Coal mine stoping roof presplitting method
By setting up multiple inclined and angled blasting holes in the periodic pressure area of the coal mining area for blasting, a weak area is formed, which solves the problem of untimely roof collapse during coal mining and improves the safety and support of coal mining. System stability.
Patent Information
- Application Number
- CN202411140959.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-10-29
AI Technical Summary
During coal mining, the failure of the hard roof to collapse in time resulted in severe roof mine pressure. The existing roof pre-cracking technology can only break the roof macroscopically, causing the support system to be damaged by huge pressure, posing a major safety hazard.
By obtaining the key layer position and period of the coal mining area to press the step distance, determine the periodic press area, and set up multiple blasting holes arranged at inclines and angles in this area for blasting to form a weak area for mining at the mining face. When reaching this area, the roof breaks or collapses to avoid damage to the support system due to huge pressure.
It effectively reduces the pressure of the roof on the support system, knows the location and time of roof collapse in advance, improves the safety of coal mine mining, reduces the risk of damage to the support system, and ensures safe production of coal mine mining.
Smart Images

Figure CN118855477A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal mining blasting pre-splitting methods, and in particular to a coal mining roof pre-splitting method. Background Art
[0002] During coal mining, the hard roof at the key layer position usually collapses in time, resulting in severe roof pressure. The relevant technology uses roof pre-splitting technology to destroy the integrity of the hard roof in advance; however, the roof pre-splitting blasting used in the relevant technology can only break the roof macroscopically, and the roof pressure is still concentrated in the periodic pressure area. When the support system supports the periodic pressure area, the roof brings huge pressure to the support system, causing damage to the support system, thereby affecting the safe production of coal mining, and even easily causing roof accidents, posing a major safety hazard. Summary of the invention
[0003] The present invention aims to solve one of the technical problems in the related art at least to a certain extent.
[0004] To this end, an embodiment of the present invention proposes a method for pre-cracking the roof of a coal mine, which weakens the periodic pressure area to form a weak area. When the mining face is pushed to the periodic pressure area, the roof at the key layer position of the periodic pressure area breaks or collapses, preventing the roof from bringing huge pressure to the support system and causing damage to the support system, thereby improving the safety of coal mine mining.
[0005] The coal mine roof pre-splitting method of the embodiment of the present invention, wherein the coal mine mining area includes a waiting mining area, a first mining roadway and a second mining roadway, the first mining roadway and the second mining roadway are relatively arranged on both sides of the waiting mining area, the waiting mining area has a mining working face, and the coal mine roof pre-splitting method includes the following steps:
[0006] Based on the historical mining data of the coal mining area, the key layer position and periodic pressure step distance of the coal mining area are obtained;
[0007] Determine the periodic pressure area according to the key layer position and the periodic pressure step;
[0008] Determine blasting hole information for the periodic pressure zone, so as to implement blasting in the periodic pressure zone based on the blasting hole information.
[0009] In some embodiments, a height range is determined according to the key layer position, a depth range is determined according to the periodic pressure step, and the periodic pressure area is determined based on the depth range and the height range.
[0010] In some embodiments, the blast hole information includes the number of blast holes, and the number of blast holes is multiple.
[0011] In some embodiments, the blasting hole information also includes blasting hole positions, and the method for setting the blasting hole positions includes: at least two of the blasting holes are set in the periodic pressure area.
[0012] In some embodiments, at least one of the blasting holes is a first blasting hole, and at least one of the blasting holes is a second blasting hole. The center lines of the first blasting hole and the second blasting hole are both parallel to the mining working face. The center line of the first blasting hole is inclined upward from the first mining tunnel to the periodic pressure area, and the center line of the second blasting hole is inclined upward from the second mining tunnel to the periodic pressure area.
[0013] In some embodiments, the blasting hole information also includes a blasting hole angle, and a method for setting the blasting hole angle includes: a center line of the first blasting hole and a horizontal plane form a first angle A1, and the first angle A1 is 45° to 60°; and / or a center line of the second blasting hole and a horizontal plane form a second angle A2, and the second angle A2 is 45° to 60°.
[0014] In some embodiments, at least one of the blasting holes is a third blasting hole, and at least one of the blasting holes is a fourth blasting hole; the third blasting hole and the fourth blasting hole are both pointed from the mining working face to the periodic pressure area, and the projections of the third blasting hole and the fourth blasting hole on the mining working face are arranged between the projections of the first blasting hole and the second blasting hole on the mining working face.
[0015] In some embodiments, the projections of the center lines of the third blasting hole and the fourth blasting hole on the mining working surface gradually approach each other from bottom to top, and the projection of the center line of the third blasting hole on the mining working surface forms a third angle A3 with the horizontal plane, and the third angle A3 is 45° to 60°; and / or the projection of the center line of the fourth blasting hole on the mining working surface forms a fourth angle A4 with the horizontal plane, and the fourth angle A4 is 45° to 60°.
[0016] In some embodiments, the mining area has a first side surface arranged toward the first mining tunnel, and the projection of the center line of the third blasting hole on the first side surface forms a fifth angle A5 with the horizontal plane, and the fifth angle A5 is 45° to 60°; and / or the projection of the center line of the fourth blasting hole on the first side surface forms a sixth angle A6 with the horizontal plane, and the sixth angle A6 is 45° to 60°.
[0017] In some embodiments, the historical mining data includes geological sketch maps and statistical data on pressure step lengths during the early period of coal mining.
[0018] The coal mine roof pre-splitting method of the embodiment of the present invention uses the periodic pressure step distance as the blasting spacing, and blasts in the periodic pressure area to weaken the periodic pressure area to form a weak area. When the mining face is pushed to the periodic pressure area, the roof at the key layer position of the periodic pressure area breaks or collapses, preventing the roof from bringing huge pressure to the support system and causing damage to the support system, thereby improving the safety of coal mine mining.
[0019] The coal mine roof pre-cracking method of the embodiment of the present invention artificially creates a weak area in the periodic pressure area, making the roof at the key layer position prone to breakage or collapse, so that the roof collapse position and collapse time can be known in advance, so as to reasonably arrange the tunnel support system, reduce the risk of damage to the support system, and improve the safety of coal mine recovery. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic diagram of the plan structure of a coal mine recovery area according to an embodiment of the present invention.
[0021] Figure 2 The present invention is a schematic flow chart of a method for pre-cracking a coal mine roof according to an embodiment of the present invention.
[0022] Figure 3 It is a projection view of a first blasting hole, a second blasting hole, a third blasting hole and a fourth blasting hole on a mining face according to an embodiment of the present invention.
[0023] Figure 4 It is a projection view of a first blasting hole, a second blasting hole, a third blasting hole and a fourth blasting hole on a first side according to an embodiment of the present invention.
[0024] Reference numerals:
[0025] 1. Area to be mined; 11. Mining working face; 12. Coal seam; 13. Key layer position; 131. Periodic pressure area; 14. First side;
[0026] 2. The first mining tunnel;
[0027] 3. Second mining tunnel;
[0028] 51. The first blasting hole; 52. The second blasting hole; 53. The third blasting hole; 54. The fourth blasting hole. DETAILED DESCRIPTION
[0029] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings. The embodiments described below with reference to the accompanying drawings are exemplary and intended to be used to explain the present invention, but should not be understood as limiting the present invention.
[0030] like Figure 1As shown, the coal mine mining area includes a mining area 1, a first mining tunnel 2 and a second mining tunnel 3. The first mining tunnel 2 and the second mining tunnel 3 are arranged on both sides of the mining area 1 relatively. The mining area 1 has a mining working face 11.
[0031] like Figure 1 and Figure 2 As shown, the coal mine roof pre-splitting method according to the embodiment of the present invention comprises the following steps:
[0032] S1. Based on the historical mining data of the coal mining area, the key layer position 13 and the periodic pressure step distance of the coal mining area are obtained;
[0033] S2, determining the periodic pressure area 131 according to the key layer position 13 and the periodic pressure step;
[0034] S3. Determine blasting hole information for the periodic pressure region 131, so as to implement blasting in the periodic pressure region 131 based on the blasting hole information.
[0035] The coal mine roof pre-splitting method of the embodiment of the present invention uses the periodic pressure step distance as the blasting spacing, and blasts in the periodic pressure area 131, weakening the periodic pressure area 131 to form a weak area. When the mining face 11 is pushed to the periodic pressure area 131, the roof of the periodic pressure area 131 breaks or collapses, preventing the roof from bringing huge pressure to the support system and causing damage to the support system, thereby improving the safety of coal mine mining.
[0036] The coal mine roof pre-cracking method of the embodiment of the present invention artificially weakens the periodic pressure area 131 into a weak area, so that the roof at the key layer position 13 is prone to breakage or collapse, so that the roof collapse position and collapse time can be known in advance, so as to reasonably arrange the tunnel support system, reduce the risk of damage to the support system, and improve the safety of coal mine recovery.
[0037] Optionally, in step S3, blasting of the periodic pressure area 131 is implemented based on the blasting hole information; wherein the blasting of the periodic pressure area 131 is implemented by explosive blasting, gas blasting or mechanical blasting, preferably explosive blasting.
[0038] Specifically, the blasting hole is charged according to the blasting regulations and relevant requirements of the blasting instructions, and then the blasting is carried out.
[0039] Optionally, the mining face 11 implements mining according to the production organization plan, and the roof of the weak area (i.e., the periodic pressure area 131) breaks or collapses at the end of one periodic pressure step mining. Then, the above S1 to S3 can be repeated, and the roof of the key layer position 13 is blasted at a position one periodic pressure step away from the mining face 11 to form a weak area again.
[0040] Therefore, the time and position of roof collapse can be calculated according to the periodic pressure step distance and the daily planned advancement of the coal mining, so that the staff can take timely protective measures and achieve safe production in coal mining.
[0041] In some embodiments, Figure 1 and Figure 3 As shown, the height range is determined according to the key layer position 13, the depth range is determined according to the periodic pressure step, and the periodic pressure area 131 is determined based on the depth range and the height range.
[0042] By further determining the specific range of the periodic pressure area 131 , the blasting hole information can be further determined, thereby being more conducive to implementing blasting in the periodic pressure area 131 .
[0043] Alternatively, if Figure 1 As described above, the width range of the periodic pressure area 131 is determined according to the distance between the first mining tunnel 2 and the second mining tunnel 3 .
[0044] Thus, the width of the periodic pressure area 131 can be further determined. The two side edges of the periodic pressure area 131 in the width direction are respectively spaced a certain distance from the first mining tunnel 2 and the second mining tunnel 3 to prevent the first mining tunnel 2 and the second mining tunnel 3 from collapsing when blasting the periodic pressure area 131.
[0045] As an example, Figure 1 As shown, the periodic pressure step distance is L, and the position with a distance L from the mining face 11 is the middle position of the periodic pressure area 131. The depth range of the periodic pressure area 131 is determined based on the middle position.
[0046] like Figure 3 As shown, the key layer position 13 is located above the coal seam 12. The height range of the periodic pressure area 131 is determined based on the key layer position 13. The boundary between the key layer position 13 and the coal seam 12 is the lower edge of the height range. The height range of the periodic pressure area 131 is a certain distance upward from the boundary between the key layer position 13 and the coal seam 12.
[0047] In some embodiments, the blast hole information includes the number of blast holes, and the number of blast holes is multiple.
[0048] By providing a plurality of blasting holes, the plurality of blasting holes can be distributed at intervals in the periodic pressure region 131 , so that the periodic pressure region 131 can be blasted more evenly.
[0049] Optionally, the number of blasting holes is four.
[0050] In some embodiments, the blasting hole information also includes blasting hole positions, and a method for setting the blasting hole positions includes: at least two blasting holes are set in the periodic pressure area 131 .
[0051] By setting the blasting holes in the periodic pressure area 131, the blasting in the periodic pressure area 131 can be directly implemented to achieve a better blasting effect, and the periodic pressure area 131 can be weakened. Therefore, when the mining face 11 is pushed to the periodic pressure area 131, the roof of the key layer position 13 of the periodic pressure area 131 is broken or collapsed, preventing the roof from bringing huge pressure to the support system and causing damage to the support system, thereby improving the safety of coal mine mining.
[0052] In some embodiments, Figure 1 and Figure 3 As shown, at least one blasting hole is the first blasting hole 51, and at least one blasting hole is the second blasting hole 52. The center lines of the first blasting hole 51 and the second blasting hole 52 are both parallel to the mining face 11. The center line of the first blasting hole 51 is inclined upward from the first mining tunnel 2 to the periodic pressure area 131, and the center line of the second blasting hole 52 is inclined upward from the second mining tunnel 3 to the periodic pressure area 131.
[0053] Through the above arrangement, the first mining tunnel 2 and the second mining tunnel 3 are respectively drilled toward the periodic pressure area 131 to form the first blasting hole 51 and the second blasting hole 52. The first blasting hole 51 and the second blasting hole 52 penetrate the coal seam 12 and penetrate into the key layer position 13. Thus, the explosives can be loaded into the depth of the first blasting hole 51 and the second blasting hole 52, so that the explosives reach the key layer position 13 to implement the blasting of the key layer roof of the periodic pressure area 131. At the same time, the first blasting hole 51 and the second blasting hole 52 are symmetrically arranged, and the shock wave generated by the explosion of the explosives can evenly act on the rock at the key layer position 13, thereby making full use of the blasting energy of the explosives and improving the blasting efficiency.
[0054] In some embodiments, the blasting hole information also includes the blasting hole angle, and the method for setting the blasting hole angle includes: the center line of the first blasting hole 51 forms a first angle A1 with the horizontal plane, and the first angle A1 is 45°~60°; and / or the center line of the second blasting hole 52 forms a second angle A2 with the horizontal plane, and the second angle A2 is 45°~60°.
[0055] By setting the inclination angles of the first blasting hole 51 and the second blasting hole 52 to the above range, the shock wave generated by the explosion of the explosives impacts the surrounding rocks from the blasting hole, and the impact force on the rocks in all directions is more uniform, thereby further increasing the uniformity of the shock wave distribution and improving the blasting efficiency.
[0056] In addition, by setting the inclination angle of the first blasting hole 51 and the second blasting hole 52 to the above-mentioned range, the height of the first blasting hole 51 and the second blasting hole 52 can be reduced and the length of the first blasting hole 51 and the second blasting hole 52 can be increased, so that more explosives can be placed in the key layer position 13 of the periodic pressure area 131 to achieve a better blasting effect.
[0057] In some embodiments, Figure 1 and Figure 3 As shown, at least one blasting hole is the third blasting hole 53, and at least one blasting hole is the fourth blasting hole 54; the third blasting hole 53 and the fourth blasting hole 54 are both pointed from the mining face 11 to the periodic pressure area 131, and the projections of the third blasting hole 53 and the fourth blasting hole 54 on the mining face 11 are arranged between the projections of the first blasting hole 51 and the second blasting hole 52 on the mining face 11.
[0058] Through the above arrangement, holes are drilled obliquely upward from the mining face 11 toward the periodic pressure area 131 to form the third blasting hole 53 and the fourth blasting hole 54. The projections of the third blasting hole 53 and the fourth blasting hole 54 on the mining face 11 are arranged between the projections of the first blasting hole 51 and the second blasting hole 52 on the mining face 11. The multiple blasting holes are more evenly distributed in the periodic pressure area 131. The shock waves generated by the explosion of explosives in the multiple blasting holes can be more evenly distributed at the top plate position of the periodic pressure area 131, so that the top plate at the key layer position 13 is evenly broken, preventing large rocks of the hard top plate from collapsing, thereby further improving the safety of top plate collapse.
[0059] In some embodiments, Figure 3 As shown, the projections of the center lines of the third blasting hole 53 and the fourth blasting hole 54 on the mining face 11 are gradually approached from bottom to top, and the projection of the center line of the third blasting hole 53 on the mining face 11 forms a third angle A3 with the horizontal plane, and the third angle A3 is 45° to 60°; and / or the projection of the center line of the fourth blasting hole 54 on the mining face 11 forms a fourth angle A4 with the horizontal plane, and the fourth angle A4 is 45° to 60°.
[0060] By setting the inclination angle of the third blasting hole 53 and the fourth blasting hole 54 to the above-mentioned range, the length of the third blasting hole 53 and the fourth blasting hole 54 can be increased while reducing the depth and height of the third blasting hole 53 and the fourth blasting hole 54, so that more explosives can be placed in the key layer position 13 of the periodic pressure area 131 to achieve a better blasting effect.
[0061] In addition, the third blasting hole 53 and the fourth blasting hole 54 are gradually approached along the depth direction of the periodic pressure area 131. In other words, the third blasting hole 53 and the first blasting hole 51 have the same inclination direction, and the fourth blasting hole 54 and the second blasting hole 52 have the same inclination direction, so that the third blasting hole 53 and the first blasting hole 51 have a spacing, and the fourth blasting hole 54 and the second blasting hole 52 have a spacing, so that the first blasting hole 51, the second blasting hole 52, the third blasting hole 53 and the fourth blasting hole 54 are more evenly distributed in the periodic pressure area 131, so that the blasting of the periodic pressure area 131 is more uniform.
[0062] As an example, Figure 1 and Figure 3 As shown, the first blasting hole 51, the second blasting hole 52, the third blasting hole 53 and the fourth blasting hole 54 form projections on the mining face 11, wherein the third blasting hole 53 is arranged in parallel with the projection of the first blasting hole 51, the fourth blasting hole 54 is arranged in parallel with the projection of the second blasting hole 52, and the projections of the third blasting hole 53 and the fourth blasting hole 54 are symmetrical to each other; thus, the first blasting hole 51, the second blasting hole 52, the third blasting hole 53 and the fourth blasting hole 54 are arranged at intervals along the width direction of the periodic pressure area 131, so that the periodic pressure area 131 can be blasted more evenly to achieve a better blasting effect.
[0063] In some embodiments, Figure 4 As shown, the mining area 1 has a first side surface 14 arranged toward the first mining tunnel 2, and the projection of the center line of the third blasting hole 53 on the first side surface 14 forms a fifth angle A5 with the horizontal plane, and the fifth angle A5 is 45° to 60°; and / or the projection of the center line of the fourth blasting hole 54 on the first side surface 14 forms a sixth angle A6 with the horizontal plane, and the sixth angle A6 is 45° to 60°.
[0064] Through the above arrangement, the third blasting hole 53 and the fourth blasting hole 54 are arranged obliquely along the depth direction, height direction and width direction of the periodic pressure area 131, which can further increase the length of the third blasting hole 53 and the fourth blasting hole 54, so that more explosives can be placed in the third blasting hole 53 and the fourth blasting hole 54 to achieve a better blasting effect.
[0065] As an example, Figure 1 and Figure 3 As shown, the first side surface 14 is arranged vertically, and the first side surface 14 is the side wall of the first mining tunnel 2 close to the mining area 1 , and the first mining tunnel 2 and the first side surface 14 .
[0066] In some embodiments, the historical mining data includes geological sketch maps and statistics on the pressure step lengths during the early coal mining period.
[0067] The key layer position 13 can be obtained through the geological sketch map in order to determine the height range of the periodic pressure area 131; the periodic pressure step distance data in the early stage of coal mining can be used to obtain the periodic pressure step distance of the coal mining area or similar geological conditions, and further obtain the position and depth range of the periodic pressure area 131, and then drill blasting holes, and blast the periodic pressure area 131 to form a weak area. When the mining face 11 is pushed to the periodic pressure area 131, the roof of the key layer position 13 of the periodic pressure area 131 breaks or collapses, preventing the roof from bringing huge pressure to the support system and causing damage to the support system, thereby improving the safety of coal mining.
[0068] Optionally, in other embodiments, the step distance may be determined by calculating the cycle based on the properties of the coal seam 12 in the coal mining area.
[0069] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are illustrative and are not to be construed as limitations on the present invention. Changes, modifications, substitutions and variations of the above embodiments by those of ordinary skill in the art are all within the scope of protection of the present invention.
Claims
1. A method for pre-splitting roof in coal mining, characterized in that: The coal mine mining area comprises a mining area (1), a first mining roadway (2) and a second mining roadway (3), wherein the first mining roadway (2) and the second mining roadway (3) are arranged on two sides of the mining area (1) relative to each other, and the mining area (1) has a mining working face (11). The coal mine mining roof pre-splitting method comprises the following steps: Based on the historical mining data of the coal mining area, the key layer position (13) and the periodic pressure step distance of the coal mining area are obtained; Determining a periodic pressure region (131) according to the key layer position (13) and the periodic pressure step; Determine blasting hole information for the periodic pressure region (131) to achieve blasting of the periodic pressure region (131) based on the blasting hole information.
2. The method for pre-splitting the coal mine roof according to claim 1, characterized in that: A height range is determined according to the key layer position (13), a depth range is determined according to the periodic pressure step, and the periodic pressure area (131) is determined based on the depth range and the height range.
3. The method for pre-splitting the coal mine roof according to claim 2, characterized in that: The blasting hole information includes the number of blasting holes, and the number of blasting holes is multiple.
4. The method for pre-splitting the coal mine roof according to claim 3, characterized in that: The blasting hole information also includes blasting hole positions, and the method for setting the blasting hole positions includes: at least two of the blasting holes are set in the periodic pressure area (131).
5. The method for pre-splitting the coal mine roof according to claim 4, characterized in that: At least one of the blasting holes is a first blasting hole (51), and at least one of the blasting holes is a second blasting hole (52). The center lines of the first blasting hole (51) and the second blasting hole (52) are both parallel to the mining face (11). The center line of the first blasting hole (51) is inclined upward from the first mining tunnel (2) to the periodic pressure zone (131), and the center line of the second blasting hole (52) is inclined upward from the second mining tunnel (3) to the periodic pressure zone (131).
6. The method for pre-splitting the coal mine roof according to claim 5, characterized in that: The blast hole information also includes a blast hole angle, and the method for setting the blast hole angle includes: a center line of the first blast hole (51) forms a first angle A1 with a horizontal plane, and the first angle A1 is 45° to 60°; and / or The center line of the second blasting hole (52) forms a second angle A2 with the horizontal plane, and the second angle A2 is 45° to 60°.
7. The method for pre-splitting the coal mine roof according to claim 5, characterized in that: At least one of the blasting holes is a third blasting hole (53), and at least one of the blasting holes is a fourth blasting hole (54); The third blasting hole (53) and the fourth blasting hole (54) are both pointed from the mining working face (11) to the periodic pressure area (131), and the projections of the third blasting hole (53) and the fourth blasting hole (54) on the mining working face (11) are arranged between the projections of the first blasting hole (51) and the second blasting hole (52) on the mining working face (11).
8. The method for pre-splitting the coal mine roof according to claim 7, characterized in that: The projections of the center lines of the third blasting hole (53) and the fourth blasting hole (54) on the mining working face (11) gradually approach each other from bottom to top, and the projection of the center line of the third blasting hole (53) on the mining working face (11) forms a third angle A3 with the horizontal plane, and the third angle A3 is 45° to 60°; and / or The projection of the center line of the fourth blasting hole (54) on the mining working face (11) forms a fourth angle A4 with the horizontal plane, and the fourth angle A4 is 45° to 60°.
9. The method for pre-splitting roof in coal mining according to claim 8, characterized in that: The mining area (1) has a first side surface (14) arranged toward the first mining tunnel (2), and a projection of a center line of the third blasting hole (53) on the first side surface (14) forms a fifth angle A5 with a horizontal plane, and the fifth angle A5 is 45° to 60°; and / or The projection of the center line of the fourth blasting hole (54) on the first side surface (14) forms a sixth angle A6 with the horizontal plane, and the sixth angle A6 is 45° to 60°.
10. The method for pre-splitting roof in coal mining according to any one of claims 1 to 9, characterized in that: The historical mining data include geological sketch maps and statistical data on pressure step distances during the early period of coal mining.