Steelmaking-continuous casting heat batch plan optimization method and device

By using ε constraint framework and dichotomous heuristic selection in the steelmaking-continuous casting furnace batch plan, it solves the difficulty between decision makers' preferences and actual production in the prior art. The problem of finding balance has improved the efficiency and optimization effect of steelmaking-continuous casting production.

CN118886550APending Publication Date: 2024-11-01NORTHEASTERN UNIV AT QINHUANGDAO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410933381.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing batch planning optimization method for steelmaking-continuous casting furnaces is difficult to find a balance between decision makers' preferences and actual production focus, and the difficulty of solving multi-objective mathematical model increases due to the increase in order number and slab attribute data, resulting in efficiency. low.

Method used

The multi-objective steel furnace sub-batch planning model under the ε constraint framework is adopted, the slab difference target is used as the optimization target, and the weight target is converted as the constraint condition. The best endpoint is selected through sub-problem parameter update and dichotomy heuristics. Optimize the batch planning of steelmaking-continuous casting furnaces.

Benefits of technology

It reduces the difficulty of solving mathematical models, provides more collaborative optimization solutions, improves the integrated optimization efficiency and production efficiency of steel enterprises, and can optimize goals according to decision makers' preferences and reduces redundant calculations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118886550A_ABST
    Figure CN118886550A_ABST
Patent Text Reader

Abstract

The invention provides a steelmaking-continuous casting heat batch plan optimization method and device, and belongs to the technical field of industrial process production plans, and the method comprises the steps: constructing a multi-target heat batch plan model under an epsilon constraint framework; a multi-target heat batch planning model under an epsilon constraint framework is solved, Q end points with equal distances are divided in a value range of a non-committed material weight target, each end point provides a sub-problem needing to be solved, each sub-problem generates a non-dominated solution, the number of optimal ends is selected in a heuristic mode by adopting a dichotomy, and the number of the optimal ends is calculated. And optimizing the steelmaking-continuous casting heat batch plan by adopting the optimized multi-target heat batch plan model under the epsilon constraint framework to obtain a batch plan optimization result. According to the method, the number of effective sub-problems can be rapidly detected through the heuristic rule based on the dichotomy, the calculation burden of redundant sub-problems in a traditional epsilon constraint frame is avoided, and meanwhile more heat schemes are provided for collaborative optimization of all stages of batch planning problems.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of industrial process production planning, and in particular relates to a steelmaking-continuous casting furnace batch planning optimization method and device. Background Art

[0002] The steel manufacturing industry provides basic raw materials for other industries such as construction and transportation. Steel companies must improve production efficiency and reduce production costs by developing and establishing efficient production systems. The steel production system is divided into ironmaking, steelmaking-continuous casting, and rolling. Steelmaking-continuous casting is regarded as the bottleneck of the entire production system due to its machine capacity and production constraints. Steelmaking-continuous casting is further divided into batch planning decisions and workshop scheduling decisions. Batch planning decisions provide optimization objects for workshop scheduling decisions. In actual industrial production, steelmaking furnace batch planning is the basis of batch planning, and downstream production planning is to optimize the output data of furnace batch planning as input data. Therefore, compiling high-quality furnace batch planning that conforms to the actual production process is of great significance to improving the production efficiency of steelmaking-continuous casting and reducing material and energy consumption.

[0003] Slab is the basic unit of furnace batch planning optimization. The steel grade, width and delivery date of the slab are determined according to the requirements of the intermediate contract or the final contract. The batch planning of steelmaking furnaces is based on the pre-selected pool of slabs with given attributes as input conditions. According to the approximation of steel grade, width and delivery date, and considering the production process constraints, the optimization scheme is comprehensively analyzed to build a multi-objective mathematical model. The solution method that appeals to the characteristics of the mathematical model is designed. Therefore, the difficulty of solving the multi-objective mathematical model will increase exponentially due to the increase in the number of orders and the growth of slab attribute data. In order to reduce the difficulty of solving the mathematical model and improve the optimization efficiency, the processing method of the multi-objective mathematical model has received extensive attention and research. The current research methods are mainly divided into: multi-objective-linear summation, multi-objective-linear weighting and Pareto model based on the original multi-objective solution. The multi-objective-linear summation method is to directly sum multiple objective functions, which has the advantage of simple implementation. However, it is difficult to accurately characterize objective functions with different orders of magnitude or different properties. The multi-objective-linear weighted method is a method of assigning weight coefficients to each objective function and then summing them. This method has the advantage of decision maker preference and can assign appropriate weight coefficients to the objective function preferred by the decision maker. However, this method has poor robustness, and the error generated by the objective function with a high weight coefficient will have a greater impact on the system. The Pareto model can better characterize multi-objective functions and generate multiple Pareto non-dominated solutions, but it cannot select the main optimization objectives according to the decision maker's preference or the focus of actual production. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present application proposes a method and device for optimizing steelmaking-continuous casting furnace batch planning.

[0005] In a first aspect, the present application proposes a method for optimizing steelmaking-continuous casting furnace batch planning, comprising:

[0006] Establishing the optimization objectives of the multi-objective steelmaking furnace batch planning mathematical model, wherein the optimization objectives include: slab difference objective and uncommissioned material weight objective;

[0007] Determine the constraints of the mathematical model for multi-objective steelmaking heat batch planning;

[0008] The slab difference target is taken as the optimization target, the weight target of the uncommissioned material is transformed into a constraint condition, and a multi-objective batch planning model under the ε constraint framework is constructed.

[0009] Solve the multi-objective batch planning model under the ε constraint framework to obtain the value range of the weight target without commissioned materials;

[0010] Divide the value range of the weight target without any delegated material into Q endpoints with equal distances. Each endpoint provides a subproblem to be solved. Each subproblem produces a non-dominated solution. Calculate the subproblem parameters based on the value range of the weight target without any delegated material and Q.

[0011] A multi-objective batch planning model under the framework of ε constraint is adopted to update the sub-problem parameters;

[0012] Use binary search heuristic to select the best end Q * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained;

[0013] The multi-objective batch planning model under the optimized ε constraint framework is used to optimize the batch planning of steelmaking-continuous casting furnaces, and the batch planning optimization results are obtained.

[0014] The optimization objectives of establishing a multi-objective steelmaking furnace batch planning mathematical model include:

[0015] The optimization objective is to minimize the penalty for the difference in properties between slabs in the same heat, which is called the slab difference objective;

[0016] The optimization objective is to minimize the sum of no-commission penalties, which is called the no-commission weight objective.

[0017] The constraint conditions for determining the multi-objective steelmaking furnace batch planning mathematical model include:

[0018] Each slab can only be processed in one heat at most;

[0019] Only when slab j is selected as the cluster center, other slabs can be clustered with slab j and processed in the same heat;

[0020] The number of furnaces required for the processing is the set value;

[0021] The total weight of slabs processed in one furnace shall not exceed the furnace capacity.

[0022] The slab difference target is taken as the optimization target, the weight target of the uncommissioned material is converted into a constraint condition, and a multi-objective batch planning model under the ε constraint framework is constructed. The calculation formula is as follows:

[0023] Minimize F1(x)+α×(s2 / (r2))

[0024] Constraints:

[0025] x ij ≤x jj ,{i=1,2,...,N}.{j=1,2,...,N}

[0026]

[0027]

[0028] F2(x)+s2=ε 2,q

[0029] Where x = {x ij} i∈N,j∈N , N is the total number of slabs in the pre-selection pool, α is a sufficiently small number, ranging from 10 -6 -10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of uncommissioned materials, U is the number of furnaces, T is the furnace capacity, and x jj is a 0-1 decision variable, when the slab is selected as the cluster center x jj =1, otherwise x jj =0;x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,g i represents the weight of the i-th slab.

[0030] The multi-objective batch planning model under the ζ constraint framework is solved to obtain the value range of the weight target without commissioned materials, including:

[0031] Without considering the non-commissioned material weight target, only optimizing the slab difference target, solving the first sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the first optimal solution;

[0032] Without considering the slab difference target, only optimizing the weight target of uncommissioned materials, solving the second sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the second optimal solution;

[0033] According to the first optimal solution and the second optimal solution, a profit table is calculated;

[0034] The value range of the target weight of uncommissioned materials is read from the income table.

[0035] The sub-problem parameters are calculated as follows:

[0036]

[0037] Among them, ε 2,q is the sub-problem parameter, F2 is the lower limit of the value range of the target weight without commissioned materials. is the upper limit of the value range of the target weight without commissioned materials, Q is the number of endpoints with equal distances, and q is the qth endpoint.

[0038] The multi-objective batch planning model under the sub-problem parameter update ζ constraint framework is calculated as follows:

[0039] MinimizeF1(x)+α×(s2 / (r2))

[0040] Constraints:

[0041] x ij ≤x jj ,{i=1,2,...,N}.{j=1,2,...,N}

[0042]

[0043]

[0044]

[0045] F2(x)+s2=ε 2,q , {q=1,2,...,Q}

[0046] Where x = {x ij} i∈N,j∈N , α is a sufficiently small number, ranging from 10 -6 -10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are the sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of the uncommissioned material, U is the number of furnaces, T is the furnace capacity, ε 2,q is the sub-problem parameter, F2 is the lower limit of the value range of the target weight without commissioned materials. The upper limit of the value range of the non-commissioned material weight target, Q is the number of endpoints with equal distance, q is the qth endpoint, N is the total number of slabs in the pre-selection pool, x jj is a 0-1 decision variable. When slab j is selected as the cluster center, x jj =1, otherwise x jj =0;x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,g i represents the weight of the i-th slab.

[0047] The binary heuristic method is used to select the best end Q * The number of is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained, including:

[0048] Determine whether the non-dominated solution meets the rules of effective planning;

[0049] If the non-dominated solution meets the rules of the effective plan, then determine whether the non-dominated solution meets the rules of the effective plan;

[0050] If the non-dominated solution meets the requirements of valid solutions, the number of valid solutions is calculated;

[0051] According to the number of valid solutions, the best endpoint Q is selected based on the bisection heuristic * The optimized multi-objective batch planning model under the ε constraint framework is obtained.

[0052] If the non-dominated solution meets the requirements of the valid solution, the number of valid solutions is calculated, including:

[0053] Step S7.3.1: Initialize the number of valid solutions: For a given endpoint Q value, let N ES (Q) = 0, N ES (Q) is the number of valid solutions corresponding to Q;

[0054] Step S7.3.2: For a given Q, calculate the subproblem parameters and obtain ε 2,q .

[0055] Step S7.3.3: For ε 2,q, solve the multi-objective batch planning model under the updated ε constraint framework, and obtain x (q) , N (q) +, F1 (q) , where x (q) represents the solution to the qth subproblem, N (q)+ represents the number of slabs compiled into the furnace plan in the solution of the qth sub-problem, F1 *(q) represents the objective function of the qth subproblem;

[0056] Step S7.3.4: If F1 *(q) =F1 *(q-1) , then N ES (Q) = N ES (Q); if F1 *(q) ≠F1 *(q-1) , then N ES (Q) = N ES (Q)+1;

[0057] Step S7.3.5: If Then q=q+1, and return to step S7.3.2, where N is the total number of slabs, is the effective coefficient, if Then output the number of valid solutions N ES (Q).

[0058] According to the number of valid solutions, the best endpoint Q is selected based on the dichotomy heuristic * The optimized multi-objective batch planning model under the ε constraint framework is obtained, including:

[0059] Step S7.4.1: Initialize the maximum and minimum endpoints: in, is the minimum number of endpoints, is the maximum number of endpoints, M is a number that can ensure N ES (M) obtain the most effective solutions;

[0060] Step S7.4.2: If but like The output at this time is As the best endpoint Q * quantity;

[0061] Step S7.4.3: Calculate based on steps S7.3.1 to S7.3.5 The number of effective solutions as well as The number of effective solutions

[0062] Step S7.4.4: If and but like but like or Then output Output at this time As the best endpoint Q * Quantity, where Δ represents the stopping condition.

[0063] In the second aspect, the present application proposes a steelmaking-continuous casting furnace batch planning optimization device, comprising:

[0064] An optimization target establishment module is used to establish the optimization targets of the multi-target steelmaking furnace batch planning mathematical model, wherein the optimization targets include: slab difference target and uncommissioned material weight target;

[0065] A constraint determination module is used to determine the constraint conditions of the multi-objective steelmaking furnace batch planning mathematical model;

[0066] The planning model building module is used to take the slab difference target as the optimization target, convert the weight target of the uncommissioned material into a constraint condition, and build a multi-objective batch planning model under the ε constraint framework;

[0067] Range acquisition module, used to solve the multi-objective batch planning model under the ε constraint framework and obtain the value range of the weight target without commissioned materials;

[0068] The parameter calculation module is used to divide the value range of the weight target without entrusted materials into Q endpoints with equal distances. Each endpoint provides a sub-problem to be solved. Each sub-problem generates a non-dominated solution. The sub-problem parameters are calculated according to the value range of the weight target without entrusted materials and Q.

[0069] A model updating module is used to update the multi-objective batch planning model under the ε constraint framework using sub-problem parameters;

[0070] Quantity calculation module, used to select the best end Q using a binary heuristic * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained;

[0071] The result optimization module is used to optimize the steelmaking-continuous casting furnace batch plan by using the multi-objective furnace batch planning model under the optimized ε constraint framework to obtain the batch planning optimization result.

[0072] Beneficial effects:

[0073] The present application proposes a method and device for optimizing batch planning of steelmaking-continuous casting furnaces, which can decompose the original problem into multiple sub-problems for solution based on the decision maker's preferences or the performance indicators emphasized by the steel production enterprise as the main optimization target, thereby reducing the difficulty of solving the mathematical model. The solution to each sub-problem is a Pareto non-dominated solution, and these solutions together constitute a Pareto solution set, which provides more collaborative optimization solutions for the downstream production plan of steelmaking-continuous casting, thereby improving the integrated optimization efficiency and production benefits of steel enterprises. BRIEF DESCRIPTION OF THE DRAWINGS

[0074] Figure 1 A flow chart of a steelmaking-continuous casting furnace batch planning optimization method of this embodiment;

[0075] Figure 2 Improved ε-constraint framework flow chart of this embodiment;

[0076] Figure 3 Schematic diagram of the number of iterations and the number of valid solutions of the traditional ε-constraint method;

[0077] Figure 4 Schematic diagram of the number of iterations and the number of valid solutions of the improved ε-constraint method of this embodiment;

[0078] Figure 5 A principle block diagram of a steelmaking-continuous casting furnace batch planning optimization device of this embodiment. DETAILED DESCRIPTION

[0079] The specific implementation of the present application is further described in detail below in conjunction with the drawings and examples.

[0080] The furnace batch plan is the basis of the batch plan for the steelmaking-continuous casting section. With the rapid development of the market demand of steel enterprises towards multiple varieties, small batches and on-time delivery, the integrated production process of steelmaking-continuous casting batch plan has sharply increased the functional requirements for the flexibility, yield rate and time dynamic balance of the furnace batch plan. Therefore, the preparation of high-quality furnace batch plans is of great significance to improving steelmaking production efficiency and reducing material and energy consumption.

[0081] This application proposes a steelmaking-continuous casting furnace batch planning optimization method and device, establishes a multi-objective mathematical model for furnace batch planning, and develops an improved ε-constraint optimization framework. This application can quickly detect the number of effective sub-problems through heuristic rules based on dichotomy, avoiding the computational burden of redundant sub-problems in the traditional ε-constraint method (ε-constraint method). At the same time, this method can obtain multiple Pareto non-dominated solutions, providing more furnace solutions for the collaborative optimization of each stage of the batch planning problem.

[0082] Embodiment 1:

[0083] This embodiment proposes a steelmaking-continuous casting furnace batch planning optimization method, such as Figure 1 , Figure 2 As shown, including:

[0084] Step S1: establishing the optimization target of the multi-target steelmaking furnace batch planning mathematical model, wherein the optimization target includes: a slab difference target and a non-commissioned material weight target;

[0085] Step S2: determining the constraint conditions of the multi-objective steelmaking furnace batch planning mathematical model;

[0086] Step S3: Taking the slab difference target as the optimization target, converting the weight target of the uncommissioned material into a constraint condition, and constructing a multi-objective batch planning model under the ε constraint framework;

[0087] Step S4: solving the multi-objective batch planning model under the ε constraint framework to obtain the value range of the weight target without commissioned materials;

[0088] Step S5: Divide the value range of the weight target without entrusted materials into Q endpoints with equal distances, each endpoint provides a sub-problem to be solved, each sub-problem generates a non-dominated solution, and calculates the sub-problem parameters according to the value range of the weight target without entrusted materials and Q;

[0089] Step S6: using sub-problem parameters to update the multi-objective batch planning model under the ε constraint framework;

[0090] Step S7: Use the binary search heuristic to select the best end Q * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained;

[0091] Step S8: The multi-objective batch planning model under the optimized ε constraint framework is used to optimize the steelmaking-continuous casting batch planning to obtain the batch planning optimization result.

[0092] In step S1, the optimization objectives of establishing a multi-objective steelmaking heat batch planning mathematical model include:

[0093] Step S1.1: Minimizing the penalty for the difference in properties between slabs in the same heat is taken as the optimization objective, which is called the slab difference objective;

[0094]

[0095] Where F1 is the slab difference target, N is the total number of slabs in the pre-selected pool, i and , are the slab sequence indexes, i∈{1,...,N}, j∈{1,...,N}, i≠j. It is the penalty generated when slab i and slab j are processed in the same heat but with different steel grades. It is the penalty incurred when slab i and slab are processed in the same heat but with different widths. is the penalty generated when slab i and slab are processed in the same heat but have different delivery dates. ij is a 0-1 decision variable. When slab i and slab x are processed in the same furnace, ij =1, otherwise x ij =0.

[0096] Step S1.2: The optimization objective is to minimize the sum of no-commissioned material penalties, which is called the no-commissioned material weight objective.

[0097]

[0098] in, represents the penalty caused by no material per unit weight in the heat with slab as the cluster center. T represents the heat capacity. x jj is a 0-1 decision variable. When slab j is selected as the cluster center, x jj =1, otherwise x jj =0. g i represents the weight of the i-th slab.

[0099] In this embodiment, the optimization objective of the batch planning of the furnace is mainly considered from the following two aspects. First, since the properties of the slabs are not consistent, during the optimization process, the steel grade differences, specification differences and delivery period differences of the slabs in the same furnace are minimized according to the steelmaking process constraints and the property restrictions of the slabs that make up the same furnace. Secondly, as a device for smelting molten steel, each furnace of the converter has its use cost, and the furnace capacity is usually several times the weight of the slabs. When the total weight of the slabs that meet the properties of the same furnace does not meet the full furnace production requirements, it is necessary to add uncommissioned plates that do not correspond to user orders to the furnace, which increases production costs and inventory costs. Therefore, minimizing the property differences between slabs in the same furnace and minimizing the weight of uncommissioned materials are taken as optimization goals.

[0100] In step S2, the constraint conditions of the multi-objective steelmaking heat batch planning mathematical model are determined, including:

[0101] Step S2.1: Slab allocation uniqueness constraint: Each slab can be processed in at most one heat.

[0102]

[0103] Step S2.2: Decision variable x ij With x jj Relationship constraint: Only when a slab is selected as the cluster center, other slabs can be clustered with it and processed in the same heat.

[0104] x ij ≤x jj ,{i=1,2,...,N}.{j=1,2,...,N}. (4)

[0105] Step S2.3: Constraint on the number of furnaces: The number of furnaces required for the processing process is a set value, that is, the number of furnaces required for the processing process is fixed.

[0106]

[0107] Among them, U represents the number of furnaces.

[0108] Step S2.4: Furnace capacity constraint: The total weight of the slabs processed in the furnace does not exceed the furnace capacity.

[0109]

[0110] Where T is the furnace capacity and gi represents the weight of the i-th slab.

[0111] In step S3, the slab difference target is taken as the optimization target, the weight target of the uncommissioned material is converted into a constraint condition, and a multi-objective batch planning model under the ε constraint framework is constructed. The calculation formula is as follows:

[0112] MinimizeF1(x)+α×(s2 / (r2)) (7)

[0113] Subject to:

[0114] Eq.(3)-(6), and (8)

[0115] F2(x)+s2=ε 2,q (9)

[0116] Where x = {x ij} i∈N,j∈N , α is a sufficiently small number, ranging from 10 -6-10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are the sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of the uncommissioned material, U is the number of furnaces, T is the furnace capacity, and x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,x jj is a 0-1 decision variable, when the slab is selected as the cluster center x jj =1, otherwise x jj =0. g i Represents the weight of the i-th slab. ε 2,q It represents the upper limit assigned to F2 in order to achieve the improved ε-constraint. and F2 The calculation method of ε is given in step S4.3. 2,q The calculation method of is performed in step S5.

[0117] In step S4, the multi-objective batch planning model under the ε constraint framework is solved to obtain the value range of the weight target without commissioned materials, including:

[0118] Step S4.1: Ignoring the non-commissioned material weight target, only optimizing the slab difference target, solving the first sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the first optimal solution;

[0119] In this embodiment, the difference target F1 between slabs is optimized, that is, the first sub-model (CHBPM IECM -I), and reward the first optimal solution

[0120] (CHBPM IECM -I)

[0121]

[0122] Subject to:

[0123] Eq.(3)-(6) (11)

[0124] Step S4.2: Ignoring the slab difference target, only optimizing the weight target of the uncommissioned material, solving the second sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the second optimal solution;

[0125] In this embodiment, the weight target F2 without the material is optimized, that is, the second sub-model (CHBPM IECM-II), and reward the second best solution

[0126] (CHBPM IECM -II)

[0127]

[0128] Subject to:

[0129] Eq.(3)-(6) (13)

[0130] Step S4.3: Calculate a profit table according to the first optimal solution and the second optimal solution;

[0131] In this embodiment, the income table is calculated as shown in Table 1. The value range of the target weight F2 without the commissioned material

[0132] Table 1. Income statement

[0133]

[0134] Step S4.4: Read the value range of the weight target of the uncommissioned material from the income table.

[0135] In step S5, the sub-problem parameters are calculated as follows:

[0136]

[0137] Among them, ε 2,q is the sub-problem parameter, F2 is the lower limit of the value range of the target weight without commissioned materials. is the upper limit of the value range of the weight target without commissioned materials, Q is the number of endpoints with equal distances, and q is the qth endpoint. Divide into Q endpoints with equal distances, each endpoint provides a subproblem to be solved, and each subproblem produces a Pareto non-dominated solution.

[0138] In step S6, the multi-objective batch planning model under the ε constraint framework is updated using sub-problem parameters The calculation formula is as follows:

[0139]

[0140]

[0141] Subject to:

[0142] Eq.(3)-(6),(14)and(16)

[0143] F2(x)+s2=ε 2,q , {q=1,2,...,Q} (17)

[0144] Where x = {x ij} i∈N,j∈N α is a sufficiently small number, ranging from 10 -6 -10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are the sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of the uncommissioned material, U is the number of furnaces, T is the furnace capacity, ε 2,q is the sub-problem parameter, F2 is the lower limit of the value range of the target weight without commissioned materials. is the upper limit of the value range of the target weight without commissioned materials, Q is the number of endpoints with equal distance, q is the qth endpoint, x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,x jj is a 0-1 decision variable. When slab j is selected as the cluster center, x jj =1, otherwise x jj =0. g i represents the weight of the i-th slab.

[0145] In step S7, the optimal end Q is selected by using the binary search heuristic method. * The number of is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained, including:

[0146] Step S7.1: Determine whether the non-dominated solution meets the rules of the effective plan;

[0147] In this embodiment, the rule for formulating an effective plan is: the slab pre-selection pool contains a total number of N slabs. When the number of slabs selected in the steelmaking furnace batch plan satisfies the following formula, it is called an effective plan:

[0148]

[0149] Among them, N + Indicates the number of slabs selected in the furnace batch plan. is the effective coefficient, and its value range is For example, when N = 100, When , the meaning of formula (18) is: when the total number of slabs included in the batch plan of steelmaking furnace is greater than 95 slabs, it is an effective plan. The selection of the effective coefficient is specified according to the actual production demand of the steel plant.

[0150] Step S7.2: If the non-dominated solution meets the rules of the effective plan, determine whether the non-dominated solution meets the requirements of the effective plan; Q * The minimum value of Q that maximizes the number of effective solutions is the optimal number of endpoints Q * While satisfying the effective plan of formula (18), there will be multiple combination schemes due to different combinations of slabs. The formation of multiple combination schemes is due to the fact that formula (17) is obtained by traversing the q value. Each update of the q value corresponds to a sub-problem. Solving the sub-problem will get a solution. If the solution is an effective plan, then determine whether it is an effective plan.

[0151] In this embodiment, the effective solution is to select the solution with the minimum upper limit of F2 as an effective solution when the number of slabs in the batch is an effective plan and the main target value F1 remains unchanged among multiple solutions. 2,q In the process of taking values ​​from small to large (i.e., the increase of the value of constraint (17) containing F2(x)), first, the objective function {MinimizeF1(x)+α×(s2 / (r2))} will be reduced by changing the combination of slabs (F1(x) and F2(x) conflict with each other, so when one of the objectives increases, the other decreases). After a certain point, when it is no longer possible to reduce the objective by changing the combination, the objective can only be reduced by removing the slabs with the largest attribute difference in the same furnace. When only considering changing the combination to reduce the objective, because the furnace batch planning optimization model belongs to 0-1 integer programming, the values ​​of the decision variables are not continuous. Therefore, there will be a situation where the upper limit of the objective ε 2,q After the value of is updated twice or even multiple times, the slab attribute difference penalty target remains unchanged. In this case, select ε 2,q The solution with the minimum value is selected as an effective solution. Therefore, when the number of slabs in the furnace is constant, the solution with the minimum upper limit of F2 is selected as an effective solution.

[0152] It can be understood that if there is a non-dominated solution that does not conform to the rules of the effective plan or does not conform to the provisions of the effective solution, then the non-dominated solution is removed, such as Figure 3 and Figure 4 The square points in the middle are non-dominated solutions that are removed.

[0153] Step S7.3: If the non-dominated solution meets the requirements of the valid solution, the number of valid solutions is calculated, including:

[0154] Step S7.3.1: Initialize the number of valid solutions: For a given endpoint Q value, let N ES (Q) = 0, N ES (Q) is the number of valid solutions corresponding to Q;

[0155] Step S7.3.2: For a given Q, use equation (14) to calculate the subproblem parameters and obtain ε 2,q .

[0156] Step S7.3.3: For ε 2,q , solve the multi-objective batch planning model under the updated ε constraint framework, and obtain x (q) , N (q) +, F1 (q) , where x (q) represents the solution to the qth subproblem, N (q)+ represents the number of slabs compiled into the furnace plan in the solution of the qth sub-problem, F1 *(q) represents the objective function of the qth subproblem;

[0157] Step S7.3.4: If F1 *(q) =F1 *(q-1) , then N ES (Q) = N ES (Q); if F1 *(q) ≠F1 *(q-1) , then N ES (Q) = N ES (Q)+1;

[0158] Step S7.3.5: If Then q=q+1, and return to step S7.3.2, where N is the total number of slabs, is the effective coefficient, if Then output the number of valid solutions N ES (Q).

[0159] Step S7.4: According to the number of valid solutions, select the best endpoint Q based on the bisection heuristic * The optimized multi-objective batch planning model under the ε constraint framework is obtained, including:

[0160] Step S7.4.1: Initialize the maximum and minimum endpoints: in, is the minimum number of endpoints, is the maximum number of endpoints, M is a number that can ensure N ES (M) obtain the most effective solutions;

[0161] Step S7.4.2: If but like The output at this time is As the best endpoint Q * quantity;

[0162] Step S7.4.3: Calculate based on steps S7.3.1 to S7.3.5 The number of effective solutions as well as The number of effective solutions

[0163] Step S7.4.4: If and but like but like or Then output Output at this time As the best endpoint Q * Quantity, where Δ represents the stop condition. and When the distance is not greater than Δ, use express

[0164] In this embodiment, the optimal number of endpoints Q based on the dichotomy heuristic is * The traditional ε-constraint method lacks a method for selecting the Q value. The trial-and-error method not only increases the scale of the problem but also increases the amount of calculation, which in turn increases the burden of solving the problem. The improved ε-constraint framework selects the optimal number of endpoints Q based on the dichotomy heuristic. * . It effectively reduces the amount of calculation caused by the trial and error method and achieves good optimization results.

[0165] In this embodiment, Matlab+Yalimp+Cplex language programming is used, and the Cplex solver is called to solve the subproblems. Yalimp is a Matlab toolbox that can provide a language for describing mathematical models and call solvers. The implementation is performed on a PC with an Intel Core i5 5200 CPU 4GB Windows 10 / 64-bit operating system. Table 2 shows the parameter values ​​involved in the embodiment.

[0166] Table 2. Parameter values

[0167]

[0168] Table 3 compares the objective function values ​​of the linear weighted method and the improved ε-constraint method for solving the furnace batch planning based on a set of random data from a large steel plant. The data scales are {80, 120, 160} respectively. Since the objective function solved by the linear weighted method has a weight coefficient, it cannot be directly compared with the objective function value solved by the improved ε-constraint model. Therefore, this paper substitutes the solution obtained by the linear weighted method into the improved ε-constraint framework to generate the objective function, and compares the generated objective function with the improved ε-constraint optimal solution. In this way, it is possible to analyze whether the solution based on the linear weighted method still has room for optimization under the improved ε-constraint framework.

[0169] Table 3. Comparison of objective function values ​​between linear weighted method and improved ε-constraint

[0170]

[0171] Among them, ω1 and ω2 are the weight coefficients of F1 and F2 in the linear weighting method, and Represents the optimal solution obtained based on the linear weighted method Substitute into the objective function obtained in the improved ε-constraint method. and It represents the objective function optimized by the improved ε-constraint method. By analyzing Table 2, we can know that:

[0172] (1) Under the condition of the same data sample size, the greater the difference in the weight coefficient ratio, the greater the error generated and the worse the quality of the objective function. The optimization objective based on the improved ε-constraint framework method is not affected by the weight coefficient.

[0173] (2) Under the same sample data scale, the upper limit of the objective function under the improved ε-constraint framework is smaller than the minimum objective function value solved by the linear weighted method. Therefore, for the optimal solution optimized by the linear weighted method, there is still room for optimization under the improved ε-constraint framework.

[0174] Table 4. Comparison of running time between traditional ε-constraint and improved ε-constraint method

[0175]

[0176]

[0177] Table 4 compares the running time of the traditional ε-constraint and the improved ε-constraint method. The two methods select the same initial value. The traditional ε-constraint method searches in descending order from the maximum value, while the improved ε-constraint method searches in binary search. From the comparison results, it can be seen that the improved ε-constraint has a clear advantage in running time. Figure 3 and Figure 4 It can be seen from the comparison that the improved ε-constraint method can obtain the same Figure 3 The same number of valid solutions.

[0178] In summary, combined with the embodiments, it is verified that the present invention has greater advantages in solution quality and running time in the process of processing the mathematical model of steelmaking furnace batch planning optimization problem.

[0179] Embodiment 2:

[0180] This embodiment proposes a steelmaking-continuous casting furnace batch planning optimization device, such as Figure 5 As shown, it includes: an optimization target establishment module, a constraint condition determination module, a plan model construction module, a range acquisition module, a parameter calculation module, a model update module, a quantity calculation module and a result optimization module; the optimization target establishment module, the constraint condition determination module, the plan model construction module, the range acquisition module, the parameter calculation module, the model update module, the quantity calculation module and the result optimization module are connected in sequence;

[0181] An optimization target establishment module is used to establish the optimization targets of the multi-target steelmaking furnace batch planning mathematical model, wherein the optimization targets include: slab difference target and uncommissioned material weight target;

[0182] A constraint determination module is used to determine the constraint conditions of the multi-objective steelmaking furnace batch planning mathematical model;

[0183] The planning model building module is used to take the slab difference target as the optimization target, convert the weight target of the uncommissioned material into a constraint condition, and build a multi-objective batch planning model under the ε constraint framework;

[0184] Range acquisition module, used to solve the multi-objective batch planning model under the ε constraint framework and obtain the value range of the weight target without commissioned materials;

[0185] The parameter calculation module is used to divide the value range of the weight target without entrusted materials into Q endpoints with equal distances. Each endpoint provides a sub-problem to be solved. Each sub-problem generates a non-dominated solution. The sub-problem parameters are calculated according to the value range of the weight target without entrusted materials and Q.

[0186] A model updating module is used to update the multi-objective batch planning model under the ε constraint framework using sub-problem parameters;

[0187] Quantity calculation module, used to select the best end Q using a binary heuristic * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained;

[0188] The result optimization module is used to optimize the steelmaking-continuous casting furnace batch plan by using the multi-objective furnace batch planning model under the optimized ε constraint framework to obtain the batch planning optimization result.

Claims

1. A method for optimizing steelmaking-continuous casting furnace batch planning, characterized in that: include: Establishing the optimization objectives of the multi-objective steelmaking furnace batch planning mathematical model, wherein the optimization objectives include: slab difference objective and uncommissioned material weight objective; Determine the constraints of the mathematical model for multi-objective steelmaking heat batch planning; The slab difference target is taken as the optimization target, the weight target of the uncommissioned material is transformed into a constraint condition, and a multi-objective batch planning model under the ε constraint framework is constructed. Solve the multi-objective batch planning model under the ε constraint framework to obtain the value range of the weight target without commissioned materials; Divide the value range of the weight target without any delegated material into Q endpoints with equal distances. Each endpoint provides a subproblem to be solved. Each subproblem produces a non-dominated solution. Calculate the subproblem parameters based on the value range of the weight target without any delegated material and Q. A multi-objective batch planning model under the framework of ε constraint is adopted to update the sub-problem parameters; Use binary search heuristic to select the best end Q * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained; The multi-objective batch planning model under the optimized ε constraint framework is used to optimize the batch planning of steelmaking-continuous casting furnaces, and the batch planning optimization results are obtained.

2. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The constraint conditions for determining the multi-objective steelmaking furnace batch planning mathematical model include: Each slab can only be processed in one heat at most; Only when slab j is selected as the cluster center, other slabs can be clustered with slab j and processed in the same heat; The number of furnaces required for the processing is the set value; The total weight of slabs processed in one furnace shall not exceed the furnace capacity.

3. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The slab difference target is taken as the optimization target, the weight target of the uncommissioned material is converted into a constraint condition, and a multi-objective batch planning model under the ε constraint framework is constructed. The calculation formula is as follows: Minimize F1(x)+α×(s2 / (r2)) Constraints: F2(x)+s2=ε 2,q Where x = {x ij } i∈N,j∈N , α is a sufficiently small number, ranging from 10 -6 -10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of uncommissioned materials, U is the number of furnaces, T is the furnace capacity, and x jj is a 0-1 decision variable. When slab j is selected as the cluster center, x jj =1, otherwise x jj =0;x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,g i represents the weight of the i-th slab, and N is the total number of slabs in the pre-selection pool.

4. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The multi-objective batch planning model under the ε constraint framework is solved to obtain the value range of the weight target without commissioned materials, including: Without considering the non-commissioned material weight target, only optimizing the slab difference target, solving the first sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the first optimal solution; Without considering the slab difference target, only optimizing the weight target of uncommissioned materials, solving the second sub-model of multi-objective batch planning under the ε constraint framework, and obtaining the second optimal solution; According to the first optimal solution and the second optimal solution, a profit table is calculated; The value range of the target weight of uncommissioned materials is read from the income table.

5. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The sub-problem parameters are calculated as follows: Among them, ε 2,q is the sub-problem parameter, F 2 is the lower limit of the value range of the target weight without commissioned materials. is the upper limit of the value range of the target weight without commissioned materials, Q is the number of endpoints with equal distances, and q is the qth endpoint.

6. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The multi-objective batch planning model under the sub-problem parameter update ε constraint framework is calculated as follows: Minimize F1(x)+α×(s2 / (r2)) Constraints: F2(x)+s2=ε 2,q {q=1,2,…,Q} Where x = {x ij } i∈N,j∈N , α is a sufficiently small number, ranging from 10 -6 -10 -3 , s2 is a non-negative slack variable without material weight objective, r2 is the difference in the value range of the target weight without the commissioned material, ε 2,q are the sub-problem parameters, F1(x) is the slab difference target, F2(x) is the weight target of the uncommissioned material, U is the number of furnaces, T is the furnace capacity, ε 2,q is the sub-problem parameter, F 2 is the lower limit of the value range of the target weight without commissioned materials. is the upper limit of the value range of the weight target without commissioned materials, Q is the number of endpoints with equal distance, q is the qth endpoint, N is the total number of slabs in the pre-selection pool, and x jj is a 0-1 decision variable. When slab j is selected as the cluster center, x jj =1, otherwise x jj =0;x ij is a 0-1 decision variable. When slab i and slab j are processed in the same furnace, x ij =1, otherwise x ij =0,g i represents the weight of the i-th slab.

7. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 1, characterized in that: The binary heuristic method is used to select the best end Q * The number of is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained, including: Determine whether the non-dominated solution meets the rules of effective planning; If the non-dominated solution meets the rules of the effective plan, then determine whether the non-dominated solution meets the rules of the effective plan; If the non-dominated solution meets the requirements of valid solutions, the number of valid solutions is calculated; According to the number of valid solutions, the best endpoint Q is selected based on the bisection heuristic * The optimized multi-objective batch planning model under the ε constraint framework is obtained.

8. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 7, characterized in that: If the non-dominated solution meets the requirements of the valid solution, the number of valid solutions is calculated, including: Step S7.3.1: Initialize the number of valid solutions: For a given endpoint Q value, let N ES (Q) = 0, N ES (Q) is the number of valid solutions corresponding to Q; Step S7.3.2: For a given Q, calculate the subproblem parameters and obtain ε 2,q ; Step S7.3.3: For ε 2,q , solve the multi-objective batch planning model under the updated ε constraint framework, and get Among them, x (q) represents the solution to the qth subproblem, N (q)+ represents the number of slabs compiled into the heat plan in the solution of the qth sub-problem, represents the objective function of the qth subproblem; Step S7.3.4: If F1*=F1 *(q-1) , then N ES (Q) = N ES (Q); if F1 *(q) ≠F1 *(q-1) , then N ES (Q) = N ES (Q)+1; Step S7.3.5: If Then q=q+1, and return to step S7.3.2, where N is the total number of slabs, is the effective coefficient, if Then output the number of valid solutions N ES (Q).

9. The method for optimizing steelmaking-continuous casting furnace batch planning according to claim 7, characterized in that: According to the number of valid solutions, the best endpoint Q is selected based on the dichotomy heuristic * The optimized multi-objective batch planning model under the ε constraint framework is obtained, including: Step S7.4.1: Initialize the maximum and minimum endpoints: in, is the minimum number of endpoints, is the maximum number of endpoints, M is a number that can ensure N ES (M) obtain the most effective solutions; Step S7.4.2: If but like The output at this time is As the best endpoint Q * quantity; Step S7.4.3: Calculate based on steps S7.3.1 to S7.3.5 The number of effective solutions as well as The number of effective solutions Step S7.4.4: If and but like but like or Then output Output at this time As the best endpoint Q * Quantity, where Δ represents the stopping condition.

10. A steelmaking-continuous casting furnace batch planning optimization device, characterized in that: include: An optimization target establishment module is used to establish the optimization targets of the multi-target steelmaking furnace batch planning mathematical model, wherein the optimization targets include: slab difference target and uncommissioned material weight target; A constraint determination module is used to determine the constraint conditions of the multi-objective steelmaking furnace batch planning mathematical model; The planning model building module is used to take the slab difference target as the optimization target, convert the weight target of the uncommissioned material into a constraint condition, and build a multi-objective batch planning model under the ε constraint framework; Range acquisition module, used to solve the multi-objective batch planning model under the ε constraint framework and obtain the value range of the weight target without commissioned materials; The parameter calculation module is used to divide the value range of the weight target without entrusted materials into Q endpoints with equal distances. Each endpoint provides a sub-problem to be solved. Each sub-problem generates a non-dominated solution. The sub-problem parameters are calculated according to the value range of the weight target without entrusted materials and Q. A model updating module is used to update the multi-objective batch planning model under the ε constraint framework using sub-problem parameters; Quantity calculation module, used to select the best end Q using a binary heuristic * The number of batch size is obtained, and the multi-objective batch planning model under the optimized ε constraint framework is obtained; The result optimization module is used to optimize the steelmaking-continuous casting furnace batch plan by using the multi-objective furnace batch planning model under the optimized ε constraint framework to obtain the batch planning optimization result.