Upstroke type integrated bridge building machine suitable for portal pier cast-in-place beam and construction method
By designing a variety of leg structures and intelligent vibration devices on the bridge building machine, the transportation and installation problems of steel bar parts in the existing technology are solved, and the direct overall lifting and efficient construction of steel bar parts are realized, and the construction efficiency and quality are improved.
Patent Information
- Application Number
- CN202410942516.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-01
AI Technical Summary
When existing bridge building machines transport and install reinforced bar parts, it is difficult to achieve overall lifting and quality assurance, and reinforced bar parts are prone to deform when changing the conveying method, affecting construction efficiency and quality.
An upstream integrated bridge building machine including main beam, walking guide area, concrete pouring steaming area and feeding and molding maintenance area was designed, using front legs, middle legs, rear legs and auxiliary legs. Structure ensures that the steel bar parts can be transported directly into the formwork as a whole, and improves construction efficiency and quality through deployable auxiliary legs and intelligent vibration devices.
It realizes direct overall transportation and efficient lifting of steel bar parts, reduces operating time, improves construction efficiency and mold quality, and ensures the overall processing advantages and quality stability of steel bar parts.
Smart Images

Figure CN118880739A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of bridge construction equipment, in particular to an upward integrated bridge-building machine suitable for cast-in-place beams of gate-type piers and a construction method. Background Art
[0002] A mobile bridge-building machine is a kind of equipment that comes with its own formwork and can use piers as supports to cast-in-place bridges. During cast-in-place construction, workers usually need to tie steel bars in the external formwork system. There are more than 10,000 steel bar tying nodes for each span of cast-in-place beams. The tying workload is large, the labor intensity is high, and the construction risk is high. In the prior art, mechanized and intelligent technologies for producing steel bar components have been introduced. For example, our company's technology CN112404316A is a concrete segment beam steel bar processing production line based on steel bar components, which can produce steel bar components in an industrialized, mechanized and automated manner, greatly improving the production efficiency of steel bar components. There are also some bridge-building machines in the prior art, such as CN111996916A, a cast-in-place box girder integrated construction equipment and construction method, or CN112112075A, a self-propelled cast-in-place box girder integrated bridge-building machine. The problem with these devices is that since the legs of the bridge-building machine are supported on the side walls of the box girder, the width between the legs is smaller than the width of the steel bar components, making it difficult to transport the steel bar components into the formwork. If the steel bar components need to be disassembled, transported to the formwork and then spliced, the advantages of the overall processing of the steel bar components cannot be demonstrated, and the overall quality of the steel bar components is difficult to guarantee. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide an upward integrated bridge-building machine and a construction method suitable for cast-in-place beams of portal piers, which can ensure that the steel bar components do not need to change the transportation method and can be directly hoisted into the template as a whole. The operation and hole-passing are convenient, and deformation of the steel bar components can be avoided during the process of changing the transportation method and changing the lifting point.
[0004] In order to solve the above technical problems, the technical solution of the present invention is: an upward integrated bridge-building machine suitable for cast-in-place beams of portal piers, comprising a main beam, wherein the main beam is provided with a material loading and demoulding curing area, a concrete pouring and steaming curing area and a walking guide area in sequence along the bridge direction; At least two cranes are arranged on the main beam and travel along the main beam; A front guide beam is provided in the walking guide area, and a front support leg is provided at the end of the free end of the front guide beam; Middle legs and rear legs are provided in the concrete pouring and steaming area; A second auxiliary leg and a first auxiliary leg are provided in the loading, demoulding and curing area. The second auxiliary leg and the first auxiliary leg adopt an avoidable structure so that the steel bar components can be directly transported to the outer formwork system in the concrete pouring and steaming area.
[0005] In a preferred solution, the second auxiliary leg and the first auxiliary leg are supported at a position of the cast beam close to the side wall of the beam, the legs of the second auxiliary leg and the first auxiliary leg are hingedly connected to the main beam, mounting seats are provided on the outer sides of the legs and the main beam, and the leg folding cylinder is connected to the mounting seat to drive the second auxiliary leg and the first auxiliary leg to unfold or lower, and when the second auxiliary leg or the first auxiliary leg is unfolded, the steel bar component can pass under the second auxiliary leg or the first auxiliary leg.
[0006] In a preferred solution, two connection points are provided between the second auxiliary supporting leg and the first auxiliary supporting leg and the main beam, which are respectively a hinged connection by a rotating pin on the outer side and a removal connection by a movable pin on the inner side.
[0007] In a preferred solution, each leg of the second auxiliary leg and the first auxiliary leg adopts a double leg unit structure, and each leg unit corresponds to a rotating pin or a movable pin respectively; A liftable structure is provided at the bottom of each leg unit.
[0008] In the preferred solution, liftable leg lifting piers are provided on both sides of the top of the rear legs, leg guide rail seats are provided on the inner sides of the leg lifting piers, and walking guide rails are provided at the bottom of the main beam. When the leg lifting piers are lowered, the leg guide rail seats are slidably connected with the walking guide rails. In a preferred solution, the second auxiliary supporting leg, the first auxiliary supporting leg and the rear supporting leg are supported on the cast beam, and the middle supporting leg and the front supporting leg are supported on the gate-shaped pier.
[0009] In a preferred solution, a carriage track is provided on the cross beam fixedly connected to the main beam, and the carriage is movably arranged on the carriage track; There are at least two groups of cranes, distributed along the direction of the bridge. Each group of cranes has two cranes, located on both sides of the main beam, close to the side walls of the cast beam.
[0010] In the preferred solution, a placing machine and an intelligent vibrating device are provided in the concrete pouring and steaming area.
[0011] In a preferred solution, a suspension beam is provided in the concrete pouring and steaming area, the outer mold system is connected to the suspension beam, and the mold erection or demoulding operation is completed by the lateral movement of the outer mold system.
[0012] In a preferred solution, cross beams are provided on both sides of the main beam, the top of the suspension beam is slidably connected to the cross beam, and a traction device is provided between the suspension beam and the cross beam to pull the suspension beam to move laterally; The outer formwork system is located inside the suspension beams on both sides.
[0013] In a preferred solution, the steel bar component is a complete steel bar component of a segment beam, and the inner mold is installed inside the steel bar component; When erecting the formwork, one end of the hanger is connected to the crossbeam, and the other end passes through the external formwork system and is connected to the suspension beam.
[0014] A construction method using the above-mentioned upward integrated bridge-building machine is characterized by comprising the following steps: S1. After the bridge-building machine moves to its position, it is supported by the middle outrigger and the rear outrigger, of which the rear outrigger is supported on the cast beam and the middle outrigger is supported on the gate-shaped pier; S2, produce the whole section of steel bar parts behind the bridge construction machine, and complete the assembly of steel bar parts, inner molds and prestressed pipes; S3, transport the steel bar components to the rear end of the bridge construction machine by using a beam transport vehicle; S4. Expand the second auxiliary leg to transport the steel bar components to the loading, demoulding and curing area; S5. Lower the second auxiliary outrigger, unfold the first auxiliary outrigger, hoist the rear outrigger to the position of the middle outrigger, connect the crane to the steel bar component, and lift the steel bar component off the beam transport vehicle; S6. At the concrete pouring and steaming area, the crane hoists the steel bar components into the outer formwork system in a way that the front is low and the back is high, and the steel bar components are accurately positioned and fixed in the outer formwork system; S7, hoist the rear outrigger back to the top of the poured beam, lift and support the rear outrigger, and the bridge-building machine is now supported by the middle outrigger and the rear outrigger; S8, pouring concrete into the outer formwork system through a concrete placing boom and vibrating the concrete; S9, the second auxiliary outrigger is deployed, and the beam transport vehicle withdraws; S10. After demoulding, the bridge-building machine moves to the next portal pier and continues the pouring construction.
[0015] In the preferred solution, the middle legs and the rear legs are slidably connected to the main beam, and a traction device is provided between the middle legs and the rear legs and the main beam to traction the main beam to move; The middle outrigger and the rear outrigger pull the main beam to the next portal pier until the front outrigger falls on the portal pier, and then the middle outrigger is hoisted to the next portal pier by the crane, and the rear outrigger moves to the next cast beam, thus completing the movement of the bridge-building machine through the hole.
[0016] In the preferred solution, after the bridge-building machine moves into place, the traction device pulls the suspension beam to move to the middle of the beam, installs the template anti-misalignment anchor, checks the pre-arch of the bottom template of the outer template system, and adjusts it; checks the pre-arch of the top template, and adjusts it.
[0017] In the preferred solution, during pouring, multiple placing machines are used for placing materials, an intelligent vibrating device is used to vibrate the side walls of the beams, and manual vibration is used for the bottom plate and top plate.
[0018] In the preferred solution, the intelligent vibrating device can move along the longitudinal direction of the bridge and has a retractable structure. A gravity detection sensor, a travel sensor and a visual sensor are provided on the intelligent vibrating device; When vibrating the side wall of the beam, the visual sensor is used to detect the position of the opening on the outer mold system, the intelligent vibrating device moves to the top of the opening, the vibrating rod of the intelligent vibrating device falls, the stroke sensor feeds back the falling stroke, and the gravity detection sensor determines the depth position of the vibrating rod and whether it is blocked by steel bars. If it is detected that it is blocked by steel bars, the vibrating rod is lifted and moved a certain distance before continuing to vibrate.
[0019] In the preferred solution, the gravity detection sensor feeds back the gravity change of the vibrating rod. As the gravity change slows down, it is judged that the vibrating rod is in contact with the concrete, and the vibration time is started. After the preset vibration time is reached, the intelligent vibrating device moves to the next vibrating station to continue vibrating. If the gravity detection sensor reports that the gravity of the vibrating rod is greatly reduced and this trend does not change after a period of time, it is determined that the vibrating rod is in contact with the steel bar and is blocked by the steel bar. At this time, the timing is stopped, the vibrating rod is lifted and moved to a nearby position and then lowered again. When the vibrating rod starts working again nearby, the vibration time is recalculated.
[0020] In the preferred solution, the poured beams are steam-cured with formwork in the concrete pouring and steam-curing area; When curing with formwork, supply positive pressure steam or steam with alternating positive and negative pressures; After demoulding, the cast beams are demoulded and steamed in the material loading and demoulding curing area.
[0021] The present invention provides an upward integrated bridge-building machine and a construction method suitable for cast-in-place beams of portal piers, which have the following technical advantages compared with the prior art: 1. The present invention adopts a structure supported by front legs, middle legs, rear legs and two groups of auxiliary legs to ensure reliable force and convenient and safe operation when passing through holes.
[0022] 2. The present invention adopts a structure of deployable auxiliary legs and rear legs that can be quickly disassembled and assembled, so that the steel bar components can be directly transported as a whole into the outer mold of the formwork, greatly reducing the operation time in the formwork and improving the construction efficiency and the quality of the formwork.
[0023] 3. The structure of the rear legs provided in the present invention facilitates relative sliding with the main beam, can improve the supporting effect, and can conveniently move the rear legs to the position of the middle legs to avoid steel bar components.
[0024] 4. The auxiliary legs adopt a double hinge pin structure, which can ensure sufficient supporting force while being flexible to avoid.
[0025] 5. The intelligent vibrating device provided in the present invention can further improve the construction efficiency, especially improve the vibration construction efficiency of the box girder side wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 It is a side view of the bridge-building machine of the present invention.
[0027] Figure 2 It is a side view of the bridge-building machine of the present invention in the initial state.
[0028] Figure 3 It is a structural schematic diagram of the auxiliary legs of the bridge-building machine of the present invention.
[0029] Figure 4 It is a side view of the bridge-building machine of the present invention when steel bars are fed into the machine.
[0030] Figure 5 It is a schematic diagram of the structure of the bridge-building machine of the present invention when the auxiliary legs are unfolded.
[0031] Figure 6 It is a side view of the bridge-building machine of the present invention when the steel bar component passes over the second auxiliary support leg.
[0032] Figure 7 It is a schematic cross-sectional view of the bridge-building machine of the present invention when the steel bar components are hoisted.
[0033] Figure 8 It is a side view of the steel bar components of the bridge-building machine of the present invention being hoisted high and low into the casting bin.
[0034] Fig. 9 It is a cross-sectional schematic diagram of the steel bar components of the bridge-building machine of the present invention being hoisted into a casting bin.
[0035] Fig.10 It is a side view of the positioning of the steel bar components of the bridge-building machine of the present invention in the outer mold system.
[0036] Fig.11 It is a schematic cross-sectional view of the steel bar components of the bridge-building machine of the present invention when positioned in the outer mold system.
[0037] Fig.12 It is a schematic diagram of the structure of the bridge-building machine of the present invention when passing through a hole.
[0038] Fig.13 It is a schematic cross-sectional view of the outer mold system of the bridge-building machine of the present invention when demoulding.
[0039] In the figure: crane 1, main beam 2, walking guide rail 201, ceiling 3, placing machine 4, beam transport vehicle 5, steel bar component 6, first auxiliary outrigger 7, rear outrigger 8, outrigger lifting pier 81, outrigger guide rail seat 82, door pier 9, suspension beam 10, intelligent vibrating device 11, middle outrigger 12, front outrigger 13, second auxiliary outrigger 14, front guide beam 15, outrigger folding cylinder 16, cast beam 17, movable pin 18, rotating pin 19, traction device 20, cross beam 21, outer mold system 22, hanger 23, loading and demoulding curing area A, concrete pouring and steaming curing area B, walking guide area C. DETAILED DESCRIPTION
[0040] Embodiment 1: like Figure 1 , 2 In the invention, an upward integrated bridge-building machine suitable for cast-in-place beams of portal piers comprises a main beam 2, and the main beam 2 is provided with a loading and demoulding curing area A, a concrete pouring and steaming curing area B and a walking guide area C in sequence along the bridge direction; the loading and demoulding curing area A is used to cure the cast-in-place beams after demoulding, and preferably, a mobile shed is used to steam-cure the cast-in-place beams during curing; the concrete pouring and steaming curing area B is used to erect molds, place steel bar components, pour and steam-cure with molds, and the walking guide area C is provided with a front guide beam 15, and a front support leg 13 is provided at the end of the front guide beam 15, which is used to fall on the next portal pier 9 and guide the main beam to pass through the hole.
[0041] At least two cranes 1 are provided on the main beam 2 and move along the main beam 2 ; preferably, the cranes 1 are divided into two groups, one group is arranged at the front and one group is arranged at the rear, each group has two cranes 1 , and four cranes 1 are used to lift the steel bar components 6 .
[0042] A front guide beam 15 is provided in the walking guide area C, and a front support leg 13 is provided at the free end of the front guide beam 15; A middle support leg 12 and a rear support leg 8 are provided in the concrete pouring and steam curing area B; A second auxiliary leg 14 and a first auxiliary leg 7 are provided in the loading, demoulding and curing area A. The second auxiliary leg 14 and the first auxiliary leg 7 adopt an avoidable structure so that the steel bar component 6 can be directly transported to the outer mold system 22 of the concrete pouring and steaming area B.
[0043] In the preferred solution, the second auxiliary leg 14 and the first auxiliary leg 7 are supported on the cast beam 17 near the side wall of the beam, the legs of the second auxiliary leg 14 and the first auxiliary leg 7 are hingedly connected to the main beam 2, and mounting seats are provided on the outer sides of the legs and the main beam 2. The leg folding cylinder 16 is connected to the mounting seat and the main beam 2 to drive the second auxiliary leg 14 and the first auxiliary leg 7 to unfold or lower. When the second auxiliary leg 14 or the first auxiliary leg 7 is unfolded, the steel bar component 6 can pass under the second auxiliary leg 14 or the first auxiliary leg 7.
[0044] The preferred solution is Figure 5 In the embodiment, two connection points are arranged between the second auxiliary leg 14 and the first auxiliary leg 7 and the main beam 2, namely, the outer rotating pin 19 is hingedly connected, and the inner movable pin 18 is removed and connected. That is, when the second auxiliary leg 14 and the first auxiliary leg 7 need to be unfolded, the inner movable pin 18 is first removed, and then the leg folding cylinder 16 drives the second auxiliary leg 14 and the first auxiliary leg 7 to unfold.
[0045] The preferred solution is Figure 5 In the embodiment, each leg of the second auxiliary leg 14 and the first auxiliary leg 7 adopts a double leg unit structure, and each leg unit corresponds to the rotating pin 19 or the movable pin 18 respectively; A liftable structure is provided at the bottom of each leg unit, and the liftable structure is a screw jack or a hydraulic jack.
[0046] The preferred solution is Fig.11 , 13 In the middle, both sides of the top of the rear leg 8 are provided with liftable leg lifting piers 81, the inner side of the leg lifting piers 81 is provided with a leg guide rail seat 82, and the bottom of the main beam 2 is provided with a walking guide rail 201. When the leg lifting piers 81 are lowered, the leg guide rail seat 82 is slidably connected with the walking guide rail 201; The preferred solution is Figure 3 In the embodiment, the second auxiliary leg 14, the first auxiliary leg 7 and the rear leg 8 are supported on the cast beam 17. Figure 1 The middle leg 12 and the front leg 13 are supported on the gate-shaped pier 9.
[0047] The preferred solution is Figure 6 , 9 In the embodiment, a traveling track is provided on a crossbeam fixedly connected to the main beam 2, and the traveling vehicle 1 is movably arranged on the traveling track; There are at least two groups of cranes, which are distributed along the longitudinal direction of the bridge. Each group of cranes 1 has two cranes, which are located on both sides of the main beam 2, close to the side walls of the cast beam 17 on both sides.
[0048] The preferred solution is Figure 1 , 2 In , 4, 6, and 8, a concrete placing machine 4 and an intelligent vibrating device 11 are provided in the concrete pouring and steaming area B. The concrete placing machine 4 is used to transport concrete for pouring, and the intelligent vibrating device 11 is used to vibrate in the bin.
[0049] The preferred solution is Figure 1 , 9 In the embodiment, a suspension beam 10 is provided in the concrete pouring and steaming area B, an outer mold system 22 is connected to the suspension beam 10, and the mold erecting or demoulding operation is completed by the lateral movement of the outer mold system 22.
[0050] The preferred solution is Fig. 9 In the embodiment, cross beams 21 are provided on both sides of the main beam 2, the top of the suspension beam 10 is slidably connected to the cross beam 21, and a traction device 20 is provided between the suspension beam 10 and the cross beam 21 to pull the suspension beam 10 to move laterally; The outer mold system 22 is located inside the suspension beams 10 on both sides.
[0051] The preferred solution is Figure 8 , 10 In the embodiment, the steel bar component 6 is a complete steel bar component of a segment beam, and the inner mold is installed inside the steel bar component 6; When the mold is erected, one end of the suspension rod 23 is connected to the cross beam 21 , and the other end passes through the outer mold system 22 and is connected to the suspension beam 10 .
[0052] Embodiment 2: like Figures 2~13 A construction method using the above-mentioned upward integrated bridge-building machine comprises the following steps: S1. After the bridge-building machine moves to its position, it is supported by the middle leg 12 and the rear leg 8, wherein the rear leg 8 is supported on the cast beam 17, and the middle leg 12 is supported on the gate-shaped pier 9; S2. Behind the bridge-building machine, Figure 1 The position on the middle left side produces the full-segment steel bar component 6, completing the assembly of the steel bar component, inner mold and prestressed pipe; S3, using the beam transport vehicle 5 to transport the steel bar component 6 to the rear end of the bridge construction machine; S4, unfold the second auxiliary legs 14 to facilitate the passage of the steel bar component 6, and the beam transport vehicle 5 transports the steel bar component 6 to the loading and demoulding curing area A; S5, lower the second auxiliary leg 14, unfold the first auxiliary leg 7, and hoist the rear leg 8 to the position of the middle leg 12 by the crane 1. The crane 1 is connected to the steel bar component 6, and the steel bar component 6 is lifted off the beam transport vehicle 5; S6. At the concrete pouring and steaming area B, the crane 1 hoists the steel bar component 6 into the outer mold system 22 in a manner of hoisting from low at the front to high at the back, and accurately positions and fixes the steel bar component 6 in the outer mold system 22; S7, hoist the rear leg 8 back to the top of the cast beam 17, lift and support the rear leg 8, and the bridge-building machine is now supported by the middle leg 12 and the rear leg 8; S8, pouring concrete into the outer mold system 22 between the inner mold and the outer mold through the concrete placing machine 4, and vibrating; S9, the second auxiliary legs 14 are unfolded, and the beam transport vehicle 5 exits; S10, after demoulding, the bridge construction machine moves to the next portal pier 9 and continues the pouring construction.
[0053] In the preferred solution, the middle leg 12 and the rear leg 8 are slidably connected to the main beam 2, and a traction device is provided between the middle leg 12 and the rear leg 8 and the main beam 2 to traction the main beam 2 to move; The middle leg 12 and the rear leg 8 pull the main beam 2 to move to the next portal pier 9 until the front leg 13 falls on the portal pier 9, and then the middle leg 12 is hoisted to the next portal pier 9 by the crane 1, and the rear leg 8 is moved to the next cast beam 17, thus completing the movement of the bridge-building machine through the hole.
[0054] The preferred solution is Fig. 9 In the process, after the bridge construction machine moves into place, the traction device 20 pulls the suspension beam 10 to move to the middle of the cross beam 21, installs the template anti-misalignment anchor, checks the bottom template pre-arch of the outer template system 22, and adjusts it; checks the top template pre-arch, and adjusts it.
[0055] The preferred solution is Fig.10 During pouring, multiple placing machines 4 are used for placing materials, an intelligent vibrating device 11 is used to vibrate the side walls of the beam, and manual vibration is used for the bottom plate and the top plate.
[0056] The preferred solution is Fig.11 In the embodiment, the intelligent vibrating device 11 can move along the longitudinal direction of the bridge and has a retractable structure. A gravity detection sensor, a travel sensor and a visual sensor are provided on the intelligent vibrating device 11; When vibrating the side wall of the beam, the visual sensor is used to detect the position of the opening on the outer mold system 22, the intelligent vibrating device 11 moves to the top of the opening, the vibrating rod of the intelligent vibrating device 11 falls, and the stroke sensor feeds back the falling stroke. The depth position of the vibrating rod is determined according to the gravity detection sensor, and whether it is blocked by steel bars. If it is detected that it is blocked by steel bars, the vibrating rod is lifted and moved a certain distance before continuing to vibrate.
[0057] In the preferred solution, the gravity detection sensor feeds back the gravity change of the vibrating rod. Due to the buoyancy of the concrete, as the gravity change slows down, it is judged that the vibrating rod is in contact with the concrete, and the vibration time is started. After the preset vibration time is reached, the intelligent vibrating device 11 moves to the next vibrating station to continue vibrating. If the gravity detection sensor reports that the gravity of the vibrating rod is greatly reduced and this trend does not change after a period of time, it is determined that the vibrating rod is in contact with the steel bar and is blocked by the steel bar. At this time, the timing is stopped, the vibrating rod is lifted and moved to a nearby position and then lowered again. When the vibrating rod starts working again nearby, the vibration time is recalculated.
[0058] The preferred solution is Figures 10 to 13 In the middle, the poured beam 17 is steam-cured with formwork in the concrete pouring and steam-curing area B; When curing with formwork, positive pressure steam or steam with alternating positive and negative pressure is supplied to allow steam to penetrate into the tiny gaps in the concrete to improve the hydration effect of the concrete. After demolding, the cast beam 17 is subjected to demolding steam curing in the material loading and demolding curing area A.
[0059] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. An upward integrated bridge-building machine suitable for cast-in-place beams of portal piers, characterized by: The main beam (2) is provided with a material loading and demoulding curing area (A), a concrete pouring and steam curing area (B) and a walking guide area (C) in sequence along the longitudinal direction of the bridge; At least two cranes (1) are provided on the main beam (2) and travel along the main beam (2); A front guide beam (15) is provided in the walking guide area (C), and a front support leg (13) is provided at the end of the free end of the front guide beam (15); A middle support leg (12) and a rear support leg (8) are provided in the concrete pouring and steam curing area (B); A second auxiliary support leg (14) and a first auxiliary support leg (7) are provided in the material loading, demoulding and curing area (A). The second auxiliary support leg (14) and the first auxiliary support leg (7) adopt an avoidable structure so that the steel bar component (6) can be directly transported to the outer mold system (22) of the concrete pouring and steaming curing area (B).
2. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: The second auxiliary leg (14) and the first auxiliary leg (7) are supported at positions of the cast beam (17) close to the beam side wall. The legs of the second auxiliary leg (14) and the first auxiliary leg (7) are hingedly connected to the main beam (2). A mounting seat is provided on the outer sides of the legs and the main beam (2). The leg folding cylinder (16) is connected to the mounting seat to drive the second auxiliary leg (14) and the first auxiliary leg (7) to unfold or fold. When the second auxiliary leg (14) or the first auxiliary leg (7) is unfolded, the steel bar component (6) can pass under the second auxiliary leg (14) or the first auxiliary leg (7).
3. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: Two connection points are provided between the second auxiliary support leg (14) and the first auxiliary support leg (7) and the main beam (2), which are respectively a hinged connection by a rotating pin (19) on the outside and a movable pin (18) on the inside.
4. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 3 is characterized in that: Each leg of the second auxiliary leg (14) and the first auxiliary leg (7) adopts a double leg unit structure, and each leg unit corresponds to a rotating pin (19) or a movable pin (18); A liftable structure is provided at the bottom of each leg unit.
5. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: Liftable leg lifting piers (81) are provided on both sides of the top of the rear leg (8), a leg guide rail seat (82) is provided on the inner side of the leg lifting pier (81), and a walking guide rail (201) is provided at the bottom of the main beam (2); when the leg lifting pier (81) is lowered, the leg guide rail seat (82) is slidably connected to the walking guide rail (201).
6. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to any one of claims 1 to 5, characterized in that: The second auxiliary supporting leg (14), the first auxiliary supporting leg (7) and the rear supporting leg (8) are supported on the cast beam (17), and the middle supporting leg (12) and the front supporting leg (13) are supported on the gate-shaped pier (9).
7. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: A carriage track is provided on a crossbeam fixedly connected to the main beam (2), and the carriage (1) is movably arranged on the carriage track; There are at least two groups of cranes, which are distributed along the longitudinal direction of the bridge. Each group of cranes (1) has two cranes, which are respectively located on both sides of the main beam (2) and close to the side walls of the cast beam (17).
8. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: A concrete placing machine (4) and an intelligent vibrating device (11) are provided in the concrete pouring and steaming area (B).
9. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 or 7, characterized in that: The concrete pouring and steaming area (B) is provided with a suspension beam (10), the outer mold system (22) is connected to the suspension beam (10), and the mold erection or demoulding operation is completed by lateral movement of the outer mold system (22).
10. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 8 is characterized in that: Cross beams (21) are provided on both sides of the main beam (2), the top of the suspension beam (10) is slidably connected to the cross beam (21), and a traction device (20) is provided between the suspension beam (10) and the cross beam (21) to traction the suspension beam (10) to move horizontally; The outer mold system (22) is located inside the suspension beams (10) on both sides respectively.
11. The upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 1 is characterized in that: The steel bar component (6) is a complete steel bar component of a segment beam, and the inner mold is installed inside the steel bar component (6); When the mold is erected, one end of the suspension rod (23) is connected to the crossbeam (21), and the other end passes through the outer mold system (22) and is connected to the suspension beam (10).
12. A construction method using the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to any one of claims 1 to 11, characterized in that The following steps are involved: S1. After the bridge-building machine moves to the right position, it is supported by the middle legs (12) and the rear legs (8), wherein the rear legs (8) are supported on the cast beams (17), and the middle legs (12) are supported on the gate-shaped piers (9); S2, producing the steel bar parts (6) of the whole section at the rear of the bridge-building machine, and completing the assembly of the steel bar parts, inner molds and prestressed pipes; S3, using a beam transport vehicle (5) to transport the steel bar component (6) to the rear end of the bridge construction machine; S4, unfolding the second auxiliary support leg (14) to transport the steel bar component (6) to the loading, demoulding and curing area (A); S5, lowering the second auxiliary leg (14), unfolding the first auxiliary leg (7), lifting the rear leg (8) to the position of the middle leg (12) by the crane (1), connecting the crane (1) with the steel bar component (6), and lifting the steel bar component (6) off the beam transport vehicle (5); S6. At the concrete pouring and steam curing area (B), the crane (1) hoists the steel bar component (6) into the outer mold system (22) in a manner of hoisting from low to high at the front, and accurately positions and fixes the steel bar component (6) in the outer mold system (22); S7, hoisting the rear outrigger (8) back to the top of the poured beam (17), lifting and supporting the rear outrigger (8), at which time the bridge-building machine is supported by the middle outrigger (12) and the rear outrigger (8); S8, pouring concrete into the outer formwork system (22) through the concrete placing machine (4), and vibrating the concrete; S9, the second auxiliary support leg (14) is unfolded, and the beam transport vehicle (5) withdraws; S10, after demoulding, the bridge construction machine moves to the next portal pier (9) and continues the pouring construction.
13. The construction method of the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 12, characterized in that: The middle supporting leg (12) and the rear supporting leg (8) are slidably connected to the main beam (2), and a traction device is provided between the middle supporting leg (12), the rear supporting leg (8) and the main beam (2) for traction of the main beam (2) to move; The middle outrigger (12) and the rear outrigger (8) pull the main beam (2) to move toward the next portal pier (9) until the front outrigger (13) falls on the portal pier (9), and then the middle outrigger (12) is hoisted to the next portal pier (9) by the crane (1), and the rear outrigger (8) is moved to the next cast beam (17), thus completing the through-hole movement of the bridge construction machine.
14. The construction method of the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 12, characterized in that: After the bridge construction machine moves to the right position, the traction device (20) pulls the suspension beam (10) to move toward the middle of the cross beam (21), installs the template anti-misalignment anchor, checks the bottom template pre-arch of the outer template system (22), and adjusts it; checks the top template pre-arch, and adjusts it.
15. The construction method of the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 12, characterized in that: During pouring, multiple placing machines (4) are used to place the material, an intelligent vibrating device (11) is used to vibrate the side wall of the beam, and manual vibration is used at the bottom plate and top plate.
16. The construction method of the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 15, characterized in that: The intelligent vibrating device (11) can move along the longitudinal direction of the bridge and has a retractable structure. The intelligent vibrating device (11) is provided with a gravity detection sensor, a travel sensor and a visual sensor; When vibrating the side wall of the beam, a visual sensor is used to detect the position of the opening on the outer mold system (22), the intelligent vibrating device (11) moves to the top of the opening, the vibrating rod of the intelligent vibrating device (11) falls, the stroke sensor feeds back the falling stroke, and the depth position of the vibrating rod is determined based on the gravity detection sensor, and it is determined whether it is blocked by steel bars. If it is detected that it is blocked by steel bars, the vibrating rod is lifted and moved a certain distance before continuing to vibrate.
17. The construction method of the upward integrated bridge-building machine suitable for the cast-in-place beam of the portal pier according to claim 15 is characterized in that: The detection sensor feeds back the gravity change of the vibrating rod. As the gravity change slows down, it is judged that the vibrating rod is in contact with the concrete, and the vibration time is started. After the preset vibration time is reached, the intelligent vibrating device (11) moves to the next vibrating station to continue vibrating; If the gravity detection sensor reports that the gravity of the vibrating rod is greatly reduced and this trend does not change after a period of time, it is determined that the vibrating rod is in contact with the steel bar and is blocked by the steel bar. At this time, the timing is stopped, the vibrating rod is lifted and moved to a nearby position and then lowered again. When the vibrating rod starts working again nearby, the vibration time is recalculated.
18. The construction method of the upward integrated bridge-building machine suitable for cast-in-place beams of portal piers according to claim 15, characterized in that: The poured beam (17) is steam-cured with formwork in the concrete pouring and steam-curing area (B); When curing with formwork, supply positive pressure steam or steam with alternating positive and negative pressures; After demoulding, the cast beam (17) is demoulded and steam-cured in the loading and demoulding curing area (A).
Citation Information
Patent Citations
Cast-in-place box girder integrated construction equipment and construction method thereof
CN111996916A
Self-propelled cast-in-place box girder integrated bridge building machine
CN112112075A
Concrete segmental beam reinforcing steel bar processing production line based on reinforcing steel bar components
CN112404316A
Cited By
Method for pouring epoxy resin gasket between main beam flange and shoulder beam of travelling crane
CN120620525A