Bare soil spraying control method and system
Automatically identify and spray control of bare soil through image recognition technology, solve the problem of complex dust prevention operations on the construction site, realize automatic spraying, simplify the construction process, and reduce the dust generation and manual labor intensity.
Patent Information
- Application Number
- CN202411232210.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-11-05
AI Technical Summary
The dust-proofing method at the existing construction site is complex in operation, requiring manual measurement of the bare soil area and laying a green net, which affects the progress of the project and is prone to measurement errors and waste of materials.
Image recognition technology is used to automatically identify and spray the bare soil. By obtaining construction site images, identifying the bare soil coordinates and spraying, monitoring the bare soil status in real time, and completing the spraying process automatically, avoiding the layout and removal of green nets.
It realizes simplicity of operation and automatic dust protection, reduces the intensity of manual labor and dust generation, and improves construction efficiency and accuracy.
Smart Images

Figure CN118893034A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of dust prevention at construction sites, and in particular to a bare soil spraying control method and system. Background Art
[0002] In order to effectively reduce dust pollution at construction sites, it is usually necessary to cover all exposed soil on the site with green nets to reduce the content of particulate matter in the air and avoid damaging the environment.
[0003] At present, many construction sites still use manual on-site surveys to measure bare soil area, but the manual method is inefficient and prone to measurement errors that affect the accuracy of the measurement, resulting in material waste or material shortages. Some construction sites also use artificial intelligence methods to identify bare soil, mainly through classification algorithms to identify construction site images, and directly output information on whether the image contains bare soil. When bare soil information is identified, relevant prompts are issued, and relevant personnel arrange green nets based on the prompt information.
[0004] However, although green net covering can prevent dust, the operation of green net covering is complicated and requires operations such as green net laying. In the later construction process, the green net needs to be removed before construction can proceed, which affects the progress of the project.
[0005] Therefore, the dust prevention method at the construction site in the prior art has the technical problem of complex operation. Summary of the invention
[0006] The present invention provides a bare soil spraying control method and system, which solves the technical problem of complex operation of dust prevention methods at construction sites in the prior art.
[0007] Some implementation plans adopted to solve the above technical problems include: In a first aspect, a bare soil spraying control method comprises the following steps: Acquire construction site images; Identify whether there is bare soil at the construction site according to the construction site image, if there is no bare soil, continue to acquire the construction site image, if there is bare soil, proceed to the next step; Determine whether the bare soil needs to be sprayed, wherein whether the bare soil needs to be sprayed is determined based on whether the bare soil can generate dust, and if spraying is not required, continue to acquire the construction site image, and if spraying is required, proceed to the next step; Determining bare soil coordinates, wherein the bare soil coordinates are determined according to the construction site image; The bare soil is sprayed according to the bare soil coordinates, wherein the state of the bare soil being sprayed is obtained in real time during the spraying process, and whether the spraying is finished is determined according to the state of the bare soil being sprayed. The spraying is finished when the bare soil humidity meets the requirements, and the spraying continues if the bare soil humidity does not meet the requirements.
[0008] Preferably, in the step of identifying whether there is bare soil at the construction site based on the construction site image, a pixel detection model is used to determine whether there is bare soil at the construction site.
[0009] Preferably, the step of determining whether the bare soil needs spraying comprises the following steps: Obtain image data of dust generated by bare soil in the current construction site as reference data; Acquire the bare soil image data in the construction site image as actual data; The actual data is compared with the reference data, and whether the bare soil in the construction site image can generate dust is determined based on the actual data and the reference data. When the bare soil in the construction site image can generate dust, the bare soil in the construction site image needs to be sprayed; when the bare soil in the construction site image cannot generate dust, the bare soil in the construction site image does not need to be sprayed.
[0010] Preferably, the determining of bare soil coordinates comprises the following steps: Determine a reference object in the construction site image, and fit a coordinate axis in the construction site image according to the reference object in the construction site image; The bare soil coordinates are determined according to the fitted coordinate axes.
[0011] Preferably, spraying the bare soil according to the bare soil coordinates comprises the following steps: Determine a spraying area according to the bare soil coordinates; The spraying area is sprayed using the spraying equipment in the spraying area.
[0012] Preferably, the determination of whether spraying is finished is made based on the state of bare soil being sprayed. When the bare soil moisture meets the requirement, spraying is finished. If the bare soil moisture does not meet the requirement, spraying is continued. Whether the bare soil moisture meets the requirement is determined based on the amount of water used for spraying.
[0013] Preferably, the spraying is terminated based on the state of bare soil being sprayed. When the bare soil humidity meets the requirement, the spraying is terminated. If the bare soil humidity does not meet the requirement, the spraying is continued. Whether the bare soil humidity meets the requirement is determined based on the color of the bare soil being sprayed.
[0014] In a second aspect, a bare soil spray control system includes an image acquisition component for acquiring an image of a construction site; a data processing component, communicating with the image acquisition component, and processing the image acquired by the image acquisition component as follows: identifying whether there is bare soil at the construction site according to the construction site image, if there is no bare soil, the image acquisition component continues to acquire the construction site image, if there is bare soil, determining whether the bare soil needs to be sprayed, wherein determining whether the bare soil needs to be sprayed is based on whether the bare soil can generate dust, and if spraying is not required, the image acquisition component continues to acquire the construction site image, and when the bare soil needs to be sprayed, determines the bare soil coordinates, wherein the bare soil coordinates are determined according to the construction site image; a control component, communicating with the data processing component; and a spraying component for spraying the bare soil, wherein the control component controls the corresponding spraying component to spray the bare soil according to the bare soil coordinates, obtains the state of the bare soil being sprayed in real time during the spraying process, determines whether the spraying is finished according to the state of the bare soil being sprayed, and finishes the spraying when the bare soil humidity meets the requirements, and continues the spraying if the bare soil humidity does not meet the requirements.
[0015] Preferably, the bare soil spray control system further comprises a water volume monitor for monitoring the water output of the spray component, and the water volume monitor communicates with the control component via the data processing component.
[0016] Preferably, the spray assembly is a high-pole sprinkler.
[0017] Compared with the prior art, the present invention has the following advantages: 1. Spraying method is used for dust prevention. Compared with green net covering, it does not need to arrange green net. It only needs to spray water on the bare soil, which is very convenient to operate. In addition, since it does not need to arrange green net, it does not affect the construction period.
[0018] 2. This solution can automatically identify bare soil, reduce manpower, and can be deployed on the cloud and mobile terminals. It is convenient and easy to use, effectively reducing the labor intensity of operators, and can also monitor the construction site in real time.
[0019] 3. This solution can realize automatic spraying and unattended operation. When bare soil appears at the construction site, spraying can be completed automatically, effectively reducing the dust generated at the construction site. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] For the purpose of explanation, several embodiments of the present invention technology are described in the following drawings. The following drawings are incorporated into this text and constitute a part of the specific embodiment. In some cases, well-known structures and components are shown in block diagram form to avoid obscuring the concept of the present invention subject technology.
[0021] Figure 1 The figure is a flow chart of a bare soil spraying control method.
[0022] Figure 2 Flow chart for determining whether bare soil requires spraying.
[0023] Figure 3 Flowchart for determining bare soil coordinates.
[0024] Figure 4 The figure is a flow chart for spraying bare soil according to the bare soil coordinates.
[0025] Figure 5 This is a structural block diagram of a bare soil sprinkler control system.
[0026] Figure 6 Schematic diagram of the distribution of image acquisition components and spray components at the construction site.
[0027] As shown in the figure: 1. Image acquisition component, 2. Data processing component, 3. Control component, 4. Spray component, 5. Water volume monitor. DETAILED DESCRIPTION
[0028] The specific embodiments shown below are intended to be descriptions of various configurations of the subject technology of the present invention, and are not intended to represent the only configuration that the subject technology of the present invention can be put into practice. The specific embodiments include specific details intended to provide a thorough understanding of the subject technology of the present invention. However, it will be clear and obvious to those skilled in the art that the subject technology of the present invention is not limited to the specific details shown herein, and can be put into practice without these specific details.
[0029] It can be understood that, in this document, relational terms such as “first” and “second” are intended to distinguish one entity or operation from another entity or operation, and are not intended to express or imply any actual relationship or order between these entities or operations.
[0030] The terms "comprises," "comprising," or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.
[0031] Reference Figures 1 to 4 As shown, in a first aspect, a bare soil spraying control method comprises the following steps: Acquire images of the construction site: Usually, monitoring equipment can be used to acquire images of the construction site. There can be one or more monitoring equipment. The more monitoring equipment there are, the better the monitoring performance. At the same time, when there are multiple monitoring equipment, it is also beneficial to locate the bare soil coordinates.
[0032] Identify whether there is bare soil at the construction site according to the construction site image, if there is no bare soil, continue to acquire the construction site image, if there is bare soil, proceed to the next step; Determine whether the bare soil needs to be sprayed, wherein whether the bare soil needs to be sprayed is determined based on whether the bare soil can generate dust, and if spraying is not required, continue to acquire the construction site image, and if spraying is required, proceed to the next step; Determining bare soil coordinates, wherein the bare soil coordinates are determined according to the construction site image; The bare soil is sprayed according to the bare soil coordinates, wherein the state of the bare soil being sprayed is obtained in real time during the spraying process, and whether the spraying is finished is determined according to the state of the bare soil being sprayed. The spraying is finished when the bare soil humidity meets the requirements, and the spraying continues if the bare soil humidity does not meet the requirements.
[0033] In some embodiments, in the process of identifying whether there is bare soil at the construction site based on the construction site image, a pixel detection model is used to determine whether there is bare soil at the construction site. The pixel detection model can be obtained through machine learning training of any existing semantic segmentation network, for example, through training of U-Net, PSPNet, etc. The purpose of the pixel detection model is to identify bare soil images containing bare soil pixels from the construction site image. The output of the pixel detection model is actually a pixel matrix, and the position of each element in the pixel matrix represents the relative position of the pixel in the construction site image, and the value of each element represents whether the pixel corresponds to a bare soil pixel or a non-bare soil pixel. In other words, bare soil identification and bare soil positioning can be completed in the same step.
[0034] In some embodiments, the step of determining whether the bare soil needs spraying comprises the following steps: Obtain image data of dust generated by bare soil in the current construction site as reference data; Acquire the bare soil image data in the construction site image as actual data; The actual data is compared with the reference data, and whether the bare soil in the construction site image can generate dust is determined based on the actual data and the reference data. When the bare soil in the construction site image can generate dust, the bare soil in the construction site image needs to be sprayed; when the bare soil in the construction site image cannot generate dust, the bare soil in the construction site image does not need to be sprayed.
[0035] Specifically, bare soil does not need to be sprayed all the time. When bare soil is kept moist, dust generation can be prevented. Therefore, it is only necessary to keep bare soil moist. Dry bare soil and moist bare soil have different colors. Therefore, color analysis can be used to determine whether bare soil can generate dust. In other words, whether the dryness of bare soil can generate dust. Bare soil only needs to be sprayed when it can generate dust.
[0036] In some embodiments, relative to the above-described bare soil coordinate determination method, another bare soil coordinate determination method is described below, wherein the bare soil coordinate determination method includes the following steps: Determine a reference object in the construction site image, and fit a coordinate axis in the construction site image according to the reference object in the construction site image; The bare soil coordinates are determined according to the fitted coordinate axes.
[0037] The reference object may be other monitors, or a spraying device, etc. For example, an independent identification feature may be set for each monitor or monitoring device, the position of the reference object is determined according to the independent identification feature, and then the actual position of the bare soil is determined according to the reference object.
[0038] In some embodiments, spraying the bare soil according to the bare soil coordinates comprises the following steps: Determine a spraying area according to the bare soil coordinates; The spraying area is sprayed using the spraying equipment in the spraying area.
[0039] Usually the construction site has a large area, and a single spraying device cannot meet the spraying operation of the entire construction site. Therefore, after the spraying area is determined according to the bare soil coordinates, the spraying equipment in the spraying area is used to spray the bare soil.
[0040] In some embodiments, the determination of whether spraying is to be terminated is made based on the state of bare soil being sprayed. Spraying is terminated when the bare soil moisture meets the requirements, and spraying continues if the bare soil moisture does not meet the requirements, wherein whether the bare soil moisture meets the requirements is determined based on the amount of water used for spraying.
[0041] That is, the amount of water sprayed by the spraying device is monitored during the process, and the temperature of the bare soil can be determined based on the amount of water.
[0042] Alternatively, in some embodiments, the determination of whether spraying is finished is made based on the state of the bare soil being sprayed. When the bare soil humidity meets the requirement, spraying is finished. If the bare soil humidity does not meet the requirement, spraying is continued. Wherein, whether the bare soil humidity meets the requirement is determined based on the color of the bare soil being sprayed. Bare soils with different humidity have different colors, so whether the temperature of the bare soil meets the requirement can be determined based on the color, for example, by using the above-mentioned pixel detection model to make the determination.
[0043] Reference Figures 5 to 6 As shown, in a second aspect, a bare soil spraying control system includes an image acquisition component 1 for acquiring a construction site image; The data processing component 2 communicates with the image acquisition component 1, and processes the image acquired by the image acquisition component 1 as follows: identifying whether there is bare soil at the construction site according to the construction site image, if there is no bare soil, the image acquisition component 1 continues to acquire the construction site image, if there is bare soil, determining whether the bare soil needs to be sprayed, wherein the bare soil needs to be sprayed is determined according to whether the bare soil can generate dust, and when spraying is not required, the image acquisition component 1 continues to acquire the construction site image, and when the bare soil needs to be sprayed, the bare soil coordinates are determined, wherein the bare soil coordinates are determined according to the construction site image; A control component 3, communicating with the data processing component 2; And a spray component 4 is used to spray the bare soil, wherein the control component 3 controls the corresponding spray component 4 to spray the bare soil according to the bare soil coordinates, obtains the state of the bare soil being sprayed in real time during the spraying process, and determines whether the spraying is finished according to the state of the bare soil being sprayed. The spraying is finished when the bare soil humidity meets the requirements, and the spraying continues if the bare soil humidity does not meet the requirements.
[0044] In some embodiments, the bare soil spray control system further includes a water volume monitor 5 for monitoring the water output of the spray component 4 , and the water volume monitor 5 communicates with the control component 3 through the data processing component 2 .
[0045] In some embodiments, the spray assembly 4 is a high-pole sprayer. The spray assembly 4 can also be other spray equipment.
[0046] The above describes the subject technical solution and corresponding details of the present invention. It can be understood that the above description is only some implementation plans of the subject technical solution of the present invention, and some details may be omitted during the specific implementation.
[0047] In addition, in some embodiments of the above invention, multiple embodiments may be implemented in combination, and various combinations are not listed one by one due to space limitations. Those skilled in the art can freely combine and implement the above embodiments as needed in specific implementation to obtain a better application experience.
[0048] When implementing the subject technical solution of the present invention, those skilled in the art can obtain other detailed configurations or drawings based on the subject technical solution of the present invention and the drawings. Obviously, these details still fall within the scope covered by the subject technical solution of the present invention without departing from the subject technical solution of the present invention.
Claims
1. A bare soil spraying control method, characterized in that: The method includes the following steps: acquiring a construction site image; identifying whether there is bare soil at the construction site based on the construction site image, and continuing to acquire the construction site image if there is no bare soil, and proceeding to the next step if there is bare soil; determining whether the bare soil needs to be sprayed, wherein determining whether the bare soil needs to be sprayed is based on whether the bare soil can generate dust, and continuing to acquire the construction site image when spraying is not required, and proceeding to the next step when the bare soil needs to be sprayed; determining the bare soil coordinates, wherein the bare soil coordinates are determined based on the construction site image; spraying the bare soil based on the bare soil coordinates, wherein the state of the bare soil being sprayed is acquired in real time during the spraying process, and determining whether the spraying is ended based on the state of the bare soil being sprayed, and ending the spraying when the bare soil humidity meets the requirements, and continuing the spraying if the bare soil humidity does not meet the requirements.
2. The bare soil spraying control method according to claim 1, characterized in that: In the step of identifying whether there is bare soil at the construction site according to the construction site image, a pixel detection model is used to determine whether there is bare soil at the construction site.
3. The bare soil spraying control method according to claim 1, characterized in that: The determining whether bare soil needs to be sprayed includes the following steps: obtaining image data when bare soil in the current construction site generates dust as reference data; obtaining the bare soil image data in the construction site image as actual data; comparing the actual data with the reference data, and determining whether the bare soil in the construction site image can generate dust based on the actual data and the reference data. When the bare soil in the construction site image can generate dust, the bare soil in the construction site image needs to be sprayed, and when the bare soil in the construction site image cannot generate dust, the bare soil in the construction site image does not need to be sprayed.
4. The bare soil spraying control method according to claim 1, characterized in that: The method of determining the bare soil coordinates comprises the following steps: determining a reference object in the construction site image, fitting a coordinate axis in the construction site image according to the reference object in the construction site image; and determining the bare soil coordinates according to the fitted coordinate axis.
5. The bare soil spraying control method according to claim 1, characterized in that: The spraying of bare soil according to the bare soil coordinates comprises the following steps: determining a spraying area according to the bare soil coordinates; and spraying the spraying area using a spraying device in the spraying area.
6. The bare soil spraying control method according to claim 1, characterized in that: The spraying is terminated according to the state of bare soil being sprayed. When the bare soil moisture meets the requirement, the spraying is terminated. If the bare soil moisture does not meet the requirement, the spraying is continued. Whether the bare soil moisture meets the requirement is determined according to the amount of water used for spraying.
7. The bare soil spraying control method according to claim 1, characterized in that: The spraying is terminated according to the state of the bare soil being sprayed. When the bare soil humidity meets the requirement, the spraying is terminated. If the bare soil humidity does not meet the requirement, the spraying is continued. Whether the bare soil humidity meets the requirement is determined according to the color of the bare soil being sprayed.
8. A bare soil spraying control system, characterized in that: The invention comprises an image acquisition component (1) for acquiring an image of a construction site; and a data processing component (2) for communicating with the image acquisition component (1) and performing the following processing on the image acquired by the image acquisition component (1): identifying whether there is bare soil at the construction site based on the image of the construction site; if there is no bare soil, the image acquisition component (1) continues to acquire images of the construction site; if there is bare soil, determining whether the bare soil needs to be sprayed; wherein determining whether the bare soil needs to be sprayed is based on whether the bare soil can generate dust; and if spraying is not required, the image acquisition component (1) continues to acquire images of the construction site. image, determining bare soil coordinates when bare soil needs to be sprayed, wherein the bare soil coordinates are determined according to the construction site image; a control component (3) communicating with the data processing component (2); and a spraying component (4) for spraying the bare soil, wherein the control component (3) controls the corresponding spraying component (4) to spray the bare soil according to the bare soil coordinates, and obtains the state of the bare soil being sprayed in real time during the spraying process, and determines whether the spraying is to be ended according to the state of the bare soil being sprayed, and ends the spraying when the bare soil humidity meets the requirements, and continues the spraying if the bare soil humidity does not meet the requirements.
9. The bare soil spraying control system according to claim 8, characterized in that: The bare soil spraying control system further comprises a water volume monitor (5) for monitoring the water output of the spraying component (4); the water volume monitor (5) communicates with the control component (3) via the data processing component (2).
10. The bare soil spraying control system according to claim 8, characterized in that: The spray assembly (4) is a high-pole sprayer.
Citation Information
Patent Citations
Construction site bare soil identification method and device, computer equipment and storage medium
CN113902893A
Bare soil monitoring and early warning method and device, computer equipment and storage medium
CN114005036A
Spraying control method and device for automatic dust fall
CN114011177A
Automatic spraying dust fall control method and system for construction site
CN118122061A
Portable dust suppression effect testing and comparing device
CN212031413U