Annular hanging beam welding method
Through automatic welding technology of track-type and wheel-type welding robots, the problems of low welding efficiency and poor quality of ring-mounted beams are solved, efficient and precise welding is achieved, labor intensity and cost are reduced, and it is suitable for welding needs of a variety of materials.
Patent Information
- Application Number
- CN202411073520.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-05
AI Technical Summary
The existing ring-hanging beam welding technology is low efficiency, poor quality, high labor intensity, and high personnel skills requirements, making it difficult to meet the needs of high welding quality.
Automatic welding is carried out using crawler-type and wheel-type welding robots. The inner and outer ring sides of the ring hoist beam are welded simultaneously through the first and second welds. The preset program is used to move flexibly between each station. , reduce manual climbing and handling, and realize automatic welding.
Improve welding efficiency and quality, reduce construction costs, and reduce the demand for high-level welders. It is suitable for batch non-standard parts welding of carbon steel and stainless steel materials, and realizes flat welding, horizontal welding, vertical welding and fillet welds. High-precision welding alleviates workers' labor intensity and improves safety.
Smart Images

Figure CN118893342A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of metal welding, and in particular relates to a ring suspension beam welding method. Background Art
[0002] The steel containment vehicle-shaped ring crane beam is an important nuclear-grade equipment for nuclear power units and a critical path for lifting and hoisting key equipment in nuclear power plants. It is a box-type frame structure installed inside the steel containment cylinder to support the ring crane of the nuclear power plant. It needs to withstand huge dynamic and static loads for a long time during its service, so extremely high requirements are placed on the quality of the welds.
[0003] The welds of the ring beam assembly are mainly fillet welds without full penetration, and the height of the weld fillet is mostly between 19mm and 25mm. The welding volume of the ring beam is large, and the weld filler metal volume of a single unit is more than 3.7 tons, and the material is low-alloy steel. In the prior art, all ring beam assemblies are manually welded using semi-automatic gas shielded welding. During welding, the operator needs to keep the welding gun at an appropriate angle to the workpiece surface and at an appropriate distance from the workpiece, and then evenly move the welding gun to weld the workpiece.
[0004] However, this traditional manual welding method requires high skills of personnel, high labor intensity, low welding efficiency and poor welding quality. Summary of the invention
[0005] The present application provides a ring suspension beam welding method, which can improve welding efficiency and has higher welding quality.
[0006] The present application provides a ring-suspended beam welding method, which is used for welding a ring-suspended beam, wherein the ring-suspended beam comprises an inner ring side and an outer ring side arranged opposite to each other in a radial direction, the ring-suspended beam comprises a plurality of assembly plates, and a plurality of welding positions are formed between the plurality of assembly plates; the ring-suspended beam has a first part and a second part connected to each other along a height direction; the ring-suspended beam welding method comprises: using a first welding part to weld the welding position along the inner ring side of the first part; using a second welding part to weld the welding position along the outer ring side of the first part; flipping the ring-suspended beam along the height direction of the ring-suspended beam; using a first welding part to weld the welding position along the inner ring side of the second part; using a second welding part to weld the welding position along the outer ring side of the second part; wherein the first welding part and the second welding part simultaneously weld different welding positions on the inner ring side and the outer ring side; performing surface quality inspection on the welds formed on the welding positions; and using the first welding part and the second welding part to weld temporary attachments to the ring-suspended beam.
[0007] As in the above-mentioned ring hanger beam welding method, the multiple assembly plates of the ring hanger beam include a top plate, a bottom plate, a web plate and at least two vertical plates, the top plate and the bottom plate are arranged opposite to each other in the vertical direction, and the web plate and the vertical plates are both arranged between the top plate and the bottom plate; the two side surfaces of the web plate along the thickness direction are respectively facing the inner ring side and the outer ring side, and at least two vertical plates are respectively arranged on the opposite sides of the web plate along the thickness direction; welding positions are formed between the top plate, the bottom plate, the web plate and the vertical plates; the first welding part is used to weld the welding positions, specifically including: using the first welding part to weld the welding positions between the surfaces of the bottom plate, the vertical plate and the web plate close to the inner ring side; using the second welding part to weld the welding positions, specifically including: using the second welding part to weld the welding positions between the surfaces of the bottom plate, the vertical plate and the web plate close to the outer ring side.
[0008] As in the above-mentioned ring beam welding method, welding is performed on the welding positions, including: spot welding the assembly plate; performing base welding on the welding positions; performing filling welding on the welding positions that have been base welded; and performing cover welding on the welding positions that have been filled welded.
[0009] As in the above-mentioned ring beam welding method, after base welding is performed on the welding position and before filling welding is performed on the welding position that has undergone base welding, it also includes: flatness inspection, visual inspection and magnetic particle inspection on the welding position that has undergone base welding; grinding and polishing the welding position that has undergone base welding.
[0010] As in the above-mentioned ring hanging beam welding method, before welding the welding position, it also includes: preheating the ring hanging beam to make the temperature of the ring hanging beam reach a preset temperature.
[0011] As in the above-mentioned ring beam welding method, the preset temperature range is 106°C-181°C.
[0012] As in the above-mentioned ring hanging beam welding method, the welding height of the first welding part and the second welding part in the vertical direction is H1, the height of the ring hanging beam is H2, and the ratio of H1 to H2 is (1:2)-(5:8).
[0013] As in the above-mentioned ring suspension beam welding method, optionally, there is a first welding position between the bottom plate and the vertical plate, and between the top plate and the vertical plate, the first welding position extends along the first direction, and there is a second welding position between the bottom plate and the web plate, and between the top plate and the web plate, the second welding position extends along the second direction; there is a third welding position between the vertical plate and the web plate, and the third welding position extends along the vertical direction; the first direction, the second direction and the vertical direction intersect each other; welding is performed on the welding positions between the surfaces of the bottom plate, the vertical plate and the web plate close to the inner ring side, including: welding the first welding position; welding the second welding position; welding the third welding position.
[0014] As in the above-mentioned ring hanging beam welding method, the number of welding layers at the first welding position and the third welding position is the same and is less than the number of welding layers at the second welding position.
[0015] In the above-mentioned ring suspension beam welding method, the number of welding layers at the first welding position and the third welding position is 2-5 layers; and / or the number of welding layers at the second welding position is 5-8 layers.
[0016] The present application provides a ring hanging beam welding method, which is used for welding the ring hanging beam, wherein the ring hanging beam includes an inner ring side and an outer ring side arranged opposite to each other in a radial direction, and the ring hanging beam includes a plurality of assembly plates, and a plurality of welding positions are formed between the plurality of assembly plates; the ring hanging beam has a first part and a second part connected to each other along the height direction; the ring hanging beam welding method includes: using a first welding part to weld the welding position along the inner ring side of the first part; using a second welding part to weld the welding position along the outer ring side of the first part; flipping the ring hanging beam along the height direction of the ring hanging beam; using a first welding part to weld the welding position along the inner ring side of the second part; using a second welding part to weld the welding position along the outer ring side of the second part; wherein the first welding part and the second welding part simultaneously weld different welding positions on the inner ring side and the outer ring side. The present application provides a ring hanging beam welding method, which can improve welding efficiency and has high welding quality.
[0017] Beneficial technical effects achieved by this application:
[0018] (1) The present invention provides a ring beam welding method that can be applied to mobile full-scene nuclear power steel containment vehicle-shaped ring beams. The present application adopts a crawler welding robot and a wheeled welding robot to weld mobile full-scene nuclear power steel containment vehicle-shaped ring beams. Compared with existing gantry or cantilever type structural robots, the mobile automatic welding device adopts the "equipment to find the workpiece" method, which has the advantages of good accessibility, wide welding range, small footprint, low site requirements, short transportation time, and high equipment investment return rate. Compared with manual welding, the mobile The automatic welding device has the advantages of high welding precision, good welding quality, fast welding speed, low construction cost, less demand for high-level welders, and the ability to reach high and narrow places. It is suitable for the welding of batch non-standard parts of carbon steel and stainless steel materials, and can realize fillet welds and groove welding in flat welding, horizontal welding, and vertical welding positions. The robot structure is divided into wheeled and crawler types, which can realize the welding of products with a height of less than 4m, achieve "equipment finding workpieces", reduce the flipping and transportation of welding workpieces, flexibly reach the designated welding station, no tooling is required, and welding can be carried out as soon as it arrives, thereby improving production efficiency and product quality.
[0019] (2) The present application adopts the first welding part and the second welding part to weld the inner ring side and the outer ring side of the ring hanging beam at the same time, and the first welding part and the second welding part can be flexibly moved between the various workstations of the ring hanging beam according to the set program. There is no need to manually climb to high positions or narrow places for welding, which can reduce the labor intensity of workers, has higher safety, simplifies complex tasks, saves management costs, and improves the working environment.
[0020] In addition to the technical problems solved by the present application, the technical features that constitute the technical scheme, and the beneficial effects brought about by the technical features of the technical scheme described above, other technical problems that can be solved by a ring hanger beam welding method provided by the present application, other technical features included in the technical scheme, and the beneficial effects brought about by these technical features will be further described in detail in the specific embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a flow chart of a ring hanging beam welding method provided in an embodiment of the present application;
[0022] Figure 2 It is a schematic diagram of a ring hanging beam welding method provided in an embodiment of the present application;
[0023] Figure 3 This is a front view of a ring hanging beam provided in an embodiment of the present application;
[0024] Figure 4 It is a structural schematic diagram of the inner ring side of a ring suspension beam provided in an embodiment of the present application from a perspective;
[0025] Figure 5 is a structural schematic diagram of the inner ring side of a ring suspension beam provided in an embodiment of the present application from another perspective;
[0026] Figure 6 It is a structural schematic diagram of the outer ring side of a ring suspension beam provided in an embodiment of the present application;
[0027] Figure 7 It is a schematic diagram of the bottom welding of the first welding position and the third welding position of a ring hanging beam provided in an embodiment of the present application;
[0028] Figure 8 It is a schematic diagram of the filling and covering welding of the first welding position and the third welding position of a ring suspension beam provided in an embodiment of the present application;
[0029] Fig. 9 It is a structural schematic diagram of a crawler welding robot provided in an embodiment of the present application;
[0030] Fig.10 It is a structural schematic diagram of a wheeled welding robot provided in an embodiment of the present application.
[0031] Reference numerals:
[0032] 100-ring hanging beam; 110-top plate; 120-bottom plate; 130-web plate; 140-vertical plate; 150-inner ring side; 160-outer ring side; 170-first welding position; 180-second welding position; 190-third welding position;
[0033] 200 - first welding part; 300 - second welding part; 400 - crawler welding robot; 500 - wheeled welding robot. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0035] The steel containment vehicle-shaped ring crane beam is an important nuclear-grade equipment for nuclear power units and a critical path for lifting and hoisting key equipment in nuclear power plants. It is a box-type frame structure installed inside the steel containment cylinder to support the ring crane of the nuclear power plant. It needs to withstand huge dynamic and static loads for a long time during its service, so extremely high requirements are placed on the quality of the welds.
[0036] The welds of the ring beam assembly are mainly fillet welds without full penetration, and the height of the weld angle is mostly between 19mm and 25mm. The welding volume of the ring beam is large, and the weld filler metal volume of a single unit alone is more than 3.7 tons. The material is low-alloy steel, and the wall thickness of the ring beam is in the range of 38.1-44.5mm. The assembly is vertically assembled. In the prior art, all ring beam assemblies are manually welded using semi-automatic gas shielded welding. During welding, the operator needs to keep the welding gun at an appropriate angle to the workpiece surface and a proper distance between the welding gun and the workpiece, and then evenly move the welding gun to weld the workpiece.
[0037] However, this traditional manual welding method requires high skills of personnel, high labor intensity, low welding efficiency and poor welding quality.
[0038] To this end, the present application provides a ring hanging beam welding method, which uses a first welding part and a second welding part to weld different sides of the ring hanging beam at the same time, has a faster welding speed, can complete the welding operation in a shorter time, and adopts this double-sided welding process, so that the pressure of the weld is more uniform, the welds on both sides of the ring hanging beam are smoother, and the welding quality is better. Among them, the welding process is automatic gas shielded welding. At the same time, the first welding part and the second welding part can be flexibly moved between the various stations of the ring hanging beam along a preset trajectory, so that they can reach the designated welding position, and can be welded as they arrive. By flipping the ring hanging beam, the position to be welded is within the operable range of the first welding part and the second welding part, and there is no need to manually climb to a high position or a narrow position for welding, which can alleviate the intensity of manual labor and has higher safety.
[0039] In this embodiment, reference Figure 1 As shown, the present application provides a ring hanging beam welding method for welding a ring hanging beam 100, the ring hanging beam 100 includes an inner ring side 150 and an outer ring side 160 arranged opposite to each other in a radial direction, the ring hanging beam 100 includes a plurality of assembly plates, and a plurality of welding positions are formed between the plurality of assembly plates; the ring hanging beam 100 has a first part and a second part connected to each other in a height direction; the ring hanging beam welding method includes:
[0040] S101. Use a first welding piece to weld the welding position along the inner ring side of the first part.
[0041] S102, using a second welding piece to weld the welding position along the outer ring side of the first part.
[0042] The first welding piece 200 and the second welding piece 300 have a self-propelled function, and the operator controls the first welding piece 200 and the second welding piece 300 to make the first welding piece 200 and the second welding piece 300 move between different workstations of the ring hanging beam 100 to weld different welding positions of the ring hanging beam 100. The steps of carrying the ring hanging beam 100 can be reduced, the welding process can be shortened, and the welding efficiency can be significantly improved.
[0043] Exemplary, reference Fig. 9 and Fig.10 As shown, the first welding member 200 and the second welding member 300 may be wheeled welding robots or tracked welding robots. In this embodiment, the wheeled welding robot 500 welds the inner ring side 150 and the tracked welding robot 400 welds the outer ring side 160 as an example for description.
[0044] In this embodiment, reference Figure 2As shown, before welding, the first welding piece 200 and the second welding piece 300 need to be taught so that the first welding piece 200 and the second welding piece 300 can record the coordinates, speed and other information of the welding trajectory in real time. After the teaching is completed, the first welding piece 200 and the second welding piece 300 generate a corresponding welding program according to the recorded trajectory information. After the formal welding, the first welding piece 200 and the second welding piece 300 can be welded according to the stored welding program with just one-key start.
[0045] Specifically, the first welding part 200 and the second welding part 300 are both provided with cameras, which are arranged above the first welding part 200 and the second welding part 300, and the cameras can rotate around the first welding part 200 and the second welding part 300 to capture the positions of the bottom plate 120, the vertical plate 140 and the web plate 130 in real time.
[0046] In this embodiment, the main features of the wheeled welding robot or crawler welding robot are that the position programming and process parameter library development under multiple layers and multiple channels at different positions are completed through a large number of process tests, and the actual on-site process is continuously summarized and optimized and improved to achieve automatic tracking of welds and automatic welding routing. The final weld formation is beautiful and consistent, and the amount of post-weld grinding is greatly reduced. In addition, the welding efficiency can be effectively improved by adopting a welding method in which a welding robot and an operator work together. Compared with the traditional manual welding method, in this embodiment, one operator can control two welding robots, and the overall comprehensive welding efficiency can reach more than 2.5 times that of manual welding.
[0047] Specifically, the welding robot in this embodiment also includes a contact positioning and arc tracking module. The welding gun and the robotic arm are arranged at the front end of the vehicle chassis. The welding robot is controlled to perform fillet welds in flat, horizontal and vertical welding positions.
[0048] S103, flipping the ring suspension beam along the height direction of the ring suspension beam.
[0049] In this embodiment, after the first welding piece 200 and the second welding piece 300 are welded to the first part of the ring hanging beam 100, the ring hanging beam 100 is turned over by a crane. Specifically, the turning angle is 180°, so that the first welding piece 200 and the second welding piece 300 can weld the remaining part to be welded of the ring hanging beam 100. Compared with the traditional manual welding method, there is no need for manual climbing to a high position or a narrow position for welding, which can reduce the labor intensity of manual labor and has higher safety.
[0050] S104, using the first welding piece to weld the welding position along the inner ring side of the second part.
[0051] Specifically, the second part may be located near the bottom of the ring-hanging beam 100 , or near the top of the ring-hanging beam 100 . The position of the second part is not limited in this embodiment.
[0052] S105, using the second welding piece to weld the welding position along the outer ring side of the second part.
[0053] Specifically, the inner ring side 150 and the outer ring side 160 may be distributed on the ring beam 100 at equal distances along the first direction, or may be distributed on the ring beam 100 at unequal distances. In this embodiment, the positions of the inner ring side 150 and the outer ring side 160 are not limited.
[0054] The first welding piece 200 and the second welding piece 300 are welded to different welding positions on the inner ring side 150 and the outer ring side 160 simultaneously. The purpose of such arrangement is to prevent the side of the assembly plate from fusing under the action of thermal stress.
[0055] In this embodiment, reference Figures 3 to 6 As shown, the multiple assembly plates of the ring hanging beam 100 include a top plate 110, a bottom plate 120, a web plate 130 and at least two vertical plates 140. The top plate 110 and the bottom plate 120 are arranged opposite to each other in the vertical direction, and the web plate 130 and the vertical plates 140 are arranged between the top plate 110 and the bottom plate 120; the two side surfaces of the web plate 130 in the thickness direction face the inner ring side 150 and the outer ring side 160 respectively, and at least two vertical plates 140 are arranged on the opposite sides of the web plate 130 in the thickness direction; welding positions are formed between the top plate 110, the bottom plate 120, the web plate 130 and the vertical plates 140 for forming welds to weld the assembly plates together. Among them, the web plates 130 are arranged along the length direction of the top plate 110 to divide the ring hanging beam 100 into a plurality of chambers.
[0056] The first welding member 200 is used to weld the welding position, specifically including: using the first welding member 200 to weld the welding position between the bottom plate 120 , the vertical plate 140 and the surface of the web 130 close to the inner ring side 150 .
[0057] The second welding member 300 is used to weld the welding position, specifically including: the second welding member 300 is used to weld the welding position between the bottom plate 120 , the vertical plate 140 and the surface of the web 130 close to the outer ring side 160 .
[0058] S106, performing surface quality inspection on the weld formed at the welding position.
[0059] S107: Use the first welding piece and the second welding piece to weld a temporary attachment to the ring hanging beam.
[0060] In a possible implementation, welding is performed on the welding positions, including: spot welding the assembly plate; performing base welding on the welding positions; performing fill welding on the welding positions that have been base welded; and performing cover welding on the welding positions that have been fill welding.
[0061] Among them, before welding, the surface of each assembly board to be welded needs to be polished to clean up the oil, rust, burrs and other oxides within 25mm on both sides of the welding area. After cleaning, the surface of the assembly board is cleaned with acetone and other reagents until the metallic luster is exposed to ensure that the metal surface is clean during the welding process, which helps to form a stronger weld, thereby improving the strength and durability of the weld.
[0062] The assembly plates are assembled and spot welded according to the arrangement sequence of the ring beam 100 to play a role of pre-fixation. Specifically, in order to prevent welding deformation, temporary accessories can be welded during the assembly process to play a role of support and rigid fixation.
[0063] For example, the spot welding process can be manual welding or automatic welding. The welding parameters are: welding current 80-120A, welding voltage: 19-25V, welding speed: 9-10cm / min, wire feeding speed: 440-470cm / min, gas flow: 15-25L / min. The specific welding parameters can be selected according to the actual welding materials and the thickness of each assembly plate.
[0064] In this embodiment, the welding current can be 80A, 100A, 120A, or any value between 80-120A, the welding voltage can be 19V, 20V, 21V, or any value between 19-25V, the welding speed can be 9cm / min, 10cm / min, or any value between 9-10cm / min, the wire feeding speed can be 440cm / min, 450cm / min, 460cm / min, or any value between 440-470cm / min, and the gas flow rate can be 15L / min, 16L / min, 17L / min, or any value between 15-25L / min.
[0065] In this embodiment, the welding parameters of the base welding and the filling welding are the same, and the specific welding parameters are as follows: welding current 115-140A, welding voltage: 19-25V, gas flow: 20-25L / min, the distance between the first welding part 200 and the second welding part 300 and the ring hanging beam 100 is: 80-160cm. Welding current 115-140A, welding voltage: 19-25V, dry extension 20-25mm (voltage fine-tuning: -6.0 to -8.5), welding speed: 5.5-6.5cm / min, wire feeding speed: 440-470cm / min, swing amplitude: 6.0-7.5mm, swing frequency: 0.8-1.0Hz, swing dwell: left / right dwell is 0.6-1.3s, gas flow: 20-25L / min (gas cylinder pressure is at least 2MPa), distance from robot base to workpiece: 80-90cm (crawler) / 140-160cm (wheeled), outrigger lifting height: 22-25cm (wheeled) / (no limit on crawler, as long as the outrigger is under force). Specifically, the type of mixed gas is 20% CO 2 and 80% Ar mixed gas.
[0066] In this embodiment, the welding current can be 115A, 120A, 130A, 140A, or any value between 115-140A, the welding voltage can be 19V, 20V, 21V, 22V, or any value between 19-25V, and the gas flow rate can be 20L / min, 21L / min, 22L / min, 23L / min, or any value between 20-25L / min. In this embodiment, the welding parameters are adjusted according to the actual working conditions.
[0067] In this embodiment, the distance between the first welding piece 200 and the second welding piece 300 and the ring beam 100 is 80 cm, so as to ensure that there is a sufficient safety distance between the first welding piece 200 and the second welding piece 300 and the ring beam 100 to avoid collision and interference.
[0068] In a possible implementation, after performing backing welding on the welding position and before performing filler welding on the welding position after backing welding, the method further includes: performing flatness inspection, visual inspection and magnetic particle inspection on the welding position after backing welding.
[0069] Among them, the purpose of weld flatness detection is to ensure the surface flatness of the weld to avoid stress concentration and structural strength reduction caused by uneven welds. Specifically, when the flatness of the weld surface is detected to be low, a grinder or polisher can be used to grind and polish the weld position after base welding to repair the weld surface.
[0070] Among them, visual inspection is to observe the appearance of the weld with the naked eye to check whether there are obvious defects such as cracks, lack of fusion, etc. This method is simple and fast, and can find some obvious appearance defects, but it is limited by the experience and skill level of the inspectors.
[0071] Among them, magnetic particle testing is a more advanced detection method, which uses the aggregation of magnetic particles in a magnetic field to show defects. This method can detect tiny cracks and defects that are difficult to find by visual inspection, because after the ferromagnetic material is magnetized, the magnetic particles on the surface will show the location, size and shape of the defects, thereby improving the sensitivity and accuracy of the detection.
[0072] In a possible implementation, before welding the welding position, the method further includes: preheating the ring hanging beam 100 so that the temperature of the ring hanging beam 100 reaches a preset temperature.
[0073] Among them, before welding, the ring beam 100 needs to be preheated, so that the ring beam 100 can maintain a higher temperature during the welding process to reduce the temperature gradient during welding, thereby reducing welding stress and deformation. In addition, after preheating the ring beam 100, the hardening tendency of the weld and the heat-affected zone can also be reduced, thereby reducing the risk of cracks.
[0074] The preheating process is a complex process, and the preheating temperature needs to consider various factors such as material type and material thickness. The wall thickness of the ring beam 100 is 38.1-44.5 mm, and the wall thickness of the ring beam 100 is 38.1 mm, 39 mm, 44.5 mm, or any value between 38.1 and 44.5 mm. The material of the ring beam 100 is carbon steel, and the preset temperature range can be selected from 106°C to 181°C, and it is ensured that the temperature of each weld layer is not higher than 181°C. In this embodiment, the wall thickness is 39 mm as an example, and accordingly, the preheating temperature is selected as 106°C, which can achieve a better preheating effect.
[0075] Specifically, the preheating process and the teaching process can be carried out simultaneously, which can effectively reduce the welding time and improve the welding efficiency.
[0076] In a possible implementation, the welding height of the first welding piece 200 and the second welding piece 300 along the vertical direction is H1, the height of the ring hanging beam 100 is H2, and the ratio of H1 to H2 is (1:2)-(5:8).
[0077] During welding, the first welded part 200 and the second welded part 300 are welded from bottom to top. In this embodiment, the maximum lifting height of the first welded part 200 and the second welded part 300 is 4 meters, and the height of the ring beam 100 is 2.4 meters. Correspondingly, the ratio of H1 to H2 is 5:8.
[0078] Specifically, when the robotic arms of the first welding part 200 and the second welding part 300 are lifted to the maximum height, the ring beam 100 needs to be flipped so that the remaining part of the ring beam 100 to be welded falls within the operable range of the first welding part 200 and the second welding part 300.
[0079] In one possible implementation, reference Figure 3 and Figure 6 As shown, there is a first welding position 170 between the bottom plate 120 and the vertical plate 140, and between the top plate 110 and the vertical plate 140, and the first welding position 170 extends along the first direction; there is a second welding position 180 between the bottom plate 120 and the web plate 130, and between the top plate 110 and the web plate 130, and the second welding position 180 extends along the second direction; there is a third welding position 190 between the vertical plate 140 and the web plate 130, and the third welding position 190 extends along the vertical direction; the first direction, the second direction and the vertical direction intersect each other;
[0080] The welding positions between the bottom plate 120 , the vertical plate 140 and the web plate 130 close to the inner ring side 150 are welded, including: welding the first welding position 170 ; welding the second welding position 180 ; and welding the third welding position 190 .
[0081] During the welding process, a reasonable setting of the welding sequence can reduce stress concentration and evenly distribute the input heat to ensure smooth welding.
[0082] In this embodiment, when performing base welding, the first welding part 200 and the second welding part 300 are used to weld the first welding position 170, the second welding position 180 and the third welding position 190 in sequence. After the welding of the first part or the second part of the ring hanging beam 100 is completed, the ring hanging beam 100 is flipped 180° by a crane, and then the base welding is continued for the remaining parts of the ring hanging beam 100 to be welded.
[0083] Specifically, for ease of understanding, the inner ring side 150 of the ring hanger beam 100 is referred to as the A side, and the outer ring side 160 of the ring hanger beam 100 is referred to as the B side. Correspondingly, the welding positions in the first part of the A side are referred to as A1, A2, A3, A4 and A5, and the welding positions in the second part of the A side are referred to as A6, A7 and A8; the welding positions in the first part of the B side are referred to as B1, B2, B3, B4 and B5, and the welding positions in the second part of the B side are referred to as B6, B7 and B8, as shown in FIG. Figures 4 to 6 As shown. Among them, B6 and B7 are symmetrical to B4 and B5 respectively.
[0084] The first part may be located near the bottom of the ring beam 100 or near the top of the ring beam 100. In this embodiment, the first part located near the bottom of the ring beam 100 is taken as an example for description.
[0085] During welding, in order to reduce welding deformation, on the basis of ensuring full penetration, try to adopt multi-layer and multi-pass welding technology with small specifications, short arcs, thin and narrow welds. The two machines are symmetrically arranged to weld on both sides at the same time. When welding each compartment, A1, A4, B1, and B2 are welded alternately. Among them, during the filling and cover welding of the ring hanger beam 100, the second layers of A1, A4, B1, and B2 also need to be staggered. The welding order of each weld is A1, A4, A3, A5, A2, A6, A7, A8 (front), B1, B2, B4, B5, B3, B6, B7, B8 (back), and the layer temperature of each weld must be ensured to be no higher than 181°C.
[0086] Among them, when performing base welding, the welding sequence is as follows:
[0087] ① The wheeled robot teaches A1-A5 (5) base welds at one time; ② During the teaching of the wheeled robot, the riveter preheats A1, A4, A3, A5, and A2 welds in turn, and the teaching and preheating are completed simultaneously; ③ Start welding and weld A1, A4, A3, A5, and A2 base welds in turn; ④ The crawler robot teaches B1-B5 (5) base welds at one time; ⑤ During the teaching of the crawler robot, the riveter preheats B1, B2, B4, B5, and B3 base welds; ⑥ Start welding and weld B1, B2, B4, B5, and B3 base welds in turn; ⑦ Each chamber cycles through steps ① to ⑥ in turn to weld the lower half of the ring hanging beam; ⑧ After the welding below half the height of both sides of the vertical plate 140 is completed, turn the workpiece over and cycle through steps ① to ⑦, and continue welding the other half until the base weld of the entire ring hanging beam 100 is completed.
[0088] Among them, when performing filling welding and cap welding, the welding sequence is as follows:
[0089] ① The wheeled robot teaches the A1 and A4 filling and covering welds at one time; ② During the wheeled robot teaching, the riveter preheats the A1 and A4 welds in turn; ③ Start welding and weld the A1 and A4 filling and covering welds; ④ The crawler robot teaches the B1 and B2 filling and covering welds at one time; ⑤ During the crawler robot teaching, the riveter preheats the B1 and B2 welds; ⑥ Start welding and weld the B1 and B2 filling and covering welds; ⑦ Each chamber Cycle steps ① to ⑥ in sequence; ⑧ After the welding of A1, A4, B1, and B2 filling caps is completed, teach the A3, A5, A2 and B4, B5, and B3 filling cap welds in sequence on both sides of the ring hanging beam; ⑨ During the teaching of the crawler / wheeled robot, the riveter preheats the A3, A5, A2 and B4, B5, and B3 welds in sequence; ⑩ Start welding, and weld the A3, A5, A2 and B4, B5, and B3 filling cap welds on both sides of the ring hanging beam 100 at the same time; Each chamber cycles through steps ⑧-⑩ in sequence until the A3-A5 and B3-B5 filling capping welds of the entire ring beam 100 are welded; After the welding of A1-A5 and B1-B5 is completed, the workpiece is turned over, and the wheeled and crawler robots are used to teach the A6-A8 and B6-B8 filling and covering welds at one time. During the teaching period, the riveter preheats the A6, A7, A8 and B6, B7, B8 welds in turn. After the preheating reaches 106°C, the welding is started, and the A6, A7, A8 and B6, B7, B8 filling and covering welds are welded; Each chamber cycles in turn Steps are continued until the entire workpiece filling and cover welds are completed.
[0090] In this embodiment, α1 is 45°, and the weld angle height is controlled at 12-14 mm. The weld angle height can be selected from 12 mm, 13 mm, 14 mm or any value between 12-14 mm. In this embodiment, the weld foot height of 12 mm is taken as an example.
[0091] For example, Figure 8 Schematic diagram of the filling cap welding of the first welding position and the third welding position. In this embodiment, α2 and α3 are 45°, the final weld foot height is 19 mm, and the welding gun posture is detailed in FIG. Figure 8 .
[0092] The first welding position 170 and the third welding position 190 adopt a two-layer three-pass welding process. Specifically, the first welding position 170 and the third welding position 190 only need to weld one layer when performing base welding, and need to weld two layers when performing filling welding.
[0093] Specifically, in this embodiment, the uppermost welding layer of the first welding position 170 and the third welding position 190 can serve as both a filling layer and a cover layer.
[0094] In this embodiment, when performing cover welding, the first welding member 200 and the second welding member 300 are used to perform cover welding on the second welding position 180 along the second direction.
[0095] In a possible implementation, the number of welding layers of the first welding position 170 and the third welding position 190 is the same and is less than the number of welding layers of the second welding position 180 .
[0096] In this embodiment, in order to reduce welding deformation, on the basis of ensuring sufficient penetration, a multi-layer and multi-pass welding process with small specifications, short arcs, and thin and narrow welds is adopted as much as possible, and two welding parts are symmetrically arranged on both sides of the ring suspension beam 100 for simultaneous welding.
[0097] Specifically, the second welding position 180 is in a high stress area. To ensure the overall strength and safety of the welded structure, the number of welding layers at the second welding position 180 is greater than that at the first welding position 170 and the third welding position 190 .
[0098] In a possible implementation, the number of welding layers of the first welding position 170 and the third welding position 190 is 2-5 layers; the number of welding layers of the second welding position 180 is 5-8 layers.
[0099] Specifically, by welding different numbers of layers at different positions of the ring hanging beam 100, the generation of cracks can be effectively prevented. Exemplarily, the number of welding layers of the first welding position 170 and the third welding position 190 can be 2 layers, 3 layers, 4 layers and 5 layers, or any value between 2-5 layers, and the number of welding layers of the second welding position 180 can be 5 layers, 6 layers, 7 layers and 8 layers, or any value between 5-8 layers. Among them, as an optional embodiment, the number of welding layers of the first welding position 170 and the third welding position 190 is 2 layers, and the number of welding layers of the second welding position 180 is 5 layers.
[0100] Therefore, the present application provides a ring-suspended beam welding method for welding a ring-suspended beam, wherein the ring-suspended beam includes an inner ring side and an outer ring side arranged opposite to each other in a radial direction, and the ring-suspended beam includes multiple assembly plates, and multiple welding positions are formed between the multiple assembly plates; the ring-suspended beam has a first part and a second part connected to each other along the height direction; the ring-suspended beam welding method includes: using a first welding part to weld the welding position along the inner ring side of the first part; using a second welding part to weld the welding position along the outer ring side of the first part; flipping the ring-suspended beam along the height direction of the ring-suspended beam; using a first welding part to weld the welding position along the inner ring side of the second part; using a second welding part to weld the welding position along the outer ring side of the second part; wherein the first welding part and the second welding part simultaneously weld different welding positions on the inner ring side and the outer ring side; performing surface quality inspection on the welds formed on the welding positions; and using the first welding part and the second welding part to weld temporary accessories to the ring-suspended beam.
[0101] It should be noted that the embodiments represented by "one embodiment", "an embodiment", "an exemplary embodiment", "some embodiments", etc. mentioned in the specification may include specific features, structures or characteristics, but not every embodiment may include the specific features, structures or characteristics. In addition, such phrases do not necessarily refer to the same embodiment. In addition, when describing specific features, structures or characteristics in conjunction with an embodiment, it is within the knowledge of those skilled in the art to implement such features, structures or characteristics in conjunction with other embodiments that are explicitly or not explicitly described.
[0102] In general, terms should be understood, at least in part, by the context in which they are used. For example, the terms "one or more" as used herein may be used to describe any feature, structure, or characteristic in a singular sense, or may be used to describe a combination of features, structures, or characteristics in a plural sense, depending, at least in part, on the context. Similarly, terms such as "an" may also be understood to convey singular usage or to convey plural usage, depending, at least in part, on the context.
[0103] It should be easily understood that “on,” “above,” and “over” in the present disclosure should be interpreted in the broadest manner, so that “on” not only means “directly on something,” but also includes the meaning of “on something” with intervening features or layers therebetween, and “above” or “over” not only includes the meaning of “above” or “over,” but also may include the meaning of “above” or “over something” with no intervening features or layers therebetween (i.e., directly on something).
[0104] In addition, spatially relative terms, such as "below," "below," "beneath," "above," "above," etc., may be used herein for ease of description to describe the relationship of one element or feature relative to other elements or features as shown in the figures. Spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation shown in the figures. The device may have other orientations (rotated 90 degrees or at other orientations), and the spatially relative descriptors used herein may likewise be interpreted accordingly.
[0105] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for welding a ring beam, It is characterized in that Used for welding a ring suspension beam, the ring suspension beam (100) comprising an inner ring side (150) and an outer ring side (160) arranged opposite to each other in a radial direction, the ring suspension beam (100) comprising a plurality of assembly plates, a plurality of welding positions being formed between the plurality of assembly plates; The ring suspension beam (100) has a first portion and a second portion connected to each other along the height direction; The ring hanging beam welding method comprises: Using a first welding piece, welding the welding position along the inner ring side of the first part; Using a second welding piece to weld the welding position along the outer ring side of the first part; Turning over the ring hanging beam along the height direction of the ring hanging beam; Using the first welding piece, welding the welding position along the inner ring side of the second part; Using the second welding piece, welding the welding position along the outer ring side of the second part; Wherein, the first welding piece and the second welding piece simultaneously weld different welding positions on the inner ring side and the outer ring side; Performing surface quality inspection on the weld formed on the welding position; The temporary attachment is welded to the ring hanger beam using the first welding piece and the second welding piece.
2. The ring beam welding method according to claim 1, It is characterized in that The plurality of assembly plates of the ring beam (100) include a top plate (110), a bottom plate (120), a web plate (130) and at least two vertical plates (140), wherein the top plate (110) and the bottom plate (120) are arranged opposite to each other in a vertical direction, and the web plate (130) and the vertical plates (140) are both arranged between the top plate (110) and the bottom plate (120); The two side surfaces of the web (130) along the thickness direction respectively face the inner ring side (150) and the outer ring side (160), and at least two vertical plates (140) are respectively arranged on opposite sides of the web (130) along the thickness direction; The welding positions are formed between the top plate (110), the bottom plate (120), the web plate (130) and the vertical plate (140); Using the first welding member (200) to weld the welding position specifically includes: Using the first welding member (200), welding the welding positions between the bottom plate (120), the vertical plate (140) and the surface of the web plate (130) close to the inner ring side (150); The second welding member (300) is used to weld the welding position, specifically comprising: The second welding member (300) is used to weld the welding positions between the bottom plate (120), the vertical plate (140) and the surfaces of the web (130) close to the outer ring side (160).
3. The ring beam welding method according to claim 2, It is characterized in that Welding the welding position includes: spot welding the assembly plate; Performing base welding on the welding position; Performing fill welding on the welding position after the base welding; The welding position after the filling welding is subjected to the cap welding.
4. The ring beam welding method according to claim 3, It is characterized in that After performing base welding on the welding position and before performing fill welding on the welding position after the base welding, the method further includes: Performing flatness inspection, visual inspection and magnetic particle inspection on the welding position after the base welding; The welding position after the base welding is ground and polished.
5. The ring beam welding method according to any one of claims 2 to 4, It is characterized in that Before welding the welding position, the method further includes: preheating the ring hanging beam to make the temperature of the ring hanging beam reach a preset temperature.
6. The ring beam welding method according to claim 5, It is characterized in that The preset temperature range is 106°C-181°C.
7. The ring beam welding method according to any one of claims 2 to 4, It is characterized in that The welding height of the first welding part and the second welding part in the vertical direction is H1, the height of the ring hanging beam is H2, and the ratio of H1 to H2 is (1:2)-(5:8).
8. The ring beam welding method according to any one of claims 2 to 4, It is characterized in that A first welding position (170) is provided between the bottom plate (120) and the vertical plate (140), and between the top plate (110) and the vertical plate (140), and the first welding position (170) extends along a first direction; a second welding position (180) is provided between the bottom plate (120) and the web plate (130), and between the top plate (110) and the web plate (130), and the second welding position (180) extends along a second direction; a third welding position (190) is provided between the vertical plate (140) and the web plate (130), and the third welding position (190) extends along a vertical direction; the first direction, the second direction and the vertical direction intersect each other; Welding the welding positions between the bottom plate (120), the vertical plate (140) and the surface of the web (130) close to the inner ring side (150) comprises: Welding the first welding position (170); Welding the second welding position (180); The third welding position (190) is welded.
9. The ring beam welding method according to claim 8, It is characterized in that The number of welding layers of the first welding position (170) and the third welding position (190) is the same, and is less than the number of welding layers of the second welding position (180).
10. The ring beam welding method according to claim 9, It is characterized in that The number of welding layers of the first welding position (170) and the third welding position (190) is 2-5 layers; And / or, the number of welding layers of the second welding position (180) is 5-8 layers.