Demounting and building synchronous construction method for in-situ reconstruction extradosed cable-stayed bridge
By adopting the synchronous construction method of rebuilding the low tower cable-stayed bridge in situ on the old concrete beam cable-stayed bridge, using bridge deck cranes, floating cranes and tower cranes to simultaneously remove the old bridge and build a new bridge, the solution is to solve the problem of The problem of long construction cycles has reduced the impact on river navigation, achieved shortening of construction periods and reducing channel occupation time.
Patent Information
- Application Number
- CN202411131877.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-19
AI Technical Summary
Old concrete beam cable-stayed bridges are difficult to meet safety requirements after operation and need to be demolished and rebuilt. The construction period of conventional demolition and construction methods is long, especially when the bridge is a navigable river channel, it occupies a long time to affect the navigation of the river channel.
The synchronous construction method of demolition and construction of the low tower cable-stayed bridge is adopted in situ, including erecting steel trestles and assembly brackets of the main beams of the new bridge on both sides of the old bridge, and using bridge deck cranes and floating cranes to remove the main spans and side spans of the old bridge. , set up the main beam and cable-stayed cable of the new bridge, gradually remove the old bridge and build a new bridge, use tower cranes and floating cranes to complete the assembly and connection of the main tower and main beam of the new bridge, and realize the in-situ reconstruction of the new bridge.
The construction period is shortened, the impact on river navigation is reduced, and the demolition of old bridges and the assembly of the main beams of new bridges is achieved simultaneously, avoiding the problem of excessive construction period.
Smart Images

Figure CN118880749A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of bridge construction, and relates to an in-situ reconstruction construction of an old bridge after demolition, and specifically to a simultaneous demolition and construction method for in-situ reconstruction of a cable-stayed bridge. Background Art
[0002] After a certain number of years of operation, old concrete beam cable-stayed bridges will inevitably suffer various structural damages. If they still cannot meet the requirements for safe operation after repair, they need to be demolished and rebuilt. Given the short service life of concrete beams and the difficulty of construction, steel trusses are generally used as the main beams of new cable-stayed bridges.
[0003] The conventional demolition and reconstruction idea is: first demolish the old bridge → clear the site → then build a new bridge, but the construction period is long. When there is a navigable river under the bridge, the waterway will be occupied for a long time, which has a great impact on the normal navigation of the river. Summary of the invention
[0004] The purpose of the present invention is to provide a method for synchronously dismantling and reconstructing a low-tower cable-stayed bridge in situ to solve the above problems, so as to shorten the construction period and reduce the impact on river navigation.
[0005] The technical solution of the present invention is as follows:
[0006] A method for simultaneous dismantling and reconstruction of an in-situ reconstruction of a low-tower cable-stayed bridge, wherein the cable-stayed bridge is a double-tower structure, including a main span and two side spans, the main beam of the old bridge is a concrete continuous beam structure, and the main beam of the new bridge is a steel truss beam; the method is characterized in that it comprises the following steps:
[0007] (1) On the outer sides of the two spans of the old bridge, steel trestles were constructed from both banks to the river as temporary passages for construction workers; along the longitudinal direction of the river, new bridge main beam assembly brackets were set up on both sides of each old bridge tower, and side span brackets were set up under the cast-in-place section of the side span of the old bridge;
[0008] (2) Use a bridge crane to remove the closure section of the main span of the old bridge; use a floating crane to remove the closure section of the side span of the old bridge, and at the same time dismantle the cast-in-place section of the side span of the old bridge;
[0009] (3) Use a bridge crane to symmetrically dismantle the main span and side span girder segments of the old bridge, and dismantle the corresponding inclined cables. At the same time, use a floating crane to assemble the main beams of the new bridge from the far end to the main tower on the assembly bracket of the new bridge girder. Assemble the main beam of one side span on the assembly bracket on one side of each main tower, and assemble the main beam of half the main span on the assembly bracket on the other side. The main beam of the new bridge located above the main tower abutment will not be assembled first, leaving space for the removal of the old abutment and the construction of the new abutment.
[0010] (4) After the main beam of the old bridge is dismantled, a tower crane is installed on the main tower support of the old bridge, and the tower crane is used to dismantle the main tower of the old bridge; after the main tower of the old bridge is dismantled, the tower crane is dismantled;
[0011] (5) Remove the old bridge cap, construct a new bridge cap in the original location, and install a turntable on the new cap;
[0012] (7) installing a tower crane on the new foundation, using the tower crane to construct a new bridge main tower, with the new main tower supported on the turntable;
[0013] (8) Use a tower crane to install all the stay cables on the new main tower, and then remove the tower crane; use a floating crane to assemble the remaining main beams of the new bridge, and complete the permanent connection between the main beams and the main tower; connect all the stay cables to the steel trusses and tension them; unload the assembly bracket of the main beam of the new bridge, and perform system conversion. The vertical force of the new bridge is supported by the turntable;
[0014] (9) Rotate the main beam of the new bridge horizontally into position and lock the turntable;
[0015] (10) Use floating crane to install the middle span closure section and the side span closure section to complete the in-situ reconstruction of the cable-stayed bridge.
[0016] The present invention is applicable to the in-situ dismantling and reconstruction of a low-tower cable-stayed bridge. While dismantling the old bridge, the main beam of the newly built cable-stayed bridge is assembled on both sides of the tower along the longitudinal direction of the river. After the old tower cap and tower column are dismantled, a new cap is built in the original position, a turntable is installed on the cap, and the cable tower of the new bridge is constructed on the turntable to complete the cable-stayed cable connection between the cable tower and the main beam. Then, the main beam of the new bridge is horizontally rotated into place, and finally the main beam of the new bridge is connected to complete the construction of the new bridge. Since there is no conflict between the dismantling construction of the old bridge and the assembly position of the main beam of the new bridge, the dismantling and reconstruction can be carried out simultaneously, which can greatly shorten the construction period and reduce the time of occupying the main channel. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a construction flow chart of the present invention;
[0018] Figure 2 It is a side view of the erected trestle, side span supports and the assembly supports of the main beam of the new bridge along the bridge direction;
[0019] Figure 3 It is a schematic diagram of the plan structure of the erected trestle, side span supports and the assembly supports of the main beam of the new bridge;
[0020] Figure 4 It is a schematic diagram of the side view of the dismantling of the main span closure section, side span closure section and side span cast-in-place section of the old bridge;
[0021] Figure 5 It is a side view of the dismantling of the old bridge girders and the simultaneous assembly of the new bridge girders;
[0022] Figure 6 It is a schematic diagram of the plane state of dismantling the main beam of the old bridge and assembling the main beam of the new bridge at the same time;
[0023] Figure 7 This is a schematic diagram of the tower crane dismantling the main tower of the old bridge;
[0024] Figure 8 This is a side view of the structure after the construction of the main tower foundation of the new bridge is completed;
[0025] Fig. 9 This is a schematic diagram of the plane structure after the construction of the main tower foundation of the new bridge is completed;
[0026] Fig.10 This is a schematic diagram of the status of the main tower of the new bridge under construction by the tower crane;
[0027] Fig.11 This is a side view of the new bridge's main tower and the new bridge's main beam connected by cable-stayed cables;
[0028] Fig.12 It is a schematic diagram of the plane structure in which the main tower of the new bridge is connected to the main beam of the new bridge through the inclined cable;
[0029] Fig.13 This is a side view along the longitudinal direction of the river where the main beam of the new bridge is connected to the main tower of the new bridge through cable stays;
[0030] Fig.14 This is a schematic diagram of the state of the main beam of the new bridge during horizontal rotation;
[0031] Fig.15 This is a top-down diagram of the main beam of the new bridge after it has been rotated horizontally into position;
[0032] Fig.16 This is a schematic diagram of the side view of the main beam of the new bridge after it has been rotated horizontally into position;
[0033] Fig.17 This is a side view diagram of the new bridge when construction is completed. DETAILED DESCRIPTION
[0034] The method of the present invention is described below through a specific embodiment. In this embodiment, a cable-stayed bridge across a navigable river is a double-tower structure, including a main span and two side spans. Because the structure is aging and cannot be completely repaired, it needs to be demolished and a new cable-stayed bridge needs to be rebuilt in situ. The main beam of the old bridge is a concrete continuous beam structure, and the main beam of the new bridge is a steel truss beam. In order to shorten the construction period and reduce the impact on the navigation of the river, the method of the present invention is used for construction. The construction process is as follows: Figure 1 The specific construction method is as follows:
[0035] (1) Figure 2 , Figure 3 As shown, on the outer sides of the two side spans of the old bridge, steel trestles 1 are constructed from both banks to the river as temporary passages for construction equipment and personnel; along the longitudinal direction of the river, new bridge main beam assembly brackets 3 are respectively set up on both sides of each old bridge main tower 2; side span brackets 4 are set up under the cast-in-place section of the side span of the old bridge to temporarily support the cast-in-place section of the side span when the joint section of the old bridge is dismantled;
[0036] (2) Figure 4 As shown, the bridge crane 5 is used to remove the closure section of the main span of the old bridge; the floating crane 6 is used to remove the closure section of the side span of the old bridge, and at the same time, the cast-in-place section of the side span of the old bridge is dismantled;
[0037] (3) Figure 5 , Figure 6 As shown, the main span and side span main beams 7 of the old bridge are symmetrically dismantled in sections by using a bridge crane 5, and the corresponding old bridge inclined cables 8 are dismantled. At the same time, the new bridge main beams 9 are assembled from the far end to the main tower direction on the new bridge main beam assembly bracket 3 by using a floating crane 6. A side span main beam is assembled on the assembly bracket on one side of each main tower, and a main beam of half the main span is assembled on the assembly bracket on the other side. The new bridge main beam located above the main tower abutment is not assembled first, and space is reserved for dismantling the old abutment and constructing the new abutment.
[0038] (4) Figure 7 As shown, after the main beam of the old bridge is dismantled, a tower crane 11 is installed on the main tower pedestal 10 of the old bridge, and the main tower 2 of the old bridge is dismantled by using the tower crane 11; after the main tower of the old bridge is dismantled, the tower crane is dismantled;
[0039] (5) Figure 8 , Fig. 9 As shown, the old bridge cap is removed, and then a new bridge cap 12 is constructed in situ, and a horizontal rotating turntable 13 is installed in the middle of the top of the new cap 12;
[0040] (7) Fig.10 As shown, a tower crane 11 is installed on the new pedestal 12, and a new bridge main tower 14 is constructed by using the tower crane, the bottom of which is supported on a turntable 13 on the pedestal; all the new bridge inclined cables 15 are installed on the new main tower 14 by using the tower crane, and then the tower crane is removed;
[0041] (8) Fig.11 , Fig.12 , Fig.13 As shown, the remaining new bridge main beam 9, i.e., the new bridge main beam located above the abutment, is assembled by floating crane, and the new main beam 9 is permanently connected to the new main tower 14; all new inclined cables 15 are connected to the new main beam 9 and tensioned; the new bridge main beam assembly bracket is unloaded, so that the top height of the main beam assembly bracket 3 is lowered and out of contact with the new bridge main beam 9, and the system conversion is realized, and the vertical force of the new bridge is supported by the turntable 13;
[0042] (9) Fig.14 , Fig.15 , Fig.16 As shown, a traction device is used to pull the main beam of the new bridge to rotate horizontally. When the main beam 9 of the new bridge rotates horizontally, the main tower 14 rotates together with it. After the main beam 9 of the new bridge is rotated horizontally into place, the turntable 13 is locked;
[0043] (10) Fig.17As shown, the middle span closure section 16 and the side span closure section 17 of the new bridge are installed by means of a floating crane, thereby completing the in-situ reconstruction of the cable-stayed bridge.
Claims
1. A method for simultaneous dismantling and reconstruction of an in-situ low-tower cable-stayed bridge, wherein the cable-stayed bridge is a double-tower structure, including a main span and two side spans, the main beam of the old bridge is a concrete continuous beam structure, and the main beam of the new bridge is a steel truss beam; characterized in that: The following steps are involved: (1) On the outer sides of the two spans of the old bridge, steel trestles were constructed from both banks to the river as temporary passages for construction workers; along the longitudinal direction of the river, new bridge main beam assembly brackets were set up on both sides of each old bridge tower, and side span brackets were set up under the cast-in-place section of the side span of the old bridge; (2) Use a bridge crane to remove the closure section of the main span of the old bridge; use a floating crane to remove the closure section of the side span of the old bridge, and at the same time dismantle the cast-in-place section of the side span of the old bridge; (3) Use a bridge crane to symmetrically dismantle the main span and side span girder segments of the old bridge, and dismantle the corresponding inclined cables. At the same time, use a floating crane to assemble the main beams of the new bridge from the far end to the main tower on the assembly bracket of the new bridge girder. Assemble the main beam of one side span on the assembly bracket on one side of each main tower, and assemble the main beam of half the main span on the assembly bracket on the other side. The main beam of the new bridge located above the main tower abutment will not be assembled first, leaving space for the removal of the old abutment and the construction of the new abutment. (4) After the main beam of the old bridge is dismantled, a tower crane is installed on the main tower support of the old bridge, and the tower crane is used to dismantle the main tower of the old bridge; after the main tower of the old bridge is dismantled, the tower crane is dismantled; (5) Remove the old bridge cap, construct a new bridge cap in the original location, and install a turntable on the new cap; (7) installing a tower crane on the new foundation, using the tower crane to construct a new bridge main tower, with the new main tower supported on the turntable; (8) Use a tower crane to install all the stay cables on the new main tower, and then remove the tower crane; use a floating crane to assemble the remaining main beams of the new bridge, and complete the permanent connection between the main beams and the main tower; connect all the stay cables to the steel trusses and tension them; unload the assembly bracket of the main beam of the new bridge, and perform system conversion. The vertical force of the new bridge is supported by the turntable; (9) Rotate the main beam of the new bridge horizontally into position and lock the turntable; (10) Use floating crane to install the middle span closure section and the side span closure section to complete the in-situ reconstruction of the cable-stayed bridge.
Citation Information
Patent Citations
Method for monitoring construction of channel bridge demolition
CN101644033A
Construction method and special guard screen for static demolition and home position reconstruction of overpass bridge
CN107268462A
Quick changing method and system of expressway overline bridge
CN109468960A
Construction method for widening, dismantling and reconstructing suspended beam T-shaped navigation bridge
CN113481881A
Steel pipe pile casing for in-situ reconstruction of collapsed bridge
CN116043827A
Cited By
Synchronous demolition and construction method for in-situ reconstruction of extradosed cable-stayed bridge
WO2026040256A1