Precise positioning method for first steel tower section of ultrahigh multi-limb steel-concrete combined tower column

Through total station and axial force automatic monitoring technology, combined with temperature and stress monitoring, an overall model of the tower limbs was established to achieve the precise positioning of the first steel tower segment of the ultra-high multi-limb steel-concrete composite tower column, solving the problem of accurate construction during construction. Problems that are difficult to locate are solved and the installation accuracy is improved.

CN118855243APending Publication Date: 2024-10-29CCCC SHEC FOURTH ENG +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410836717.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

In the construction of ultra-high multi-limb steel-concrete composite tower columns, the precise positioning of the first steel tower segment is difficult. Existing technology cannot effectively achieve millimeter-level precise positioning, which is greatly affected by external loads, temperature and measurement errors.

Method used

A total station is used to measure the influence of the tower crane on the tower column. The locking structure connects the tower limbs as a whole. Automatic axial force monitoring instruments are installed to establish a temperature field and offset model. Through temperature monitoring and stress wireless monitoring technology, the tower is realized Precise positioning of limb top displacement, and improved positioning accuracy through multiple measurements and data corrections.

Benefits of technology

The installation accuracy of the first steel tower segment of each tower limb at the steel-concrete combined section reaches +3.0mm in plane, no more than 1.5mm in the same direction, +5.0mm in elevation, no more than 1.5mm in the same direction, solving structural problems. Construction technical challenges brought about by design innovation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118855243A_ABST
    Figure CN118855243A_ABST
Patent Text Reader

Abstract

The invention discloses a method for accurately positioning a first steel tower section suitable for an ultrahigh multi-limb steel-concrete combined tower column. Arranging a measurement working base point corresponding to each tower limb; respectively rotating a group of tower cranes in four directions, and measuring the influence quantity of each tower crane on the tower column by the total station; all the tower limbs are synchronously constructed to the steel-concrete combined section, and all the tower limbs are connected into an integral structure through a locking structure; an automatic axial force monitoring instrument is mounted on the locking structure; arranging temperature monitoring points, establishing a tower limb overall temperature field, and monitoring tower limb top displacement caused by temperature change; establishing models of different hoisting weights and directions of the tower crane, internal and external temperature fields of a tower limb and offset of the tower limb, and raising neutral free positions of a single tower limb and an integral structure; building a tower limb top control reference; and the first section steel tower is positioned. According to the method, the mounting and positioning precision of the first steel tower section of each tower limb at the steel-concrete combined section is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of long-span cable-stayed bridge construction, and in particular to a method for accurately positioning a Shougang tower segment of an ultra-high multi-limb steel-concrete composite tower column. Background Art

[0002] At present, cable-stayed bridges with main spans exceeding one kilometer are constantly emerging, and structural designs are constantly innovating, such as the Changtai Yangtze River Bridge in Jiangsu and the Chaoma Yangtze River Bridge in Anhui. The main towers exceeding 300 meters high use steel structures for the upper tower columns, which effectively avoid the problems of long-distance pumping and maintenance difficulties of large-volume concrete; the middle and lower tower columns use four-limb reinforced concrete structures, which improve the overall stiffness of the main tower columns, reduce the cross-sectional size of the single-limb tower columns, and reduce the risk of cracking during the concrete construction stage. The above innovations in structural design have brought new challenges to construction technology.

[0003] The tower column is constructed in sections. Figure 2 At the steel-concrete joint section shown in the figure, the first steel tower segment of the four tower limbs must be accurately positioned. The first steel tower segment is the installation reference for the subsequent steel tower segments, which is crucial and requires installation accuracy to reach the millimeter level. At this time, the four tower limbs at the steel-concrete joint section, which are over 200m high, have not yet formed an overall structure. The rigidity of a single tower limb is weak. Affected by external factors such as external loads, temperature, and wind, the deformation itself reaches the centimeter level and the synchronization is poor. In addition, the measurement error caused by the measurement reference surface is also close to the centimeter level. According to literature records, some experts and scholars believe that "due to external environmental factors such as sunlight, the deformation of high tower columns is large, and construction measurement work should be arranged in a stable time period at night." Some experts and scholars believe that "the use of follow-up measurement technology can eliminate the influence of tower column deformation on construction measurement work." Such views cannot completely solve the above-mentioned precise positioning problem.

[0004] Most of the existing positioning methods cannot efficiently achieve accurate positioning of the Shougang Tower segments; for example, Chinese patent CN116377887A discloses a construction method for accurately adjusting and closing high tower column steel tower segments, which includes the following steps: S1, installing an active cross brace at the third section of the top concrete tower column to adjust the deviation that occurs during the construction of the concrete tower column; S2, installing four stepped steel piers at the steel-concrete joint sections of the left and right tower limbs, and the steel piers are installed in groups of two at the corresponding steel-concrete joint sections, and a three-way jack is placed on each steel pier to lift up the starting segment steel tower column, which is named ST1, and the starting segment steel tower column is accurately adjusted by the three-way jack. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a method for accurately positioning the Shougang Tower segments of an ultra-high multi-limb steel-concrete composite tower column, which can effectively improve the installation and positioning accuracy of the first steel tower segment of each tower limb at the steel-concrete joint section.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0007] The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-limb steel-concrete composite tower column comprises the following steps:

[0008] Step 1: Arrange the measurement work base points for each tower limb;

[0009] Step 2: Rotate a group of tower cranes in four directions respectively, and use the total station to measure the influence of each tower crane on the tower column;

[0010] Step 3: All tower limbs are constructed synchronously to the steel-concrete joint section, and a locking structure is used to connect all tower limbs into an integral structure;

[0011] Step 4: Install an axial force automatic monitoring instrument on the locking structure;

[0012] Step 5: Arrange temperature monitoring points, establish the overall temperature field of the tower limb, and implement the displacement monitoring of the top of the tower limb caused by temperature change;

[0013] Step 6: Establish the tower crane's different lifting weights and orientations, the temperature field inside and outside the tower limbs, and the tower limb offset model to improve the neutral free position of the individual tower limbs and the overall structure;

[0014] Step 7: Establish the control benchmark at the top of the tower limb;

[0015] Step 8: Repeat step 7 in different time periods. The difference between the secondary coordinates of all working base points is no more than 1.5 mm, and the average value is used;

[0016] Step 9: Position the first section of the steel tower.

[0017] Furthermore, in step 1,

[0018] The maintenance of the ground control network is the benchmark for the precise positioning of the steel tower, and is also the basis for the detection of the neutral position of the tower limbs. The ground control points are arranged around the tower column in the form of strip foundations, and the long side of the strip foundation faces the tower column, which is conducive to the control of the displacement in this direction. The tower limb displacement observation and tower top benchmark measurement will be able to achieve an accuracy of ±1mm.

[0019] The tower limb monitoring adopts the pre-buried fixed end on the tower top. The monitoring target point is also used as the positioning working base point of the first section steel tower, which is designed as an omnidirectional rotating spherical structure. According to the line of sight of the total station, its alignment direction is remotely controlled through a rotating pan-tilt form to meet the aiming requirements of ground observation and free station observation on the tower top.

[0020] Furthermore, in step 2,

[0021] At night when the temperature is relatively constant, each tower crane is rotated in four directions when not working and in a balanced state. The position changes of all working base points on the top of the tower limb are synchronously observed at the control points arranged on the ground along the axis of the main tower. The offset value of the tower crane in each direction is obtained by subtracting the mean value of each point from that in each direction, and the influence of the horizontal force of the tower crane buttress on the displacement of the top of the tower limb when the tower crane is in an eccentric state and in a balanced state is determined; then the cutting size of the tower top locking device is determined.

[0022] Furthermore, in step 3,

[0023] Every two tower limbs are connected by steel pipe horizontal braces. The horizontal cross brace is only provided with a jacking structure at one end, which is composed of support embedded parts, support and corbel structure, jack and pad beam; the other end of the horizontal cross brace is directly connected to the support, and connected to the tower column through the support embedded parts; the jacking force is determined by structural calculation, and after the jacking of the cross brace is completed, the pad structure is hoisted to the designed position by a tower crane, and welded and fixed so that the tower limb is in a locked state, thus forming an overall structure.

[0024] Furthermore, in step 4,

[0025] Select the test point and force measurement direction according to the structural requirements, and require the strain gauge to be in the same direction as the force direction; install the mounting mold tube into the mounting seat, and make the two ends of the mounting mold tube flush with the side of the mounting seat, and fix the mounting mold tube with screws; grind the surface of the steel structure, and fix the mounting seat on the horizontal support of the steel pipe by spot welding; after the mounting seat cools down, remove the mounting mold tube and install the strain gauge into the mounting seat. The strain gauge should be in the middle of the two mounting seats, with the outlet box facing upwards, and tighten the screws of the mounting seat;

[0026] The stress wireless monitoring technology transmits the stress change value monitored by the stress sensor to the system interface in the form of network data through the data communication module, realizing real-time monitoring of stress changes.

[0027] Furthermore, in step 5,

[0028] Wall-mounted and outdoor temperature sensors are arranged inside and outside the tower limbs from the bottom to the top and at one-quarter, one-half and three-quarters of the tower column height to establish the temperature field inside and outside the tower column. At the same time, clear weather with a large temperature difference is selected to use a total station to monitor the displacement change of the monitoring point on the top of the tower limb, and 24-hour tower limb top displacement monitoring is implemented. Based on a large amount of monitoring data, the stable time range of the bridge tower structure of this design type is determined.

[0029] Furthermore, in step 6,

[0030] Each tower crane independently rotates in four directions under eccentric load and observes the tower column synchronously. Under different eccentric loads and different orientations, the tower column offset is analyzed as a whole to obtain the relationship curve between hoisting weight and orientation.

[0031] The interpolation model of different hoisting weights and orientations of the tower crane and the stable time range of the overall temperature change of the tower column is obtained to provide a neutral free position of the tower column for steel tower hoisting.

[0032] Furthermore, in step 7,

[0033] Choose a breezy night with the tower crane in a balanced state; set the total station on the top of the tower limb, use the free station method, three measurements for each side and corner, and transfer the ground reference to all working base points on the top of the tower limb; when measuring, correct the temperature, air pressure, and humidity in real time. After measurement, change the side length from the measurement reference plane to the control network projection plane.

[0034] Furthermore, in step 9,

[0035] The first section of the steel tower is positioned based on the eight working base points at the top of the tower limb. The free station method of the total station is used to measure the positioning data of the first section of the steel tower. The free station position should be the symmetrical center position formed by the eight reference points to enhance the strength of the graph. The adsorption observation platform suitable for steel structures can meet the flexible installation of the total station to maximize the accuracy.

[0036] During the positioning process of the first section of the steel tower, the axial force of the locking device is monitored at all times. When the axial force changes within the threshold range, the total station is set up on the observation platform on the top of the tower. By observing the prism device of the sample impact point of the steel tower, the three-dimensional coordinates of the characteristic points of the steel tower are collected. According to the relationship between the position of the steel piers distributed on the top of the concrete tower and the steel tower structure, a correction model is established to achieve one-click rapid and repeated adjustments until the requirements are met; when the axial force changes exceed the threshold, the tower limb displacement monitoring and tower crane rotation and temperature field monitoring results are recalculated and analyzed, and steps 7 and 8 are repeated to correct the working base point coordinate data, and the deviation of the steel tower segment is adjusted in the same way as above.

[0037] Compared with the prior art, the present invention has the following advantages:

[0038] The precise positioning method of the Shougang Tower segment of the super-high multi-leg steel-concrete composite tower column is reasonably designed, which can make the installation accuracy of the first steel tower segment of each tower leg at the steel-concrete joint section reach: + 3.0mm and the same direction deviation does not exceed 1.5mm, elevation + 5.0mm and the same-direction deviation does not exceed 1.5mm, thus solving the construction technology problems caused by structural design innovation; effectively improving the installation and positioning accuracy of the first steel tower segment of each tower limb at the steel-concrete joint section. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] The following is a brief description of the contents and symbols in the drawings of this specification:

[0040] Figure 1 It is a schematic diagram of the operation flow of the positioning method of the present invention.

[0041] Figure 2 This is a construction structure diagram of the steel-concrete combined section of multiple tower limbs of the present invention.

[0042] Figure 3 It is a schematic diagram of the multi-tower limb consolidation and locking structure of the present invention.

[0043] Figure 4 for Figure 3 A partial enlarged schematic diagram is shown in the figure.

[0044] Figure 5 This is a schematic diagram of the positioning and control of the first section of the steel tower of the present invention.

[0045] Figure 6 for Figure 5 A partial enlarged schematic diagram is shown in the figure.

[0046] Figure 7 This is the automatic monitoring diagram of multiple tower limbs of the present invention. DETAILED DESCRIPTION

[0047] The specific implementation modes of the present invention will be further explained in detail below through the description of embodiments with reference to the accompanying drawings.

[0048] like Figures 1 to 7 As shown, the first steel tower segment precise positioning method applicable to super-high multi-leg steel-concrete composite tower column comprises the following steps:

[0049] Step 1: Arrange the measurement work base points for each tower limb;

[0050] Step 2: Rotate a group of tower cranes in four directions respectively, and use the total station to measure the influence of each tower crane on the tower column;

[0051] Step 3: All tower limbs are constructed synchronously to the steel-concrete joint section, and a locking structure is used to connect all tower limbs into an integral structure;

[0052] Step 4: Install an axial force automatic monitoring instrument on the locking structure;

[0053] Step 5: Arrange temperature monitoring points, establish the overall temperature field of the tower limb, and implement the displacement monitoring of the top of the tower limb caused by temperature change;

[0054] Step 6: Establish the tower crane's different lifting weights and orientations, the temperature field inside and outside the tower limbs, and the tower limb offset model to improve the neutral free position of the individual tower limbs and the overall structure;

[0055] Step 7: Establish the control benchmark at the top of the tower limb;

[0056] Step 8: Repeat step 7 in different time periods. The difference between the secondary coordinates of all working base points is no more than 1.5 mm, and the average value is used;

[0057] Step 9: Position the first section of the steel tower.

[0058] This method for accurately locating the first steel tower segment of an ultra-high multi-leg steel-concrete composite tower column can achieve the following installation accuracy for the first steel tower segment of each tower leg at the steel-concrete joint section: + 3.0mm and the same direction deviation does not exceed 1.5mm, elevation + 5.0mm and the unidirectional deviation does not exceed 1.5mm, thus solving the construction technical problems caused by structural design innovation and effectively improving the installation and positioning accuracy of the first steel tower segment of each tower limb at the steel-concrete joint section.

[0059] The present invention takes four tower limbs as an example to describe the technical solution, which specifically includes the following steps:

[0060] Step 1. Arrange four measurement work base points on the four tower limbs:

[0061] The maintenance of the ground control network is the benchmark for the precise positioning of the steel tower, and is also the basis for the detection of the neutral position of the tower limbs. The ground control points are arranged around the tower column in the form of strip foundations. The bottom of the foundation is driven with inclined piles in an eight-shaped shape. The long side of the strip foundation faces the tower column, which is conducive to the control of displacement in this direction. The tower limb displacement observation and tower top benchmark measurement will be able to achieve an accuracy of ±1mm.

[0062] The tower limb monitoring adopts the pre-buried fixed end on the tower top. The monitoring target point also serves as the positioning working base point of the first section steel tower. It is designed as an omnidirectional rotating spherical device. According to the line of sight of the total station, its alignment direction is remotely controlled through a rotating pan-tilt form to meet the aiming requirements of ground observation and free station observation on the tower top.

[0063] Step 2. Rotate the three tower cranes in four directions respectively, and use a total station with a nominal accuracy of 05″ to measure the influence of each tower crane on the tower column:

[0064] At night when the temperature is relatively constant, each tower crane is rotated in four directions when not working and in a balanced state (the main arm is facing the longitudinal and transverse directions of the bridge respectively). The position changes of the four working base points on the top of the tower limb are synchronously observed at the control points arranged on the ground along the axis of the main tower. The offset value of the tower crane in each direction is obtained by subtracting the mean value of each point from that in each direction, and the influence of the horizontal force of the tower crane buttress on the displacement of the top of the tower limb when the tower crane is in an eccentric state and in a balanced state is determined; then the cutting size of the tower top locking device is determined.

[0065] Step 3. The four tower limbs are constructed synchronously to the steel-concrete joint section, and the four tower limbs are connected into an integral structure using a locking structure:

[0066] Every two tower limbs are connected by steel pipe horizontal braces. The horizontal cross brace is only equipped with a top-pushing structure at one end, which is composed of support embedded parts, support and bracket structure, jack and cushion beam; the other end of the horizontal cross brace is directly connected to the support and connected to the tower column through the support embedded parts. The top thrust is determined by structural calculation. After the top push of the horizontal brace is completed, the cushion structure is hoisted to the designed position by a tower crane and welded and fixed so that the tower limb is in a locked state, thus forming an integral structure.

[0067] Step 4. Install an automatic axial force monitoring instrument on the locking structure, such as Figure 3 and 4 As shown:

[0068] Select the test point and force measurement direction according to the structural requirements, and require the strain gauge to be in the same direction as the force direction (parallel to the axis of the strain gauge). Install the mounting mold tube into the mounting seat, with both ends of the mounting mold tube flush with the side of the mounting seat, and fix the mounting mold tube with screws; polish the surface of the steel structure with coarse gauze, and fix the mounting seat on the horizontal support of the steel pipe by spot welding; after the mounting seat cools down, remove the mounting mold tube and install the strain gauge into the mounting seat. The strain gauge should be in the middle of the two mounting seats, with the outlet box facing up, and tighten the screws of the mounting seat.

[0069] The stress wireless monitoring technology transmits the stress change value monitored by the stress sensor to the system interface in the form of network data through the data communication module, realizing real-time monitoring of stress changes.

[0070] Step 5. Arrange temperature monitoring points, establish the overall temperature field of the tower limb, and implement the displacement monitoring of the top of the tower limb caused by temperature change:

[0071] Wall-mounted and outdoor temperature sensors are installed inside and outside the tower from the bottom to the top and at one-quarter, one-half, and three-quarters of the tower column height to establish the temperature field inside and outside the tower column. At the same time, a total station with a nominal accuracy of 0.5″ is used to monitor the displacement change of the monitoring point on the top of the tower limb on sunny days with a large temperature difference, and 24-hour displacement monitoring of the top of the tower limb is implemented. After a large amount of monitoring data, the stable time range of the bridge tower structure of this design type is determined.

[0072] Step 6. Establish the tower crane's different lifting weights and orientations, the temperature field inside and outside the tower limbs, and the tower limb offset model to achieve the neutral position freedom of the individual tower limbs and the overall structure:

[0073] Each tower crane independently rotates in four directions under the eccentric load state and observes the tower column synchronously. The tower column offset of the three tower cranes under different eccentric loads and different orientations is analyzed as a whole to obtain the relationship curve between the lifting weight and orientation.

[0074] Combined with the data analysis results of step 6, obtain the interpolation model within the stable time range of tower crane's different lifting weights and orientations and the overall temperature change of the tower column, and provide the neutral free position of the tower column for steel tower hoisting;

[0075] Step 7. Establishment of control benchmark for the top of tower limb:

[0076] Choose a breezy night, with the tower crane in a balanced state; set the TS50 total station on the top of the tower limb, use the free station method, measure three times each for the sides and corners, and transfer the ground reference to the four working base points on the top of the tower limb. During measurement, correct the temperature, air pressure, and humidity in real time. After measurement, change the side length from the measurement reference plane to the control network projection plane;

[0077] Step 8. Repeat step 7 in different time periods (00:00-04:00 at night for two consecutive days). The difference between the secondary coordinates of the four working base points is no more than 1.5 mm, and the average value is used.

[0078] Step 9. Position the first section of the steel tower:

[0079] The first section of the steel tower is positioned based on the eight working base points at the top of the tower limb. Figure 5 As shown in the figure, the free station method of the total station is used to measure the positioning data of the first section of the steel tower. The free station position should be near the symmetrical center position formed by the 8 reference points to enhance the strength of the graph; the adsorption observation platform suitable for steel structures can meet the flexible installation of the total station to maximize the accuracy; in view of the actual working environment limitations, according to the principle of negligibility in engineering design, the best area for free station is derived, and the location area of ​​the free station can be displayed according to the distribution of the reference points and the error gradient;

[0080] During the positioning process of the first section of the steel tower, the axial force of the locking device is monitored at all times. When the axial force changes within the threshold range, a TS50 total station is set up on the observation platform on the top of the tower. By observing the prism device of the steel tower sample impact point, the three-dimensional coordinates of the characteristic points of the steel tower are collected. According to the relationship between the position of the steel piers distributed on the top of the concrete tower and the steel tower structure, a correction model is established to achieve one-click rapid and repeated adjustments until the requirements are met. When the axial force changes exceed the threshold, the tower limb displacement monitoring and tower crane rotation and temperature field monitoring results are recalculated and analyzed, and steps 7 and 8 are repeated to correct the working base point coordinate data, and the deviation of the steel tower segment is adjusted in the same way as above.

[0081] The preferred specific embodiments of the method of the present invention are:

[0082] Step 1. Ground control benchmark and tower top monitoring and control system, such as Figure 3 As shown;

[0083] Four strip foundation mandatory observation piers are built in the longitudinal and transverse axis directions of the steel tower. The layout range of the control points is determined according to the influence of the horizontal axis error of the total station (elevation angle less than 30 degrees) and the tower height (200m) (the horizontal distance from the center of the tower should be greater than 400m). Using the GNSS static observation method, the dedicated control network is connected with the primary control points of the bridge to establish a stable ground control benchmark and convert it into an independent coordinate system for the construction bridge axis.

[0084]

[0085] The tower limb monitoring and first-segment steel tower positioning work base points are arranged at the diagonal corners of each tower limb (parallel to the diagonal formed by the four tower limbs) of the tower top. A total of 8 points are equipped with embedded anchor rods. The position of the prism rotating spherical device is remotely controlled through a rotating pan-tilt platform to meet the needs of ground tower limb deviation monitoring and observation direction adjustment of free stationing on the tower top.

[0086] Step 2. Continuous observation of the free state of the tower limbs;

[0087] At night when the temperature is relatively constant, three tower cranes (tower crane 1#, tower crane 2#, and tower crane 3#) rotate synchronously in four directions (the main arms are facing the longitudinal and transverse directions of the bridge respectively) in the non-working state and the balancing state. The coordinates of the eight monitoring points on the top of the tower can be monitored synchronously to obtain the deviation of each tower limb in the longitudinal and transverse axis directions. The mean of the monitoring values ​​of the monitoring points in the four directions of rotation represents the free position of each tower limb, so that the deviation value of the tower limb at any time can be determined by comparing the monitoring value of the monitoring point at a certain moment with the mean value, ensuring the accurate size of the locking device.

[0088] Table 1: Example data Table 1

[0089]

[0090] In this example, observation data confirms the deviation of the tower crane from the mean in the four directions of rotation when balanced; it is used to support the determination of the free state of the tower limb and the calculation basis of the cutting length of the locking device.

[0091] Table 2: Example data table 2

[0092]

[0093] Through practical examples, it can be proved that when the tower crane is overloaded and balanced, the horizontal thrust of the tower crane buttress on the single tower limb is different, which is manifested as inconsistent displacement of the tower limb when rotating in a single direction, but the average of the four directions of rotation, that is, the free position of the tower limb, is consistent.

[0094] Step 3. The four tower limbs are constructed synchronously to the steel-concrete joint section, and the four tower limbs are connected into an integral structure using a locking device, such as Figure 4 As shown;

[0095] Each two tower limbs are connected by steel pipe horizontal bracing, using Q235B steel pipe The horizontal cross brace is only provided with a jacking structure at one end, which is composed of support embedded parts, support and corbel structure, jack and cushion beam; the other end of the horizontal cross brace is directly connected to the support and connected to the tower column through the support embedded parts.

[0096] Combined with step 2, the coordinate difference between the monitoring point coordinates of the free position of each tower limb and the monitoring point coordinates at the time of installation can be determined to determine the adjustment amount of the theoretical length of the locking device of the quadrilateral formed by the four tower limbs in the longitudinal and transverse directions. Apply a top thrust to the horizontal cross brace for adjustment. After the free position adjustment of each tower limb is completed, weld and fix it so that the tower limb is in a locked state, thus forming an overall structure.

[0097] Step 4. Install an automatic axial force monitoring instrument on the locking device, such as Figure 4 As shown;

[0098] Select the test point and force measurement direction according to the structural requirements. The strain gauge is required to be in the same direction as the force direction (parallel to the axis of the strain gauge). Install the mounting mold tube into the mounting seat. The two ends of the mounting mold tube are flush with the side of the mounting seat. Fix the mounting mold tube with screws. Polish the surface of the steel structure with coarse gauze, and fix the mounting seat on the horizontal support of the steel pipe by spot welding. After the mounting seat cools down, remove the mounting mold tube and install the strain gauge into the mounting seat. The strain gauge should be in the middle of the two mounting seats, and the outlet box should face upwards; tighten the screws of the mounting seat.

[0099] The stress wireless monitoring technology transmits the stress change value monitored by the stress sensor to the system interface in the form of network data through the data communication module, realizing real-time monitoring of stress changes. According to Hooke's law of elastic deformation of steel pipe under stress: is the elastic deformation

[0100] F is the applied force

[0101] L is the length of the steel pipe

[0102] E is the elastic modulus

[0103] A is the force bearing area

[0104] Table 3: The relationship between the calculated stress and deformation of the actual material is given by the above stress calculation formula

[0105]

[0106] According to the early warning threshold, the deformation alarm value is determined to be 0.8 of the allowable value, and whether the overall structure of the tower top is stable is determined.

[0107] Step 5. Arrange temperature monitoring points, establish the overall temperature field of the tower limb, and implement the displacement monitoring of the top of the tower limb caused by temperature change;

[0108] Wall-mounted and outdoor temperature sensors are installed inside and outside the tower limbs from the bottom to the top and at one-quarter, one-half, and three-quarters of the tower column height to establish the temperature field inside and outside the tower column. At the same time, a clear day with a large temperature difference and no construction work on the tower column (mainly when the tower crane is in a static state) is selected, and a total station with a nominal accuracy of 0.5″ is set up on the dedicated control observation pier on the longitudinal and transverse axes to monitor the displacement change of the monitoring point on the top of the tower limb, implement 24-hour displacement observation of each temperature monitoring section of the tower limb, record the observation time, sunshine direction, collect temperature values ​​at the sections inside and outside the tower column, and draw the displacement change curve of the tower column affected by temperature, and determine the time range and correction model for the free stability of the tower column.

[0109] Step 6. Establish models for different lifting weights and orientations of the tower crane, the temperature field inside and outside the tower limbs, and the tower limb offset to achieve neutral position freedom for individual tower limbs and the overall structure.

[0110] Each tower crane independently rotates in four directions under the eccentric load state and observes the tower column synchronously. The tower column offset of the three tower cranes under different eccentric loads and different orientations is analyzed as a whole to obtain the relationship curve between the lifting weight and orientation.

[0111] That is: the overall impact of the displacement of tower limbs caused by the eccentric loading of the three tower cranes and the orientation of the tower cranes on the displacement of the tower top.

[0112] 1# tower crane: eccentric load position α1, displacement x1 = x t *cosα1;y1=y t *sinα1

[0113] 2# tower crane: eccentric load position α2, displacement x2=x t *cosα2;y2=y t *sinα2

[0114] 3# tower crane: eccentric load position α3, displacement x3 = x t *cosα3;y1=y t *sinα3

[0115] x t y is the longitudinal displacement of the tower limb under the eccentric load; t It is the lateral displacement of the tower limb due to the unbalanced load of the hoisting weight.

[0116] The monitoring result of the tower column at any time, i.e. the center deviation of the tower column (the mean deviation of 8 monitoring points X, Y) is verified with the comprehensive impact value of the three tower cranes: X=x1+x2+x3; Y=y1+y2+y3.

[0117] Combined with the data analysis results of step 5 and step 6, the interpolation model of the tower crane with different lifting weights and orientations and the overall temperature change stability time range of the tower column is obtained to provide a neutral free position of the tower column for steel tower hoisting.

[0118] Step 7. Establish the control benchmark of the tower limb top.

[0119] Choose a breezy night when the tower crane is in a balanced state. Set the TS50 total station on the mandatory observation piers on the top of the four tower limbs, and use the free station method to observe the ground control dedicated axis point and the other three tower limb monitoring points and working base points. Observe the edge and corner combination for three rounds each. During measurement, correct the temperature, air pressure and humidity in real time.

[0120] Total station position: tower limbs 1#, 2#, 3#, 4#; observation points: ground control points (Z1, Z2, Z3, Z4), tower top working base points (JC1, JC2, JC3, JC4, JC5, JC6, JC7, JC8)

[0121] After the measurement, the side length is changed from the measurement reference plane to the control network projection plane, and the overall adjustment is performed to obtain unified control of the ground and the tower top.

[0122] Step 8. Repeat step 7 in different time periods. The difference between the secondary coordinates of the four working base points should not exceed 1.5 mm, and the average value is used.

[0123] Step 9. Position the first section of the steel tower.

[0124] like Figure 5 As shown, the first section of the steel tower is positioned based on the 8 working base points at the top of the tower limb. The total station free station method is used to measure the positioning data of the first section of the steel tower. The 8 working base points are arranged on both sides of the corner points of an approximate rectangle. The adsorption observation platform suitable for steel structures can meet the flexible installation of the total station to maximize accuracy. According to the factors affecting the error in the plane accuracy of the free station, the following are the principles for selecting the station locations:

[0125] ① It is advisable to set the site near the intersection of the perpendicular midlines of the rectangular sides of the tower column;

[0126] ② To improve the accuracy of station setting, the station should be set up to observe the surrounding working base points as evenly as possible to increase the verification conditions and redundant observation data.

[0127] During the positioning of the first section of the steel tower, the axial force of the locking device is monitored at all times. When the axial force changes within the threshold range, a TS50 is set up on the observation platform on the top of the tower to collect the three-dimensional coordinates of the characteristic points of the steel tower by observing the prism device of the steel tower sample punching point. According to the relationship between the position of the steel piers distributed on the top of the concrete tower and the steel tower structure, a correction model is established to achieve one-click rapid and repeated adjustments until the requirements are met;

[0128] From the rigid relationship of the geometric points, it can be seen that the support point of the steel pier is in the target coordinate system, and the characteristic points of the steel tower are transformed and adjusted to the theoretical position of the target coordinate system through translation parameters (Δx, Δy, Δz), rotation parameters (ωx, ωy, ωz) and scaling parameters (m).

[0129]

[0130] When the axial force change exceeds the threshold, the tower limb displacement monitoring, tower crane rotation and temperature field monitoring results are recalculated and analyzed, and steps 7 and 8 are repeated to correct the working base point coordinate data, and the deviation of the steel tower segment is adjusted using the above method.

[0131] The present invention is described above by way of example in conjunction with the accompanying drawings. It is obvious that the specific implementation of the present invention is not limited to the above-mentioned method. As long as various non-substantial improvements are made using the concept and technical solution of the present invention, or the concept and technical solution of the present invention are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.

Claims

1. A method for accurately positioning the segments of the Shougang Tower of an ultra-high multi-limb steel-concrete composite tower column, characterized in that: The following steps are involved: Step 1: Arrange the measurement work base points for each tower limb; Step 2: Rotate a group of tower cranes in four directions respectively, and use the total station to measure the influence of each tower crane on the tower column; Step 3: All tower limbs are constructed synchronously to the steel-concrete joint section, and a locking structure is used to connect all tower limbs into an integral structure; Step 4: Install an axial force automatic monitoring instrument on the locking structure; Step 5: Arrange temperature monitoring points, establish the overall temperature field of the tower limb, and implement the displacement monitoring of the top of the tower limb caused by temperature change; Step 6: Establish the tower crane's different lifting weights and orientations, the temperature field inside and outside the tower limbs, and the tower limb offset model to improve the neutral free position of the individual tower limbs and the overall structure; Step 7: Establish the control benchmark at the top of the tower limb; Step 8: Repeat step 7 in different time periods. The difference between the secondary coordinates of all working base points is no more than 1.5 mm, and the average value is used; Step 9: Position the first section of the steel tower.

2. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-limb steel-concrete composite tower column as claimed in claim 1 is characterized by: In the step 1, The maintenance of the ground control network is the benchmark for the precise positioning of the steel tower, and is also the basis for the detection of the neutral position of the tower limbs. The ground control points are arranged around the tower column in the form of strip foundations, and the long side of the strip foundation faces the tower column, which is conducive to the control of the displacement in this direction. The tower limb displacement observation and tower top benchmark measurement will be able to achieve an accuracy of ±1mm. The tower limb monitoring adopts the pre-buried fixed end on the tower top. The monitoring target point is also used as the positioning working base point of the first section steel tower, which is designed as an omnidirectional rotating spherical structure. According to the line of sight of the total station, its alignment direction is remotely controlled through a rotating pan-tilt form to meet the aiming requirements of ground observation and free station observation on the tower top.

3. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In the step 2, At night when the temperature is relatively constant, each tower crane is rotated in four directions when not working and in a balanced state. The position changes of all working base points on the top of the tower limb are synchronously observed at the control points arranged on the ground along the axis of the main tower. The offset value of the tower crane in each direction is obtained by subtracting the mean value of each point from that in each direction, and the influence of the horizontal force of the tower crane buttress on the displacement of the top of the tower limb when the tower crane is in an eccentric state and in a balanced state is determined; then the cutting size of the tower top locking device is determined.

4. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 3, Every two tower limbs are connected by steel pipe horizontal braces. The horizontal cross brace is only provided with a jacking structure at one end, which is composed of support embedded parts, support and corbel structure, jack and pad beam; the other end of the horizontal cross brace is directly connected to the support, and connected to the tower column through the support embedded parts; the jacking force is determined by structural calculation, and after the jacking of the cross brace is completed, the pad structure is hoisted to the designed position by a tower crane, and welded and fixed so that the tower limb is in a locked state, thus forming an overall structure.

5. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 4, Select the test point and force measurement direction according to the structural requirements, and require the strain gauge to be in the same direction as the force direction; install the mounting mold tube into the mounting seat, and make the two ends of the mounting mold tube flush with the side of the mounting seat, and fix the mounting mold tube with screws; grind the surface of the steel structure, and fix the mounting seat on the horizontal support of the steel pipe by spot welding; after the mounting seat cools down, remove the mounting mold tube and install the strain gauge into the mounting seat. The strain gauge should be in the middle of the two mounting seats, with the outlet box facing upwards, and tighten the screws of the mounting seat; The stress wireless monitoring technology transmits the stress change value monitored by the stress sensor to the system interface in the form of network data through the data communication module, realizing real-time monitoring of stress changes.

6. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 5, Wall-mounted and outdoor temperature sensors are arranged inside and outside the tower limbs from the bottom to the top and at one-quarter, one-half and three-quarters of the tower column height to establish the temperature field inside and outside the tower column. At the same time, clear weather with a large temperature difference is selected to use a total station to monitor the displacement change of the monitoring point on the top of the tower limb, and 24-hour tower limb top displacement monitoring is implemented. Based on a large amount of monitoring data, the stable time range of the bridge tower structure of this design type is determined.

7. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 6, Each tower crane independently rotates in four directions under eccentric load and observes the tower column synchronously. Under different eccentric loads and different orientations, the tower column offset is analyzed as a whole to obtain the relationship curve between hoisting weight and orientation. The interpolation model of different hoisting weights and orientations of the tower crane and the stable time range of the overall temperature change of the tower column is obtained to provide a neutral free position of the tower column for steel tower hoisting.

8. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 7, Choose a breezy night with the tower crane in a balanced state; set the total station on the top of the tower limb, use the free station method, three measurements for each side and corner, and transfer the ground reference to all working base points on the top of the tower limb; when measuring, correct the temperature, air pressure, and humidity in real time. After measurement, change the side length from the measurement reference plane to the control network projection plane.

9. The method for accurately positioning the segments of the Shougang Tower of the ultra-high multi-leg steel-concrete composite tower column as claimed in claim 1 is characterized by: In step 9, The first section of the steel tower is positioned based on the eight working base points at the top of the tower limb. The free station method of the total station is used to measure the positioning data of the first section of the steel tower. The free station position should be the symmetrical center position formed by the eight reference points to enhance the strength of the graph. The adsorption observation platform suitable for steel structures can meet the flexible installation of the total station to maximize the accuracy. During the positioning process of the first section of the steel tower, the axial force of the locking device is monitored at all times. When the axial force changes within the threshold range, the total station is set up on the observation platform on the top of the tower. By observing the prism device of the sample impact point of the steel tower, the three-dimensional coordinates of the characteristic points of the steel tower are collected. According to the relationship between the position of the steel piers distributed on the top of the concrete tower and the steel tower structure, a correction model is established to achieve one-click rapid and repeated adjustments until the requirements are met; when the axial force changes exceed the threshold, the tower limb displacement monitoring and tower crane rotation and temperature field monitoring results are recalculated and analyzed, and steps 7 and 8 are repeated to correct the working base point coordinate data, and the deviation of the steel tower segment is adjusted in the same way as above.

Citation Information

Patent Citations

  • Ultrahigh-space diamond-shaped four-tower-limb cable bent tower and construction method thereof

    CN114717939A

  • Precise positioning method for steel tower

    CN115727797A

  • Rapid measurement and control method for sectional hoisting of far-shore ultrahigh steel tower

    CN117308898A

  • Far-shore space four-limb bridge tower total prism linear monitoring system and monitoring method thereof

    CN117990065A

  • Control method for closure construction of four tower limbs of cable-stayed bridge tower

    CN118148019A