Offshore photovoltaic prefabricated concrete composite pile and construction method thereof

The triangular concrete pile foundation and steel hoop structure of precast concrete combined piles and combined with steel trusses to form a spatial truss structure, which solves the problem of insufficient bending load-bearing capacity of traditional offshore photovoltaic pile foundations and achieves material saving and load capacity improvement.

CN118895751APending Publication Date: 2024-11-05POWERCHINA HUADONG ENG CORP LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411204548.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

When traditional offshore photovoltaic pile foundation structures withstand wave force and water flow force, they have insufficient bending load resistance and large material usage, resulting in large bending moments near the mud surface and excessive material consumption.

Method used

Precast concrete combined piles are used to form triangular edges through a combined structure of concrete pile foundation and steel hoop, and combined with steel truss structure, a space truss structure is formed to improve bending load-bearing capacity, and the material usage is reduced through prestressed concrete piles.

Benefits of technology

The bending bearing capacity and horizontal load capacity of offshore photovoltaic pile foundations are improved, the material usage and engineering costs are reduced, the bending moment of the pile body near the mud surface is reduced, and the economics of the overall structure is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895751A_ABST
    Figure CN118895751A_ABST
Patent Text Reader

Abstract

The invention provides an offshore photovoltaic precast concrete composite pile which comprises a pile structure, the pile structure comprises a concrete pile foundation and a steel hoop, the concrete pile foundation is triangular on the vertical projection plane of the composite pile, the concrete pile foundation comprises a concrete pile vertically arranged along the composite pile and an end point forming the triangular shape, and the steel hoop is arranged on the concrete pile foundation. The pile structure further comprises a truss structure, and the steel hoops are connected with the ends of the truss structure to form triangular edges, so that overflowing spaces are formed between the adjacent concrete piles. According to the prefabricated concrete combined pile, the multiple high-strength prestressed concrete piles are adopted, the multiple prestressed concrete piles are connected together through the steel truss structure to form a space truss structure, and the space truss structure serves as an overall stressed pile foundation structure, so that the combined pile is high in horizontal load bearing capacity and bending moment bearing capacity; and therefore, the pile body material and the work amount are saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pile foundations for offshore photovoltaics, and in particular to a precast concrete composite pile for offshore photovoltaics and a construction method thereof. Background Art

[0002] With the reform of my country's energy structure, new energy has made great progress. Among them, offshore photovoltaics has emerged as an emerging field in the photovoltaic industry, and has been widely recognized by the market due to its large planable capacity and vast land use.

[0003] Offshore photovoltaic piles, as the supporting structure of offshore suspension photovoltaic brackets, not only bear the conventional deadweight and wind load, but also need to bear the wave force and water flow force that are much greater than those of onshore structures, resulting in a large load on the pile foundation structure, especially large horizontal force and bending moment. Traditional offshore photovoltaic piles have large cantilever heights and large horizontal loads, so that the pile body has a large bending moment near the mud surface. Therefore, traditional pile foundations use prestressed concrete pipe piles or steel pipe piles with cantilever structures, which have large bending moments near the mud surface, large pile cross-sections, and large material consumption. Summary of the invention

[0004] The first object of the present invention is to provide a composite pile that can improve the bending bearing capacity and reduce the material consumption. To this end, the present invention adopts the following technical solutions:

[0005] A prefabricated concrete composite pile for offshore photovoltaics, comprising a pile structure, wherein the pile structure comprises a concrete pile foundation and a steel hoop, wherein the concrete pile foundation is triangular in shape on the vertical projection plane of the composite pile, and the concrete pile foundation comprises concrete piles vertically arranged along the composite pile to form triangular end points, and the pile structure further comprises a truss structure, wherein the steel hoop is connected to the end of the truss structure to form a triangular side portion, so that there is a flow space between adjacent concrete piles; the steel hoop comprises an end steel hoop, wherein the end steel hoop has an upper end steel hoop and a lower end steel hoop, wherein the upper end steel hoop is located at the upper end of the concrete pile, and the lower end steel hoop is located at the lower end of the concrete pile, and the pile structure is vertically arranged in at least two layers, and the lower end steel hoop of the upper pile structure is fixedly connected to the upper end steel hoop of the lower pile structure.

[0006] Furthermore: a reinforcing hoop is provided at the connection between the upper and lower layers of the concrete piles, one end of the reinforcing hoop is connected to the outer surface of the lower end steel hoop, and the other end of the reinforcing hoop is connected to the outer surface of the upper end steel hoop.

[0007] Furthermore: the upper end steel hoop includes an upper end cover, the upper end cover is located on the upper end surface of the concrete pile, the lower end steel hoop includes a lower end cover, the lower end cover is located on the lower end surface of the concrete pile, and the upper end cover is fixedly connected to the lower end cover at the connection between the upper and lower layers of the concrete piles.

[0008] Furthermore: the upper end steel hoop also includes an upper cylindrical hoop body connected to the upper end cover, and the upper cylindrical hoop body is sleeved on the outside of the concrete pile; the lower end steel hoop also includes a lower cylindrical hoop body connected to the lower end cover, and the lower cylindrical hoop body is sleeved on the outside of the concrete pile; the truss structure includes an oblique rod assembly, and the ends of the oblique rod assembly are respectively connected to the upper cylindrical hoop body and the lower cylindrical hoop body of the concrete pile on the adjacent side.

[0009] Further: the pile body of the concrete pile is provided with an intermediate steel hoop, the intermediate steel hoop is cylindrical, and the intermediate steel hoop is located between the upper end steel hoop and the lower end steel hoop, the diagonal rod assembly has a first diagonal rod and a second diagonal rod, the intermediate steel hoop is provided with a first connecting portion connected to the first diagonal rod, and the intermediate steel hoop is also provided with a second connecting portion connected to the second diagonal rod, the first diagonal rod and the second diagonal rod are shaped on the intermediate steel hoop, the first diagonal rod is also connected to the upper cylindrical hoop body of the adjacent concrete pile, and the second diagonal rod is also connected to the lower cylindrical hoop body of the adjacent concrete pile.

[0010] Furthermore: the truss structure includes a cross bar, and in the vertical direction of the combined pile, the upper cylindrical hoop body of the top pile structure is provided with a third connecting portion, and the third connecting portion is connected to the end of the cross bar.

[0011] Furthermore: a turning ear is provided on the cross bar, and the turning ear includes a stopper and a support tube, the support tube is cylindrical, and on the axial projection surface of the support tube, the projection surface of the outer contour of the support tube is located within the projection surface of the outer contour of the stopper; at least one pair of turning ears is provided, and the turning ears are respectively provided on the cross bar on the opposite side of one of the concrete piles as a reference.

[0012] Furthermore: in the vertical projection of the composite pile, the concrete pile foundation is in the shape of an equilateral triangle, the center of the equilateral triangle is defined as o, and the support tube includes an intermediate connecting pipe connected to the cross bars on both sides in opposite directions, the intermediate connecting pipe passes through the center, and the intermediate connecting pipe is arranged along the axial direction of one of the cross bars.

[0013] Furthermore: the top-level pile structure is provided with a detachable pile hammer connection structure and a pile hammer, the pile hammer connection structure comprises a supporting platform plate and a connecting plate, the supporting platform plate is located on the top of the upper end cover, the supporting platform plate is connected to the upper end cover by bolts, the connecting plate is located on the top of the supporting platform plate, and the clamp at the bottom of the pile hammer can be connected to the connecting plate.

[0014] The second object of the present invention is to provide a construction method that is convenient to construct. To this end, the present invention adopts the following technical solutions:

[0015] A construction method for precast concrete composite piles for offshore photovoltaics, comprising the following contents:

[0016] S1: Processing and welding the components of the pile structure on land to form the integrated combined pile;

[0017] S2: Transportation of the combined pile: Hang the lifting rope of the lifting equipment on the turning lifting lug of the combined pile, lift the combined pile until it is lifted onto the transport ship, lay the combined pile flat on the deck of the transport ship, loosen the lifting rope after lifting, and unhook the lifting rope from the turning lifting lug;

[0018] S3: Repeat step S2 until the deck of the transport ship is covered with the combined piles, and then place a separation pad on the upper part of the combined piles of this layer, the bottom of the separation pad abuts against the end steel hoop and / or the middle steel hoop, and the separation pad forms an upper placement platform, and continue to repeat step S2 to hoist the combined piles onto the separation pad;

[0019] S4: The transport ship transports the assembled piles to the construction sea area;

[0020] S5: Installing the pile hammer connection structure: connecting the support platform plate to the upper end cover of the pile structure on the top floor, and fixing them with the bolts;

[0021] S6: Hanging the lifting rope of the lifting equipment on the turning lifting lug of the combined pile, lifting the combined pile, lifting the combined pile to the installation position, and the combined pile is initially buried in the mud under the action of its own weight;

[0022] S7: The pile hammer is clamped on the connecting plate by the clamp, the pile hammer is fixed to the top of the concrete pile, and a plurality of the pile hammers of the composite pile are connected in parallel to sink the composite pile to a required elevation.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] The precast concrete composite pile of the present invention adopts a plurality of high-strength prestressed concrete piles, and the plurality of prestressed concrete piles are connected together by a steel truss structure to form a spatial truss structure as an integrally stressed pile foundation structure. Therefore, compared with the bending mode of the traditional cantilever pile, not only the overall cost of the pile foundation can be reduced, but also the main material of the composite pile is in the tension and compression mode, and the pile has a large tension and compression bearing capacity, so the composite pile has a strong ability to withstand horizontal loads and bending moments, thereby saving pile body materials and engineering workload. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic elevation diagram of the precast concrete composite pile of the present invention;

[0026] Figure 2 for Figure 1 Top view of the composite pile;

[0027] Figure 3 for Figure 1 The main view of the pile end in the middle pile body;

[0028] Figure 4 for Figure 1 Sectional view of the pile body at the pile end;

[0029] Figure 5 for Figure 1 The main view of the pile body;

[0030] Figure 6 for Figure 1 Sectional view of the pile body;

[0031] Figure 7 for Figure 1 The main view of the joint between the middle and upper pile bodies and the pile ends;

[0032] Figure 8 for Figure 1 The cross-section of the joint between the middle and upper pile bodies;

[0033] Fig. 9 for Figure 1 A top view of the top of the middle composite pile;

[0034] Fig.10 for Fig. 9 Schematic diagram of the middle turning lifting lug;

[0035] Fig.11 for Figure 1 Schematic diagram of the connection between the top of the middle composite pile and the vibratory hammer;

[0036] Fig.12 It is a schematic diagram of stacking multi-layer composite piles on a transport ship in the present invention;

[0037] Fig.13 for Fig.12 Side view of the . DETAILED DESCRIPTION

[0038] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.

[0039] This embodiment uses Figure 1 The axial direction of the concrete pile a in the figure is the vertical direction of the composite pile, for explanation.

[0040] like Figure 1-10 As shown, a prefabricated concrete composite pile for offshore photovoltaics includes a pile structure 1, the pile structure 1 includes a concrete pile foundation 11 and a steel hoop, the concrete pile foundation 11 is triangular in shape on the vertical projection surface of the composite pile, the concrete pile foundation 11 includes a concrete pile a vertically arranged along the composite pile to form a triangular end point, the pile structure 1 also includes a truss structure 13, the steel hoop is connected to the end of the truss structure 13 to form a triangular side, so that there is a flow space between adjacent concrete piles a, compared with traditional offshore photovoltaic piles, the concrete pile a is reduced in height. The contact surface and contact area of ​​the mud surface attachment make the composite pile have strong ability to withstand horizontal loads and bending moments; the steel hoop includes an end steel hoop 12, and the end steel hoop 12 has an upper end steel hoop 121 and a lower end steel hoop 122. The upper end steel hoop 121 is located at the upper end of the concrete pile a, and the lower end steel hoop 122 is located at the lower end of the concrete pile a. The pile structure 1 is vertically arranged in at least two layers. The lower end steel hoop 122 of the upper pile structure 1 is fixedly connected to the upper end steel hoop 121 of the lower pile structure 1 to form a whole, which is convenient for one-time completion of construction.

[0041] Based on the above content, the pile structure 1 is in the shape of a triangular prism, and the pile structure 1 has a first pile body 111, a second pile body 112, and a third pile body 113. The first pile body 111, the second pile body 112, and the third pile body 113 are one of the above-mentioned multiple concrete piles a. Accordingly, in order to ensure that the height of the combined pile can meet the actual elevation requirements, it can be assembled by splicing multiple layers of pile structures 1, which can reduce the processing difficulty of a single concrete pile a compared to the case where the concrete pile a directly meets the actual elevation requirements.

[0042] At the same time, the material of the truss structure 13 is steel, and the first pile body 111, the second pile body 112, and the third pile body 113 are connected together by the truss structure 13 to form a spatial truss structure. Compared with the traditional structure using steel pipe piles, the concrete pile body of this embodiment has high strength, less materials, low cost, and good economy. In addition, the combined pile changes the stress characteristics of the traditional cantilever pile, and the spatial truss structure is jointly stressed. Compared with the bending mode of the traditional cantilever pile, the main material of the combined pile is a tension and compression mode, and the pile has a large tension and compression bearing capacity, so the combined pile has a stronger ability to withstand horizontal loads and bending moments. If the multi-pile pile foundation is a non-integral structure as described above, each pile body needs to be sunk one by one, and each pile needs to be re-moved and re-positioned after sinking. In addition, due to the high precision control requirements between the piles, the auxiliary positioning measures are complicated and the auxiliary positioning tooling costs are high, resulting in a long construction period and high costs for the traditional multi-pile foundation.

[0043] In this embodiment, the concrete pile a uses the end steel hoop 12 fixedly connected thereto to connect and fix the concrete piles a of the upper and lower pile structures 1. Specifically, the upper end steel hoop 121 includes an upper end cover 1212, which is located on the upper end surface of the concrete pile a, and the lower end steel hoop 122 includes a lower end cover 1222, which is located on the lower end surface of the concrete pile a. At the connection between the upper and lower concrete piles a, the upper end cover 1212 is fixedly connected to the lower end cover 1222. This ensures the connection strength of the concrete piles a of the upper and lower pile structures 1.

[0044] In this embodiment, the connection of the concrete piles a of the upper and lower pile structures 1 is fixed by welding using end steel hoops 12, and a reinforcing hoop body 15 is provided at the connection of the upper and lower concrete piles a, one end of the reinforcing hoop body 15 is connected to the outer surface of the lower end steel hoop 122, and the other end of the reinforcing hoop body 15 is connected to the outer surface of the upper end steel hoop 121, so as to further improve the connection strength of the concrete piles a of the upper and lower pile structures 1 and ensure the overall stability of the combined piles.

[0045] In this embodiment, the upper end steel hoop 121 also includes an upper cylindrical hoop body 1211 connected to the upper end cover 1212, and the upper cylindrical hoop body 1211 is sleeved on the outside of the concrete pile a. The lower end steel hoop 122 also includes a lower cylindrical hoop body 1222 connected to the lower end cover 1222, and the lower cylindrical hoop body 1222 is sleeved on the outside of the concrete pile a. The truss structure 13 includes an inclined rod assembly, and the ends of the inclined rod assembly are respectively connected to the upper cylindrical hoop body 1211 and the lower cylindrical hoop body 1222 of the adjacent side concrete pile a, so that the concrete piles a on the adjacent sides of the pile structure 1 can be quickly and effectively connected, and the connection strength at the connection with the inclined rod assembly is guaranteed.

[0046] The pile body of the concrete pile a is provided with an intermediate steel hoop 14, which is cylindrical and located between the upper end steel hoop 121 and the lower end steel hoop 122. The inclined rod assembly comprises a first inclined rod 132 and a second inclined rod 133. The intermediate steel hoop 14 is provided with a first connecting portion connected to the first inclined rod 132, and the intermediate steel hoop 14 is also provided with a second connecting portion connected to the second inclined rod 133. The first inclined rod 132 and the second inclined rod 133 are V-shaped on the intermediate steel hoop 14 (at Figure 5 From the perspective of the embodiment of the present invention, the first inclined rod 132 is also connected to the upper cylindrical hoop 1211 of the adjacent concrete pile a, and the second inclined rod 133 is also connected to the lower cylindrical hoop 1222 of the adjacent concrete pile a.

[0047] Based on the above content Figure 1 As shown in , a connection space is formed between adjacent side concrete piles a, the number of first inclined rods 132 is two, the middle pipe sections of the two first inclined rods 132 are cross-arranged, the number of second inclined rods 133 is two, the middle pipe sections of the two second inclined rods 133 are cross-arranged, and there is a gap between the first inclined rod 132 and the second inclined rod 133, and the distance between the first connecting part and the second connecting part in the axial direction of the concrete pile a is the minimum spacing of the above-mentioned gap. Therefore, the inclined rod assembly is connected and fixed to the end steel hoop 12 and the middle steel hoop 14 to ensure the connection strength with the concrete pile a, thereby ensuring the overall strength of the pile structure 1 and the stability of the pile structure 1.

[0048] Of course, when the number of the middle steel hoops 14 on the same concrete pile a is at least two, a third diagonal rod (not shown in the figure) can be set. When the number of the third diagonal rods is two, the middle pipe sections of the two third diagonal rods can also be cross-arranged. In the area of ​​the connecting space, one end of the third diagonal rod is connected to the upper middle steel hoop 14 of one of the concrete piles a, and the other end of the third diagonal rod is connected to the lower middle steel hoop 14 of another concrete pile a, so as to enhance the overall stability of the pile structure 1.

[0049] In this embodiment, the first inclined rod 132 and the second inclined rod 133 are made of round steel pipes to reduce the construction difficulty when sinking the pile. At the same time, in order to make the combined pile sinking more smoothly, a pile tip (not shown in the figure) can be provided at the bottom of the lower end steel hoop 122 of the concrete pile a of the bottom pile structure 1 to reduce the difficulty of sinking the pile.

[0050] Based on the above content, it should be explained that the end steel hoop 12 and the middle steel hoop 14 are connected to the main reinforcement in the concrete pile a when the pile body is manufactured, so the reliability of the connection between the truss structure 13 and the prestressed concrete pile can be guaranteed.

[0051] In this embodiment, the truss structure 13 includes a cross bar 131. In the vertical direction of the combined pile, the upper cylindrical hoop 1211 of the top pile structure 1 is provided with a third connection portion, and the third connection portion is connected to the end of the cross bar 131. The cross bar 131 strengthens the connection stability of the top of the top pile structure 1, and the cross bar 131 can strengthen the connection strength with the concrete pile a by being connected and fixed to the upper cylindrical hoop 1211. At the same time, it can also ensure that when the pile hammer 5 is installed on the top pile structure 1 and construction is carried out during offshore construction, the stability of the pile structure 1 is correspondingly guaranteed.

[0052] In this embodiment, a turning ear 2 is provided on the cross bar 131, and the turning ear 2 includes a stopper 21 and a supporting tube 22. The supporting tube 22 is cylindrical, and on the axial projection surface of the supporting tube 22, the projection surface of the outer contour of the supporting tube 22 is located within the projection surface of the outer contour of the stopper 21, and the stopper 21 is connected to the end of the supporting tube 22 away from the cross bar 131; at least one pair of turning ears 2 is provided, and the turning ears 2 are respectively provided on the cross bar 131 on the opposite side of one of the concrete piles a as a reference, so that the force is not emphasized on one side during lifting, ensuring smooth lifting when the combined pile is lifted.

[0053] The cylindrical support tube 22 can cooperate with the lifting rope. The lifting rope only needs to be put on the support tube 22 without hooks and pins. The stopper 21 can prevent the lifting rope from detaching from the support tube 22.

[0054] In the vertical projection of the combined pile, the concrete pile foundation 11 is in the shape of an equilateral triangle, the center of which is defined as o, and the support pipe 22 includes an intermediate pipe 221 connected to the two side cross bars 131 in opposite directions, the intermediate pipe 221 passes through the center, and the intermediate pipe 221 is arranged along the axial direction of one of the cross bars 131. This is to reduce the occurrence of the center of gravity shift during the lifting process of the combined pile, and ensure the smooth lifting process.

[0055] It should be noted that the turning lifting lug 2 is horizontally arranged before lifting, so that the lifting rope can be conveniently hung on the supporting tube 22. After lifting, because the lifting rope can rotate freely on the outer surface of the supporting tube 22, the composite pile is originally placed horizontally. Under the lifting action of the lifting equipment, the composite pile can be placed horizontally from the original horizontal position to the vertical position under the action of its own weight. Figure 1 Similarly, when the combined pile is hoisted to the designated position (e.g., deck), when the lower end steel hoop 122 of the bottom pile structure 1 contacts the deck, it can automatically adapt and adjust the angle with the cooperation of the hoisting equipment until it is level with the deck. And the unhooking of the lifting rope and the turning lifting lug 2 is also convenient, just loosen the lifting rope, no need to remove the hook, making the hoisting process fast and convenient.

[0056] In this embodiment, in order to solve the problem of sinking the composite pile, a temporary pile hammer connecting tool and a connecting structure between the tool and the pile hammer are set at the top of the prestressed concrete pile. Specifically, the top pile structure 1 is provided with a detachable pile hammer connecting structure 4 and a pile hammer 5. The pile hammer connecting structure 4 includes a supporting platform plate 41 and a connecting plate 122. The supporting platform plate 41 is located at the top of the upper end cover 1212. The supporting platform plate 41 and the upper end cover 1212 are connected by bolts 43. The connecting plate 122 is located at the top of the supporting platform plate 41. The clamp 51 at the bottom of the pile hammer 5 can be connected to the connecting plate 122. In this way, the pile hammer 5 can be reliably and conveniently fixed to the top of the concrete pile a, and multiple pile hammers 5 are connected in parallel to sink the composite pile to the required elevation.

[0057] It should be noted that, in order to solve the problem of marine transportation of composite piles, the composite piles are transported in a multi-layer stacking manner, so that the multi-layer composite piles are stacked in a pyramid shape on the transport ship 6 for transportation, and separation pads 7 are provided between each layer of composite piles. The bottom of the separation pad 7 abuts against the end steel hoop 12 and / or the middle steel hoop 14 of the lower composite pile, and the top of the separation pad 7 abuts against the end steel hoop 12 and / or the middle steel hoop 14 of the upper composite pile, so as to ensure stability when placed on the transport ship 6. In this embodiment, the separation pad 7 can be a sleeper.

[0058] See also Figure 1-13 When constructing the combined pile, the specific steps are as follows:

[0059] S1: Processing and welding the components of the pile structure 1 on land to form an integral composite pile;

[0060] S2: Transportation of the modular pile: Hang the lifting rope of the lifting equipment on the turning lug 2 of the modular pile, lift the modular pile until it is lifted onto the transport ship 5, lay the modular pile flat on the deck of the transport ship 5, loosen the lifting rope after the lifting is completed, and unhook the lifting rope from the turning lug 2;

[0061] S3: Repeat step S2 until the deck of the transport ship 5 is covered with composite piles, then place a separator 7 on the upper part of the lower composite piles, the bottom of the separator 7 abuts against the end steel hoop 12 and / or the middle steel hoop 14, and the separator 7 forms an upper placement platform, and continue to repeat step S2 to hoist the composite piles onto the separator 7 until the transport ship 5 is fully loaded;

[0062] S4: The transport ship 5 transports the modular piles to the construction sea area;

[0063] S5: Install the pile hammer connection structure 4: connect the support platform plate 41 to the upper end cover 1212 of the top pile structure 1 and fix them with bolts 43;

[0064] S6: Hang the lifting rope of the lifting equipment on the turning lifting lug 2 of the composite pile, lift the composite pile, lift the composite pile to the installation position, and the composite pile is initially buried in the mud under the action of its own weight;

[0065] S7: The pile hammer 5 is clamped on the connecting plate 122 by the clamp 51, the pile hammer 5 is fixed to the top of the concrete pile a, and multiple pile hammers 5 of the composite pile are connected in parallel to sink the composite pile to the required elevation;

[0066] S8: Repeat S1-S7 to install the composite pile structure at other locations in the target construction sea area.

[0067] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be covered within the protection scope of the present invention.

Claims

1. A prefabricated concrete composite pile for offshore photovoltaics, Features: The pile structure (1) comprises a concrete pile foundation (11) and a steel hoop, wherein the concrete pile foundation (11) is triangular in shape on the vertical projection surface of the composite pile, the concrete pile foundation (11) comprises concrete piles (a) vertically arranged along the composite piles to form triangular end points, the pile structure (1) further comprises a truss structure (13), the steel hoop is connected to the end of the truss structure (13) to form a triangular side portion, so that there is a flow space between adjacent concrete piles (a); The steel hoop comprises an end steel hoop (12), wherein the end steel hoop (12) has an upper end steel hoop (121) and a lower end steel hoop (122), wherein the upper end steel hoop (121) is located at the upper end of the concrete pile (a), and the lower end steel hoop (122) is located at the lower end of the concrete pile (a), and the pile structure (1) is vertically arranged in at least two layers on the combined pile, and the lower end steel hoop (122) of the upper pile structure (1) is fixedly connected to the upper end steel hoop (121) of the lower pile structure (1).

2. A precast concrete composite pile for offshore photovoltaics according to claim 1, Features: A reinforcing hoop (15) is provided at the connection between the upper and lower layers of the concrete piles (a), wherein one end of the reinforcing hoop (15) is connected to the outer surface of the lower end steel hoop (122), and the other end of the reinforcing hoop (15) is connected to the outer surface of the upper end steel hoop (121).

3. A precast concrete composite pile for offshore photovoltaics according to claim 1 or 2, Features: The upper end steel hoop (121) includes an upper end cover (1212), and the upper end cover (1212) is located on the upper end surface of the concrete pile (a). The lower end steel hoop (122) includes a lower end cover (1222), and the lower end cover (1222) is located on the lower end surface of the concrete pile (a). At the connection between the upper and lower layers of the concrete piles (a), the upper end cover (1212) and the lower end cover (1222) are fixedly connected.

4. A precast concrete composite pile for offshore photovoltaics according to claim 3, Features: The upper end steel hoop (121) further comprises an upper cylindrical hoop body (1211) connected to the upper end cover (1212), and the upper cylindrical hoop body (1211) is sleeved on the outside of the concrete pile (a); the lower end steel hoop (122) further comprises a lower cylindrical hoop body (1222) connected to the lower end cover (1222), and the lower cylindrical hoop body (1222) is sleeved on the outside of the concrete pile (a); the truss structure (13) comprises an inclined rod assembly, and the ends of the inclined rod assembly are respectively connected to the upper cylindrical hoop body (1211) and the lower cylindrical hoop body (1222) of the concrete pile (a) on the adjacent side.

5. A precast concrete composite pile for offshore photovoltaics according to claim 4, Features: The pile body of the concrete pile (a) is provided with an intermediate steel hoop (14), the intermediate steel hoop (14) is cylindrical, and the intermediate steel hoop (14) is located between the upper end steel hoop (121) and the lower end steel hoop (122). The diagonal rod assembly comprises a first diagonal rod (132) and a second diagonal rod (133). The intermediate steel hoop (14) is provided with a first connecting portion connected to the first diagonal rod (132), and the intermediate steel hoop (14) is also provided with a second connecting portion connected to the second diagonal rod (133). The first diagonal rod (132) and the second diagonal rod (133) are V-shaped on the intermediate steel hoop (14). The first diagonal rod (132) is also connected to the upper cylindrical hoop body (1211) of the adjacent concrete pile (a), and the second diagonal rod (133) is also connected to the lower cylindrical hoop body (1222) of the adjacent concrete pile (a).

6. A precast concrete composite pile for offshore photovoltaics according to claim 4, Features: The truss structure (13) comprises a cross bar (131), and in the vertical direction of the composite pile, the upper cylindrical hoop (1211) of the top pile structure (1) is provided with a third connecting portion, and the third connecting portion is connected to the end of the cross bar (131).

7. A precast concrete composite pile for offshore photovoltaics according to claim 6, Features: The cross bar (131) is provided with a turning lug (2), the turning lug (2) comprising a stopper (21) and a support tube (22), the support tube (22) being cylindrical, and on the axial projection surface of the support tube (22), the projection surface of the outer contour of the support tube (22) is located within the projection surface of the outer contour of the stopper (21); At least one pair of turning lifting eyes (2) is provided. The turning lifting eyes (2) are respectively provided on the cross bar (131) on the opposite side of one of the concrete piles (a) with reference to the concrete pile (a).

8. A precast concrete composite pile for offshore photovoltaics according to claim 7, Features: In the vertical projection of the combined pile, the concrete pile foundation (11) is in the shape of an equilateral triangle, the center of the equilateral triangle is defined as o, and the support tube (22) includes an intermediate connecting pipe (221) connected to the cross bars (131) on two sides in opposite directions, the intermediate connecting pipe (221) passes through the center, and the intermediate connecting pipe (221) is arranged along the axial direction of one of the cross bars (131).

9. The precast concrete composite pile for offshore photovoltaic according to claim 3, Features: The pile structure (1) at the top layer is provided with a detachable pile hammer connection structure (4) and a pile hammer (5), wherein the pile hammer connection structure (4) comprises a supporting platform plate (41) and a connecting plate (122), wherein the supporting platform plate (41) is located on the top of the upper end cover (1212), the supporting platform plate (41) and the upper end cover (1212) are connected via bolts (43), the connecting plate (122) is located on the top of the supporting platform plate (41), and the clamp (51) at the bottom of the pile hammer (5) can be connected to the connecting plate (122).

10. A construction method for precast concrete composite piles for offshore photovoltaics, Features: The construction of a precast concrete composite pile for offshore photovoltaics as claimed in any one of claims 1 to 9 comprises the following contents: S1: Processing and welding the components of the pile structure (1) on land to form the integrated combined pile; S2: Transportation of the combined pile: Hang the lifting rope of the lifting equipment on the turning lifting lug (2) of the combined pile, lift the combined pile until it is lifted onto the transport ship (5), lay the combined pile flat on the deck of the transport ship (5), loosen the lifting rope after lifting, and unhook the lifting rope from the turning lifting lug (2); S3: Repeat step S2 until the deck of the transport ship (5) is covered with the combined piles, and then place a separation pad (7) on the upper part of the combined piles of this layer, the bottom of the separation pad (7) abuts against the end steel hoop (12) and / or the middle steel hoop (14), and the separation pad (7) forms an upper placement platform, and continue to repeat step S2 to hoist the combined piles onto the separation pad (7); S4: the transport ship (5) transports the assembled piles to the construction sea area; S5: Installing the pile hammer connection structure (4): connecting the support platform plate (41) to the upper end cover (1212) of the top pile structure (1), and fixing them with the bolts (43); S6: Hanging the lifting rope of the lifting equipment on the turning lifting lug (2) of the combined pile, lifting the combined pile, lifting the combined pile to the installation position, and the combined pile is initially buried in the mud under the action of its own weight; S7: The pile hammer (5) is clamped on the connecting plate (122) by the clamp (51), the pile hammer (5) is fixed to the top of the concrete pile (a), and a plurality of the pile hammers (5) of the composite pile are connected in parallel to sink the composite pile to a required elevation.

Citation Information

Patent Citations

  • Steel hoop truss type elevated pile cap tower crane foundation construction method and structure

    CN102561384A

  • Method for hoisting pile legs of self-elevating wind turbine installation vessel in turn-over way

    CN102720197A

  • On-water sand-filling rock-socketed steel pipe pile working platform and construction method thereof

    CN108547276A

  • Large component turning-over lifting method and device

    CN109850761A

  • Pile hammer that shakes executes and beats precast pile pile cover device

    CN206267150U