Prefabricated floor slab installation device and installation method

By designing a combination device of track beams, mobile pickup platforms and hoisting truss vehicles in prefabricated buildings, the problem of low installation efficiency of prefabricated floor slabs is solved, and the rapid installation and coverage of multiple prefabricated floor slabs is achieved, which significantly reduces the construction period and Staff workload.

CN118850985BActive Publication Date: 2025-01-17HUBEI SYNTHETIC SPACE TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411315385.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2025-01-17
Estimated Expiration
2044-09-20

AI Technical Summary

Technical Problem

In prefabricated buildings, the installation efficiency of prefabricated floor slabs is low, resulting in an extended construction period, and the working surface of the floor slab to be installed cannot bear the temporary turnover and resettlement of multiple prefabricated floor slabs, which limits the lifting and installation efficiency.

Method used

A prefabricated floor slab installation device is designed, including track beams, mobile pickup platforms and hoisting truss trucks. The layered operation of the lifting truss trucks and mobile pickup platforms is realized through the layered operation on the track beams, allowing multiple stacking and hoisting at the same time. The prefabricated floor slab is used to hoist and transport single prefabricated floor slabs, reducing the workload and time of the tower crane.

Benefits of technology

The installation efficiency of prefabricated floor slabs has been improved, and the single lifting volume has been increased from one piece to four to eight pieces, reducing the construction period, enhancing the construction coverage and stability, and reducing the workload of construction personnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118850985B_ABST
    Figure CN118850985B_ABST
Patent Text Reader

Abstract

The present application relates to a prefabricated floor installation device and installation method, including a track beam fixedly installed on a vertical member, the track beam including a first track and a second track, the first track and the second track are respectively arranged on two adjacent rows of vertical members, and the first track and the second track are arranged correspondingly; a mobile receiving platform for stacking prefabricated floor panels to be installed, the mobile receiving platform is slidably installed on the track beam; a hoisting truss for hoisting a single prefabricated floor panel, the hoisting truss is slidably installed on the track beam; the mobile receiving platform and the hoisting truss operate in layers on the track beam; the hoisting truss includes a horizontal driving component for driving the horizontal movement of the prefabricated floor panel and a vertical driving component for driving the vertical movement of the prefabricated floor panel. The present application can improve the vertical transportation and horizontal installation efficiency of the prefabricated floor panel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of prefabricated buildings, and in particular to a prefabricated floor slab installation device and installation method. Background Art

[0002] Prefabricated buildings refer to buildings that transfer a large amount of on-site work in traditional construction methods to factories, where building components and accessories such as floor slabs, wall panels, stairs, balconies, etc. are processed and manufactured in factories, and then transported to the construction site and assembled and installed on site through reliable connection methods.

[0003] When constructing prefabricated floor slabs, a tower crane is usually used to hoist a single prefabricated floor slab to the designed position. Construction workers catch the hoisted prefabricated floor slab on the construction floor and guide the tower crane to move the prefabricated floor slab accurately to the designed position. The tower crane hook is then removed from the prefabricated floor slab, thus completing the hoisting of the prefabricated floor slab.

[0004] Since the work surface of the floor to be installed cannot bear the temporary turnover placement of multiple prefabricated floor panels, usually only one prefabricated floor panel can be hoisted at a time, and the next one can only be hoisted and installed after the floor panel is installed in place by the crane. A building is usually equipped with only one tower crane. It takes a lot of time to accurately move the prefabricated floor panel to the designed position, which will reduce the efficiency of hoisting and assembling the prefabricated floor panel, making the hoisting and installation of the prefabricated floor panel a constraint on the construction period of the prefabricated floor panel project. Summary of the invention

[0005] Based on the above description, the present application provides a prefabricated floor installation device and installation method to solve the problem of low installation efficiency of prefabricated floor.

[0006] In one aspect, the present application provides a prefabricated floor installation device, comprising:

[0007] A track beam is fixedly mounted on the vertical member, and includes a first track and a second track, wherein the first track and the second track are respectively arranged on two adjacent rows of vertical members, and the first track and the second track are arranged correspondingly;

[0008] A mobile receiving platform is used to stack the prefabricated floor slabs to be installed, and the mobile receiving platform is slidably installed on the track beam;

[0009] A hoisting truss vehicle is used to hoist a single prefabricated floor slab, and the hoisting truss vehicle is slidably installed on the track beam;

[0010] The mobile cargo receiving platform and the hoisting gantry vehicle run in layers on the track beam;

[0011] The hoisting gantry comprises a horizontal driving assembly for driving the prefabricated floor slab to move horizontally and a vertical driving assembly for driving the prefabricated floor slab to move vertically.

[0012] Based on the above technical solution, the present application can also be improved as follows.

[0013] Furthermore, the mobile cargo receiving platform includes multiple groups of parallel and spaced support groups, and the support groups include a transverse strut and two vertical suspension rods. The two ends of the transverse strut are respectively connected to the two vertical suspension rods, and the ends of the two vertical suspension rods away from the transverse struts are respectively slidably connected to the first track and the second track.

[0014] Furthermore, the mobile cargo receiving platform also includes a support plate arranged above the transverse support rod, and a plurality of grooves are provided at the bottom of the support plate, and a plurality of the transverse support rods are inserted into the plurality of grooves one by one.

[0015] Furthermore, a connecting piece is provided between two adjacent vertical suspension rods, and the connecting piece is fixedly connected to the vertical suspension rods on both sides at the same time.

[0016] Furthermore, the horizontal drive assembly includes at least two spaced sliding rails, both ends of which are slidingly connected to the first rail and the second rail respectively, and the vertical drive assembly is slidably mounted on the horizontal drive assembly and can slide along the sliding rails.

[0017] Furthermore, the vertical drive assembly includes a support frame and a lifting and hoisting device for lifting the prefabricated floor slabs, the support frame is slidingly connected to a plurality of the sliding rails at the same time, and the lifting and hoisting device is installed on the support frame.

[0018] Furthermore, the hoisting and lifting equipment includes a main hoisting rope and a plurality of branch ropes connected to the main hoisting rope, and the plurality of branch ropes are connected to a plurality of hoisting points of the prefabricated floor slab;

[0019] When the main hoisting ropes are all reeled in, the top surface of the prefabricated floor slabs stacked on the mobile receiving platform is located below the prefabricated floor slabs hoisted on the hoisting gantry vehicle.

[0020] Furthermore, the track beam is arranged below the designed height of the floor top plate.

[0021] Furthermore, it also includes a control system, and the mobile cargo receiving platform and the lifting gantry are both connected to the control system, which is used to control the movement of the mobile cargo receiving platform, the horizontal movement of the sliding rail, the horizontal movement of the vertical drive assembly and the lifting drive of the lifting hoisting equipment.

[0022] On the other hand, the present application also provides a method for installing a prefabricated floor slab, comprising the following installation steps:

[0023] S1. After completing the construction of the top structural beam of the lower floor, proceed with the construction of the vertical components of this floor;

[0024] S2. Fix the track beam to the vertical member and install the mobile receiving platform and the lifting gantry car on the track beam;

[0025] S3. Use a tower crane to hoist the prefabricated floor slabs and stack them on the support group of the mobile receiving platform. Multiple prefabricated floor slabs can be stacked on the mobile receiving platform;

[0026] S4: transporting a single prefabricated floor slab from the mobile receiving platform to the construction and installation location using a hoisting gantry truck, and this step can be performed simultaneously with step S3.

[0027] Compared with the prior art, the technical solution of this application has the following beneficial technical effects:

[0028] 1. The prefabricated floor slab installation device provided in the present application utilizes a mobile receiving platform to place multiple prefabricated floor slabs to be installed, creates a temporary receiving platform on the working surface for installing the prefabricated floor slabs, and then uses a lifting gantry to lift a single prefabricated floor slab, so that the lifting and installation of the prefabricated floor slabs are separated, and the lifting is increased from lifting one piece at a time to lifting four to eight pieces at a time, thereby realizing the rapid installation of the prefabricated floor slabs. While the tower crane places the prefabricated floor slabs on the mobile receiving platform, the lifting gantry can move and install the prefabricated floor slabs on the mobile receiving platform, saving installation time and also reducing the workload of construction personnel, thereby improving efficiency several times and reducing the construction period of the prefabricated floor slabs.

[0029] 2. The mobile receiving platform and the hoisting truss vehicle of the present application are connected to the track beam in layers, so that the movement tracks of the two do not interfere with each other, and the horizontal positions of the mobile receiving platform and the hoisting truss vehicle can be adjusted more flexibly, so that the installation and coverage of the prefabricated floor slabs within the span of the entire floor can be achieved, and the blind spots in construction can be reduced;

[0030] 3. The mobile receiving platform includes multiple sets of parallel and spaced support groups, so that the mobile receiving platform can more stably support multiple prefabricated floor slabs. The support frame is arranged so that the vertical drive assembly can more stably lift a single prefabricated floor slab. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A schematic diagram of the overall structure of the prefabricated floor installation device provided in this application when in use;

[0032] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0033] 1. Track beam; 11. First track; 12. Second track; 2. Mobile receiving platform; 21. Support group; 211. Horizontal support rod; 212. Vertical suspension rod; 213. First traction pulley; 3. Lifting gantry; 31. Sliding rail; 311. Second traction pulley; 32. Support frame; 33. Lifting and hoisting equipment; 331. Main lifting rope; 332. Branch rope;

[0034] 100. Vertical components; 200. Prefabricated floor slabs. DETAILED DESCRIPTION

[0035] In order to facilitate understanding of the present application, the present application will be described more fully below with reference to the relevant drawings. Embodiments of the present application are provided in the drawings. However, the present application can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present application more thorough and comprehensive.

[0036] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application.

[0037] This application provides a prefabricated floor installation device using the following construction scenario as an example, but the installation device of this application is not limited to the following scenario. During the construction of prefabricated buildings, after the construction of the first-floor beam and column structure is completed, the structural columns of the upper layer are constructed above the structural columns. After the construction of the second-floor structural columns is completed, the first-floor structural top plate is hoisted and installed, that is, the second-floor structural bottom plate is constructed.

[0038] The efficiency of transporting and installing prefabricated floor slabs by tower crane is low. The prefabricated floor slab installation device of the present application is installed on the structural columns of the second floor to improve the installation efficiency of the prefabricated floor slabs.

[0039] A prefabricated floor installation device, referring to Figure 1 , including a track beam 1, a mobile receiving platform 2 and a lifting gantry 3. The track beam 1 includes a first track 11 and a second track 12 which are arranged horizontally. The first track 11 and the second track 12 are respectively fixed on two adjacent rows of vertical members 100. The first track 11 and the second track 12 are in the same horizontal plane and are arranged correspondingly. The first track 11 and the second track 12 can be steel structures, specifically I-beams, C-shaped steels, square steel pipes or F-shaped steels with inverted cross sections. It should be noted that the vertical members 100 in the present application are not limited to vertical structural columns, but can also be temporary vertical support members or other structures capable of installing and fixing the track beam 1 of the present application. The vertical members 100 in the present application are only used to provide fixing points for the track beam 1, and the structural form is not limited.

[0040] In order to achieve stable installation of the first rail 11 and the second rail 12, the first rail 11 and the second rail 12 are connected to each intersecting vertical member 100 by high-strength bolts, and at least three connection points are set. It can also be achieved by pre-setting a detachable bracket on the vertical member 100.

[0041] A mobile receiving platform 2 and a hoisting truss 3 are installed on the track beam 1. The mobile receiving platform 2 is used to stack the prefabricated floor slabs 200, and the hoisting truss 3 is used to transport and hoist a single prefabricated floor slab 200.

[0042] Specifically, the mobile receiving platform 2 includes a plurality of support groups 21 arranged at intervals, the support group 21 includes a transverse support rod 211 and two vertical suspension rods 212, the two ends of the transverse support rod 211 are respectively connected to the two vertical suspension rods 212, one end of the vertical suspension rod 212 away from the transverse support rod 211 is slidably connected to the first track 11, and the other end of the vertical suspension rod 212 away from the transverse support rod 211 is slidably connected to the second track 12. The more the number of support groups 21, the more stable the prefabricated floor slab 200 can be supported, and only two support groups 21 are shown in the embodiment of the present application.

[0043] Specifically, a first traction pulley 213 is provided at one end of the vertical hanger 212 connected to the track beam 1. The first traction pulley 213 is slidably connected to the side wall of the first track 11, or is slidably connected to the side wall of the second track 12. By controlling the rotation direction of the first traction pulley 213, the mobile receiving platform 2 can move forward or backward along the length direction of the track beam 1.

[0044] The mobile receiving platform 2 is provided so that the tower crane only needs to hoist the prefabricated floor slabs 200 onto the mobile receiving platform 2 for stacking, and the number of hoisting by the tower crane can be changed from 1 to 4-8 at a time, thereby improving the hoisting efficiency of the tower crane. The plurality of spaced support groups 21 are provided to improve the stability of the mobile receiving platform 2 in supporting the prefabricated floor slabs 200.

[0045] In another embodiment, a pallet is provided above the transverse struts 211, and the bottom wall of the pallet is provided with grooves equal to the number of transverse struts 211. The pallet is placed on multiple transverse struts 211 at the same time, and multiple transverse struts 211 are plugged into the multiple grooves one by one. By providing the pallet, the prefabricated floor 200 can be placed on the mobile receiving platform 2 more stably, reducing the possibility of the prefabricated floor 200 sliding off the mobile receiving platform 2, and multiple prefabricated floor slabs 200 can be stacked and placed; the provision of the groove can limit the sliding of the pallet relative to the transverse struts 211, so that the positions of the pallet and the transverse struts 211 are relatively fixed. The pallet is not shown in the drawings of the present application, and multiple pallets can be provided, or only one pallet can be provided. The length of the pallet can be consistent with the length of the transverse struts 211, or it can be shorter than the length of the transverse struts 211 and can slide along the transverse struts 211.

[0046] In another embodiment, a connecting piece is further provided between two adjacent vertical suspension rods 212 on the same side, and the connecting piece is fixedly connected to the vertical suspension rods 212 on both sides at the same time. The connecting piece can specifically be a rod or a scissors brace or a plate connecting the two vertical suspension rods 212. The connecting piece can achieve the connection between the two vertical suspension rods 212. The specific structural form is not limited, and the connecting piece is not shown in the drawings. The multiple support groups 21 are connected into a whole by providing the connecting piece, thereby achieving the synchronous movement of the multiple support groups 21.

[0047] The lifting gantry 3 includes a horizontal drive assembly and a vertical drive assembly. The horizontal drive assembly is slidably set on the track beam 1, and the vertical drive assembly is slidably set on the horizontal drive assembly. For ease of understanding, the extension direction of the track beam 1 is taken as the X-axis, and the direction on the horizontal plane perpendicular to the X-axis is taken as the Y-axis. The horizontal drive assembly can move along the X-axis direction, and the vertical drive assembly can move along the Y-axis direction.

[0048] The horizontal drive assembly includes at least two sliding rails 31 arranged at intervals, and the two ends of the sliding rails 31 are respectively connected to the first rail 11 and the second rail 12 in a sliding manner. Specifically, the two ends of the sliding rails 31 are fixed with second traction pulleys 311, which are clamped above the first rail 11 and the second rail 12. By controlling the rotation of the second traction pulley 311, the horizontal drive assembly can be driven to move along the track beam 1. It should be particularly noted that the mobile receiving platform 2 and the hoisting truss 3 are respectively connected to different areas of the track beam 1 in a sliding manner. In the embodiment of the present application, the hoisting truss 3 is connected to the top wall of the track beam 1 in a sliding manner, and the mobile receiving platform 2 is connected to the side wall of the track beam 1 in a sliding manner. In other embodiments, the hoisting truss 3 can also be connected to the side wall of the track beam 1 in a sliding manner, and the mobile receiving platform 2 can be connected to the bottom wall of the track beam 1 in a sliding manner, or in other situations, so as to realize the layered connection between the mobile receiving platform 2 and the hoisting truss 3 and the track beam 1, and realize that the moving trajectory of the hoisting truss 3 does not interfere with the moving trajectory of the mobile receiving platform 2.

[0049] The vertical drive assembly includes a support frame 32 and a hoisting and lifting device 33 for hoisting a single prefabricated floor slab 200. Specifically, the support frame 32 is slidably mounted on a plurality of sliding rails 31, and both ends of the support frame 32 are respectively slidably connected to a sliding rail 31, and the hoisting and lifting device 33 is mounted and fixed on the support frame 32. By providing the support frame 32, on the one hand, the vertical drive assembly can slide along the sliding rail 31, and on the other hand, more stable support can be achieved for the hoisting and lifting device 33.

[0050] The hoisting and lifting equipment 33 includes a main hoisting rope 331 wound around a rotating shaft and a plurality of branch ropes 332 connected to the free end of the main hoisting rope 331. The free end of the branch rope 332 is connected to the prefabricated floor 200 to achieve multi-point connection of the prefabricated floor 200, so that the prefabricated floor 200 can be hoisted and transported more smoothly. The stacking height of the prefabricated floor 200 on the mobile receiving platform 2 is controlled, and the length of the branch rope 332 is reasonably set, so that when the main hoisting rope 331 is fully rolled up, the top surface of the prefabricated floor 200 stacked on the mobile receiving platform 2 is located below the prefabricated floor 200 hoisted on the hoisting gantry 3, so that the horizontal movement of the mobile receiving platform 2 and the horizontal movement of the hoisting gantry 3 do not interfere with each other.

[0051] When using the prefabricated floor 200 installation device of the present application, the prefabricated floor 200 can be hoisted and stacked on the mobile receiving platform 2 using a tower crane as a temporary loading point; and a hoisting gantry 3 can be used to hoist and transport a single prefabricated floor 200 from the mobile receiving platform 2 to the construction site to achieve the installation of the prefabricated floor 200.

[0052] The present application enables the tower crane to only lift the prefabricated floor slab 200 onto the mobile receiving platform 2, thereby reducing the workload and work complexity of the tower crane and improving the utilization efficiency of the tower crane; the prefabricated floor slab 200 is lifted by the lifting truss 3, and the moving trajectory of the lifting truss 3 does not interfere with the moving trajectory of the mobile receiving platform 2, so that the two construction processes of lifting and installing the prefabricated floor slab 200 can be carried out simultaneously, thereby improving the installation efficiency of the prefabricated floor slab 200.

[0053] Furthermore, the track beam 1 is arranged below the design height of the floor top plate, and the installation device of the prefabricated floor 200 of the present application does not interfere with the construction of the structural top plate and structural beams of this layer, thereby enabling the installation of the prefabricated floor 200 to be carried out without affecting the construction of the structural beams of this layer.

[0054] The installation device of the prefabricated floor 200 of the present application also includes a control system. The mobile receiving platform 2 and the lifting gantry 3 are both connected to the control system. The control system can control the horizontal movement of the mobile receiving platform 2 along the track beam 1, the horizontal movement of the sliding rail 31 along the track beam 1, the horizontal movement of the vertical drive component along the sliding rail 31, and the lifting drive of the lifting hoisting equipment 33. The setting of the control system can be achieved through existing technology and will not be described in detail here.

[0055] In addition, the present application also provides a method for installing a prefabricated floor slab, comprising the following installation steps:

[0056] S1, completing the construction of the top structural beam of the lower floor and the vertical component 100 of the floor;

[0057] S2, fix the track beam 1 to the vertical member 100, and install the mobile receiving platform 2 and the lifting gantry vehicle 3 on the track beam 1;

[0058] S3, using a tower crane to hoist the prefabricated floor slab 200 and stack it on the mobile receiving platform 2, where multiple prefabricated floor slabs 200 can be stacked;

[0059] S4, using the hoisting gantry vehicle 3 to transport the single prefabricated floor slab 200 from the mobile receiving platform 2 to the construction and installation location, and this step can be performed simultaneously with step S3.

[0060] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A prefabricated floor installation device, characterized in that: include: A track beam (1) is fixedly mounted on a vertical member (100), comprising a first track (11) and a second track (12), wherein the first track (11) and the second track (12) are respectively arranged on two adjacent rows of vertical members (100), and the first track (11) and the second track (12) are arranged correspondingly; A mobile receiving platform (2) for stacking prefabricated floor slabs (200) to be installed, wherein the mobile receiving platform (2) is slidably mounted on the track beam (1); A hoisting truss vehicle (3) is used to hoist a single prefabricated floor slab (200), wherein the hoisting truss vehicle (3) is slidably mounted on the track beam (1); The mobile cargo receiving platform (2) and the lifting gantry vehicle (3) operate in layers on the track beam (1); The hoisting gantry vehicle (3) comprises a horizontal driving component for driving the prefabricated floor slab (200) to move horizontally and a vertical driving component for driving the prefabricated floor slab (200) to move vertically.

2. A prefabricated floor installation device according to claim 1, characterized in that: The mobile cargo receiving platform (2) comprises a plurality of parallel and spaced support groups (21), wherein the support groups (21) comprise a transverse support rod (211) and two vertical suspension rods (212), wherein two ends of the transverse support rod (211) are respectively connected to the two vertical suspension rods (212), and ends of the two vertical suspension rods (212) away from the transverse support rod (211) are respectively slidably connected to the first track (11) and the second track (12).

3. A prefabricated floor installation device according to claim 2, characterized in that: The mobile cargo receiving platform (2) further comprises a support plate arranged above the transverse support rod (211), wherein a plurality of grooves are provided at the bottom of the support plate, and a plurality of the transverse support rods (211) are inserted into the plurality of grooves in a one-to-one correspondence.

4. A prefabricated floor installation device according to claim 2, characterized in that: A connecting piece is also provided between two adjacent vertical suspension rods (212), and the connecting piece is fixedly connected to the vertical suspension rods (212) on both sides at the same time.

5. The prefabricated floor installation device according to claim 1, characterized in that: The horizontal drive assembly comprises at least two spaced sliding rails (31), the two ends of the sliding rails (31) being respectively slidably connected to the first rail (11) and the second rail (12), and the vertical drive assembly is slidably mounted on the horizontal drive assembly and is capable of sliding along the sliding rails (31).

6. A prefabricated floor installation device according to claim 5, characterized in that: The vertical drive assembly comprises a support frame (32) and a hoisting and lifting device (33) for hoisting a prefabricated floor slab (200); the support frame (32) is slidably connected to a plurality of the sliding rails (31) at the same time; and the hoisting and lifting device (33) is installed on the support frame (32).

7. A prefabricated floor installation device according to claim 6, characterized in that: The hoisting and lifting equipment (33) comprises a main hoisting rope (331) and a plurality of branch ropes (332) each connected to the main hoisting rope (331), wherein the plurality of branch ropes (332) are connected to a plurality of hoisting points of the prefabricated floor slab (200); When the main hoisting rope (331) is completely reeled in, the top surface of the prefabricated floor slabs (200) stacked on the mobile receiving platform (2) is located below the prefabricated floor slabs (200) hoisted on the hoisting gantry vehicle (3).

8. A prefabricated floor installation device according to any one of claims 1 to 6, characterized in that: The track beam (1) is arranged below the designed height of the top plate of the floor.

9. A prefabricated floor installation device according to claim 6, characterized in that: It also includes a control system, to which the mobile cargo receiving platform (2) and the lifting gantry vehicle (3) are both connected, and is used to control the movement of the mobile cargo receiving platform (2), the horizontal movement of the sliding rail (31), the horizontal movement of the vertical drive assembly, and the lifting drive of the lifting hoisting equipment (33).

10. A method for installing a prefabricated floor, characterized in that: The installation steps include: S1. After completing the construction of the top structural beam of the lower floor, proceed with the construction of the vertical components (100) of this floor; S2, fixing the track beam (1) to the vertical member (100), and installing a mobile receiving platform (2) and a lifting gantry vehicle (3) on the track beam (1); S3, using a tower crane to hoist and stack the prefabricated floor slabs (200) onto the support group (21) of the mobile receiving platform (2), whereby a plurality of prefabricated floor slabs (200) can be stacked on the mobile receiving platform (2); S4, using a hoisting gantry vehicle (3) to transport a single prefabricated floor slab (200) from the mobile receiving platform (2) to a construction and installation location, and this step can be performed simultaneously with step S3.