Environment-friendly material shed closing structure
Through the combination of the embedded structure, ceiling structure and gas film, the gas film is fixed by using a self-tensioning device to solve the problems of high investment in the sealed structure of the raw material field and high construction difficulty, and the low cost, efficient installation and good environment of the material shed is achieved. quality.
Patent Information
- Application Number
- CN202411057139.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-01
AI Technical Summary
The closed structure of the existing raw material yard has problems such as high investment, high construction difficulty and high operating costs, especially the complex maintenance and poor environment of the gas bearing membrane structure.
Using a combination of embedded structure, ceiling structure and air film, the air film is fixed through a self-tensioning device to reduce the use of steel structures, reduce weight and investment, and at the same time, the permeability and self-cleaning characteristics of the air film are used to improve installation efficiency and environmental quality. .
It reduces the investment cost and construction difficulty of the material shed, shortens the construction cycle, improves installation efficiency, reduces maintenance workload, and improves the internal environmental quality of the raw material field.
Smart Images

Figure CN118881218A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of environmentally friendly storage structures, and in particular to an environmentally friendly material shed enclosed structure. Background Art
[0002] The raw material yard (material shed or raw material warehouse) is a storage workshop for bulk raw materials and fuels in an intelligent green and environmentally friendly integrated steel plant, and is also a key link to ensure continuous and normal production. With the country's increasing attention to environmental protection and the requirements of policy laws and regulations, the environmental protection closure of the raw material yard has gradually become a project that must be implemented for new construction and reconstruction. From the functional use, it can be concluded that the raw material yard occupies a large area, that is, long and wide, so the earliest mechanized raw material yards were arranged in the open air. In order to prevent environmental pollution caused by stacking and strong winds, and to prevent the strong winds from carrying away materials and causing great economic losses, at first, each company adopted various forms of windbreak nets and water spray devices to achieve anti-pollution and dust reduction measures. Although the investment was small, the effect was limited. The main reason was that the raw material yard was large in area. If the wind was strong or the windbreak net was not high enough, it would be impossible to achieve a good dust prevention effect, and it would be even more impossible to ensure the stability of the moisture content of the materials on rainy and snowy days, and the anti-freeze function in winter.
[0003] In recent years, closed intelligent green and environmentally friendly raw material yards have become the standard for new construction and renovation. At present, the closed forms of raw material yards in industries such as metallurgy, electricity, mining, and docks can be summarized as follows:
[0004] Spherical grid structure: This structure is a steel support with a spherical connection as the main frame. It can be designed as two or more layers according to the span size. The outside is closed with colored plates. It is also the form adopted by most raw material yards. Since the span of mechanized raw material yards is relatively large, pillars cannot be set in the middle, so the construction is difficult and the investment is high.
[0005] Thin-spoke large-span steel structure: This type of structure is a steel greenhouse with steel purlins and is closed with colored plates on the outside. This structure generally requires a load-bearing steel platform near the top, so the structure is relatively heavy, the investment is also high, and the construction is difficult.
[0006] Air-supported membrane structure: This structure uses compressed air to prop up a special membrane cloth, enclosing the entire raw material field. The outside of the membrane cloth is covered with a steel mesh to fix the air film. Due to the special structure, this raw material field must be a fully enclosed structure. All inlets and outlets are equipped with airtight devices, and are equipped with fan inlets, exhaust ports, and pressure relief valves. Because the membrane cloth needs to be supported by compressed air continuously blown in by the fan, a backup fan and backup power supply must be set up. Although this structure is simple and requires less investment, it has problems such as high operating costs, complex maintenance, and poor internal environment, which is not conducive to normal production inspections, inspections, and equipment maintenance.
[0007] Through the above analysis of several closed forms of raw material yards, although the raw material yards with the above closed structures can meet environmental protection requirements, there are also some advantages and disadvantages and defects, either large investment, or difficult construction and long construction period, or high operating costs, so inventing and creating a new closed form has become a necessary choice. Summary of the invention
[0008] In order to reduce the investment cost and construction difficulty of an environmentally friendly material shed and shorten the construction period of the material shed, the present application provides an environmentally friendly material shed closed structure.
[0009] The present application provides an environmentally friendly material shed closed structure, which adopts the following technical solutions:
[0010] An environmentally friendly material shed enclosing structure comprises an embedded structure arranged around a material yard, a ceiling structure installed on the embedded structure, and an air film covering the ceiling structure and used for enclosing the material yard, wherein the edges of the air film are fixed to the corresponding embedded structures, and the ceiling structure is provided with a plurality of groups of self-tensioning devices for supporting the air film.
[0011] By adopting the above technical solution, when installing a closed material shed, the ceiling structure can be quickly installed on the embedded structure, and the air film can be fixed to the ceiling structure by a self-tensioning device. The cooperation of the self-tensioning device and the air film can reduce the number of steel structures used compared to the existing material shed structure, and the air film replaces the color steel plate, which reduces the weight and the investment cost. During the installation process, the air film can be quickly fixed by the self-tensioning device, thereby improving the installation efficiency.
[0012] Furthermore, the ceiling structure includes multiple steel structure supports installed on the embedded structure, two adjacent steel structure supports on the embedded structure are a group, and multiple groups of steel structure supports are formed on the embedded structure, and the multiple groups of steel structure supports are evenly arranged on the embedded structure, the self-tensioning device is arranged between two adjacent steel structure supports, and multiple groups of self-tensioning devices are evenly arranged between two adjacent steel structure supports.
[0013] By adopting the above technical solution, two steel structure brackets are formed into a group, which can make the steel structure bracket of this group more stable on the embedded structure, avoid the steel structure bracket from tipping over during the process of fixing the air film, and facilitate the self-tensioning device to be set on the steel structure bracket. By setting up multiple groups of self-tensioning devices, the air film can be tensioned to the ceiling structure, thereby forming a closed structure with the embedded structure to prevent internal dust from spreading outward.
[0014] Furthermore, the steel structure support includes an arched truss arranged across the embedded structure and a pair of vertical supports symmetrically arranged at both ends of the arched truss. The arched truss and the two vertical supports are an integrated structure. The lower ends of the two vertical supports are fixed on the embedded structure. The air film covers the outside of the arched truss and the two vertical supports. Multiple groups of self-tensioning devices are evenly installed between two adjacent arched trusses and between two adjacent vertical supports.
[0015] Furthermore, a plurality of connecting beams are provided between two adjacent arched trusses and between two adjacent vertical supports, and two ends of the connecting beams are fixed to the two arched trusses or to the two vertical supports.
[0016] By adopting the above technical solution, the connecting beam can fix the two adjacent steel structure supports into one body. The two steel structure supports fixed by the connecting beam have a more stable structure, so that the two adjacent steel structures can be more stably fixed on the embedded structure.
[0017] Furthermore, the self-tensioning device includes a tensioning component suspended between two steel structure supports in the same group and a steel cable connected between two adjacent groups of steel structure supports and two opposite steel structure supports, both ends of the steel cable are connected to corresponding tensioning components, the two groups of tensioning components at the two end positions on the embedded structure are respectively connected to the end of a steel cable, and the tensioning components at the remaining positions are respectively connected to the ends of two steel cables.
[0018] By adopting the above technical solution, when fixing the air membrane, the tensioning component can tighten the steel cable so that the steel cable can be tensioned between two adjacent groups of steel structure supports, and the air membrane can be supported by the tensioned steel cable so that the air membrane can be propped up.
[0019] Furthermore, an anti-wear plate is provided on the steel cable between two adjacent groups of steel structure supports, and the anti-wear plate is in contact with the air film.
[0020] By adopting the above technical scheme, the tensioned steel cable can support the anti-wear plate, and the upper surface of the anti-wear plate can be flush with the outer surface of the arch truss and the vertical bracket. The anti-wear plate has a larger plate area, thereby increasing the contact surface between the anti-wear plate and the air film. The anti-wear plate is made of wear-resistant PVC or polymer material, and the air film is supported by the anti-wear plate to avoid long-term contact between the air film and the steel cable, which causes the air film to be worn. When the steel cable is tensioned, the anti-wear plate contacts the air film, thereby supporting the air film.
[0021] Furthermore, the tensioning component includes an outer sleeve and an inner sleeve, both of which are hollow structures with one end open. A tensioning spring is arranged inside the inner sleeve, the open end of the inner sleeve is inserted into the open end of the outer sleeve, and the inner sleeve and the outer sleeve slide relative to each other. The two ends of the tensioning spring abut against the sealed ends of the inner sleeve and the outer sleeve, and the end of the steel cable is fixed to the end of the outer sleeve or the end of the inner sleeve.
[0022] By adopting the above technical solution, the outer sleeve and the inner sleeve can fix and protect the tensioning spring, so that the tensioning spring can be compressed and deformed normally, and play the role of tightening the steel cable.
[0023] Furthermore, the tensioning component also includes a tensioning bolt rod and a tensioning nut, the tensioning bolt rod is passed through the axis of the inner sleeve, the outer sleeve and the tensioning spring, and the two ends of the tensioning bolt rod pass through the ends of the inner sleeve and the outer sleeve, the tensioning nut is threadedly connected to the end of the tensioning bolt rod close to the sealing end of the inner sleeve, and the tensioning nut can be tightened to the sealing end of the inner sleeve; the outer wall of the outer sleeve is rotatably provided with a pulling ear, the end of the pulling ear away from the outer sleeve and the end of the tensioning bolt rod away from the tensioning nut are respectively connected to the corresponding ends of the steel cable, the two groups of tensioning components located at the two ends of the embedded structure do not include pulling ears, and the ends of the tensioning bolt rod away from the tensioning nut are connected to the ends of the steel cable.
[0024] By adopting the above technical solution, the set tensioning bolt rod and pulling ear can be conveniently fixed to the steel cables at both ends of the tensioning component, and the two can move in opposite directions when the steel cable is tensioned. In the process of tensioning the steel cable, the staff gradually tightens the steel cable by turning the tensioning nut. Later, when the steel cable is loose, the staff can turn the tensioning nut.
[0025] Furthermore, the end of the pulling ear away from the outer sleeve and the end of the tensioning bolt rod away from the tensioning nut are both provided with locking buckles, and the ends of the steel cables are connected and fixed to the locking buckles.
[0026] By adopting the above technical solution, when fixing with the corresponding steel cable, the staff can quickly fix the steel cable through the lock buckle, thereby improving the installation efficiency.
[0027] Furthermore, the tensioning component also includes a pair of mounting seats fixed on two steel structure supports, and the two mounting seats are symmetrically fixed on the outer sides of two steel structure supports in the same group. A pair of pulleys are rotatably provided on the two mounting seats, and the end of the steel cable passes around the two pulleys and is fixed to the end of the pull ear or to the end of the tensioning bolt rod.
[0028] By adopting the above technical solution, the installation seat and the pulley are provided, so that the position of the steel cable can be changed downward, which is convenient for installing the tensioning component and avoiding contact between the tensioning component and the air film.
[0029] In summary, the present application includes at least one of the following beneficial technical effects:
[0030] 1. The coordination of the steel structure support, self-tensioning device and air film set in the present application greatly reduces the steel structure support supporting the closed air film and the corresponding foundation concrete engineering amount, thereby reducing the cost investment. In addition, during the construction process, the air film can be directly laid on the steel structure support, reducing the construction difficulty. The air film laid on the outside of the steel structure support is used as an external sealing material. Compared with the external sealing of color steel plates and purlins, it has the advantages of simple construction, light weight and low investment. The air film has high permeability and can also save energy. When the wind blows the air film, the air film shakes, which can remove the dust covering the outer surface of the air film, achieving a self-cleaning effect.
[0031] 2. When tensioning the air film, first use the tensioning components to tighten the two adjacent steel cables. The tensioned steel cables can serve as the supporting structure of the air film's outer closure. During the installation process, the staff does not need to make frequent adjustments, which reduces the maintenance workload;
[0032] 3. The new material shed enclosed structure of the present application abandons the shortcomings of poor internal environment and high operating costs of the air-supported membrane enclosed structure. By installing atomizing equipment on the base, the dust generated during the working process is reduced and the internal environmental quality of the raw material yard is improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0034] Figure 2 It is a schematic diagram of the side view of a closed material shed according to an embodiment of the present application;
[0035] Figure 3 It is a schematic diagram of the tensioning components on two adjacent groups of steel structure supports in the embodiment of the present application;
[0036] Figure 4 It is a schematic diagram of a tensioning assembly on an end steel structure support according to an embodiment of the present application.
[0037] Explanation of the reference numerals in the accompanying drawings: 1. Embedded structure; 11. Support member; 12. Reinforcement member; 2. Ceiling structure; 21. Steel structure support; 211. Arch truss; 212. Vertical support; 22. Connecting beam; 3. Air film; 4. Self-tensioning device; 41. Tensioning component; 411. Outer sleeve; 412. Inner sleeve; 413. Tensioning spring; 414. Tensioning bolt rod; 415. Tensioning nut; 416. Pull ear; 417. Circular pull ring; 418. Lock; 42. Steel cable; 43. Anti-wear plate; 44. Mounting seat; 45. Pulley. DETAILED DESCRIPTION
[0038] The following is combined with Figure 1-4 This application is described in further detail.
[0039] The embodiment of the present application discloses an environmentally friendly material shed enclosed structure.
[0040] Reference Figure 1 and Figure 2 An environmentally friendly material shed closed structure includes a pre-buried structure 1 which is arranged around the material yard and is in a ring shape. The inner side of the pre-buried structure 1 is used to stack various materials and plays a blocking role. A ceiling structure 2 is installed above the pre-buried structure 1, and an air film 3 is covered on the outer side of the ceiling structure 2. The edges of the air film 3 are fixed to the pre-buried structure 1. The coordinated use of the ceiling structure 2 and the air film 3 can close the top of the material yard to prevent raw material dust from diffusing outward. A plurality of sets of self-tensioning devices 4 are evenly installed on the ceiling structure 2. The self-tensioning devices 4 can support the air film 3 to the ceiling structure 2 to prevent friction between the air film 3 and the ceiling structure 2.
[0041] Reference Figure 1 and Figure 2 The embedded structure 1 includes a rectangular support member 11 which is arranged around the material yard. In the embodiment of the present application, the support member 11 can be a cast concrete retaining wall or a baffle built with a steel structure plate. During use, it can be selected according to actual conditions, but it is not limited to the above two structural forms. The inside of the annular support member 11 is used to store materials; multiple groups of vertically arranged reinforcement members 12 are arranged on the support member 11, and the multiple groups of reinforcement members 12 are evenly distributed along the annular direction of the support member 11. In the embodiment of the present application, the reinforcement member 12 can be a cast concrete column or a support column in the form of a steel structure frame. When the support member 11 is set, the reinforcement member 12 is also set at the same time. The strength of the support member 11 is increased by the reinforcement member 12, so as to avoid the material in the material yard from squeezing the support member 11 outward and prevent the support member 11 from collapsing.
[0042] Reference Figure 1 and Figure 2The ceiling structure 2 includes a plurality of steel structure brackets 21 installed on the embedded structure 1. Each two of the plurality of steel structure brackets 21 are combined into a group, and a plurality of groups of steel structure brackets 21 are formed on the embedded structure 1. The plurality of groups of steel structure brackets 21 are evenly arranged on the embedded structure 1 and along its length direction. The two ends of the two steel structure brackets 21 in each group are fixed to the upper ends of the reinforcing members 12 on the embedded structure 1, so that the weight of the steel structure brackets 21 can be distributed to the reinforcing members 12, so as to avoid the weight of the plurality of groups of steel structure brackets 21 being all used as Used on the support member 11; the steel structure support 21 includes an arched truss 211 arranged across the width direction of the embedded structure 1 and a pair of vertical supports 212 symmetrically arranged at both ends of the arched truss 211. In actual production and processing, the arched truss 211 and the two vertical supports 212 are an integrally formed structure. During installation, the steel structure support 21 is hoisted as a whole onto the embedded structure 1 for installation and fixation, and the lower ends of the two vertical supports 212 are respectively fixed to the corresponding reinforcement members 12; the air film 3 covers the arched truss 2 11 and the outside of the vertical bracket 212 are used to form a closed structure on the ceiling structure 2 to prevent the internal dust from spreading outward. The outside of the arched truss 211 and the outside of the vertical bracket 212, and the position in contact with the air film 3 are polished into a smooth structure to prevent the air film 3 from repeatedly rubbing against the arched truss 211 and the vertical bracket 212, causing damage to the air film 3. The self-tensioning device 4 is suspended between the two steel structure brackets 21 in each group, and the air film 3 can be tensioned to the steel structure bracket through the self-tensioning device 4. On the frame 21, the air film 3 can be firmly fixed on the ceiling structure 2 by fixing the edges of the air film 3 to the embedded structure 1 and tensioning the air film 3 by the self-tensioning device 4; a plurality of connecting beams 22 are arranged between two steel structure supports 21 in each group, and the plurality of connecting beams 22 are evenly distributed on the arch trusses 211 and the two vertical supports 212, and the two ends of the connecting beams 22 are respectively fixed to the two arch trusses 211 or to the two vertical supports 212, and the two steel structures are fixed into one by the plurality of connecting beams 22.
[0043] The spacing between the two steel structure supports 21 in each group is greater than or equal to 6 meters, and the spacing between two adjacent groups of steel structure supports 21 is 50-60 meters. When installing the material shed, the spacing between the two steel structure supports 21 in each group can keep the group of steel structure supports 21 stable, and prevent the steel structure supports 21 from tipping over on the embedded structure 1 when subjected to tension. The spacing between the two adjacent groups of steel structure supports 21 set in the present application can effectively reduce the number of steel structure supports 21 used. Compared with the existing steel structure supports 21, by reducing the amount of steel structure used, the closed material shed of the present application is more convenient to install and fix, which can effectively improve the efficiency of installation and construction. During the installation process, according to actual conditions, the two steel structure supports 21 can be fixed into one on the ground through the connecting beam 22, and then hoisted. Alternatively, the two steel structure supports 21 can be hoisted onto the embedded structure 1 first, and then the two steel structure supports 21 are fixed on top through the connecting beam 22. After the material shed structure is installed, the self-tensioning device 4 is installed on the steel structure support 21, and finally the air film 3 is laid.
[0044] The material of air membrane 3 is dirt-resistant membrane material, which must meet the combustion performance B1 level of GB8624-2012 "Classification of Combustion Performance of Building Materials and Products". The service life of the membrane material is more than 25 years. The membrane material parameters are:
[0045] Thickness: 1.05±0.05mm;
[0046] Tensile strength (warp / weft): 8500 / 8000N / 5cm, coating material: PVDF;
[0047] Peel Strength: ≧ 100N / 5cm;
[0048] Light transmittance: 5-8%, no need to turn on the light during the day;
[0049] Applicable temperature: -30 to 70°C;
[0050] The air film 3 material used in this application has a good light transmittance. Under normal circumstances, the lumen required for production can be achieved without turning on the lighting during the day. At the same time, due to the good light transmittance, it also has a certain light warming effect in winter.
[0051] Reference Figure 2 and Figure 3, multiple groups of self-tensioning devices 4 are evenly arranged on the arch truss 211 and the two vertical supports 212, and multiple groups are closely arranged at the connection between the vertical supports 212 and the arch truss 211. The self-tensioning device 4 includes a tensioning component 41 suspended between two adjacent steel structure supports 21 in the same group, and a pair of steel cables 42 are connected to the tensioning component 41. The steel cable 42 is arranged between the two adjacent groups of steel structure supports 21, and the two ends of the steel cable 42 are respectively connected and fixed to the tensioning component 41 between the two adjacent groups of steel structures. The steel cable 42 is tightened by the tensioning components 41 at both ends of the steel cable 42, and the air film 3 is tensioned by the tensioned steel cable 42. The steel cable 42 adopts high-strength, anti-aging and anti-rust hot-dip galvanized steel wire rope, which is covered with a PE protective layer. The air film 3 can be overlapped on the multiple steel cables 42 on the steel structure support 21 through the tightened steel cable 42, and through The set steel cable 42 supports the air film 3; the two groups of tensioning components 41 at both ends of the embedded structure 1 are respectively connected to a steel cable 42, and the tensioning components 41 at other positions are respectively connected and fixed to two steel cables 42; a plurality of anti-wear plates 43 are sleeved on each steel cable 42 between two adjacent groups of steel structure supports 21, the steel cable 42 passes through the middle of the plurality of anti-wear plates 43, and the plurality of anti-wear plates 43 are spliced on the steel cable 42 to form a long strip plate structure, the plate area of the anti-wear plate 43 is large, so that the contact surface between the anti-wear plate 43 and the air film 3 is increased, the plate material of the anti-wear plate 43 is made of wear-resistant PVC or polymer material, and the air film 3 is supported by the anti-wear plate 43 to avoid long-term contact between the air film 3 and the steel cable 42, causing the air film 3 to be worn, and when the steel cable 42 is tensioned, the anti-wear plate 43 contacts the air film 3, thereby propping up the air film 3.
[0052] The tensioning component 41 includes an outer sleeve 411 and an inner sleeve 412 in a cylindrical structure. The outer sleeve 411 is sleeved on the inner sleeve 412, and both the outer sleeve 411 and the inner sleeve 412 are hollow structures with one end open. The open end of the inner sleeve 412 is inserted into the outer sleeve 411 from the open end of the outer sleeve 411, and the outer sleeve 411 and the inner sleeve 412 are relatively slidably arranged. A tensioning spring 413 is arranged inside the inner sleeve 412, and one end of the tensioning spring 413 abuts against the closed end of the inner sleeve 412, and the other end abuts against the closed end of the outer sleeve 411. When the outer sleeve 411 and the inner sleeve 412 slide relatively, the tensioning spring 413 is compressed and stretched, and the steel cables 42 on both sides of the tensioning component 41 are fixed to the end of the outer sleeve 411 or the end of the inner sleeve 412, and the steel cables 42 are tightened by the tensioning spring 413.
[0053] Reference Figure 2 , Figure 3 and Figure 4The tensioning component 41 also includes a tensioning bolt rod 414 and a plurality of tensioning nuts 415 threadedly tightened onto the tensioning bolt rod 414. The tensioning bolt rod 414 is horizontally penetrated through the inner sleeve 412 and the outer sleeve 411, and the tensioning bolt rod 414 is located at the axis of the inner sleeve 412 and the outer sleeve. Both ends of the tensioning bolt rod 414 pass through the ends of the inner sleeve 412 and the outer sleeve 411. The tensioning spring 413 is sleeved on the tensioning bolt rod 414. The plurality of tensioning nuts 415 are located at a position of the tensioning bolt rod 414 near the closed end of the inner sleeve 412. The tensioning nut 415 is rotated to allow the tensioning nut 415 to be tightened against the closed end of the inner sleeve 412; a pull ear 416 is rotatably provided on the outer wall of the outer sleeve 411, so that the pull ear 416 can swing at the closed end of the outer sleeve 411, and the end of the pull ear 416 away from the outer sleeve 411 and the end of the tensioning bolt rod 414 away from the tensioning nut 415 can be fixed to the steel cable 42, and the outer sleeve 411 and the inner sleeve 412 are suspended between the two steel structure brackets 21 by the tightened steel cable 42. When the tension of the steel cable 42 needs to be adjusted, The staff rotates the tensioning nut 415, the inner sleeve 412 and the outer sleeve 411 slide toward each other, and compresses the tensioning spring 413, so that the steel cable 42 is gradually tightened; since the tensioning components 41 at both ends of the embedded structure 1 only need to tighten one steel cable 42, the tensioning components 41 at both ends do not include the pull ears 416, and the steel cable 42 on one side of the tensioning component 41 is fixed to the end of the tensioning bolt rod 414. In order to ensure that the tensioning component 41 can be used normally, the sealed end of the outer sleeve 411 is fixed to the steel structure bracket 21; between the pull ears 416 and The ends of the tensioning bolt rod 414 fixed to the steel cable 42 are both provided with circular pull rings 417. When fixed to the steel cable 42, the end of the steel cable 42 passes through the circular pull ring 417, which is convenient for connection with the corresponding pull ear 416 and the tensioning bolt rod 414; the end of the pull ear 416 away from the outer sleeve 411 and the end of the tensioning bolt rod 414 away from the tensioning nut 415 are both provided with lock buckles 418. When fixed to the corresponding steel cable 42, the staff can quickly fix the steel cable 42 passed through the circular pull ring 417 through the lock buckle 418, thereby improving the installation efficiency.
[0054] Reference Figure 2 , Figure 3 and Figure 4The tensioning component 41 also includes a pair of mounting seats 44 fixed on the two steel structure supports 21 of the same group. The two mounting seats 44 are symmetrically fixed on the outer sides of the two steel structure supports 21 that are far away from each other. A pair of pulleys 45 are rotatably arranged on the two mounting seats 44. The two pulleys 45 are distributed up and down on the mounting seats 44. The ends of the steel cables 42 pass around the upper pulley 45 and the lower pulley 45 in turn and are connected to the corresponding circular pull rings 417. Through the two pulleys 45 that are set, the steel cables 42 are changed from a position close to the air film 3 to a downward position, which can be conveniently connected to the tensioning component 41 to prevent the tensioning component 41 from approaching the outside and contacting the air film 3; a maintenance platform is detachably arranged between the two adjacent steel structure supports 21 of the same group and at a position below the tensioning component 41. When it is necessary to turn the nut to adjust the tightness of the steel cable 42, the staff stands on the maintenance platform for maintenance, and it is convenient for the staff to turn the tensioning nut 415.
[0055] Installation openings are provided at both ends of the embedded structure 1, and atomizing equipment is installed at the installation openings. The atomizing equipment may be a ventilating fan and a humidifier with spray. When the material shed is in use, the humidifier can spray water mist to remove dust inside the material shed. The ventilator can ventilate the inside of the material shed and allow air to flow inside the material shed.
[0056] The implementation principle of the present application is as follows: when setting up a closed material shed, an embedded structure 1 is set up in advance around the material yard according to actual conditions, the steel structure support 21 is directly hoisted above the embedded structure 1, and the two ends of the steel structure support 21 are fixed to the reinforcement 12 on the embedded structure 1, and then the corresponding self-tensioning device 4 is installed on the laid-out ceiling structure 2, and then the air film 3 is laid on the ceiling structure 2, and the edges of the air film 3 are fixed to the embedded structure 1. By adjusting the tensioning nut 415 on the self-tensioning device 4, the steel cable 42 is gradually tensioned, and the tensioned steel cable 42 can contact the air film 3 through the anti-wear plate 43, so that the air film 3 is fixed to the ceiling structure 2.
[0057] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. An environmentally friendly material shed closed structure, characterized by: The invention comprises a pre-buried structure (1) arranged around a material field, a ceiling structure (2) installed on the pre-buried structure (1), and an air membrane (3) covering the ceiling structure (2) and used for sealing the material field, wherein the edges of the air membrane (3) are fixed to the corresponding pre-buried structure (1), and the ceiling structure (2) is provided with a plurality of groups of self-tensioning devices (4) for supporting the air membrane (3).
2. The environmentally friendly material shed closed structure according to claim 1, characterized in that: The ceiling structure (2) comprises a plurality of steel structure supports (21) installed on the embedded structure (1), two adjacent steel structure supports (21) on the embedded structure (1) form a group, and multiple groups of steel structure supports (21) are formed on the embedded structure (1), and the multiple groups of steel structure supports (21) are evenly arranged on the embedded structure (1), and the self-tensioning device (4) is arranged between two adjacent steel structure supports (21), and multiple groups of self-tensioning devices (4) are evenly arranged between two adjacent steel structure supports (21).
3. The environmentally friendly material shed closed structure according to claim 2, characterized in that: The steel structure support (21) comprises an arched truss (211) arranged across the embedded structure (1) and a pair of vertical supports (212) symmetrically arranged at both ends of the arched truss (211); the arched truss (211) and the two vertical supports (212) are an integrated structure; the lower ends of the two vertical supports (212) are fixed on the embedded structure (1); the air film (3) covers the outside of the arched truss (211) and the two vertical supports (212); and a plurality of groups of self-tensioning devices (4) are evenly installed between two adjacent arched trusses (211) and between two adjacent vertical supports (212).
4. The environmentally friendly material shed closed structure according to claim 3, characterized in that: A plurality of connecting beams (22) are arranged between two adjacent arched trusses (211) and between two adjacent vertical supports (212), and two ends of the connecting beams (22) are fixed to the two arched trusses (211) or to the two vertical supports (212).
5. The environmentally friendly material shed closed structure according to claim 1, characterized in that: The self-tensioning device (4) comprises a tensioning component (41) arranged between two steel structure supports (21) in the same group, and a steel cable (42) connected between two adjacent groups of steel structure supports (21) and two opposite steel structure supports (21), wherein both ends of the steel cable (42) are connected to corresponding tensioning components (41), the two groups of tensioning components (41) located at the two end positions on the embedded structure (1) are respectively connected to the end of one steel cable (42), and the tensioning components (41) at the remaining positions are respectively connected to the ends of two steel cables (42).
6. The environmentally friendly material shed closed structure according to claim 2, characterized in that: An anti-wear plate (43) is sleeved on the steel cable (42) between two adjacent groups of steel structure supports (21), and the anti-wear plate (43) is in contact with the air film (3).
7. The environmentally friendly material shed closed structure according to claim 5, characterized in that: The tensioning component (41) includes an outer sleeve (411) and an inner sleeve (412), both of which are hollow structures with one end open. A tensioning spring (413) is arranged inside the inner sleeve (412). The open end of the inner sleeve (412) is inserted into the open end of the outer sleeve (411), and the inner sleeve (412) and the outer sleeve (411) slide relatively. The two ends of the tensioning spring (413) abut against the sealed ends of the inner sleeve (412) and the outer sleeve (411). The end of the steel cable (42) is fixed to the end of the outer sleeve (411) or the end of the inner sleeve (412).
8. The environmentally friendly material shed enclosed structure according to claim 5, characterized in that: The tensioning component (41) further comprises a tensioning bolt rod (414) and a tensioning nut (415), wherein the tensioning bolt rod (414) is inserted through the axis of the inner sleeve (412), the outer sleeve (411) and the tensioning spring (413), and the two ends of the tensioning bolt rod (414) are inserted through the ends of the inner sleeve (412) and the outer sleeve (411), and the tensioning nut (415) is threadedly connected to the end of the tensioning bolt rod (414) close to the seal of the inner sleeve (412), and the tensioning nut (415) can be tightened to the sealed end of the inner sleeve (412); the outer wall of the outer sleeve (411) is rotatably provided with a pull ear (416), and the end of the pull ear (416) away from the outer sleeve (411) and the end of the tensioning bolt rod (414) away from the tensioning nut (415) are respectively connected to the corresponding ends of the steel cable (42), and the two groups of tensioning components (41) located at the two ends of the embedded structure (1) do not include the pull ear (416), and the end of the tensioning bolt rod (414) away from the tensioning nut (415) is connected to the end of the steel cable (42).
9. The environmentally friendly material shed closed structure according to claim 8, characterized in that: The end of the pull ear (416) away from the outer sleeve (411) and the end of the tensioning bolt rod (414) away from the tensioning nut (415) are both provided with a lock buckle (418), and the end of the steel cable (42) is connected and fixed to the lock buckle (418).
10. The environmentally friendly material shed closed structure according to claim 5, characterized in that: The tensioning component (41) also includes a pair of mounting seats (44) fixed on the two steel structure supports (21), and the two mounting seats (44) are symmetrically fixed on the outer sides of the two steel structure supports (21) in the same group. A pair of pulleys (45) are rotatably arranged on the two mounting seats (44), and the end of the steel cable (42) passes around the two pulleys (45) and is fixed to the end of the pull ear (416) or to the end of the tensioning bolt rod (414).