Electrical equipment construction device and construction method thereof

By designing an electrical equipment construction device including ball screw, pressing seat and hydraulic pump, the existing steel bar straightening machine has solved the slip problem caused by small contact surface and large traction force, and achieved high-quality steel bar straightening , ensuring straightening accuracy and reducing wear.

CN118875173APending Publication Date: 2024-11-01LUOYANG COPPER(GRP) CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411017178.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

During the straightening process, the existing steel bar straightening machines have slipped from the steel bars and the straightening roller due to the small contact surface and large traction force, resulting in wear and straightening deviation.

Method used

An electrical equipment construction device was designed, using fixed box, hydraulic pump, ball screw, pressurized seat, double gear shaft and hydraulic motor, and the straightening block is driven to pressurize the steel bars through the ball screw and double gear shaft. and rotate, use hydraulic pumps and pistons for intermittent extrusion to increase contact area and clamping force to avoid slippage.

Benefits of technology

It effectively improves the straightening quality of the steel bars, reduces wear, ensures the straightening accuracy and linearity of the steel bars, and reduces wear during one-way pressurization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118875173A_ABST
    Figure CN118875173A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of electrical equipment, and discloses an electrical equipment construction device and a construction method thereof.The electrical equipment construction device comprises a fixed box and a hydraulic pump, ball screws are symmetrically and movably connected to the fixed box in a sleeving mode, ball sleeves are symmetrically and movably connected to the ball screws in a sleeving mode, and abutting bases are fixedly installed on the upper surfaces of the ball sleeves; and a hydraulic driving device is fixedly mounted on the back surface of the fixed box. The two straightening blocks are symmetrically arranged, and the arc grooves in the outer sides of the two straightening blocks are formed, so that the reinforcing steel bar is gradually straightened in the pressurizing process of the two straightening blocks, meanwhile, the straightening blocks wrap the straightening section of the reinforcing steel bar and continuously apply pressure, it is ensured that an unstraightened area and a straightened area do not interfere with each other, the straightening quality is ensured, and meanwhile when the reinforcing steel bar is straightened, the straightening efficiency is improved. And surface contact with the reinforcing steel bars is achieved through the arc grooves, the contact area with the reinforcing steel bars is increased, and the clamping force on the reinforcing steel bars is increased, so that the reinforcing steel bars are effectively pulled, and sliding, abrasion and influence on straightening precision are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electrical equipment, and in particular to an electrical equipment construction device and a construction method thereof. Background Art

[0002] In the process of construction, in order to strengthen the structural strength of the building, it is reinforced by steel bars. However, most of the steel bars are in the form of wire rods during manufacturing, processing and transportation. At the same time, they are often affected by various external forces, which causes the internal temperature to change and the internal force to increase or decrease. Therefore, the steel bars will be distorted or bent by the outside world. In the later use, a steel bar straightening machine is needed to straighten it for later use. However, the currently used steel bar straightening machines have some shortcomings, as follows:

[0003] The currently used rebar straightening machine has straightening rollers arranged at intervals above and below, so that the rebar passes between the upper and lower straightening rollers, so that the bending curvature of the rebar gradually decreases and then becomes straight. However, in this process, the straightening rollers not only need to press the rebars but also need to pull the rebars during straightening. However, the contact area between the rebars and the straightening rollers is too small. Although the upper and lower straightening rollers pressurize the rebars, during the pulling process, if the traction force required for the rebars is too large, relative slippage will still occur between the rebars and the straightening rollers, which will lead to wear on the surface of the straightening rollers, resulting in changes in the pressure on the rebars in the later stage, causing deviations in the straightening of the rebars. Summary of the invention

[0004] The present invention provides an electrical equipment construction device, which has the advantages of traction and high straightening quality, and solves the problems in the above-mentioned background technology.

[0005] The invention provides the following technical scheme: an electrical equipment construction device, comprising a fixed box and a hydraulic pump, the fixed box is symmetrically and movably sleeved with a ball screw, the ball screw is symmetrically and movably sleeved with a ball sleeve, the upper surface of the ball sleeve is fixedly installed with a pressure seat, a hydraulic drive device is fixedly installed on the back of the fixed box, the hydraulic drive device is transmission-connected with one end of the ball screw, two ends of the pressure seat are movably sleeved with a double gear shaft, the right part of the bottom surface of the pressure seat and below the double gear shaft are fixedly installed, the bottom end of the double gear shaft is fixedly connected to the output shaft of the hydraulic motor, two chains are symmetrically and movably clamped on the two double gear shafts, and straightening blocks are evenly and fixedly connected to the chains, the chains are two in a group, there are two groups in total, and they are symmetrically arranged front and back, and one group of two chains are respectively fixedly connected to the top and bottom of the inner side of the straightening block through pins.

[0006] Preferably, an arc groove is provided on the outer side surface of the straightening block, the angle of the arc groove is a, wherein 130≥a<180, and the diameter of the arc groove is the same as the diameter of the steel bar.

[0007] Preferably, the ball screw is symmetrically provided with thread grooves with opposite rotation directions.

[0008] Preferably, piston grooves are evenly formed inside the pressure seat and on one side close to the steel bar, a pressurizing piston is movably sleeved in the piston groove of the pressure seat, and the piston groove is connected to a hydraulic pump through a conduit.

[0009] Preferably, a supporting box is fixedly installed on the left part of the fixed box, the supporting box is square, and movable grooves are provided on the four sides of the supporting box. A hydraulic rod is movably connected to the supporting box and located in the movable groove, and the protruding end of the hydraulic rod is fixedly connected to a pre-adjusting block. The inner side surface of the pre-adjusting block is symmetrically provided with sliding grooves, and the top surface of the pre-adjusting block is provided with a blocking block, and the four pre-adjusting blocks are respectively connected to each other in sequence through the sliding grooves and the blocking blocks.

[0010] A construction method of an electrical equipment construction device, the steps of which are as follows:

[0011] S1, pre-straightening stage: one end of the coiled steel bar is passed through the pre-adjusting blocks, and then the hydraulic rod is extended by the hydraulic pump to press the pre-adjusting blocks to move. In this process, since the four pre-adjusting blocks are mutually limited, the pre-adjusting blocks gradually close the central square hole during movement, and the central square hole is proportionally reduced, thereby pressing the steel bars in the central square hole to pre-straighten the steel bars. After one pressing is completed, the pre-adjusting blocks are opened, and the straightening blocks pull the steel bars in the central square hole away to straighten them, and the pre-adjusting blocks press and pre-adjust the newly entered steel bars again;

[0012] S2, straightening stage: the straightening block rotates under the drive of the double gear shaft, bringing the steel bar into the arc groove of the straightening block, and the two straightening blocks on both sides of the steel bar pressurize the steel bar under the pressure of the pressure seat and the double gear shaft, so that the steel bar gradually straightens under the pressure of the two straightening blocks, and then passes through between the straightening blocks;

[0013] S3, pressurization stage: by rotating the ball screw, the symmetrically arranged ball sleeves drive the two pressure seats to move closer to the steel bars, thereby pressurizing the steel bars to straighten them. Subsequently, during the straightening process, the hydraulic pump pressure piston is retracted and reciprocated to intermittently squeeze the straightening block, thereby achieving multiple squeezing of the steel bars in turn and performing secondary pressing to adjust the curvature of the steel bars.

[0014] The present invention has the following beneficial effects:

[0015] 1. Through the symmetrical setting of two straightening blocks and the setting of the circular arc groove on their outer sides, the steel bars are gradually straightened under the pressure of the two straightening blocks. At the same time, the straightening blocks wrap the straightened sections of the steel bars and continuously apply pressure to ensure that the unstraightened areas do not interfere with the straightened areas, thereby ensuring the quality of straightening. At the same time, when the steel bars are straightened, the circular arc grooves are used to achieve surface contact with the steel bars, thereby increasing the contact area with the steel bars and increasing the clamping force on the steel bars, so as to effectively pull the steel bars and avoid slippage, which causes wear and affects the straightening accuracy.

[0016] 2. Through the setting of hydraulic rods and pre-adjusting blocks, before the steel bars enter the straightening block, they first pass through the center holes formed by the four pre-adjusting blocks, and then the hydraulic rod presses them, so that the four pre-adjusting blocks produce relative sliding and close toward the middle to press the steel bars, reduce the bending curvature of the steel bars, and pre-straighten them before entering the straightening block, reduce the straightening pressure of the straightening block on the steel bars, and limit the steel bars through the four pre-adjusting blocks, and apply pressure in four directions, so as to achieve all-round pre-adjustment of the steel bars, effectively reducing the wear of the straightening press during unidirectional pressurization. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0018] Figure 2 It is a partial cross-sectional schematic diagram of the overall structure of the present invention;

[0019] Figure 3 It is a bottom-up half-section schematic diagram of the structure of the present invention;

[0020] Figure 4 It is a top view half-section schematic diagram of the structure of the present invention;

[0021] Figure 5 This is a schematic diagram of the positions of the straightening block and the pressurizing piston of the structure of the present invention;

[0022] Figure 6 This is a schematic diagram of the ball screw structure of the present invention;

[0023] Figure 7 It is a schematic side view of the structure of the present invention;

[0024] Figure 8 This is a schematic diagram of the structural pre-adjustment block of the present invention.

[0025] In the figure: 1. fixed box; 2. ball screw; 3. ball sleeve; 4. hydraulic drive device; 5. pressure seat; 6. hydraulic motor; 7. double gear shaft; 8. chain; 9. straightening block; 10. pressurizing piston; 11. steel bar; 12. support box; 13. movable groove; 14. hydraulic rod; 15. pre-adjustment block. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] Embodiment 1

[0028] See also Figure 1-Figure 5, an electrical equipment construction device and a construction method thereof, comprising a fixed box 1 and a hydraulic pump, a ball screw 2 is symmetrically and movably sleeved on the fixed box 1, a ball sleeve 3 is symmetrically and movably sleeved on the ball screw 2, a pressing seat 5 is fixedly installed on the upper surface of the ball sleeve 3, a hydraulic drive device 4 is fixedly installed on the back of the fixed box 1, the hydraulic drive device 4 is transmission-connected to one end of the ball screw 2, a double gear shaft 7 is movably sleeved at both ends of the pressing seat 5, a double gear shaft 7 is fixedly installed on the right part of the bottom surface of the pressing seat 5 and below the double gear shaft 7, the bottom end of the double gear shaft 7 is fixedly connected to the output shaft of the hydraulic motor 6, and a chain is symmetrically and movably clamped on the two double gear shafts 7 Chain 8 is evenly and fixedly connected with straightening blocks 9, two chains 8 form a group, there are two groups in total, and they are symmetrically arranged front and back, one group of two chains 8 is respectively fixedly connected with the top and bottom of the inner side of the straightening block 9 by a pin shaft, one end of the bent steel bar 11 is inserted between the two straightening blocks 9, the straightening block 9 is driven by the double gear shaft 7 to rotate, and after the steel bar 11 enters the straightening block 9, the two straightening blocks 9 pressurize the steel bar, so that the steel bar 11 gradually straightens under the pressure of the two straightening blocks 9. In this process, since the straightening block 9 wraps the straightening section of the steel bar 11 and continuously applies pressure, the clamping force on the steel bar 11 is increased, so as to clamp the steel bar 11 1 is effectively pulled to avoid slippage, wear and tear, and affect the straightening accuracy; an arc groove is provided on the outer side of the straightening block 9, the angle of the arc groove is a, where 130≥a<180, the diameter of the arc groove is the same as the diameter of the steel bar 11, so that the steel bar 11 is located in the arc groove, and the steel bar 11 is limited and straightened to avoid the steel bar 11 shaking left and right, which affects the straightening efficiency. At the same time, the straightening block 9 realizes surface contact with the steel bar 11 through the arc groove, increases the contact area with the steel bar 11, further improves the friction force, and strengthens the traction effect; the ball screw 2 is symmetrically provided with thread grooves with opposite rotation directions, and then by setting a plurality of thread grooves on the same ball screw 2, the straightening block 9 can be directly pulled to the steel bar 11. Two sets of ball sleeves 3 are arranged to drive the pressing seat 5 to be close to each other, thereby driving the straightening block 9 to pressurize the steel bar 11, thereby enhancing the straightening effect of the steel bar 11; piston grooves are evenly provided inside the pressing seat 5 and on one side close to the steel bar 11, and a pressurizing piston 10 is movably sleeved in the piston groove of the pressing seat 5, and the piston groove is connected to the hydraulic pump through a conduit. When the straightening block 9 squeezes and straightens the steel bar 11, the pressurizing piston 10 can be retracted and reciprocated by the hydraulic pump to squeeze the straightening block 9 intermittently, and the steel bar 11 is squeezed multiple times in sequence, the curvature of the steel bar 11 is adjusted, the small bending of the steel bar 11 is eliminated, and the straightening effect of the steel bar 11 is increased;

[0029] Embodiment 2

[0030] See also Figure 6-Figure 8A support box 12 is fixedly installed on the left side of the fixed box 1. The support box 12 is square. The four sides of the support box 12 are provided with movable grooves 13. A hydraulic rod 14 is movably connected to the support box 12 and located in the movable groove 13. The protruding end of the hydraulic rod 14 is fixedly connected with a pre-adjusting block 15. The inner side of the pre-adjusting block 15 is symmetrically provided with sliding grooves. The top surface of the pre-adjusting block 15 is provided with a card block. The four pre-adjusting blocks 15 are respectively connected to each other in sequence through the sliding grooves and the card blocks. After the four pre-adjusting blocks 15 are spliced, a square through hole is formed in the center. When the steel bar 11 is transported to the construction site in a disc shape and needs to be straightened, its bending curvature is too large and it directly enters the straightening block 9, which is easy to cause Excessive extrusion and wear at the entrance causes damage to the straightening block 9, affecting the straightening effect. Therefore, before the steel bar 11 enters the straightening block 9, the steel bar 11 first passes through the center holes formed by the four pre-adjustment blocks 15, and then the hydraulic rod 14 presses, thereby generating relative slip between the four pre-adjustment blocks 15 and closing toward the middle to press the steel bar 11, thereby reducing the bending curvature of the steel bar 11, so that it can be pre-straightened before entering the straightening block 9, reducing the straightening pressure of the straightening block 9 on the steel bar 11, and limiting the steel bar 11 through the four pre-adjustment blocks 15, and applying pressure in four directions, thereby realizing all-round pre-adjustment of the steel bar 11, effectively reducing wear during unidirectional pressurization.

[0031] Working principle:

[0032] 1. Pre-straightening stage: one end of the coiled steel bar 11 is passed through the pre-adjusting blocks 15, and then the hydraulic rod 14 is extended by the hydraulic pump to press the pre-adjusting block 15 to move. In this process, since the four pre-adjusting blocks 15 are mutually limited, the pre-adjusting block 15 gradually closes the central square hole during movement, and the central square hole is proportionally reduced, thereby pressing the steel bar 11 in the central square hole to pre-straighten the steel bar 11. After one pressing is completed, the pre-adjusting block 15 is opened, and at this time the straightening block 9 pulls the steel bar 11 located in the central square hole away for straightening, and the pre-adjusting block 15 presses and pre-adjusts the newly entered steel bar 11 again;

[0033] 2. Straightening stage: The straightening block 9 rotates under the drive of the double gear shaft 7, bringing the steel bar 11 into the arc groove of the straightening block 9. The two straightening blocks 9 on both sides of the steel bar 11 pressurize the steel bar under the pressure of the pressing seat 5 and the double gear shaft 7, so that the steel bar 11 gradually straightens under the pressure of the two straightening blocks 9, and then passes through between the straightening blocks 9;

[0034] 3. Pressurization stage: by rotating the ball screw 2, the symmetrically arranged ball sleeves 3 drive the two pressure seats 5 to move closer to the steel bar 11, thereby pressurizing the steel bar 11 to straighten it. Subsequently, during the straightening process, the hydraulic pump pressure piston 10 is retracted and reciprocated to intermittently squeeze the straightening block 9, and the steel bar 11 is squeezed multiple times in turn, and a secondary pressure is performed to adjust the curvature of the steel bar 11.

[0035] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An electrical equipment construction device, comprising a fixing box (1) and a hydraulic pump, Features: A ball screw (2) is symmetrically and movably sleeved on the fixed box (1), a ball sleeve (3) is symmetrically and movably sleeved on the ball screw (2), a pressure seat (5) is fixedly installed on the upper surface of the ball sleeve (3), a hydraulic drive device (4) is fixedly installed on the back of the fixed box (1), the hydraulic drive device (4) is transmission-connected to one end of the ball screw (2), two ends of the pressure seat (5) are movably sleeved with double gear shafts (7), and the right part of the bottom surface of the pressure seat (5) is A double gear shaft (7) is fixedly installed below the double gear shaft (7), the bottom end of the double gear shaft (7) is fixedly connected to the output shaft of the hydraulic motor (6), two chains (8) are symmetrically and movably connected on the two double gear shafts (7), and a straightening block (9) is evenly and fixedly connected on the chain (8), two chains (8) form a group, there are two groups in total, and they are symmetrically arranged front and back, and the two chains (8) in one group are respectively fixedly connected to the top and bottom of the inner side of the straightening block (9) through a pin shaft.

2. An electrical equipment construction device according to claim 1, Features: The outer side surface of the straightening block (9) is provided with an arc groove, the angle of the arc groove is a, wherein 130≥a<180, and the diameter of the arc groove is the same as the diameter of the steel bar (11).

3. An electrical equipment construction device according to claim 1, Features: The ball screw (2) is symmetrically provided with thread grooves with opposite rotation directions.

4. An electrical equipment construction device according to claim 1, Features: A piston groove is evenly formed inside the pressure seat (5) and on one side close to the steel bar (11), a pressurizing piston (10) is movably sleeved in the piston groove of the pressure seat (5), and the piston groove is connected to a hydraulic pump through a conduit.

5. An electrical equipment construction device according to claim 1, Features: A support box (12) is fixedly installed on the left side of the fixed box (1), the support box (12) is square, and movable grooves (13) are provided on four sides of the support box (12). A hydraulic rod (14) is movably connected to the support box (12) and located in the movable groove (13). The protruding end of the hydraulic rod (14) is fixedly connected to a pre-adjusting block (15), and the inner side surface of the pre-adjusting block (15) is symmetrically provided with sliding grooves, and the top surface of the pre-adjusting block (15) is provided with a clamping block, and the four pre-adjusting blocks (15) are respectively connected to each other in sequence through the sliding grooves and the clamping blocks.

6. A construction method for an electrical equipment construction device according to any one of claims 1 to 5, wherein the steps are as follows: S1, pre-straightening stage: one end of the coiled steel bar (11) is passed through the pre-adjusting blocks (15), and then the hydraulic rod (14) is extended by the hydraulic pump to press the pre-adjusting block (15) to move. In this process, since the four pre-adjusting blocks (15) are mutually limited, the pre-adjusting block (15) gradually closes the central square hole during the movement, and the central square hole is proportionally reduced, thereby pressing the steel bar (11) in the central square hole to pre-straighten the steel bar (11). After the pressing is completed, the pre-adjusting block (15) is opened, and the straightening block (9) pulls the steel bar (11) in the central square hole away to straighten it, and the pre-adjusting block (15) presses and pre-adjusts the newly entered steel bar (11) again; S2, straightening stage: the straightening block (9) rotates under the drive of the double gear shaft (7), bringing the steel bar (11) into the arc groove of the straightening block (9), and the two straightening blocks (9) on both sides of the steel bar (11) pressurize the steel bar under the pressure of the pressure seat (5) and the double gear shaft (7), so that the steel bar (11) gradually straightens under the pressure of the two straightening blocks (9), and then passes through between the straightening blocks (9); S3, pressurizing stage: by rotating the ball screw (2), the symmetrically arranged ball sleeves (3) drive the two pressing seats (5) to approach the steel bar (11), thereby pressurizing the steel bar (11) and straightening it. Subsequently, during the straightening process, the hydraulic pump pressurizing piston (10) is telescopically moved back and forth to intermittently press the straightening block (9), thereby successively achieving multiple squeezing of the steel bar (11) and performing secondary pressing, thereby adjusting the curvature of the steel bar (11).

Citation Information

Patent Citations

  • Pre-adjusting traction device of double-wire rib machine

    CN209349419U