Top-limited temporary section steel bearing support integral installation construction method

By dividing the steel pipe columns of the temporary steel load-bearing bracket into bottom and top sections, and using the design of limit plates and clamps, combined with the electric hoist double-lifting point lifting technology, the installation problem under the condition of restricted top is solved, and the installation problem is achieved The efficient integrated installation of temporary steel load-bearing brackets improves efficiency and cost-effectiveness.

CN118895722APending Publication Date: 2024-11-05GUANGXI ROAD & BRIDGE ENG GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411189649.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

When bridge reinforcement or old bridge is removed, if the top of the temporary steel load-bearing bracket is limited, the crane cannot lift the steel pipe columns normally, resulting in low installation efficiency and high cost, and it is difficult for existing methods to achieve effective installation.

Method used

By dividing the steel pipe column into the bottom section and the top section, setting limit plates and clamps on the top section, vertical and oblique lifting are used for lifting vertically and obliquely, and combining with the electric hoist double-lifting point lifting bracket connection, the electric hoist is realized Overall installation of the bracket.

Benefits of technology

Under the condition of restricted top, the vertical docking of steel pipe columns and the lifting of bracket connections is efficiently completed, which improves installation efficiency and saves mechanical shifts, labor costs and construction periods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895722A_ABST
    Figure CN118895722A_ABST
Patent Text Reader

Abstract

According to the overall installation construction method for the temporary section steel bearing support with the limited top, a steel pipe stand column of the temporary section steel bearing support is divided into a bottom section and a top section which are short in length, and vertical butt joint of the steel pipe stand column can be completed under the condition that a crane cannot lift an arm to obliquely lift a steel pipe; the support linkage system is hoisted by the two electric hoists attached to the tops of the steel pipe stand columns, hoisting and positioning of the support linkage system can be efficiently completed, the distribution beam is hoisted through a crane, and therefore the profile steel bearing support is installed under the conditions that the top is limited and a crane hook cannot be located over a hoisted object, the installation efficiency is high, and the cost is low. And the machine team, the labor cost and the construction period can be saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a construction technology for integrally erecting a temporary steel load-bearing support, and in particular to an integral installation construction method for a temporary steel load-bearing support with a restricted top. Background Art

[0002] Temporary steel load-bearing brackets are often used to temporarily support the structural components of bridges in bridge projects. In the prior art, when installing temporary steel brackets, there are no structures blocking the sky, the crane can extend its arm normally, the hook is located directly above the hanging object, the steel bracket steel pipe can be vertically docked, the bracket connection system and the bracket distribution beam are normally lifted into place, and the installation is relatively easy. When reinforcing a bridge or dismantling an old bridge, it is necessary to install a temporary steel load-bearing bracket under the bridge for support. At this time, there are structures such as bridge decks blocking the upper part, and the crane boom cannot extend above the hanging object. The boom and hook can only be on the side of the hanging object. The steel pipe column of the temporary steel load-bearing bracket cannot be vertically docked, the height of the crane's auxiliary hook lifting connection system is limited, the positioning efficiency is relatively low, the construction cost is high, and the excavation of a deeper foundation pit still cannot ensure that the crane hook is above the hanging object. The original installation method is difficult to achieve the installation of the steel load-bearing bracket with a top restriction. Summary of the invention

[0003] In view of the problem that traditional installation methods are difficult to achieve installation of top-restricted steel load-bearing supports, the present invention provides an overall installation construction method for a temporary steel load-bearing support with a top restriction, which can complete the installation of the steel load-bearing support when the top is restricted and the crane hook cannot be directly above the hoisted object.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is:

[0005] A method for integrally installing a temporary steel load-bearing support with a top restriction, comprising the following steps:

[0006] A temporary steel load-bearing support is provided, the temporary steel load-bearing support comprises a steel pipe column, a support connection system and a support distribution beam, the steel pipe column comprises a bottom segment and a top segment fixed to the top of the bottom segment and coaxially arranged with the bottom segment, a first limiting plate and a second limiting plate which are oppositely arranged are convexly arranged on the top surface of the top segment, and a limiting groove is formed between the first limiting plate, the second limiting plate and the top surface of the top segment; the support connection system is fixed between two adjacent steel pipe columns, and the support distribution beam is fixed in the limiting groove;

[0007] The installation method of the steel pipe column comprises the following steps:

[0008] S11, directly vertically installing the bottom segment in place by a crane;

[0009] S12, after the bottom segment is installed in place, a plurality of stoppers are welded at intervals along the circumferential direction on the top edge of the bottom segment, and the plurality of stoppers and the top surface of the bottom segment are surrounded to form a docking groove with a side opening;

[0010] S13, using a crane to lift the top segment obliquely, moving the top segment to the top of the bottom segment by the crane, and pushing the bottom of the top segment into the docking groove along the side opening;

[0011] S14, lowering and slowly straightening the top segment by the crane so that the top segment is in a vertical state, and fixing the bottom end of the top segment to the top end of the bottom segment;

[0012] S15, repeating steps S11-S14 to complete the installation of a plurality of the steel pipe columns;

[0013] The installation method of the bracket connection system comprises the following steps:

[0014] Install an electric hoist on two adjacent steel pipe columns, use the double lifting points of the electric hoist to simultaneously lift the bracket connection system, and after the bracket connection system is lifted into place, fix it to the two adjacent steel pipe columns;

[0015] The method for installing the support distribution beam comprises the following steps:

[0016] First, fix the first limiting plate to one side edge of the top surface of the top segment, and lift the bracket distribution beam into place by a crane so that one side of the bracket distribution beam rests against the first limiting plate; then fix the second limiting plate to the top surface of the top segment and be located on the side of the bracket distribution beam away from the first limiting plate.

[0017] Furthermore, a plurality of the stoppers are fixed at intervals on the outer peripheral surface of the top end of the bottom segment, and are protruded above the top surface of the bottom segment to surround and form the docking groove, and along the pushing direction of the top segment, a plurality of the stoppers are located on the rear side of the bottom segment, and the front side of the bottom segment where the stoppers are not provided forms the side opening.

[0018] Furthermore, in step S12, a pair of clamping blocks are fixed at the top of the bottom segment, the pair of clamping blocks are located at the position of the bottom segment farthest from the side opening, the pair of clamping blocks are relatively fixed on the inner peripheral wall and the outer peripheral wall of the bottom segment, and the pair of clamping blocks are both convexly arranged above the top surface of the bottom segment, so as to form a clamping groove together with the top surface of the bottom segment;

[0019] In step S14, when the top segment is lowered by the crane, the peripheral wall on the bottom side of the top segment is inserted into the slot, and a welding point is formed by spot welding at the contact position between the top segment and the bottom wall of the slot. The top segment is pulled by the crane to rotate around the welding point, thereby slowly straightening the top segment.

[0020] Furthermore, the distance between the block fixed on the inner peripheral wall and the top surface of the bottom segment is h, and the distance between the block fixed on the outer peripheral wall and the top surface of the bottom segment is H, h <H。

[0021] Furthermore, in step S11, the method of directly vertically installing the bottom segment in place by a crane is: first lifting ears are welded on opposite sides of the upper portion of the bottom segment, and the two first lifting ears are lifted simultaneously by a crane so that the bottom segment is lifted in a vertical state.

[0022] Furthermore, in step S13, the method of using a crane to lift the top segment obliquely is as follows: a second lifting lug is welded on one side of the upper portion of the top segment, and the second lifting lug is lifted by the crane, so that the top segment is lifted in an inclined state.

[0023] Furthermore, during the installation of the bracket distribution beam, the method of lifting the bracket distribution beam into place by a crane is: lifting the opposite ends of the bracket distribution beam respectively by double cranes, and then pushing the bracket distribution beam along the side of the top segment where the second limit plate is not installed to the top surface of the top segment until one side of the bracket distribution beam abuts against the first limit plate, thereby putting the bracket distribution beam into place.

[0024] Furthermore, during the installation of the bracket connection system, the bracket connection system is set between two adjacent steel pipe columns, and the lifting ropes of the electric hoists on the two adjacent steel pipe columns are respectively lifted up to the opposite ends of the bracket connection system, and the electric hoists are started to lift the bracket connection system to a preset installation position and then fix the bracket connection system to the two adjacent steel pipe columns.

[0025] Furthermore, the bracket connection system includes a horizontal connection system and an inclined rod connection system. During hoisting, the lengths of the lifting ropes connected to the two ends of the horizontal connection system are the same, thereby ensuring that the horizontal connection system is hoisted in a horizontal posture; when hoisting the inclined rod connection system, first, the inclined rod connection system is lifted horizontally into place, and then the inclined rod connection system is adjusted to a preset inclined posture and fixed in place by adjusting the lengths of the lifting ropes connected to the two ends of the inclined rod connection system.

[0026] Due to the adoption of the above technical solution, the present invention has the following beneficial effects:

[0027] 1. The overall installation construction method of the temporary steel load-bearing support with a limited top is to divide the steel pipe column of the temporary steel load-bearing support into two shorter bottom sections and top sections, so that the vertical docking of the steel pipe columns can be completed when the crane cannot lift the arm to lift the steel pipe obliquely; the support connection system adopts two electric hoists attached to the top of the steel pipe column for lifting, which can efficiently complete the lifting and positioning of the support connection system, and the distribution beam is lifted by the crane, so as to complete the installation of the steel load-bearing support when the top is limited and the crane hook cannot be directly above the hoisted object, and the installation efficiency is high, which can save machine hours, labor costs and construction period.

[0028] 2. The overall installation construction method of the above-mentioned temporary steel load-bearing support with a restricted top is as follows: a plurality of blocks are fixed on the top surface of the bottom segment, and the plurality of blocks have docking grooves with side openings. The blocks can limit the top segment so that the top segment falls into the docking groove in a preset inclined posture; in addition, a pair of clamping blocks are fixed at the top of the bottom segment, and the pair of clamping blocks and the bottom segment are surrounded to form a clamping groove. After the top segment is lowered into the groove, the surrounding wall on one side of the bottom end of the top segment is inserted into the groove, and the contact portion between the top segment and the bottom wall of the groove is spot welded and fixed, so that the top segment can be formed into a hinged state, and the top segment can be positioned so that the top segment can only rotate but cannot move at will, thereby adjusting the top segment to be coaxial with the bottom segment as soon as possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic front view of a temporary steel load-bearing support according to a preferred embodiment of the present invention;

[0030] Figure 2 for Figure 1 The left side schematic diagram of the steel pipe column and the support distribution beam of the temporary steel load-bearing support shown;

[0031] Figure 3 This is a schematic diagram of the installation of the bottom segment of the steel pipe column in a preferred embodiment of the present invention;

[0032] Figure 4 This is a schematic diagram of the installation of the top segment of the steel pipe column in a preferred embodiment of the present invention;

[0033] Figure 5 for Figure 4 A magnified view at point A;

[0034] Figure 6 It is a partial structural schematic diagram of the bottom segment of a preferred embodiment of the present invention;

[0035] Figure 7It is a schematic diagram of the installation of the bracket connection system of the preferred embodiment of the present invention and the bracket connection system installed by a crane in the prior art;

[0036] Figure 8 This is a schematic diagram of the installation of a support distribution beam according to a preferred embodiment of the present invention;

[0037] Fig. 9 for Figure 8 Side view of

[0038] Fig.10 for Fig. 9 Enlarged view at B;

[0039] Main component symbols

[0040] 100. Temporary steel load-bearing support; 10. Steel pipe column; 11. Bottom segment; 112. First lifting eye; 12. Top segment; 121. Second lifting eye; 13. First limiting plate; 14. Second limiting plate; 15. Limiting groove; 16. Block; 161. Side opening; 163. Docking groove; 17. Block; 171. Slot; 30. Support connection system; 31. Horizontal connection system; 32. Diagonal rod connection system; 50. Support distribution beam; 200. Crane; 300. Electric hoist; 400. Bridge deck. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] It should be noted that when a component is referred to as being "fixed to" another component, it may be directly on the other component or there may also be a component centered. When a component is considered to be "connected to" another component, it may be directly connected to the other component or there may also be a component centered. When a component is considered to be "set on" another component, it may be directly set on the other component or there may also be a component centered. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.

[0043] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0044] See also Figure 1 A preferred embodiment of the present invention provides a method for overall installation of a temporary steel load-bearing support with a top restriction, which is applicable to the installation of steel load-bearing supports under various top restriction conditions, for example, when the top of the steel load-bearing support is blocked by the bridge deck 400 and the crane hook cannot be directly above the hanging object, resulting in its installation being restricted. The method for overall installation of a temporary steel load-bearing support with a top restriction comprises the following steps:

[0045] A temporary steel load-bearing support 100 is provided, comprising a steel pipe column 10, a support connection system 30 and a support distribution beam 50. The number of steel pipe columns 10 is several, and the several steel pipe columns 10 are arranged at intervals. Each steel pipe column 10 includes a bottom segment 11 and a top segment 12 fixed to the top of the bottom segment 11 and arranged coaxially with the bottom segment 11. Please refer to Figure 2 , a first limiting plate 13 and a second limiting plate 14 are convexly provided on the top surface of the top segment 12, and the first limiting plate 13, the second limiting plate 14 and the top surface of the top segment 12 are surrounded by a limiting groove 15. The number of the bracket connection system 30 is several, and each bracket connection system 30 is fixed between two adjacent steel pipe columns 10 by welding or the like; the structure of the bracket connection system 30 belongs to the prior art, and will not be described here for the sake of space saving. The number of the bracket distribution beams 50 is several, and the bracket distribution beams 50 are fixed in the corresponding limiting grooves 15 by welding or the like. The structure of the bracket distribution beams 50 belongs to the prior art, and will not be described here for the sake of space saving.

[0046] Please also see Figures 3 to 6 The installation method of the steel pipe column 10 comprises the following steps:

[0047] S11 , the bottom segment 11 is directly installed vertically in place by using the crane 200 .

[0048] Specifically, in step S11, the method of directly vertically installing the bottom segment 11 in place by the crane 200 is: a first lifting lug 112 is respectively welded on opposite sides of the upper portion of the pipe body of the bottom segment 11, and the two first lifting lugs 112 are simultaneously lifted by the crane 200, so that the bottom segment 11 is lifted in a vertical state. After being lifted in place, the bottom end of the bottom segment 11 is fixed to a support such as the ground. The method of fixing the bottom end of the bottom segment 11 belongs to the prior art and will not be described here for the sake of space.

[0049] S12, after the bottom segment 11 is installed in place, a plurality of stoppers 16 are welded at intervals along the circumferential direction on the top edge of the bottom segment 11, and the plurality of stoppers 16 and the top surface of the bottom segment 11 are surrounded to form a docking groove 163 with a side opening 161.

[0050] In this embodiment, a plurality of stoppers 16 are fixed at intervals on the outer peripheral surface of the top end of the bottom segment 11, and are protruded above the top surface of the bottom segment 11 to form a docking groove 163, and along the pushing direction of the top segment 12, a plurality of stoppers 16 are located on the rear side of the bottom segment 11, and a side opening 161 is formed on the front side of the bottom segment 11 where no stoppers 16 are provided.

[0051] In this embodiment, a pair of clamping blocks 17 are also fixed at the top of the bottom segment 11. The pair of clamping blocks 17 are located at the position farthest from the side opening 161 of the bottom segment 11. The pair of clamping blocks 17 are respectively fixed on the inner peripheral wall and the outer peripheral wall of the bottom segment 11, and the pair of clamping blocks 17 are both protruded above the top surface of the bottom segment 11 and are surrounded with the top surface of the bottom segment 11 to form a clamping groove 171. In this embodiment, the distance between the clamping block 17 fixed to the inner peripheral wall and the top surface of the bottom segment 11 is h, and the distance between the clamping block 17 fixed to the outer peripheral wall and the top surface of the bottom segment 11 is H, and h <H。

[0052] S13 , using the crane 200 to lift the top segment 12 obliquely, moving the top segment 12 to the top of the bottom segment 11 by the crane 200 , and pushing the bottom of the top segment 12 into the docking groove 163 along the side opening 161 .

[0053] Specifically, in step S13, the method of using the crane 200 to lift the top segment obliquely is as follows: a second lifting lug 121 is welded on one side of the upper part of the pipe body of the top segment 12, and the second lifting lug 121 is lifted by the auxiliary hook of the crane 200, so that the top segment 12 is lifted in an inclined state.

[0054] S14, lowering and slowly straightening the top segment 12 by means of the crane 200, so that the top segment 12 is in a vertical state, and fixing the bottom end of the top segment 12 and the top end of the bottom segment 11.

[0055] Specifically, in step S14, during the process of lowering the top segment 12 by the crane 200, the peripheral wall on one side of the bottom end of the top segment 12 is inserted into the slot 171, and a welding point is formed by spot welding at the contact position between the top segment 12 and the bottom wall of the slot 171 (i.e., the top surface of the bottom segment 11), and the top segment 12 is pulled by the crane 200 to rotate around the welding point, thereby slowly straightening the top segment 12, and as the top segment 12 rotates, the number of contact points between the top segment 12 and the bottom segment 11 increases. In this process, the contact points between the top segment 12 and the bottom segment 11 can be spot welded, thereby increasing the spot welding positions and ensuring that the hinged state of the top segment 12 and the bottom segment 11 is more secure; when the top segment 12 is straightened, the top segment 12 is coaxial with the bottom segment 11, and the bottom end of the top segment 12 and the top end of the bottom segment 11 are fixed by welding or the like.

[0056] S15, repeating steps S11-S14 to complete the installation of multiple steel pipe columns 10.

[0057] The installation method of the bracket connection system 30 includes the following steps:

[0058] Please also see Figure 7 , install the electric hoist 300 on two adjacent steel pipe columns 10, use the double lifting points of the electric hoist 300 to simultaneously lift the bracket connection system 30, and fix the bracket connection system 30 to the two adjacent steel pipe columns 10 after the bracket connection system 30 is lifted into place. Specifically, the bracket connection system 30 is set between the two adjacent steel pipe columns 10, and the lifting ropes of the electric hoist 300 on the two adjacent steel pipe columns 10 are used to lift the opposite ends of the bracket connection system 30, and the electric hoist 300 is started. After lifting the bracket connection system 30 to the preset installation position, the bracket connection system 30 is fixed to the top segment 12 or the bottom segment 11 at the corresponding position by welding or other methods. Please refer to Figure 1 The support connection system 30 includes a horizontal connection system 31 and an inclined rod connection system 32. When hoisting, the lengths of the lifting ropes connected to the two ends of the horizontal connection system 31 are the same, so as to ensure that the horizontal connection system 31 is hoisted in a horizontal posture; when hoisting the inclined rod connection system 32, first, the inclined rod connection system 32 is hoisted horizontally in place, and then the inclined rod connection system 32 is adjusted to a preset inclined posture and fixed in place by adjusting the lengths of the lifting ropes connected to the two ends of the inclined rod connection system 32. Repeat the above steps until all the support connection systems 30 are installed.

[0059] Please join us Figures 8 to 10 , the installation method of the bracket distribution beam 50 includes the following steps:

[0060] First, fix the first limiting plate 13 to one side edge of the top surface of the top segment 12, and lift the bracket distribution beam 50 into place by a crane so that one side of the bracket distribution beam 50 is against the first limiting plate 13; then fix the second limiting plate 14 to the top surface of the segment 12 and be located on the side of the bracket distribution beam 50 away from the first limiting plate 13.

[0061] Specifically, during the installation of the bracket distribution beam 50, the method of lifting the bracket distribution beam 50 into place by a crane is as follows: lift the opposite ends of the bracket distribution beam 50 by two cranes respectively, and then push the bracket distribution beam 50 along the side of the top segment 12 where the second limiting plate 14 is not installed to the top surface of the top segment 12 until one side of the bracket distribution beam 50 abuts against the first limiting plate 13, thereby putting the bracket distribution beam 50 into place. Repeat the above steps until all bracket distribution beams 50 are installed.

[0062] The above-mentioned overall installation construction method of the temporary steel load-bearing support 100 with a limited top divides the steel pipe column 10 of the temporary steel load-bearing support 100 into two shorter bottom sections 11 and top sections 12, and can complete the vertical docking of the steel pipe column 10 when the crane 200 cannot lift the arm to lift the steel pipe column 10 at an angle; two electric hoists 300 are attached to the top of the steel pipe column 10, and two electric hoists 300 are used to lift the bracket connection system 30 at two points, which can efficiently complete the lifting and positioning of the bracket connection system 30, and the distribution beam is lifted by the double cranes 200, thereby completing the installation of the steel load-bearing support when the top is limited and the crane 200 hook cannot be directly above the hoisted object, and the installation efficiency is high, which can save machine hours, labor costs and construction period.

[0063] The above-mentioned overall installation construction method of the temporarily formed steel weight-bearing support 100 with a restricted top has a plurality of stoppers 16 fixed on the top surface of the bottom section 11. The plurality of stoppers 16 have docking grooves 163 with side openings 161. The stoppers 16 can limit the top section 12, so that the top section 12 falls into the docking groove 163 in a preset inclined posture. In addition, a pair of clamping blocks 17 are fixed at the top end of the bottom section 11. The pair of clamping blocks 17 enclose to form a clamping groove 171. After the top section 12 is lowered and falls into the groove, the peripheral wall on one side of the bottom end of the top section 12 is inserted into the clamping groove 171, and spot welding is fixed at the contact part between the top section 12 and the bottom wall of the clamping groove 171, which can make the top section 12 form a hinged state and can position the top section 12, so that the top section 12 can only rotate and cannot move randomly, thereby improving the installation efficiency of the top section 12. In addition, the distance from the clamping block 17 fixed on the inner peripheral wall protruding above the top surface of the bottom section 11 is h, and the distance from the clamping block 17 fixed on the outer peripheral wall protruding above the top surface of the bottom section 11 is H, and h < H, which can make the rotation of the top section 12 more flexible during the adjustment process, and is beneficial to further improving the installation efficiency of the top section 12.

[0064] In the prior art, the hoisting of the support bracing system 30 usually adopts the method of single-point hoisting with the auxiliary hook of a crane. For example, Figure 7 the support bracing system 30 located below as shown. This method requires adjusting the crane lifting point during hoisting to ensure that the support bracing system 30 is hoisted vertically. Moreover, single-point hoisting of the support bracing system 30 is prone to force swing, resulting in inconvenience. At the same time, single-point hoisting cannot solve the installation problem of the diagonal bracing system. In this embodiment, an electric hoist can hoist the bracing system with two lifting points simultaneously, which is convenient for the adjustment, positioning and fixing of the horizontal bracing system 31, fast and convenient. At the same time, it can solve the installation problem of the diagonal bracing system 32. That is, during hoisting, first make the lengths of the suspension ropes connected to both ends of the diagonal bracing system 32 the same to hoist the diagonal bracing system 32 horizontally in place, and then adjust the lengths of the suspension ropes connected to both ends of the diagonal bracing system 32 to adjust the diagonal bracing system 32 to a preset inclined posture for positioning and fixing. Compared with the method of single-point hoisting with the auxiliary hook of a crane, it can more conveniently and quickly realize the adjustment, positioning and fixing of the horizontal bracing system 31, with low cost and better effect.

[0065] The above description is a detailed description of the preferred and feasible embodiments of the present invention. However, the embodiments are not intended to limit the scope of the patent application of the present invention. Any equivalent changes or modifications completed under the technical spirit disclosed by the present invention shall fall within the scope of the patent covered by the present invention.

Claims

1. A method for overall installation of a temporary steel load-bearing support with a limited top, characterized in that: The following steps are involved: A temporary steel load-bearing support is provided, the temporary steel load-bearing support comprises a steel pipe column, a support connection system and a support distribution beam, the steel pipe column comprises a bottom segment and a top segment fixed to the top of the bottom segment and coaxially arranged with the bottom segment, a first limiting plate and a second limiting plate which are oppositely arranged are convexly arranged on the top surface of the top segment, and a limiting groove is formed between the first limiting plate, the second limiting plate and the top surface of the top segment; the support connection system is fixed between two adjacent steel pipe columns, and the support distribution beam is fixed in the limiting groove; The installation method of the steel pipe column comprises the following steps: S11, directly vertically installing the bottom segment in place by a crane; S12, after the bottom segment is installed in place, a plurality of stoppers are welded at intervals along the circumferential direction on the top edge of the bottom segment, and the plurality of stoppers and the top surface of the bottom segment are surrounded to form a docking groove with a side opening; S13, using a crane to lift the top segment obliquely, moving the top segment to the top of the bottom segment by the crane, and pushing the bottom of the top segment into the docking groove along the side opening; S14, lowering and slowly straightening the top segment by the crane so that the top segment is in a vertical state, and fixing the bottom end of the top segment to the top end of the bottom segment; S15, repeating steps S11-S14 to complete the installation of a plurality of the steel pipe columns; The installation method of the bracket connection system comprises the following steps: Install an electric hoist on two adjacent steel pipe columns, use the double lifting points of the electric hoist to simultaneously lift the bracket connection system, and after the bracket connection system is lifted into place, fix it to the two adjacent steel pipe columns; The method for installing the support distribution beam comprises the following steps: First, fix the first limiting plate to one side edge of the top surface of the top segment, and lift the bracket distribution beam into place by a crane so that one side of the bracket distribution beam rests against the first limiting plate; then fix the second limiting plate to the top surface of the top segment and be located on the side of the bracket distribution beam away from the first limiting plate.

2. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: A plurality of the stoppers are fixed at intervals on the outer peripheral surface of the top end of the bottom segment, and are protruded above the top surface of the bottom segment to surround and form the docking groove, and along the pushing direction of the top segment, a plurality of the stoppers are located on the rear side of the bottom segment, and the front side of the bottom segment where the stoppers are not provided forms the side opening.

3. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: In step S12, a pair of clamping blocks are further fixed at the top of the bottom segment, the pair of clamping blocks are located at the position of the bottom segment farthest from the side opening, the pair of clamping blocks are relatively fixed on the inner peripheral wall and the outer peripheral wall of the bottom segment, and the pair of clamping blocks are both convexly arranged above the top surface of the bottom segment, so as to form a clamping groove together with the top surface of the bottom segment; In step S14, when the top segment is lowered by the crane, the peripheral wall on the bottom side of the top segment is inserted into the slot, and a welding point is formed by spot welding at the contact position between the top segment and the bottom wall of the slot. The top segment is pulled by the crane to rotate around the welding point, thereby slowly straightening the top segment.

4. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 3 is characterized in that: The distance between the block fixed on the inner peripheral wall and the top surface of the bottom segment is h, and the distance between the block fixed on the outer peripheral wall and the top surface of the bottom segment is H, h <H。 5. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: In step S11, the method of directly vertically installing the bottom segment in place by a crane is: first lifting ears are welded on opposite sides of the upper part of the bottom segment, and the two first lifting ears are lifted by the crane at the same time, so that the bottom segment is lifted in a vertical state.

6. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: In step S13, the method of using a crane to lift the top segment obliquely is as follows: a second lifting lug is welded on one side of the upper portion of the top segment, and the second lifting lug is lifted by the crane, so that the top segment is lifted in an inclined state.

7. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: During the installation process of the bracket distribution beam, the method of lifting the bracket distribution beam into place by a crane is: lift the opposite ends of the bracket distribution beam respectively by double cranes, and then push the bracket distribution beam along the side of the top segment where the second limit plate is not installed to the top surface of the top segment until one side of the bracket distribution beam abuts against the first limit plate, thereby putting the bracket distribution beam into place.

8. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: During the installation process of the bracket connection system, the bracket connection system is set between two adjacent steel pipe columns, and the lifting ropes of the electric hoists on the two adjacent steel pipe columns are respectively lifted to the opposite ends of the bracket connection system, and the electric hoists are started. After the bracket connection system is lifted to a preset installation position, the bracket connection system is fixed to the two adjacent steel pipe columns.

9. The overall installation construction method of a temporary steel load-bearing support with a top limit as claimed in claim 1, characterized in that: The bracket connection system includes a horizontal connection system and an inclined rod connection system. During hoisting, the lengths of the lifting ropes connected to the two ends of the horizontal connection system are the same, thereby ensuring that the horizontal connection system is hoisted in a horizontal posture; when hoisting the inclined rod connection system, first, the inclined rod connection system is lifted horizontally into place, and then the inclined rod connection system is adjusted to a preset inclined posture and fixed in place by adjusting the lengths of the lifting ropes connected to the two ends of the inclined rod connection system.