feeding pipe on the feeding equipment and the flow rate of the solidified material in the feeding pipe; the construction data acquisition module feeds back the collected data information to the central control platform, and the central control platform compares the data with the preset information, calculates the soil strength of each construction unit, corrects the preset execution parameter information, and compensates and controls the operation of the mixing equipment operation module and the feeding equipment operation module through the feedback control module, and obtains the compensation control data information;
[0054] The construction data acquisition module is connected to the background server via the wireless communication module, and the background server is connected to the data storage and evaluation module and the construction design information module, and is used to store preset execution parameter information, construction unit division information, construction data information and compensation control data information, and evaluate the construction quality of the construction site.
[0055] In this specific embodiment, the data storage evaluation module evaluates the construction quality of the constructed construction area according to the solidifying material dosage and the stirring times of the stirring head of each construction unit. When the error between the solidifying material dosage of a certain construction unit and the designed dosage is less than or equal to 5%, and the actual stirring times meet the design requirements, the construction quality of the pile is excellent; when the error is 6% to 10%, and the actual stirring times meet the design requirements, the construction quality of the pile is good; when the error is 10% to 15%, and the actual stirring times meet the design requirements, the construction quality of the pile is qualified; when the error is greater than 15%, or the actual stirring times do not meet the design requirements, the construction quality of the pile is considered to be unqualified.
[0056] In addition, the preset execution parameters in this specific embodiment are obtained through experiments after the staff surveys the construction site.
[0057] Furthermore, the stirring equipment operation module includes:
[0058] The mixing equipment moving unit obtains the center coordinates of the unit to be constructed through the central control platform, and with the help of the mixing equipment's own micro positioning sensor, controls the mixing equipment to move to the construction range of the unit to be constructed by comparing the center coordinates of the unit to be constructed with the center coordinates of the mixing equipment;
[0059] The mixing head positioning unit uses the mixing head center point satellite positioning sensor to collect the center coordinates of the mixing head, and is used to control the mixing head to move above the center coordinates of the unit to be constructed according to the center coordinates of the mixing head and the center coordinates of the unit to be constructed; and controls the posture of the mixing head through the mixing equipment inclination sensor so that the mixing head is directly at the center coordinates of the unit to be constructed;
[0060] A stirring control unit, used to control the rotation speed of the stirring head, the rotation direction of the stirring head and the moving speed of the stirring head in the depth direction according to preset execution parameter information;
[0061] The resistance feedback control unit is used to monitor and feedback the soil strength of the construction unit according to the torque of the mixing head, and to correct the preset execution parameter information through the feedback control module.
[0062] The feeding equipment operation module includes:
[0063] The material supply calculation unit is used to calculate the injection amount of the solidifying material per unit time interval on the construction unit; Figure 2 As shown, when the feeding device of this specific embodiment is a wet spraying machine, it is used to determine the amount of solidifying material used per construction unit and the converted slurry injection amount through the feeding operation module according to the water-cement ratio and the amount of solidifying material added, and obtain the spraying amount per second time interval; Figure 3 As shown, when the feeding device of this specific embodiment is a dry spraying machine, it is used to determine the amount of solidifying material per construction unit through the feeding operation module according to the solid-gas ratio and the amount of solidifying material added, and obtain the amount of ash spraying per second time interval;
[0064] The feeding unit delivers the solidified material to the mixing device by controlling the injection amount of the feeding device according to the unit time interval.
[0065] Furthermore, when the feeding equipment operation module is started, the central control platform retrieves parameters such as the water-cement ratio (solid-gas ratio) and the amount of solidifying material and transmits them to the feeding equipment operation module. When the feeding equipment is a wet spraying machine, the feeding equipment operation module automatically calculates, weighs and mixes the required amount of water and solidifying materials according to the received construction parameters, and the human-computer interaction module displays the amount of solidifying materials, water and additives; determines the amount of solidifying materials and the converted slurry injection volume of each construction unit, and calculates the spraying volume per second time interval; the feeding unit stirs and mixes the water, solidifying materials and additives according to the set stirring time and the speed of the stirring blades, and supplies slurry to the stirring equipment according to the slurry supply volume and the slurry delivery pressure.
[0066] When the feeding equipment is a dry spraying machine, the central control platform automatically calculates and weighs the required amount of curing material, the human-computer interaction module displays the curing material dosage, determines the curing material dosage of each construction unit, and calculates the amount of ash sprayed at each second time interval; the feeding unit can spray ash to the mixing equipment according to the ash supply amount and the solid-gas ratio.
[0067] For possible emergencies, manual intervention can also be adopted to manually control the slurry supply (ash spraying) of the feeding operation module.
[0068] In order to better understand the content of the present invention, the present invention is described in detail in combination with a specific implementation project: the engineering background is to reinforce the loose sand fill embankment, improve the embankment density and bearing capacity, and the design adopts shallow solidification to treat the foundation within 200cm of the roadbed, and the solidification material is ordinary Portland cement. The design strength requirement is to achieve a 7d unconfined compressive strength of not less than 0.5MPa.
[0069] Basic conditions in this implementation method: the relative density of the blown sand Dr = 0.289 ~ 0.329, the blown sand on the site is in a loose state; the dynamic penetration data is relatively discrete, and the blown sand is unevenly distributed in the vertical direction; the static load test shows that the allowable bearing capacity values of each measuring point vary greatly (75 ~ 120kPa), and the plane distribution of the blown sand is uneven; the survey shows that the existing embankment blown fill material is in a loose ~ slightly dense state, and the low bearing capacity and poor grading cannot meet the additional load strength requirements generated by vehicle driving. This project adopts wet spraying technology, with a cement addition of 10%, a water-cement ratio of 0.7, a mixing speed of 30r per minute, and a single-channel spraying method for spreading solidified materials; the construction machinery uses ALLU PM high-power agitator, installed on a hydraulic excavator, and a full set of shallow solidification mixing monitoring and control system devices are installed on this basis.
[0070] Before construction, first use the human-computer interaction module to input the construction area division information (each construction unit is 1m×1m×1m) and the plane coordinate position (X, Y) of the construction unit to be constructed this time, the construction unit curing material dosage of 10%, the curing material slurry water-cement ratio of 0.7, the construction unit stirring times of 300r, or directly call the construction parameters of the project already in the background server. The feeding operation module in the central control platform automatically calculates according to the set parameters and feedbacks that the cement consumption of each construction unit in this construction is 180kg. Combined with the stirring speed, it can be concluded that at least 10s of stirring is required in each construction unit.
[0071] After setting the construction parameters, start the equipment shift. At this time, the excavator compares the coordinates (X', Y') obtained by the Beidou positioning sensor with the plane coordinate position (X, Y) of the construction unit, and uses the electronically controlled hydraulic multi-way steering valve to control the excavator to automatically move to the area where construction is to be carried out, ensuring that the mixer can be constructed to the designated construction unit, and combined with the mixing head coordinate positioning unit, the mixing head attitude controller is used to control the mixing head to reach the plane coordinates of the designated construction unit.
[0072] After the excavator is in place, the feeding operation module is started. The quality of the solidifying material and water is controlled by the weighing device in the batching unit. The amount of solidifying material slurry with a water-binder ratio of 0.7 is about 5000kg, and the solidifying material slurry is stirred. After the set stirring time is reached, the high-pressure grouting pump starts to supply the slurry. The operation process of slurry preparation and supply can be observed on the human-computer interaction module in the background of the mixing station. If major problems occur during the slurry preparation and supply, the system will automatically alarm and intervene manually or shut down for self-inspection.
[0073] After the slurry supply begins, the central control platform immediately issues a command to start the mixing construction. The mixing equipment operation module controls the mixing equipment and the mixing head posture coordinates through the electronically controlled hydraulic multi-way steering valve according to the preset execution parameter information, controls the mixing head to reach the designated construction unit, and performs the mixing operation. At the same time, a high-pressure grouting pump or air compressor is used to implement quantitative injection of solidifying materials through the injection port until the mixing head sprays the required cement content at the designated construction unit and reaches the designed mixing times of the mixing head. During the construction process, since the torque sensor is installed in the mixing head, it can provide real-time mixing torque and convert it into soil strength in real time. When the soil strength is detected to be too high, in order to improve the effective utilization rate of solidifying materials and reduce the loss of construction equipment, the control module and the feedback control module automatically intervene to adjust the mixing speed and the injection volume of the grouting pump according to the set relationship table.
[0074] Specifically, during the mixing process, the control module and the feedback control module will calculate the soil strength based on the real-time torque data and adjust the frequency of the grouting pump, and then ensure the injection volume of the optimal solidifying material slurry through variable frequency spraying technology.
[0075] After the construction process is completed, the data storage and evaluation module will summarize and store the data collected during the entire construction, and evaluate the construction quality by comparing it with the design goals. After the construction is completed, the information data of any construction unit in the project can be reviewed.
[0076] During the construction process, since a torque sensor is installed in the mixing head, it can provide real-time mixing torque and convert it into soil strength in real time. When it is detected that the soil strength is too high, in order to improve the effective utilization rate of solidifying materials and reduce the loss of construction equipment, the control module and feedback control module automatically intervene and adjust the mixing speed and injection volume of the grouting pump according to the set control algorithm program.
[0077] Specifically, during the mixing process, the control module and the feedback control module will calculate the soil strength based on the real-time torque data and adjust the frequency of the grouting pump, and then ensure the injection volume of the optimal solidifying material slurry through variable frequency spraying technology.
[0078] Specifically, this monitoring and control system can guide the driver to construct a designated unit during the construction process and collect, calculate and control the solidification material dosage and mixing times of the construction unit in real time; during the construction process, this system can adjust the mixing speed of the mixing head according to the soft and hard properties of the soil layer, and with the support of the construction data acquisition module, control module and feedback control module, it can realize optimized variable dosage and variable speed construction, thereby achieving the purpose of saving work time and solidifying materials.
[0079] The monitoring system of the present invention can divide the entire area to be constructed into many smaller three-dimensional construction units, monitor and control the actual construction parameters of each construction unit to meet the design requirements during the construction process, and use the method of breaking the whole into parts to control the construction quality of the entire construction area. The system can collect the output torque of the mixing head in real time and continuously judge the soft and hard properties of the soil layer, so as to reasonably control the drilling and mixing action of the construction drill, realize the construction of variable speed and variable dosage during the construction process, optimize the formation of variable strength foundation, and achieve the purpose of saving man-hours and solidifying materials. The present invention can determine the dosage of solidifying materials and the number of mixing times for each construction unit according to the properties of the foundation soil layer, and can also maintain constant preset parameters during the construction process to meet the mixing uniformity and design strength of shallow solidification. Specific embodiment 2
[0081] See also Figure 4 As shown, the embodiment of the present application discloses a monitoring method for shallow solidification construction monitoring, which is implemented based on the shallow solidification construction monitoring system of specific embodiment 1, including:
[0082] S1. Establish a three-dimensional coordinate system for the construction site according to the exploration results of the construction site, and preset execution parameter information, wherein the preset execution parameter information includes the coordinates of the construction area, the construction depth H, the side length j of the construction unit plane, the depth k of the construction unit, the amount of solidified material required by the construction unit, the number of stirring times required by the construction unit, the stirring energy required by the construction unit, and the feeding pressure required by the construction unit; divide the construction site into multiple construction areas on the three-dimensional coordinate system, and divide each construction area into m×n×h construction units with a volume of j×j×k, and number each construction unit in the form of (i, p, o), where i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; and calculate the coordinates of each vertex of each construction unit and the coordinates of the center point of the construction unit;
[0083] S2. Control the mixing equipment and the feeding equipment to reach the plane coordinates of the unit to be constructed (i, p, o), so that the unit to be constructed enters the construction range of the mixing equipment; then perform the curing material injection and mixing work on the unit to be constructed according to the preset execution parameters; specifically including:
[0084] S21. According to the vertex coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing device, the mixing device and the feeding device are moved to the plane coordinates of the unit to be constructed (i, p, o) on the construction surface, so that the unit to be constructed enters the construction range of the mixing device;
[0085] S22. According to the center coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing head, the mixing head is moved to the top of the unit to be constructed (i, p, o);
[0086] S23. Control the feeding equipment and mixing equipment according to the preset execution parameters to perform the curing material injection and mixing work on the construction unit (i, p, o);
[0087] S3. Real-time collection of construction data information of the mixing equipment and the feeding equipment, the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the mixing head speed, the mixing head working temperature, the mixing head torque, the pressure of the feed pipe on the feeding equipment, the flow rate of the solidified material in the feed pipe, the current construction unit cumulative solidified material dosage, the current construction unit cumulative stirring times and the current construction unit cumulative stirring energy;
[0088] S4. Calculate the soil strength at the current position according to the torque of the mixing head, and correct the preset execution parameter information according to the soil strength; wherein the calculation formula for the soil strength is:
[0089]
[0090] C u represents soil strength; k represents the mixing head size correction factor; M represents the mixing head torque; D represents the mixing head blade diameter; H represents the mixing head blade height;
[0091] S5. Calculate the displacement speed of the mixing head according to the change of the center coordinate of the mixing head, calculate the injection amount of the solidifying material per unit time interval according to the amount of solidifying material required by the current construction unit, the actual amount of solidifying material injected and the displacement speed of the mixing head, and supply the slurry according to the feeding pressure required by the construction unit; and control the stirring of the mixing head according to the updated stirring times and stirring energy;
[0092] S6. Determine whether the current position of the mixing head reaches the depth k of the current construction unit. If so, mark the completion of the construction of the current construction unit and proceed to S7. If not, return to S5;
[0093] S7.o=o+1, determine whether o≤h is satisfied. If so, return to S2; if not, enter S8;
[0094] S8.o is reset to zero, i=i+1, and it is determined whether i≤m is satisfied. If so, p takes values from the set {0, 1, 2, ..., n} in sequence and returns to S2; if not, the shallow solidification construction in the current construction area is completed.
[0095] Compared with the prior art, the shallow solidification construction monitoring method of the present application has the following advantages: by dividing the construction site into j×j×k three-dimensional construction units in combination with the construction plane and the construction depth direction, the amount of solidification material and the number of mixing times of each construction unit are controlled based on the soil strength of the construction unit, so as to ensure the construction quality of each construction unit, thereby ensuring the construction quality of the entire construction site.
[0096] The monitoring method of the present invention can divide the entire area to be constructed into many small construction units, monitor and control the actual construction parameters of each construction unit to meet the design requirements during the construction process, and use the method of breaking the whole into parts to control the construction quality of the entire area to be constructed. In addition, the system can collect the output torque of the mixing head in real time, and continuously judge the soft and hard properties of the soil layer, so as to reasonably control the drilling and mixing actions of the construction drill, realize the construction of variable speed and variable dosage during the construction process, optimize the formation of variable strength foundation, and achieve the purpose of saving man-hours and solidifying materials; the present invention can determine the dosage of solidifying materials and the number of stirring times of the mixing head of each construction unit according to the properties of the foundation soil layer, and can also maintain constant preset parameters during the construction process to meet the mixing uniformity and design strength of shallow solidification.
[0097] In the description of the embodiments of the present application, it should be noted that in the description of the present application, terms such as "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is only for the convenience of description, and does not indicate or imply that the device or component must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present application.
[0098] In the description of the present application, the description with reference to the terms "one embodiment", "some embodiments", "in the present embodiment", "specific example", or "some examples" etc. means that the specific features, mechanisms, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, mechanisms, materials or characteristics described may be combined in a suitable manner in any one or more embodiments or examples. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0099] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.
Claims
1. A shallow layer solidification construction monitoring system is used to control the mixing equipment and feeding equipment to perform shallow layer solidification treatment on the construction site of soft soil foundation. It is characterized in that It includes human-computer interaction module, construction design information module, central control platform, mixing equipment operation module, feeding equipment operation module, construction data acquisition module, control module, background server, feedback control module and data storage and evaluation module; The human-computer interaction module is used to input preset execution parameter information including construction unit division information and display construction progress. The human-computer interaction module is connected to the central control platform through the construction design information module and is used to transmit the input preset execution parameter information to the central control platform. The construction design information module calculates the vertex coordinates and center coordinates of each construction unit according to the preset execution parameter information. The central control platform controls the mixing equipment operation module and the feeding equipment operation module through the control module to perform curing material injection and mixing processing on each construction unit in turn; the mixing equipment operation module is connected to the mixing equipment, and the feeding equipment operation module is connected to the feeding equipment; The construction data acquisition module is used to collect construction data information of the mixing equipment and the feeding equipment, and the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the rotation speed of the mixing head, the working temperature of the mixing head, the torque of the mixing head, the pressure of the feeding pipe on the feeding equipment, and the flow rate of the solidified material in the feeding pipe; the construction data acquisition module feeds back the collected data information to the central control platform, and the central control platform compares the data with the preset information, calculates the soil strength of each construction unit, corrects the preset execution parameter information, and compensates the operation of the mixing equipment operation module and the feeding equipment operation module through the feedback control module, and obtains the compensation control data information; The construction data acquisition module is connected to the background server via the wireless communication module, and the background server is connected to the data storage and evaluation module and the construction design information module, and is used to store preset execution parameter information, construction unit division information, construction data information and compensation control data information, and evaluate the construction quality of the construction site.
2. The shallow layer solidification construction monitoring system according to claim 1, It is characterized in that The preset execution parameter information includes the construction area coordinates, construction depth, construction unit plane side length, construction unit depth, the amount of solidified material required for the construction unit, the number of stirring times required for the construction unit, the stirring energy required for the construction unit and the feed pressure required for the construction unit.
3. The shallow layer solidification construction monitoring system according to claim 1, It is characterized in that The construction data acquisition module includes a mixing equipment satellite positioning sensor, a mixing equipment mixing head center point satellite positioning sensor, a mixing equipment inclination sensor, a mixing head torque sensor, a mixing head speed sensor, a mixing head temperature sensor, an ash conveying pipe pressure sensor, an ash conveying pipe flow sensor and a background weighing sensor.
4. The shallow layer solidification construction monitoring system according to claim 1, It is characterized in that The stirring equipment operation module comprises: The mixing equipment moving unit obtains the center coordinates of the unit to be constructed through the central control platform, and is used to compare the center coordinates of the unit to be constructed with the center coordinates of the mixing equipment to control the mixing equipment to move to the unit to be constructed; A mixing head positioning unit, used for controlling the mixing head to move to above the center coordinate of the unit to be constructed according to the center coordinate of the mixing head and the center coordinate of the unit to be constructed; A stirring control unit, used to control the rotation speed of the stirring head, the rotation direction of the stirring head and the moving speed of the stirring head in the depth direction according to preset execution parameter information; The resistance feedback control unit is used to monitor and feedback the soil strength of the construction unit according to the torque of the mixing head, and to control and correct the preset execution parameter information through the feedback control module.
5. The shallow layer solidification construction monitoring system according to claim 1, It is characterized in that The feeding equipment operation module includes: A material supply amount calculation unit is used to calculate the injection amount of the solidifying material per unit time of the construction unit; The feeding unit is used to control the feeding equipment to deliver the solidified material to the mixing equipment according to the injection volume per unit time.
6. A monitoring method based on the shallow layer solidification construction monitoring system according to any one of claims 1 to 5, It is characterized in that include: S1. Establish a three-dimensional coordinate system for the construction site according to the exploration results of the construction site, and preset execution parameter information, wherein the preset execution parameter information includes the coordinates of the construction area, the construction depth H, the side length j of the construction unit plane, the depth k of the construction unit, the amount of solidified material required by the construction unit, the number of stirring times required by the construction unit, the stirring energy required by the construction unit, and the feeding pressure required by the construction unit; divide the construction site into multiple construction areas on the three-dimensional coordinate system, and divide each construction area into m×n×h construction units with a volume of j×j×k, and number each construction unit in the form of (i, p, o), where i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; and calculate the coordinates of each vertex of each construction unit and the coordinates of the center point of the construction unit; S2. Control the mixing equipment to reach the plane coordinate (i, p, 0) of the unit to be constructed (i, p, o), so that the unit to be constructed enters the construction range of the mixing equipment; then perform curing material injection and mixing work on the unit to be constructed (i, p, o) according to the preset execution parameters; S3. Real-time collection of construction data information of the mixing equipment and the feeding equipment, the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the mixing head speed, the mixing head working temperature, the mixing head torque, the pressure of the feed pipe on the feeding equipment, the flow rate of the solidified material in the feed pipe, the current construction unit cumulative solidified material dosage, the current construction unit cumulative stirring times and the current construction unit cumulative stirring energy; S4. Calculate the soil strength at the current position according to the torque of the mixing head, and correct the preset execution parameter information according to the soil strength; S5. Calculate the displacement speed of the mixing head according to the change of the center coordinate of the mixing head, calculate the injection amount of the solidifying material per unit time interval according to the amount of solidifying material required by the current construction unit, the actual amount of solidifying material injected and the displacement speed of the mixing head, and supply the slurry according to the feeding pressure required by the construction unit; and control the mixing equipment and the feeding equipment according to the updated and corrected preset execution parameter information; S6. Determine whether the current position of the mixing head reaches the depth k of the current construction unit. If so, mark the completion of the construction of the current construction unit and proceed to S7. If not, return to S5; S7.o=o+1, determine whether o≤h is satisfied. If so, return to S2; if not, enter S8; S8.o is reset to zero, i=i+1, and it is determined whether i≤m is satisfied. If so, p takes values from the set {0,1,2,…,n} in sequence and returns to S2; if not, the shallow solidification construction in the current construction area is completed.
7. The monitoring method according to claim 6, It is characterized in that The S2 specifically includes: S21. According to the vertex coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing device, the mixing device is moved on the construction surface to the plane coordinates of the unit to be constructed (i, p, o), so that the unit to be constructed enters the construction range of the mixing device; S22. According to the center coordinates of the unit to be constructed (i, p, o) and the center coordinates of the mixing head, the mixing head is moved to the top of the unit to be constructed (i, p, o); S23. Control the feeding equipment and the mixing equipment to inject and mix the solidified material to the construction unit (i, p, o) according to the preset execution parameters.
8. The monitoring method according to claim 6, It is characterized in that The expression for calculating the soil strength at the current position according to the torque of the mixing head in step S4 is: C u It represents soil strength; k represents the correction coefficient of mixing head size; M represents the torque of mixing head; D represents the blade diameter of mixing head; H represents the blade height of mixing head.
Citation Information
Patent Citations
Shallow soft foundation strong on-site solidification treatment construction method
CN112695740A
Intelligent construction method and system suitable for in-situ reinforcement of large-area soft foundation
CN114036625A
Cement mixing pile soil layer identification method based on output torque
CN114855748A
Cited By
Control system for in-situ curing construction and construction method
CN121657541A
Torque depth double-closed-loop self-adaptive control method and system for in-situ curing