Support pile construction technology
Through accurate setting out and advanced rotary excavator technology, combined with environmentally friendly construction technology, the problems of low construction efficiency and large environmental impact of traditional supporting piles are solved, and efficient and environmentally friendly supporting pile construction in strata that are difficult to construct is achieved, ensuring construction Quality and environmental protection.
Patent Information
- Application Number
- CN202410905426.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-10-18
AI Technical Summary
The traditional support pile construction technology has problems such as low work efficiency and great impact on the surrounding environment. It is especially difficult to carry out effective construction in strata with high water levels, large pebbles or where long augers cannot construct.
Adopting precise lofting and positioning, advanced rotary excavator technology and environmentally friendly construction technology, through the design of casings, steel cages and conduits, combined with the pouring of high-performance concrete, a high degree of automation, rapid hole formation and pouring are achieved, reducing noise, Dust and waste emissions.
It improves the construction efficiency, ensures the quality of supporting piles is stable and reliable, has strong adaptability, reduces environmental impact, and can construct supporting piles in strata that are difficult to construct.
Smart Images

Figure CN118793041A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction engineering, and in particular to a supporting pile construction process. Background Art
[0002] Deep foundation pit support is a measure used in construction to ensure the safety of underground structures and the surrounding environment of the foundation pit. It is related to the support, reinforcement and protection of the side walls of the deep foundation pit and the surrounding environment to prevent soil collapse and groundwater infiltration. The design and construction of deep foundation pit support need to consider geological conditions, foundation pit depth, surrounding environment and other factors to ensure construction safety and project quality. The traditional support pile construction process has some limitations, such as low work efficiency and great impact on the surrounding environment during the construction process. Summary of the invention
[0003] The purpose of the present invention is to provide a support pile construction process to solve the technical problems existing in the prior art.
[0004] In order to achieve the above-mentioned object of the invention, the technical solution adopted by the present invention is:
[0005] A supporting pile construction process comprises the following steps: S1 staking out and positioning according to the design drawings, before starting the work, a measurement control network is established in the site according to the axis and the pile position arrangement, and the center point of each pile position is measured and laid out according to the control network; in order to improve the degree of automation and the hole-making speed, S2 a rotary drilling machine is put in place, the rotary drilling machine is moved to the designated pile position, and the verticality and horizontality of the rotary drilling machine are adjusted; S3 casing is buried, the casing diameter is larger than the pile hole diameter, the length should meet the requirement that the bottom of the casing enters the impermeable layer by no less than 0.5m, the top of the casing is 0.3m higher than the ground, the inclination of the casing is controlled within 1%, and the casing burying deviation does not exceed 30mm; S4 drilling and hole-making, after the casing is buried and positioned, re-measurement and positioning are carried out, appropriate drilling parameters are selected, and then the pile hole is rotary-drilled; S5 hole cleaning, after the drilling rig drills to the designed hole depth, the drill bit is lowered to the bottom of the hole, rotated slowly, and the soil expanded by the enlarged head is removed. Slag; S6 production and placement of steel cage, the steel cage is produced in sections on site to ensure that the working size and quality of the steel cage meet the design requirements, and the steel cage is placed in the column hole for fixing: S7 lowering guide tube, the guide tube is firmly fixed at the connection of the hole mouth, and a sealing ring is set. When hanging, the position should be centered, the axis should be straight, and it should be stably sunk; S8 concrete pouring, high-performance concrete is used, and it is poured into the hopper through the hole mouth. During pouring, the buried depth of the guide tube is controlled at 2 to 6 meters. Before removing the pipe, the concrete surface in the hole is measured and recorded. When the poured concrete is close to the pile top elevation, the last pouring amount is controlled to make the pile top elevation meet the design requirements; S9 pulling out the casing, after the concrete pouring is completed, the casing is pulled out, and the pouring equipment is cleaned and stacked neatly; S10 backfilling the pile hole, after the concrete pouring of the pile hole is completed, the upper part that has not been poured with concrete is backfilled, and after backfilling, the hole mouth is sealed with concrete again.
[0006] Furthermore, in S2, the error between the drill bit center and the pile position center is no more than 10 mm.
[0007] Furthermore, the working diameter of the casing in S3 is 200 mm larger than the working diameter of the pile hole.
[0008] Furthermore, in S6, the main bars and reinforcing bars are all welded, the spiral bars and the main bars are reinforced by spot welding, and the length of the steel cage is greater than 16m.
[0009] Furthermore, the connection mode of the conduit in S7 is threaded connection, the inner diameter thereof is φ250-φ280, the bottom pipe length is 4m, and the length of each middle section is generally 2.5m.
[0010] Furthermore, before the underwater concrete pouring in S8, the initial pouring volume of concrete is calculated for pile holes of different diameters and depths, and the initial pouring volume needs to be ensured during construction.
[0011] Furthermore, in S8, 1 to 2 plates of concrete are randomly selected as test blocks, and each pile is made into a group of test blocks. The prepared test blocks are demoulded after 12 hours and placed in still water for curing.
[0012] Compared with the prior art, the present invention has the following beneficial effects:
[0013] (1) The present invention can be used for construction in strata with high water levels, large pebbles, or where forward and reverse circulation and long spiral drills cannot be used for construction, and has the effects of strong adaptability and high degree of automation;
[0014] (ii) Through advanced drilling technology and construction equipment, holes can be drilled and concrete can be poured quickly, shortening the construction period and improving construction efficiency; through precise pile position setting, steel cage production and concrete pouring control, the quality of support piles can be ensured to be stable and reliable;
[0015] (III) Environmentally friendly construction materials and techniques are used. The rotary drilling rig uses the drill bit to dig soil, and then uses the Kelly telescopic drill rod to lift the drill bit out of the hole and unload the soil, thereby reducing noise, dust and waste emissions during the construction process and protecting the environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 is a flow chart of the present invention; DETAILED DESCRIPTION
[0017] In order to make the content of the present invention more clearly understood, the technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. The same parts are represented by the same figure marks. It should be noted that the words "front", "rear", "left", "right", "up" and "down" used in the following description refer to the directions in the drawings, and the words "inside" and "outside" refer to the directions toward or away from the geometric center of a specific component, respectively.
[0018] like Figure 1 As shown, this embodiment provides a support pile construction process, including the following steps:
[0019] S1 Layout and Positioning: Before starting construction, a measurement control network is established on site based on the axis and pile position layout, and the center points of each pile position are measured and laid out based on the control network.
[0020] The S2 rotary drilling rig is in place, moved to the designated pile position, and the verticality and horizontality of the rotary drilling rig are adjusted. The error between the drill bit center and the pile position center is no more than 10mm.
[0021] S3 buried casing, the diameter of the casing is larger than the diameter of the pile hole, and the specific working diameter of the casing is 200mm larger than the working diameter of the pile hole; the length should meet the requirement that the bottom of the casing enters the impermeable layer at least 0.5m, the top of the casing is 0.3m above the ground, the inclination of the casing is controlled within 1%, and the deviation of the casing does not exceed 30mm.
[0022] S4 is drilling into a hole. After the casing is buried and positioned, re-measurement and positioning are performed, appropriate drilling parameters are selected, and then the pile hole is rotary excavated.
[0023] S5 hole cleaning: after the drilling rig has drilled to the designed hole depth, lower the drill bit to the bottom of the hole and rotate it slowly to clear the soil debris expanded by the enlarged head.
[0024] S6 steel cage production and placement. The steel cage is produced in sections on site. The main bars and reinforcing bars are all welded. The spiral bars and main bars are reinforced by spot welding. The length of the steel cage is greater than 16m. Ensure that the working size and quality of the steel cage meet the design requirements. Put the steel cage into the column hole and fix it.
[0025] For S7 lower conduit, a threaded conduit with an inner diameter of φ250~φ280 and a bottom pipe length of 4m is selected. The length of each section in the middle is generally 2.5m. The conduit is firmly fixed at the hole connection and a sealing ring is set. When hanging, the position should be centered, the axis should be straight, and it should be stably sunk. It is worth mentioning that before the conduit is used, the appearance and joints of the conduit must be inspected. The appearance inspection is to check whether the conduit is deformed, pitted, bent, damaged or cracked, etc., and whether its inner wall is smooth. The joint inspection is to keep the thread of the conduit joint in good condition and it should be straight after connection. It can only be put into use after passing the inspection. The length of the conduit should be equipped according to the hole depth to meet the needs of hole cleaning and underwater concrete pouring, that is, it can reach the bottom of the hole when cleaning the hole. When pouring underwater, the bottom end of the conduit is about 0.5m away from the bottom of the hole, and concrete should be able to be smoothly poured from the conduit to the bottom of the hole.
[0026] For S8 concrete pouring, the slump of concrete is controlled at 18-22cm. High-performance concrete is poured into the hopper through the hole by a mixer truck. Before underwater concrete pouring, the initial pouring volume of concrete is calculated for pile holes of different diameters and depths. The initial pouring volume must be guaranteed during construction. The buried depth of the conduit is controlled at 2-6m during pouring. The concrete surface in the hole is measured and recorded before removing the pipe. When the poured concrete is close to the pile top elevation, the last pouring volume is controlled to make the pile top elevation meet the design requirements. During the pouring process, 1-2 plates of concrete are randomly selected as test blocks, and a group of test blocks are made for each pile. The prepared test blocks are demolded after 12 hours and placed in static water for curing. The test blocks are evaluated using mathematical statistics.
[0027] S9: Pull out the casing. After the concrete pouring is completed, pull out the casing, clean the pouring equipment, and stack them neatly.
[0028] S10 Backfill the pile hole. After the concrete pouring of the pile hole is completed, backfill the upper part that has not been poured with concrete. After backfilling, seal the hole again with concrete.
[0029] Carry out quality inspection on the completed support piles, including the bearing capacity, verticality, pile body integrity, etc., and use non-destructive testing technologies such as ultrasonic testing and low-strain testing to ensure that the quality of the support piles meets the design requirements.
[0030] It is worth noting that the construction process of the present invention can be adjusted and optimized according to specific engineering conditions to adapt to different geological conditions, foundation pit depths and support requirements.
[0031] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.
Claims
1. A support pile construction process, characterized in that: The following steps are involved: S1 Layout and positioning: Before construction begins, a measurement control network is established on site based on the axis and pile position layout, and the center points of each pile position are measured and laid out based on the control network; S2 rotary drilling machine is in place, move the rotary drilling machine to the designated pile position, and adjust the verticality and horizontality of the rotary drilling machine; S3 burying casing, the diameter of the casing is larger than the diameter of the pile hole, the length should meet the requirement that the bottom of the casing enters the impermeable layer at least 0.5m, the top of the casing is 0.3m above the ground, the inclination of the casing is controlled within 1%, and the deviation of the casing is not more than 30mm; S4 drilling into a hole, after the casing is buried and positioned, re-measurement and positioning, selecting appropriate drilling parameters, and then rotary digging the pile hole; S5 hole cleaning: after the drilling rig has drilled to the designed hole depth, lower the drill bit to the bottom of the hole and rotate it slowly to remove the soil debris expanded by the enlarged head; S6 steel cage production and placement, the steel cage is produced in sections on site to ensure that the working size and quality of the steel cage meet the design requirements, and the steel cage is placed in the column hole for fixing: S7 lower guide tube, the guide tube is firmly fixed at the hole connection, and a sealing ring is set. When hanging, the position should be centered, the axis should be straight, and it should be stably sunk; For S8 concrete pouring, high-performance concrete is used and poured into the hopper through the hole. The buried depth of the conduit is controlled at 2 to 6 meters during pouring. The concrete surface in the hole is measured and recorded before the pipe is removed. When the poured concrete is close to the pile top elevation, the last pouring amount is controlled to make the pile top elevation meet the design requirements. S9: Pull out the casing. After the concrete pouring is completed, pull out the casing, clean the pouring equipment, and stack them neatly; S10 Backfill the pile hole. After the concrete pouring of the pile hole is completed, backfill the upper part that has not been poured with concrete. After backfilling, seal the hole again with concrete.
2. The support pile construction process according to claim 1 is characterized in that: In S2, the error between the drill bit center and the pile position center is no more than 10 mm.
3. The support pile construction process according to claim 1 is characterized in that: The working diameter of the casing in S3 is 200 mm larger than the working diameter of the pile hole.
4. The support pile construction process according to claim 1 is characterized in that: In S6, the main bars and reinforcing bars are all welded, the spiral bars and the main bars are reinforced by spot welding, and the length of the steel cage is greater than 16m.
5. The support pile construction process according to claim 1 is characterized in that: The connection mode of the conduit in the S7 is threaded connection, the inner diameter thereof is φ250-φ280, the bottom pipe length is 4m, and the length of each middle section is generally 2.5m.
6. The support pile construction process according to claim 1 is characterized in that: Before the underwater concrete pouring in S8, the initial pouring volume of concrete is calculated for pile holes of different diameters and depths, and the initial pouring volume needs to be ensured during construction.
7. The supporting pile construction process according to claim 6 is characterized in that: In the S8, 1 to 2 plates of concrete are randomly selected as test blocks, and each pile is made into a group of test blocks. The prepared test blocks are demoulded after 12 hours and placed in still water for curing.