Foam light soil energy-consumption light shed tunnel structure and construction method

By using energy-absorbing protection devices and foam lightweight concrete cushions in reinforced concrete shed structures, the problems of difficulty, high cost, and insufficient safety in the construction of traditional shed structures are solved, and the structure is lightweight and highly resistant to rolling stones. impact capabilities, simplifying the construction process and improving safety.

CN118835544APending Publication Date: 2024-10-25MCC CHENGDU RES INST CO LTD

Patent Information

Application Number
CN202411264641.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

The traditional reinforced concrete shed structure is difficult to construct, has high construction costs and takes a long time, and is not safe enough when the impact load of rolling stones is large, making it difficult to ensure the stability of the structure and difficult to repair.

Method used

An energy-absorbing protection device is installed between the reinforced concrete frame and the reinforced concrete slab, and is covered with a foam lightweight concrete cushion. The polypropylene modified fiber rubber foam lightweight concrete material is used to replace the traditional sand cushion, combined with steel pipe absorption. The energy absorber and the steel backing plate form an energy-absorbing protection device to achieve double safety.

Benefits of technology

It reduces the weight and cross-sectional size of the shed structure, simplifies the construction process, reduces construction costs, improves the impact resistance of rolling stones, and ensures the safety of the structure through a double energy-absorbing mechanism, avoiding broken construction or shortening the construction time. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118835544A_ABST
    Figure CN118835544A_ABST
Patent Text Reader

Abstract

The invention discloses a foam light soil energy consumption light shed tunnel structure and a construction method, the foam light soil energy consumption light shed tunnel structure comprises a reinforced concrete frame and a reinforced concrete plate, an energy absorption protection device is arranged between the reinforced concrete plate and the reinforced concrete frame, and a foam light concrete cushion layer covers the reinforced concrete plate. The energy absorption protection device is fixed between the reinforced concrete slab and the reinforced concrete frame through bolts. The energy absorption protection device is arranged between the reinforced concrete frame and the reinforced concrete plate, residual energy (energy which is not absorbed by the cushion layer) is secondarily absorbed, and double safety guarantee is achieved. The foam lightweight concrete is adopted to replace a traditional sand cushion layer, the foam lightweight concrete is light in weight, the cushion layer load borne by the shed tunnel reinforced concrete frame structure is reduced, the sectional size of the reinforced concrete frame structure is reduced, and the economical efficiency is better achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shed-tunnel structures, and in particular to a foam lightweight soil energy-consuming lightweight shed-tunnel structure and a construction method. Background Art

[0002] The shed-tunnel structure is one of the most effective engineering measures for the prevention and control of rockfall disasters. The typical shed-tunnel structure consists of two parts: one is the reinforced concrete frame and the top plate; the other is the sand cushion layer with buffering and energy-absorbing effect covering the upper part of the reinforced concrete top plate. This type of shed-tunnel can effectively prevent the high-speed falling rocks from directly colliding with the concrete frame and causing structural damage or deformation. At the same time, the buffer layer material on the top has a certain elastic plasticity and thus has a certain deformability. When colliding with falling rocks, it can absorb most of the energy of the falling rocks through its own deformation, and the rest is transmitted to the foundation by the reinforced concrete frame. This structure mainly absorbs part of the impact energy and transmits it to the protective structure through the buffering and energy-dissipating effect of the sand cushion layer. Its technical characteristics are: increasing the thickness of the sand cushion layer and increasing the dry density of the sand cushion layer can reduce the impact force acting on the structure. Therefore, the anti-rockfall impact effect of the shed-tunnel structure can be improved by increasing the thickness and density of the sand cushion layer.

[0003] However, when the sand cushion is too thick, the density is too high, and the weight is large. Therefore, in the design of reinforced concrete shed tunnels, in addition to the need to withstand the impact of rolling stones, they also need to withstand a large sand cushion load, resulting in a large cross-sectional size of the shed tunnel components, and even in some projects, it is difficult to achieve. Its construction cost is too high, which restricts its promotion and application. Secondly, when the impact load of rolling stones is large, the energy consumption of the sand cushion layer is not enough to ensure the safety of the structure. According to the characteristics of traditional shed tunnel structures, such as difficulty, time and high cost in repair, and the shed tunnel structure is usually used in line engineering, its safety is a controlling factor to ensure the line engineering.

[0004] In addition, the traditional reinforced concrete shed tunnel structure is very large in size and weight, so it often requires a foundation with a large buried depth and large cross-sectional size. Its construction is difficult, costly, and time-consuming, and it often requires road interruption when reconstructing on the traffic line. Summary of the invention

[0005] The purpose of the present invention is to provide a foam lightweight soil energy-consuming lightweight shed tunnel structure and a construction method to solve the technical problems of the conventional reinforced concrete shed tunnel structure in the prior art, such as the high construction cost, long construction time and poor safety.

[0006] To achieve the above object, the present invention provides the following technical solutions: The present invention provides a foam lightweight soil energy-absorbing lightweight shed structure, which includes a reinforced concrete frame and a reinforced concrete slab. An energy absorption protection device is arranged between the reinforced concrete slab and the reinforced concrete frame. A foam lightweight concrete cushion layer is covered above the reinforced concrete slab. The energy absorption protection device is fixed between the reinforced concrete slab and the reinforced concrete frame by bolts.

[0007] Furthermore, the energy absorption protection device includes, from top to bottom, a support upper pad stone, an embedded steel plate, an upper steel plate, a steel tube energy absorber, a lower steel plate and a support lower pad stone, and the support upper pad stone, embedded steel plate, upper steel plate, steel tube energy absorber, lower steel plate and support lower pad stone are adjacently connected by bolts or steel bars.

[0008] Furthermore, the steel pipe energy absorber is made of a steel pipe and a steel backing plate, and the steel pipe has a diameter of 255 mm, a thickness of 8 mm, and a height of 400 mm.

[0009] Furthermore, the steel pad has a size of 400 mm×400 mm×12 mm.

[0010] Furthermore, the steel plate (the steel material is Q345, which mainly plays the role of connection and fixing) and the steel pipe (the steel material is Q235B, which mainly plays the role of energy absorption and shock absorption). The diameter, height and thickness of the steel pipe determine the energy absorption (i.e. the impact resistance of the shed hole). Therefore, the telescoping test or numerical simulation test should be used to determine whether its energy absorption meets the design requirements, so as to determine the reasonable size.

[0011] Furthermore, the foam lightweight concrete cushion layer adopts polypropylene modified fiber rubber foam lightweight concrete, and the reinforced concrete frame and reinforced concrete slab can adopt pre-customized finished products.

[0012] Foamed concrete is a green concrete with high porosity produced by adding a foaming agent to cement. It has the characteristics of light weight, low density, high energy saving and easy processing. On the other hand, the development of foamed concrete is seriously hindered by the disadvantages of traditional foamed concrete such as low strength and high porosity.

[0013] Rubber is usually used as an energy-absorbing and shock-absorbing material in construction, automobile, shipbuilding, protective engineering and other projects due to its advantages such as high elasticity, low shear modulus, high damping and viscoelasticity. When rubber is used as an energy-absorbing and shock-absorbing facility for houses, its shock-absorbing effect can reach 10% to 40%. When rubber is used as a damping layer, it dissipates more energy than silicone, and maintains the integrity of rock and concrete, reducing the degree of damage. When cement-based materials are subjected to impact loads, more microcracks will be generated inside them. As the number of impact loads increases, the cracks gradually develop until they penetrate the material. When rubber is added to cement-based materials, it absorbs part of the energy through its own high deformation, which correspondingly reduces the energy borne by the cement matrix and aggregate, achieving the effect of energy dissipation and shock absorption.

[0014] The elastic compression characteristics of rubber particles are utilized and combined with foam lightweight soil. Polypropylene fibers are added to improve the integrity to form a new material of polypropylene fiber-modified rubber foam lightweight soil. This improves the energy absorption effect of the material, reduces the stiffness of the material, and enables the material's comprehensive mechanical properties to be more fully utilized.

[0015] The present invention also provides a construction method of a foam lightweight soil energy-consuming lightweight shed-tunnel structure, comprising the following steps: S1. Production of steel pipe energy absorber: install steel pads at both ends of the steel pipe by bolts; S2. Construction of shed tunnel foundation: site leveling → laying out → foundation excavation → foundation bottoming → pouring cushion layer → formwork → steel bar binding → pouring foundation concrete, using prefabricated reinforced concrete columns, and the foundation should adopt a cup-shaped structure; S3. Installation of precast reinforced concrete columns: The precast columns and foundation cups are connected as required by the building foundation design specifications; S4. Installation of energy absorption protection device: install the support lower pad stone, lower steel plate, steel pipe energy absorber, embedded steel plate and support upper pad stone from bottom to top, and continue to install the reinforced concrete slab on the support upper pad stone through high-strength anchor bolts; S5. Fix the foam lightweight concrete cushion layer on the reinforced concrete slab by bolts.

[0016] Based on the above technical solution, the embodiments of the present invention can at least produce the following technical effects: (1) The present invention adopts polypropylene modified fiber rubber foam lightweight concrete to replace the traditional sand soil cushion layer, so as to achieve a lightweight structure.

[0017] (2) The present invention sets an energy absorption protection device between the reinforced concrete frame and the reinforced concrete slab to absorb the remaining energy (energy not absorbed by the cushion layer) for a second time, thereby achieving double safety protection.

[0018] (3) The foamed lightweight concrete cushion and energy absorption protection device can be processed and manufactured in the factory and installed on site, which ensures the construction quality and makes the construction more convenient. When the foamed lightweight soil cushion and energy absorption protection device are damaged by the impact load of rolling stones, they can be replaced and installed, which can avoid road interruption or shorten the construction time.

[0019] (4) Since foamed lightweight concrete is used instead of the traditional sand cushion layer, the foamed lightweight concrete is light in weight, and the cushion load on the reinforced concrete frame structure of the shed tunnel is reduced, making the cross-sectional size of the reinforced concrete frame structure smaller and more economical. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0021] Figure 1 is a schematic structural diagram of an embodiment of the present invention; Figure 2 is a schematic structural diagram of an embodiment of the present invention; Figure 3 is a schematic diagram of components of a steel tube energy absorber according to an embodiment of the present invention; Figure 4 is a schematic structural diagram of an energy absorption protection device according to an embodiment of the present invention; In the figure: 1. reinforced concrete frame; 2. reinforced concrete slab; 3. energy absorption protection device; 31. pad stone on the support; 32. embedded steel plate; 33. upper steel plate; 34. steel pipe energy absorber; 35. lower steel plate; 36. pad stone under the support; 4. foam lightweight concrete cushion layer; 7. steel pad; 8. steel pipe. DETAILED DESCRIPTION

[0022] The following will combine the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work belong to the scope of protection of the present invention.

[0023] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0024] Example 1 A foam lightweight soil energy-absorbing light shed structure comprises a reinforced concrete frame 1 and a reinforced concrete slab 2, an energy absorption protection device 3 is arranged between the reinforced concrete slab 2 and the reinforced concrete frame 1, a foam lightweight concrete cushion layer 4 is covered on the reinforced concrete slab 2, and the energy absorption protection device 3 is fixed between the reinforced concrete slab 2 and the reinforced concrete frame 1 by bolts.

[0025] In this embodiment, the energy absorption protection device 3 includes, from top to bottom, a support upper pad stone 31, an embedded steel plate 32, an upper steel plate 33, a steel tube energy absorber 34, a lower steel plate 35 and a support lower pad stone 36. The support upper pad stone 31, the embedded steel plate 32, the upper steel plate 33, the steel tube energy absorber 34, the lower steel plate 35 and the support lower pad stone 36 are connected to each other by bolts or steel bars.

[0026] In this embodiment, the steel tube energy absorber 34 is made of a steel tube 8 and a steel backing plate 7. The steel tube 8 has a diameter of 255 mm, a thickness of 8 mm, and a height of 400 mm.

[0027] In this embodiment, the steel backing plate 7 has a size of 400 mm×400 mm×12 mm.

[0028] In this embodiment, the foam lightweight concrete cushion layer 4 is made of polypropylene modified fiber rubber foam lightweight concrete, and the reinforced concrete frame 1 and the reinforced concrete slab 2 can be pre-customized finished products.

[0029] A construction method of a foam lightweight soil energy-consuming lightweight shed-tunnel structure comprises the following steps: S1. Production of steel pipe energy absorber: install steel pads at both ends of the steel pipe by bolts; S2. Construction of shed tunnel foundation: site leveling → laying out → foundation excavation → foundation bottoming → pouring cushion layer → formwork → steel bar binding → pouring foundation concrete, using prefabricated reinforced concrete columns, and the foundation should adopt a cup-shaped structure; S3. Installation of precast reinforced concrete columns: The precast columns and foundation cups are connected as required by the building foundation design specifications; S4. Installation of energy absorption protection device: install the support lower pad stone, lower steel plate, steel pipe energy absorber, embedded steel plate and support upper pad stone from bottom to top, and continue to install the reinforced concrete slab on the support upper pad stone through high-strength anchor bolts; S5. Fix the foam lightweight concrete cushion layer on the reinforced concrete slab by bolts.

[0030] The structures, functions and connection forms disclosed in this article can be implemented in other ways. For example, the embodiments described above are only exemplary, for example, multiple components can be combined or integrated into another component; in addition, each functional component in each embodiment of this article can be integrated into one functional component, or each functional component can exist physically separately, or two or more functional components can be integrated into one functional component.

[0031] The above is only a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several modifications and improvements without departing from the inventive concept of the present invention, which all belong to the protection scope of the present invention.

Claims

1. A foam lightweight soil energy-consuming lightweight shed-tunnel structure, characterized in that: The invention comprises a reinforced concrete frame (1) and a reinforced concrete slab (2), wherein an energy absorption protection device (3) is arranged between the reinforced concrete slab (2) and the reinforced concrete frame (1), a foamed lightweight concrete cushion layer (4) is covered above the reinforced concrete slab (2), and the energy absorption protection device (3) is fixed between the reinforced concrete slab (2) and the reinforced concrete frame (1) by means of bolts.

2. The foam lightweight soil energy-consuming lightweight shed-tunnel structure according to claim 1 is characterized in that: The energy absorption protection device (3) comprises, from top to bottom, a support upper pad stone (31), an embedded steel plate (32), an upper steel plate (33), a steel tube energy absorber (34), a lower steel plate (35), and a support lower pad stone (36); the support upper pad stone (31), the embedded steel plate (32), the upper steel plate (33), the steel tube energy absorber (34), the lower steel plate (35), and the support lower pad stone (36) are connected to each other by bolts or steel bars.

3. The foam lightweight soil energy-consuming lightweight shed-tunnel structure according to claim 2 is characterized in that: The steel tube energy absorber (34) is made of a steel tube (8) and a steel backing plate (7); the steel tube (8) has a diameter of 255 mm, a thickness of 8 mm, and a height of 400 mm.

4. The foam lightweight soil energy-consuming lightweight shed-tunnel structure according to claim 3 is characterized in that: The steel backing plate (7) has a size of 400 mm×400 mm×12 mm.

5. The foam lightweight soil energy-consuming lightweight shed-tunnel structure according to claim 1 is characterized in that: The foam lightweight concrete cushion layer (4) is made of polypropylene modified fiber rubber foam lightweight concrete, and the reinforced concrete frame (1) and the reinforced concrete slab (2) can be pre-customized finished products.

6. The construction method of the foamed lightweight soil energy-consuming lightweight shed-tunnel structure according to any one of claims 1 to 5, characterized in that: The following steps are involved: S1. Production of steel pipe energy absorber: install steel pads at both ends of the steel pipe by bolts; S2. Construction of shed tunnel foundation: site leveling → laying out → foundation excavation → foundation bottoming → pouring cushion layer → formwork → steel bar binding → pouring foundation concrete, using prefabricated reinforced concrete columns, and the foundation should adopt a cup-shaped structure; S3. Installation of precast reinforced concrete columns: The precast columns and foundation cups are connected as required by the building foundation design specifications; S4. Installation of energy absorption protection device: install the support lower pad stone, lower steel plate, steel pipe energy absorber, embedded steel plate and support upper pad stone from bottom to top, and continue to install the reinforced concrete slab on the support upper pad stone through high-strength anchor bolts; S5. Fix the foam lightweight concrete cushion layer on the reinforced concrete slab by bolts.

Citation Information

Patent Citations

  • Energy dissipation shed tunnel capable of generating plastic deformation and maintenance method thereof

    CN110714418A

  • Construction method of energy-dissipation and seismic-mitigation combined shed tunnel structure for resisting landslide collapse body impact

    CN111395213A

  • Split mounting type multi-stage energy dissipation and shock absorption steel shed tunnel structure

    CN216405158U

Cited By

  • Buried pipeline protection earth surface concrete cushion parameter design method and system based on falling rock influence

    CN119808395A

  • Design method and system for ground concrete cushion parameters of buried pipeline protection based on rockfall influence

    CN119808395B

  • Rolling stone impact resistant shed tunnel composite energy dissipation protection structure and construction method

    CN120006634A