A charging strategy optimization method and device for energy storage charging pile
By optimizing the charging strategy of energy-storage charging piles, using charging related information of electric vehicles and charging piles, dividing the charging time period and calculating the maximum expected score, the problem of poor charging flexibility of energy-storage charging piles is solved, and the lowest cost and Profit-maximizing charging effect.
Patent Information
- Application Number
- CN202411340205.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-25
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-25
AI Technical Summary
Energy storage charging piles have poor flexibility in charging strategies, resulting in exhaustion of electricity or peak and high-price charging, which cannot maximize profits and meet user cost needs.
By obtaining charging-related information of electric vehicles, dividing the charging time period, calculating the maximum expected score for each time period to optimize the charging action, controlling the charging action to optimize the charging cost of electric vehicles and the profit of charging piles, including the power grid and energy storage modules Charging method.
The reasonable and orderly charging planning of energy-storage charging piles has been realized, which maximizes the profits of charging piles and reduces the charging cost of electric vehicles, reduces the grid load, and enhances the prospects of energy-storage charging applications.
Smart Images

Figure CN118849856B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of new energy technology, and in particular to a charging strategy optimization method and device for an energy storage charging pile. Background Art
[0002] The introduction of a large number of charging piles has caused a series of problems for the power system, including the increase in peak load and overload of power facilities. In addition, large-scale grid-connected charging of electric vehicles will bring about a series of problems such as voltage control, harmonics, and supply and demand balance. Especially during periods of high electricity demand, electric vehicle charging may increase the power load in the community and may cause the community distribution transformer to overload, thereby reducing the operating safety and power quality of the distribution network. In addition, charging during peak hours will increase charging costs and bring economic pressure to charging users.
[0003] In response to the above problems, a type of energy storage charging pile is gradually being introduced into the market. It is a charging device with integrated electric energy storage. It can not only charge electric vehicles directly through the power grid, but also store part of the electric energy itself, and then use its own stored electric energy to charge electric vehicles during peak power consumption, thereby reducing the pressure on the power grid.
[0004] Compared with traditional charging piles, energy storage charging piles need to consider not only whether the electric vehicle is charged at peak times, but also the charging of the energy storage charging pile itself. However, the current charging of energy storage charging piles is mainly done at night or during idle time. However, this method is less flexible. If only charging at night is used, the stored electricity during the day may be exhausted. Users can only choose to charge at peak times at high prices (reducing the user's repurchase rate), or if the idle time is still peak electricity consumption, it is easy to increase the cost if the energy storage charging pile charges itself at this time. It can be seen that the existing method cannot guarantee the maximization of the benefits of energy storage charging piles, and cannot meet the cost requirements of users. Summary of the invention
[0005] In order to solve the above-mentioned problems in the prior art, the present invention provides a charging strategy optimization method and device for an energy storage charging pile.
[0006] In a first aspect, an embodiment of the present application provides a charging strategy optimization method for an energy storage charging pile, comprising: in response to a target electric vehicle being connected to a target charging pile, obtaining charging-related information; wherein the charging-related information includes the charging end time of the target electric vehicle, the charging demand power of the target electric vehicle, and the current remaining power of the target charging pile; based on the charging end time of the target electric vehicle, dividing the start and end time of the target electric vehicle into multiple charging time periods according to preset time intervals; starting from the second charging time period, calculating the maximum expected score of each charging time period; wherein the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action in this time period, and the target charging action is one of multiple set charging actions; in the first charging time period, charging the target electric vehicle using the current remaining power of the target charging pile; using the target charging action corresponding to the maximum expected score of each charging time period, controlling the charging action of the target charging pile until the charging demand power of the target electric vehicle is reached or the charging end time is reached.
[0007] Optionally, the multiple set charging actions include: the target charging pile charges its own energy storage module through the power grid, the target charging pile charges the target electric vehicle through its own energy storage module, the target charging pile charges the target electric vehicle through the power grid, and the target charging pile charges the target electric vehicle and its own energy storage module at the same time through the power grid.
[0008] Optionally, starting from the second charging time period, for each charging time period, the expected score of the charging time period is calculated, including: constructing a state vector based on the grid unit price, charging unit price and the remaining power demand of the target electric vehicle corresponding to the charging time period in the current charging time period; wherein the grid unit price represents the unit price of electricity provided by the grid in the current charging time period, and the charging unit price represents the unit price of electricity provided by the target charging pile to the target electric vehicle; determining the expected score corresponding to the state vector; wherein the expected score includes a reward function and a state comparison function; the state comparison function represents the expected score of multiple set charging actions based on the charging amount of the previous charging time period; the reward function represents the reward score output after comparing the charging cost and profit corresponding to the set charging action adopted in the current charging time period with the charging cost and profit of the previous charging time period.
[0009] Optionally, the reward score is defined as: if the charging cost corresponding to the set charging action adopted in the current charging time period is lower than the charging cost of the previous charging time period, the reward score is increased by one; if the profit corresponding to the set charging action adopted in the current charging time period is higher than the profit of the previous charging time period, the reward score is increased by one; if the charging cost corresponding to the set charging action adopted in the current charging time period is the same as the charging cost of the previous charging time period, and the profit corresponding to the set charging action adopted in the current charging time period is the same as the profit of the previous charging time period, the reward score is increased by one.
[0010] Optionally, after the target electric vehicle leaves the target charging pile, the method further includes: in response to the current remaining power of the target charging pile not reaching a set minimum power value, and the current time node is not in a peak interval, charging the energy storage module of the target charging pile itself through the power grid until the set minimum power value is reached; wherein the peak interval is determined by historical power consumption data and / or real-time power consumption monitoring data.
[0011] Optionally, the method also includes: in response to the current remaining power of the target charging pile being between the set minimum power value and the maximum capacity value of the target charging pile, charging the target charging pile's own energy storage module through the power grid during a low-peak interval until the maximum capacity of the target charging pile is reached; wherein the low-peak interval is determined by historical power consumption data and / or real-time power consumption monitoring data.
[0012] Optionally, the charging-related information also includes the user's selection of an unordered charging demand, and the method also includes: charging the target electric vehicle using the current remaining power of the target charging pile; wherein, when the current remaining power of the target charging pile does not meet the charging demand of the target electric vehicle, the target charging pile charges the target electric vehicle through the power grid.
[0013] Optionally, the method also includes: in each charging time period, obtaining the maximum power supply power of the target area where the target charging pile is located, and the baseline load of the target area during the charging time period; wherein, in each charging time period, the operating power of the target charging pile is controlled to be less than the difference between the maximum power supply power of the target area and the baseline load of the target area.
[0014] Optionally, before the target electric vehicle is connected to the target charging pile, the method further includes: sending the current remaining power of the target charging pile and the corresponding charging unit price to a user terminal corresponding to the target electric vehicle.
[0015] In a second aspect, the present application provides a charging strategy optimization device for an energy storage charging pile, comprising: an acquisition module, for acquiring charging-related information in response to a target electric vehicle being connected to a target charging pile; wherein the charging-related information includes the charging end time of the target electric vehicle, the charging demand power of the target electric vehicle, and the current remaining power of the target charging pile; a segmentation module, for segmenting the start and end time of the target electric vehicle into multiple charging time periods according to a preset time interval based on the charging end time of the target electric vehicle; a calculation module, for calculating the maximum expected score of each charging time period starting from the second charging time period; wherein the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action in this time period, and the target charging action is one of multiple set charging actions; in the first charging time period, the target electric vehicle is charged using the current remaining power of the target charging pile; a charging optimization module, for using the target charging action corresponding to the maximum expected score of each charging time period to control the charging action of the target charging pile until the charging demand power of the target electric vehicle is reached or the charging end time is reached.
[0016] The beneficial effects of the present invention include:
[0017] This application is based on the consideration of the charging cost of the target electric vehicle and / or the profit of the target charging pile. This method can be effectively applied to the optimization of the charging strategy of the energy storage charging pile, that is, during the charging process, the action of the target charging pile is controlled with the charging cost of the target electric vehicle and / or the profit of the target charging pile as the purpose. The whole process not only takes into account the effective charging of the target electric vehicle with the lowest cost, but also takes into account the energy storage state of the target charging pile itself, how to maximize profits. It can be seen that the method provided in the embodiment of the present application can carry out reasonable and orderly charging planning for energy storage charging, based on ensuring the load of the power grid, maximizing the profit of the target charging pile and / or reducing the charging cost of the target electric vehicle, which can further strengthen the application of energy storage charging piles, that is, it opens up new prospects for the application of energy storage charging. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A flowchart of the steps of a charging strategy optimization method for an energy storage charging pile provided by an embodiment of the present invention;
[0019] Figure 2 A flowchart of another charging strategy optimization method for energy storage charging piles provided by an embodiment of the present invention;
[0020] Figure 3 A module block diagram of a charging strategy optimization device for an energy storage charging pile provided by an embodiment of the present invention;
[0021] Figure 4 A module block diagram of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0022] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.
[0023] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0024] Compared with traditional charging piles, energy storage charging piles need to consider not only whether the electric vehicle is charged at peak times, but also the charging of the energy storage charging pile itself. However, the current charging of energy storage charging piles is mainly done at night or during idle time. However, this method is less flexible. If only charging at night is used, the stored electricity during the day may be exhausted. Users can only choose to charge at peak times at high prices (reducing the user's repurchase rate), or if the idle time is still peak electricity consumption, it is easy to increase the cost if the energy storage charging pile charges itself at this time. It can be seen that the existing method cannot guarantee the maximization of the benefits of energy storage charging piles, and cannot meet the cost requirements of users.
[0025] In view of the above problems, the present application proposes the following embodiments to solve the above technical problems.
[0026] See also Figure 1 , an embodiment of the present application provides a charging strategy optimization method for an energy storage charging pile, including: steps 101 to 104.
[0027] Step 101: in response to a target electric vehicle being connected to a target charging pile, obtaining charging-related information.
[0028] Among them, the charging-related information includes the charging end time of the target electric vehicle, the charging power required by the target electric vehicle, and the current remaining power of the target charging pile.
[0029] For example, when the target electric vehicle is connected to the target charging pile, the target charging pile can obtain the remaining power and capacity of the target electric vehicle. At this time, the charging demand power of the target electric vehicle can be the capacity of the target electric vehicle minus the remaining power of the target electric vehicle.
[0030] Of course, the charging power requirement of the target electric vehicle may also be customized by the user. For example, the user only wants to charge to 80% of the capacity. This application does not limit this.
[0031] Step 102: Based on the charging end time of the target electric vehicle, the start and end time of the target electric vehicle is divided into a plurality of charging time periods according to preset time intervals.
[0032] In the embodiment of the present application, the above-mentioned preset time interval can be 0.5 hours, 1 hour, 1.5 hours, 2 hours, etc., which is not limited here.
[0033] Step 103: Starting from the second charging time period, the maximum expected score of each charging time period is calculated.
[0034] Among them, the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action during this period, and the target charging action is one of multiple set charging actions; in the first charging time period, the current remaining power of the target charging pile is used to charge the target electric vehicle.
[0035] The plurality of set charging actions are associated with the operation of the target charging pile. The types of operation of the target charging pile include self-charging and charging the target electric vehicle.
[0036] Here, the maximum expected score can be determined based on the grid unit price in different charging time periods. The grid electricity price represents the unit price of electricity provided by the grid during the current charging time period. It should be noted that in order to adjust the grid load and achieve off-peak charging, the grid unit price in different time periods is different. Generally, the grid unit price in the peak interval is higher than the grid unit price in the off-peak interval. The grid unit price is not exactly the same in different peak intervals or different off-peak intervals.
[0037] The charging cost of the target electric vehicle can be expressed as the charging unit price of the user charging during this period multiplied by the charging power; where the charging unit price represents the unit price of electricity provided by the target charging pile to the target electric vehicle. The profit of the target charging pile can be expressed as the charging power charged during this period multiplied by the difference between the charging unit price provided by the target electric vehicle and the grid unit price provided by the grid.
[0038] The charging price provided by the target charging pile to the target electric vehicle is usually set according to the grid price, and as the grid price increases, the increase in the charging price decreases (set according to market acceptance to maintain competitiveness). For example, in the off-peak period, the grid price is 0.3 yuan / kWh, and the charging price is set at 0.6 yuan / kWh, while in the peak period, the grid price is 1 yuan / kWh, and the charging price is set at 1.2 yuan / kWh.
[0039] In other words, the lower the cost of charging electric vehicles during off-peak periods, the higher the profit of charging piles for electric vehicles during off-peak periods. At the same time, charging piles for charging their own energy storage modules during off-peak periods can also bring the highest profit.
[0040] Therefore, in this step, the charging action of the target charging pile in each charging time period starting from the second charging time period is determined based on the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile.
[0041] Step 104: adopting the target charging action corresponding to the maximum expected score of each charging time period to control the charging action of the target charging pile until the charging demand power of the target electric vehicle is reached or the charging end time is reached.
[0042] Finally, orderly charging is achieved by adopting the target charging action corresponding to the maximum expected score of each charging time period. It should be noted that the embodiment of the present application is considered with the charging cost of the target electric vehicle and / or the profit of the target charging pile as the purpose. This method can be effectively applied to the optimization of the charging strategy of the energy storage charging pile, that is, during the charging process, the action of the target charging pile is controlled with the charging cost of the target electric vehicle and / or the profit of the target charging pile as the purpose. The whole process not only considers the effective charging of the target electric vehicle with the lowest cost, but also considers the energy storage state of the target charging pile itself, and how to maximize profits. It can be seen that the method provided in the embodiment of the present application can carry out reasonable and orderly charging planning for energy storage charging, based on ensuring the load of the power grid, maximizing the profit of the target charging pile and / or reducing the charging cost of the target electric vehicle, which can further strengthen the application of energy storage charging piles, that is, it opens up new prospects for the application of energy storage charging.
[0043] Optionally, the multiple set charging actions include: the target charging pile charges its own energy storage module through the power grid, the target charging pile charges the target electric vehicle through its own energy storage module, the target charging pile charges the target electric vehicle through the power grid, and the target charging pile charges the target electric vehicle and its own energy storage module at the same time through the power grid.
[0044] That is, in this embodiment, four different charging actions are involved. In practical applications, the four different charging actions are used to determine the maximum expected score, thereby determining the target charging action corresponding to the time period.
[0045] See also Figure 2 Optionally, starting from the second charging time period, for each charging time period, the expected score of the charging time period is calculated, including: step 201 to step 202.
[0046] Step 201: construct a state vector based on the grid unit price, charging unit price and the remaining required power of the target electric vehicle corresponding to the charging time period in the current charging time period.
[0047] Among them, the grid unit price represents the unit price of electricity provided by the grid during the current charging period, and the charging unit price represents the unit price of electricity provided by the target charging pile to the target electric vehicle.
[0048] That is, , and Constructing the state vector .in, Indicates charging time period The grid unit price, Indicates charging time period The charging unit price, Indicates charging time period The corresponding remaining power demand of the target electric vehicle.
[0049] Step 202: Determine the expected score corresponding to the state vector.
[0050] Among them, the expected score includes a reward function and a state comparison function; the state comparison function represents the expected score of adopting multiple set charging actions based on the charging amount of the previous charging time period; the reward function represents the reward score output after comparing the charging cost and profit corresponding to the set charging action adopted in the current charging time period with the charging cost and profit of the previous charging time period.
[0051] Optionally, the reward score is defined as: if the charging cost corresponding to the set charging action adopted in the current charging time period is lower than the charging cost of the previous charging time period, the reward score is increased by one; if the profit corresponding to the set charging action adopted in the current charging time period is higher than the profit of the previous charging time period, the reward score is increased by one; if the charging cost corresponding to the set charging action adopted in the current charging time period is the same as the charging cost of the previous charging time period, and the profit corresponding to the set charging action adopted in the current charging time period is the same as the profit of the previous charging time period, the reward score is increased by one.
[0052] For example, the reward function is R, where R represents the charging cost corresponding to the set charging action adopted in the current charging time period. Charging cost compared to the previous charging period For comparison, if Lower than , then the value of the reward function R + 1. And, the profit corresponding to the set charging action adopted in the current charging time period Profit from the previous charging period For comparison, if Higher than , then the value of the reward function R is +1. In addition, if the charging cost corresponding to the set charging action adopted in the current charging time period is Charging cost compared to the previous charging period The same, and the profit corresponding to the set charging action used in the current charging time period Profit from the previous charging period If they are the same, the value of reward R is +1.
[0053] The above comparisons are all based on the same charge capacity.
[0054] In the embodiment of the present application, the expression of the expected score corresponding to the state vector can be:
[0055] ;
[0056] in, Represents the expected score corresponding to the current state vector; represents the computational expectation, R represents the reward function in the above embodiment, represents the attenuation factor, Indicates different charging settings. Indicates that if the set charging action was used in the last charging time period The corresponding expected score; represents the state vector of the last charging period. Finally, the maximum expected score corresponds to The target charging action is shown in the figure.
[0057] Optionally, after the target electric vehicle leaves the target charging pile, the method further includes: in response to the current remaining power of the target charging pile not reaching a set minimum power value, and the current time node is not in a peak interval, charging the target charging pile's own energy storage module through the power grid until the set minimum power value is reached; wherein the peak interval is determined by historical power consumption data and / or real-time power consumption monitoring data.
[0058] Here, a minimum power value is set for each target charging pile, and the minimum power value can be set to at least meet the charging demand of one electric vehicle.
[0059] When the current remaining power of the target charging pile does not reach the set minimum power value, it is possible to first determine whether the current time node is in the peak interval. If not, the target charging pile's own energy storage module is charged through the power grid until the set minimum power value is reached.
[0060] In one embodiment, historical power consumption data may be acquired in advance, and whether the current time node is in a peak period may be determined based on the historical power consumption data.
[0061] In one implementation, whether the current time node is in a peak period can be determined based on real-time power consumption monitoring data. The real-time power consumption monitoring data can specifically be the power grid unit price at the current time node or the power grid load data in the current area.
[0062] Of course, in one embodiment, historical electricity consumption data and real-time electricity consumption monitoring data may be combined to jointly determine whether the current time node is in a peak interval, and this application does not limit this.
[0063] That is, the embodiment of the present application also provides a charging strategy optimization when the target electric vehicle leaves the target charging pile, through which the power reserve of the target charging pile itself can be reasonably regulated.
[0064] Optionally, the method also includes: in response to the current remaining power of the target charging pile being between a set minimum power value and a maximum capacity value of the target charging pile, charging the target charging pile's own energy storage module through the power grid during a low-peak interval until the maximum capacity of the target charging pile is reached; wherein the low-peak interval is determined by historical power consumption data and / or real-time power consumption monitoring data.
[0065] Different from the above-mentioned embodiment, the above-mentioned embodiment considers that only when it is not in the peak interval, the target charging pile charges its own energy storage module to the set minimum power value through the power grid to meet the charging needs of at least one electric vehicle. That is, charging to the set minimum power value can be performed in any time period except the peak interval. This step is only for the low-peak interval, and the target charging pile's own energy storage module is charged through the power grid only in the low-peak interval until the maximum capacity of the target charging pile is reached. And within a cycle, it usually includes a peak interval, a low-peak interval, and a connection interval between the peak interval and the low-peak interval. In other words, the above-mentioned embodiment considers the demand problem, and the latter involves profit maximization. In this way, the target charging pile's own energy reserve can be reasonably regulated.
[0066] Optionally, the charging-related information also includes a user-selected disordered charging demand, and the method also includes: using the current remaining power of the target charging pile to charge the target electric vehicle; wherein, when the current remaining power of the target charging pile does not meet the charging demand of the target electric vehicle, the target charging pile charges the target electric vehicle through the power grid.
[0067] That is, the energy storage charging pile also provides users with an unordered charging method, that is, a plug-and-charge method, and in this embodiment, it is preferred to use the current remaining power of the target charging pile to charge the target electric vehicle (usually, the target charging pile is charged at off-peak time, so the charging electricity price is lower).
[0068] Of course, in other embodiments, the target charging pile can also determine whether the current time node is a low-peak interval. If so, the target electric vehicle is directly charged unordered through the power grid.
[0069] Optionally, the method also includes: in each charging time period, obtaining the maximum power supply power of the target area where the target charging pile is located, and the baseline load of the target area during the charging time period; wherein, in each charging time period, the operating power of the target charging pile is controlled to be less than the difference between the maximum power supply power of the target area and the baseline load of the target area.
[0070] That is, during the entire charging process, the operating power of the target charging pile needs to be controlled to be less than the difference between the maximum power supply power of the target area and the baseline load of the target area. The specific expression is:
[0071] ;
[0072] in, Indicates the target charging pile in the time period The operating power, Indicates the maximum power supply, Indicates the target area in the time period Baseline load.
[0073] It should be noted that the operating power of the above-mentioned target charging pile in the time period may refer to the power of the target charging pile itself charging, the power of discharging to the target electric vehicle, etc.
[0074] It can be seen that the charging strategy optimization process of the energy storage charging pile provided in the embodiments of the present application takes power load as the basic requirement, reduces the burden on the power grid, and rationally utilizes power resources.
[0075] Optionally, before the target electric vehicle is connected to the target charging pile, the method further includes: sending the current remaining power of the target charging pile and the corresponding charging unit price to a user terminal corresponding to the target electric vehicle.
[0076] That is, here, each charging pile can send the real-time current remaining power and the corresponding charging unit price to the user. Since different charging piles may be charged at different time periods, they can correspond to different charging unit prices. When considering in practice, users can reasonably choose which charging pile to use for charging based on the current remaining power of each charging pile and the corresponding charging unit price, thereby providing users with a better user experience.
[0077] See also Figure 3Based on the same inventive concept, the present application provides a charging strategy optimization device 300 for an energy storage charging pile, comprising: an acquisition module 301, for acquiring charging-related information in response to a target electric vehicle being connected to a target charging pile; wherein the charging-related information includes the charging end time of the target electric vehicle, the charging demand power of the target electric vehicle, and the current remaining power of the target charging pile; a segmentation module 302, for segmenting the start and end time of the target electric vehicle into a plurality of charging time periods according to a preset time interval based on the charging end time of the target electric vehicle; a calculation module 303, for calculating the maximum expected score of each charging time period starting from the second charging time period; wherein the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action in this time period, and the target charging action is one of a plurality of set charging actions; in the first charging time period, the target electric vehicle is charged using the current remaining power of the target charging pile; a charging optimization module 304, for controlling the charging action of the target charging pile using the target charging action corresponding to the maximum expected score of each charging time period until the charging demand power of the target electric vehicle is reached or the charging end time is reached.
[0078] See also Figure 4 Based on the same inventive concept, the present application embodiment provides a module frame of an electronic device 400 that applies the above method. The electronic device 400 includes: at least one processor 401 ( Figure 4 Only one is shown in the figure), a memory 402, a computer program 403 stored in the memory 402 and executable on at least one processor 401, and when the processor 401 executes the computer program 403, the steps of the method in any of the foregoing embodiments are implemented.
[0079] The electronic device 400 may be a server, a charging pile, or a device that can be connected to a charging pile, etc.
[0080] Those skilled in the art will understand that Figure 4 The electronic device 400 is merely an example and does not constitute a limitation on the electronic device 400 , and may include more or less components than those shown in the figure, or may combine certain components, or may include different components.
[0081] The processor 401 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.
[0082] In some embodiments, the memory 402 may be an internal storage unit of the electronic device 400, such as a hard disk or memory of the electronic device 400. In other embodiments, the memory 402 may also be an external storage device of the electronic device 400, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the electronic device 400. Further, the memory 402 may also include both an internal storage unit of the electronic device 400 and an external storage device.
[0083] It should be noted that the above-mentioned systems, devices, etc. are based on the same concept as the method embodiments of the present application. The modules designed for the systems, the steps performed by the devices, and the technical effects brought about can all be found in the method embodiment section and will not be repeated here.
[0084] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.
[0085] An embodiment of the present application further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.
[0086] An embodiment of the present application provides a computer program product. When the computer program product runs on a mobile terminal, the mobile terminal can implement the steps in the above-mentioned method embodiments when executing the computer program product.
[0087] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium can at least include: any entity or device that can carry the computer program code to the camera / electronic device, recording medium, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, RandomAccess Memory), electrical carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a disk or an optical disk.
[0088] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0089] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0090] In the embodiments provided in the present application, it should be understood that the disclosed devices / network equipment and methods can be implemented in other ways. For example, the device / network equipment embodiments described above are merely schematic. For example, the division of the modules or units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0091] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0092] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A charging strategy optimization method for energy storage charging piles, characterized in that: include: In response to the target electric vehicle being connected to the target charging pile, acquiring charging related information; wherein the charging related information includes the charging end time of the target electric vehicle, the charging required power of the target electric vehicle, and the current remaining power of the target charging pile; Based on the charging end time of the target electric vehicle, dividing the start and end time of the target electric vehicle into a plurality of charging time periods according to preset time intervals; Starting from the second charging time period, the maximum expected score of each charging time period is calculated; wherein the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action in this time period, and the target charging action is one of multiple set charging actions; in the first charging time period, the target electric vehicle is charged using the current remaining power of the target charging pile; The target charging action corresponding to the maximum expected score of each charging time period is used to control the charging action of the target charging pile until the charging demand power of the target electric vehicle is reached or the charging end time is reached; The multiple set charging actions include: the target charging pile charges its own energy storage module through the power grid, the target charging pile charges the target electric vehicle through its own energy storage module, the target charging pile charges the target electric vehicle through the power grid, and the target charging pile charges the target electric vehicle and its own energy storage module through the power grid at the same time; Starting from the second charging time period, for each charging time period, the expected score of the charging time period is calculated, including: constructing a state vector based on the grid unit price, charging unit price and the remaining required power of the target electric vehicle corresponding to the charging time period in the current charging time period; wherein the grid unit price represents the unit price of electricity provided by the grid in the current charging time period, and the charging unit price represents the unit price of electricity provided by the target charging pile to the target electric vehicle; determining the expected score corresponding to the state vector; wherein the expected score includes a reward function and a state comparison function; the state comparison function represents the expected score of multiple set charging actions based on the charging amount of the previous charging time period; the reward function represents the reward score output after comparing the charging cost and profit corresponding to the set charging action adopted in the current charging time period with the charging cost and profit of the previous charging time period; The reward score is defined as: if the charging cost corresponding to the set charging action adopted in the current charging time period is lower than the charging cost of the previous charging time period, the reward score is increased by one; if the profit corresponding to the set charging action adopted in the current charging time period is higher than the profit of the previous charging time period, the reward score is increased by one; if the charging cost corresponding to the set charging action adopted in the current charging time period is the same as the charging cost of the previous charging time period, and the profit corresponding to the set charging action adopted in the current charging time period is the same as the profit of the previous charging time period, the reward score is increased by one.
2. The charging strategy optimization method for energy storage charging piles according to claim 1 is characterized in that: After the target electric vehicle leaves the target charging pile, the method further includes: In response to the current remaining power of the target charging pile not reaching the set minimum power value, and the current time node is not in the peak interval, charging the energy storage module of the target charging pile itself through the power grid until the set minimum power value is reached; The peak interval is determined by historical electricity consumption data and / or real-time electricity consumption monitoring data.
3. The charging strategy optimization method for energy storage charging piles according to claim 2 is characterized in that: The method further comprises: In response to the current remaining power of the target charging pile being between the set minimum power value and the maximum capacity value of the target charging pile, charging the energy storage module of the target charging pile itself through the power grid during the off-peak period until the maximum capacity of the target charging pile is reached; The low-peak interval is determined by historical electricity consumption data and / or real-time electricity consumption monitoring data.
4. The charging strategy optimization method for energy storage charging piles according to claim 1 is characterized in that: The charging related information also includes a user selecting an unordered charging requirement, and the method further includes: Using the current remaining power of the target charging pile to charge the target electric vehicle; When the current remaining power of the target charging pile does not meet the charging demand of the target electric vehicle, the target charging pile charges the target electric vehicle through the power grid.
5. The charging strategy optimization method for energy storage charging piles according to claim 1 is characterized in that: The method further comprises: In each charging time period, obtaining the maximum power supply power of the target area where the target charging pile is located, and the baseline load of the target area in the charging time period; Wherein, in each charging time period, the operating power of the target charging pile is controlled to be less than the difference between the maximum power supply power of the target area and the baseline load of the target area.
6. The charging strategy optimization method for energy storage charging piles according to claim 1 is characterized in that: Before the target electric vehicle is connected to the target charging pile, the method further includes: The current remaining power of the target charging pile and the corresponding charging unit price are sent to the user terminal corresponding to the target electric vehicle.
7. A charging strategy optimization device for energy storage charging piles, characterized in that: include: An acquisition module, configured to acquire charging-related information in response to the target electric vehicle being connected to the target charging pile; wherein the charging-related information includes the charging end time of the target electric vehicle, the charging power required by the target electric vehicle, and the current remaining power of the target charging pile; A segmentation module, configured to segment the start and end time of the target electric vehicle into a plurality of charging time periods according to a preset time interval based on the charging end time of the target electric vehicle; A calculation module, configured to calculate the maximum expected score of each charging time period starting from the second charging time period; wherein the maximum expected score represents the optimal charging cost of the target electric vehicle and / or the optimal profit of the target charging pile corresponding to the target charging action in this time period, and the target charging action is one of a plurality of set charging actions; in the first charging time period, the target electric vehicle is charged using the current remaining power of the target charging pile; A charging optimization module, used to control the charging action of the target charging pile by using the target charging action corresponding to the maximum expected score of each charging time period, until the charging demand power of the target electric vehicle is reached or the charging end time is reached; The multiple set charging actions include: the target charging pile charges its own energy storage module through the power grid, the target charging pile charges the target electric vehicle through its own energy storage module, the target charging pile charges the target electric vehicle through the power grid, and the target charging pile charges the target electric vehicle and its own energy storage module through the power grid at the same time; The calculation module is further specifically used to construct a state vector based on the grid unit price, charging unit price and the remaining required power of the target electric vehicle corresponding to the charging time period in the current charging time period; wherein the grid unit price represents the unit price of electricity provided by the grid in the current charging time period, and the charging unit price represents the unit price of electricity provided by the target charging pile to the target electric vehicle; determine the expected score corresponding to the state vector; wherein the expected score includes a reward function and a state comparison function; the state comparison function represents the expected score of multiple set charging actions based on the charging amount of the previous charging time period; the reward function represents the reward score output after comparing the charging cost and profit corresponding to the set charging action adopted in the current charging time period with the charging cost and profit of the previous charging time period; The reward score is defined as: if the charging cost corresponding to the set charging action adopted in the current charging time period is lower than the charging cost of the previous charging time period, the reward score is increased by one; if the profit corresponding to the set charging action adopted in the current charging time period is higher than the profit of the previous charging time period, the reward score is increased by one; if the charging cost corresponding to the set charging action adopted in the current charging time period is the same as the charging cost of the previous charging time period, and the profit corresponding to the set charging action adopted in the current charging time period is the same as the profit of the previous charging time period, the reward score is increased by one.
Citation Information
Patent Citations
Electric vehicle charging management method based on urban infrastructure and system
CN105244931A
Multi-charging-mode charging pile control method considering matching of electric vehicles
CN112277711A
Charging load control method and device for electric vehicle charging station
CN117207817A
Smart parking lot charging pile charging control method and system considering power grid electricity price
CN117621898A