Strip mine strong discharge steep slope mining method
By obtaining the mining parameters and designing safety distances of open-pit coal mines, optimizing the mining process and equipment of open-pit mines, the safety distance between the inner discharge site and the multi-coal seam cross-mining work is solved, and the coal resource recovery rate and production efficiency are improved, ensuring that Slope stability.
Patent Information
- Application Number
- CN202410991170.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-07-23
AI Technical Summary
The existing open-pit mining methods failed to effectively consider the spatial and temporal evolution process of the inner soil discharge field and the upper multi-coal seam cross-mining work forward, and the safe distance between the upper multi-coal seam cross-mining work and the inner soil discharge field was not determined. , resulting in insufficient mining efficiency and safety.
By obtaining the mining parameters of the composite coal seam and designing multiple distance combination schemes, the slope stability coefficient Fs is calculated using numerical simulation software, the safe distance between the cross-mining work of each coal seam and the inner discharge site, and the appropriate mining technology and Equipment, establish mining work surfaces and abandon transportation paths, and optimize the mining process.
It improves the recovery rate of coal resources and the economic benefits of production processes, and ensures the safety and stability of the slope and mining efficiency.
Smart Images

Figure CN118895974A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of open-pit coal mining, in particular to an open-pit mine strong drainage steep slope mining method. Background Art
[0002] The benefits of implementing strong drainage technology in open-pit mines are: first, fully occupying the internal drainage space, shortening the transportation distance, reducing the external drainage costs, effectively reducing production costs, and improving the economic benefits of open-pit mines; second, shortening the space and time of exposure of high, steep and long slopes, which is beneficial to the stability of the slopes; third, improving the recovery rate of coal resources in open-pit coal mines and extending the service life of the mining area. The traditional mining method is that when the deep coal seam mining is completed and the internal dumping yard is drained to a certain scale to the upper coal seam floor, the mining equipment returns to the starting position of the deep coal seam horizontal mining working side to re-establish the upper coal seam horizontal mining working line, resulting in delayed internal drainage and complex production management.
[0003] Patent CN112855162A discloses a method for mining the upper coal seam of a composite coal seam open-pit mine by mining against the wall. This method uses the inner dump step to form a working space, arranges mining equipment, and uses the inner dump step working plate to perform segmented recovery of the resources covered by the upper coal seam of the end wall, and mines the upper coal seam and the interlayer between the coal seam and the mining level together, and points out that the length of the end wall coal recovered in the stage in the advancement direction is equal to the width of the dump flat plate; Patent CN113742949B discloses a method for determining the mining width of a high-position coal seam in a composite coal seam open-pit mine. This method calculates the width of each flat plate between the coal seams by adjusting the width of each flat plate. The difference between the width of the flat plate before and after the coal seam is adjusted, the relationship between the width of the flat plate and the mining width is found, and the high-position coal seam is mined by using the supporting effect of the inner row of horizontal mining; Patent CN111364999A discloses an integrated replacement method for the end wall pressure coal mining and filling of an open-pit coal mine. The method divides the end wall pressure coal of the open-pit mine into several mining stages of equal length, and divides each stage into front and rear segments. The tunneling and filling operations are carried out alternately according to the front and rear segments to complete the replacement of the end wall pressure coal, realize the continuous mining and filling of the end wall pressure coal, and can maximize the mining of the end wall resources, but there are problems such as large tunneling engineering, long time period, high cost, and difficult construction. These patents are all studies on the mining method of open-pit mines and the mining width of the upper coal seam, and do not consider the temporal and spatial evolution of the mining process during the advancement of the internal dump and the upper multi-coal seam horizontal mining working side, and do not determine the safe distance between the upper multi-coal seam horizontal mining working side and the internal dump. Therefore, there is an urgent need to seek a method for forced steep slope mining in open-pit mines to provide technical support for subsequent open-pit mining. Summary of the invention
[0004] The purpose of the present invention is to provide a method for forced drainage steep wall mining in an open-pit mine, which fully considers the mining parameters, processes and equipment during the advancement of the inner dump and the multi-coal seam horizontal mining working wall, and determines the safe distance between the multi-coal seam horizontal mining working wall and the inner dump, thereby guiding the forced drainage steep wall mining operation in the open-pit mine and improving the mining efficiency and quality.
[0005] To achieve the above object, the present invention provides the following solutions:
[0006] A method for mining steep slopes in an open-pit mine by forced drainage, the method comprising the following steps:
[0007] S1, according to the open-pit coal mining design, obtain the step form and mining parameters of the horizontal mining working side, end side and inner dump slope of each coal seam in the composite coal seam;
[0008] S2, determine the mining process based on the length of the working line and the distance between the horizontal mining work area and the inner dump;
[0009] S3, determining the operating equipment used for mining based on the mining parameters and mining process;
[0010] S4, based on the distance between the horizontal mining working side and the inner dump of each coal seam, design a variety of distance combination schemes, and use numerical simulation software to calculate the slope stability coefficient F from the lowest coal seam to the surface in various distance combination schemes s , select the distance combination scheme that meets the set conditions as the optimal design scheme for the safe distance between the horizontal mining working side and the internal dump of each coal seam;
[0011] S5, determine the initial trench position and trench size of each coal seam horizontal mining working section, dig the trench according to the coal seam trend, and establish a mining working face beside the trench to carry out mining operations;
[0012] S6. After the horizontal mining working side and internal dump of each coal seam are formed, a zoned disposal method is adopted to determine the disposal and transportation routes of the waste materials generated by the horizontal mining working side of each coal seam.
[0013] Furthermore, in S2, the mining process is determined according to the length of the working line and the transportation distance between the horizontal mining working area and the inner dump, which specifically includes:
[0014] Taking into account the length of the working line and the transportation distance between the horizontal mining working area and the inner dumping yard, a suitable open-pit mining process is selected from the single-bucket excavator-truck mining process, the bucket wheel excavator-belt conveyor process and the semi-continuous mining process.
[0015] Furthermore, the S3, based on the mining parameters and mining process, determines the operating equipment used for mining, specifically including:
[0016] Select appropriate operating equipment based on the mining process, step mining parameters and in combination with the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015).
[0017] Further, in S4, the setting condition specifically refers to:
[0018] |F s -K|≤0.005
[0019] Among them, K is the slope safety reserve coefficient.
[0020] Furthermore, in S4, the slope safety reserve coefficient K is: the slope safety reserve coefficient when mining the lowest coal seam is determined based on the service life of the slope and the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015).
[0021] Furthermore, in S5, the initial trenching position of each coal seam horizontal mining working side is determined, specifically by the following method:
[0022] The composite coal seams are numbered from top to bottom, with the top coal seam numbered M1, the second coal seam numbered M2, and so on until the bottom Nth coal seam is numbered M N , N is a positive integer ≥ 2;
[0023] When the top elevation of the inner dump reaches the coal seam M N-i When the floor elevation is determined, the coal seam M N-i The initial trench opening position of the horizontal mining working group, where i is a positive integer ≥1 and ≤N-1;
[0024] Repeat the previous step. When the top elevation of the inner dump reaches the bottom elevation of coal seam M1, determine the initial trench opening position for the horizontal mining working side of coal seam M1.
[0025] Furthermore, in S5, a mining face is established beside the trench to carry out mining operations, which specifically includes:
[0026] Beside the opening ditch, a mining face is established according to the mining parameters of the horizontal mining working face of each coal seam. In the process of advancing the horizontal mining working face of each coal seam, the mining belts are mined one by one, and each time a mining belt is mined, the working line is extended by one mining width.
[0027] Furthermore, the S5 also includes: the bottom line of the lowest step slope of the horizontal mining working side of each coal seam is kept at a set safety distance from the bottom line of the step slope at the top elevation of the inner spoil dump.
[0028] Furthermore, in S6, after the horizontal mining working platform and the internal dumping site of each coal seam are formed, a zoned dumping method is adopted to determine the dumping and transportation path of the dumping materials generated by the horizontal mining working platform of each coal seam, specifically including:
[0029] After the horizontal mining working area and the internal dump of each coal seam are formed, coordinated development is carried out with set coordinated development steps, the same advancement speed is maintained, the top elevation of the internal dump is used as the zoning standard, and the disposal operation is carried out using a zoning disposal method.
[0030] According to the specific embodiment provided by the present invention, the present invention discloses the following technical effects: the open-pit mine strong drainage steep wall mining method provided by the present invention, firstly, according to the open-pit coal mine mining design, the step form and mining parameters of the horizontal mining working wall, end wall and inner dump slope of each coal seam in the composite coal seam are obtained; and the mining process is determined according to the length of the working line and the transportation distance between the horizontal mining working wall and the inner dump, and the operating equipment used for mining is determined in combination with the mining process; secondly, the slope stability coefficient F from the lowest coal seam to the surface in various distance combination schemes is calculated by using numerical simulation software s , determine the safe distance between the horizontal mining working side of each coal seam and the inner dump; finally, determine the initial section ditch position and the size of the section ditch of each coal seam horizontal mining working side, dig the section ditch, and establish the mining working face for mining operations; in addition, a zoning disposal method is adopted to determine the disposal and transportation path of the waste materials generated by the horizontal mining working side of each coal seam, so as to improve the disposal operation efficiency. It can be seen that the present invention provides clear guidance for the strong drainage steep wall mining operation of open-pit mines from the perspective of mining parameters, mining processes and operating equipment, and based on the slope stability coefficient F s The safe distance between the horizontal mining working area and the inner dump of each coal seam has been determined, which can effectively improve the coal resource recovery rate, optimize the production process and economic benefits while ensuring the safety and stability of the slope. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0032] Figure 1 Flow chart of the open-pit mine strong drainage steep slope mining method in an embodiment of the present invention;
[0033] Figure 2 This is a schematic cross-sectional diagram of a steep wall of a strong drainage system in an embodiment of the present invention;
[0034] Figure 3 It is a schematic diagram of the horizontal mining and internal drainage of an open-pit coal mine in an embodiment of the present invention;
[0035] Figure 4 The safe distance between the M2 horizontal mining working wall and the inner dumping ground is 50m, and the safe distance between the M1 horizontal mining working wall and the inner dumping ground is 40m in the embodiment of the present invention, and the schematic diagram of the strong drainage steep wall mining;
[0036] Figure 5 The safe distance between the M2 horizontal mining working wall and the inner dumping ground is 90m, and the safe distance between the M1 horizontal mining working wall and the inner dumping ground is 50m in the embodiment of the present invention, and the schematic diagram of the strong drainage steep wall mining;
[0037] Figure 6 The schematic diagram of numerical simulation results of strong drainage steep wall mining is that the safety distance between the M2 horizontal mining working wall and the inner dump is 50m, and the safety distance between the M1 horizontal mining working wall and the inner dump is 40m in the embodiment of the present invention;
[0038] Figure 7 The schematic diagram of numerical simulation results of strong drainage steep wall mining is that the safety distance between the M2 horizontal mining working wall and the inner dump is 90m, and the safety distance between the M1 horizontal mining working wall and the inner dump is 50m in the embodiment of the present invention;
[0039] Figure 8 It is a schematic diagram showing that the bottom line of the lowest step slope of the inner spoil dump slope and the bottom line of the lowest step slope of the M2 horizontal mining working slope maintain a safe distance of 50m in an embodiment of the present invention;
[0040] Fig. 9 This is a schematic diagram of the initial trenching operation area of the M1 horizontal mining working gang in an embodiment of the present invention;
[0041] Fig.10 It is a partial enlarged schematic diagram of the initial trenching operation area of the M1 horizontal mining working gang in an embodiment of the present invention;
[0042] Fig.11 This is a schematic diagram of the bottom line of the inner dump +666 flat plate slope and the bottom line of the lowest step slope of the M1 horizontal mining working slope maintaining a safe distance of 40m in the embodiment of the present invention;
[0043] Fig.12 It is a schematic diagram of the coordinated development of the M2 horizontal mining working side, the M1 horizontal mining working side and the inner dump in an embodiment of the present invention;
[0044] Fig.13 It is a schematic diagram of the zoning disposal of the internal spoil field in an embodiment of the present invention. DETAILED DESCRIPTION
[0045] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] The purpose of the present invention is to provide a method for forced drainage steep wall mining in an open-pit mine, which fully considers the mining parameters, processes and equipment during the advancement of the inner dump and the multi-coal seam horizontal mining working wall, and determines the safe distance between the multi-coal seam horizontal mining working wall and the inner dump, so as to guide the forced drainage steep wall mining operation in the open-pit mine; overcomes the defect that the existing open-pit mining method does not consider the temporal and spatial evolution process of the mining procedure during the advancement of the inner dump and the upper multi-coal seam horizontal mining working wall, and does not determine the safe distance between the upper multi-coal seam horizontal mining working wall and the inner dump.
[0047] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0048] like Figure 1 As shown, the open-pit mine strong drainage steep slope mining method provided by the present invention comprises the following steps:
[0049] S1, according to the open-pit coal mining design, obtain the step form and mining parameters of the horizontal mining working side, end side and inner dump slope of each coal seam in the composite coal seam;
[0050] S2, determine the mining process according to the length of the working line and the transportation distance between the horizontal mining working side and the inner dump; specifically, comprehensively consider the length of the working line and the transportation distance between the horizontal mining working side and the inner dump, and select a suitable open-pit mining process from the single bucket excavator-truck mining process, the bucket wheel excavator-belt conveyor process and the semi-continuous mining process;
[0051] S3, determining the operating equipment used for mining based on the mining parameters and mining process;
[0052] S4, based on the distance between the horizontal mining working side and the inner dump of each coal seam, design a variety of distance combination schemes, and use numerical simulation software to calculate the slope stability coefficient F from the lowest coal seam to the surface in various distance combination schemes s , select the one that meets |F s The distance combination scheme with the condition of -K|≤0.005 is the optimal design scheme for the safe distance between the horizontal mining working wall and the inner dump of each coal seam; K is the slope safety reserve coefficient, which is specifically determined according to the slope service life and the "Design Code for Open-pit Mines in Coal Industry" (GB50197-2015) to determine the slope safety reserve coefficient when mining the lowest coal seam;
[0053] S5, determine the initial section trench position and the size of the section trench for each coal seam, dig the section trench according to the direction of the coal seam, and establish a mining face beside the section trench to carry out mining operations; for composite coal seams, they can be numbered from top to bottom, with the top coal seam numbered M1, the second coal seam numbered M2, and so on until the bottom Nth coal seam is numbered M N, N is a positive integer ≥ 2; when the top elevation of the inner dump develops to the coal seam M N-i When the floor elevation is determined, the coal seam M N-i The initial trench opening position of the horizontal mining working side, where i is a positive integer ≥1 and ≤N-1; repeat the previous step, and when the top elevation of the inner dump develops to the bottom elevation of the coal seam M1, the initial trench opening position of the horizontal mining working side of the coal seam M1 is determined;
[0054] S6. After the horizontal mining working side and internal dump of each coal seam are formed, a zoned disposal method is adopted to determine the disposal and transportation routes of the waste materials generated by the horizontal mining working side of each coal seam.
[0055] Example:
[0056] The present invention takes the northern slope of an open-pit coal mine in Inner Mongolia as a specific embodiment to illustrate the open-pit mine strong drainage steep slope mining method, which specifically includes the following steps:
[0057] Step 1: Number the composite coal seams from top to bottom, with the top coal seam numbered M1, the second coal seam numbered M2, and so on until the bottom Nth coal seam is numbered M N , for the northern slope of an open-pit coal mine in Inner Mongolia, there are two coal layers, that is, N = 2, numbered from top to bottom, the top coal layer is numbered M1, and the bottom coal layer is numbered M2;
[0058] Step 2: According to the open-pit coal mining design, obtain the step form and mining parameters of the horizontal working wall, end wall and inner dump of each coal seam;
[0059] The steps and mining parameters of the northern slope of an open-pit coal mine in Inner Mongolia, the horizontal mining working wall of coal seam M1 and coal seam M2, and the inner dump are shown in Table 1. The slope morphology from the mining area to the boundary is as follows: Figure 2 By measuring the cross-sectional area of steep-wall mining M1 and M2 and the strike length of the end wall, it can be found that the amount of recovered coal resources is 770,000 tons.
[0060] Table 1 Parameters and forms of steps on each slope
[0061]
[0062] Step 3: According to the service life of the slope and the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015), the slope safety reserve coefficient K is determined when mining the lowest coal seam M2;
[0063] In this embodiment, the service life of the non-working slope is less than 10 years, and the slope safety reserve coefficient K is selected as 1.2.
[0064] Step 4: Select the appropriate mining process based on the length of the working line and the distance between the working gang and the inner dump;
[0065] In this embodiment, the working line is arranged horizontally, that is, perpendicular to the direction of the open-pit mine. Figure 3 As shown, the working line is short, and a mobile and flexible single-bucket excavator-truck mining process should be selected.
[0066] Step 5: Select the corresponding operating equipment according to the mining process, bench mining parameters and the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015);
[0067] In this embodiment, the step heights of the M2 and M1 horizontal mining working sides of the coal seam are both 12m. According to the provisions on the step height of intermittent mining technology in the "Design Code for Open-pit Mines in Coal Industry" (GB50197-2015), the bucket capacity should be 4m 3 A single-bucket excavator, and based on the previous car-shovel coordination relationship in my country's open-pit coal mines, a dump truck with a load capacity of 30t should be selected.
[0068] Step 6: Based on the distance between the horizontal mining working side and the inner dump of each coal seam, design a variety of distance combination schemes, and use numerical simulation software to calculate the slope stability coefficient F from the lowest coal seam M2 to the surface in various schemes. s , when the slope stability factor F s Comply with |F s When -K|≤0.005, the optimal design scheme for the safe distance between the horizontal mining working side and the internal dumping area of each coal seam can be obtained;
[0069] In this embodiment, two schemes are established. Scheme 1 is that the safety distance between the horizontal mining working side and the inner dump of coal seam M1 is 40m, and the safety distance between the horizontal mining working side and the inner dump of coal seam M2 is 50m. Figure 4 As shown in the figure; Option 2 is that the safety distance between the horizontal mining working side and the inner dump of coal seam M1 is 50m, and the safety distance between the horizontal mining working side and the inner dump of coal seam M2 is 90m. Figure 5 The slope stability of the two schemes is calculated respectively, and the calculation results are shown in Figure 6 , Figure 7 As shown. Among them, the slope stability coefficient F s =1.204, |1.204-1.2|<0.005 meets the slope stability requirements; Scheme 2 slope stability coefficient F s =1.184, |1.184-1.2|>0.005 does not meet the slope stability requirements. Therefore, it is finally determined that the safety distance between the horizontal mining working side of the coal seam M1 and the inner dump is 40m, and the safety distance between the horizontal mining working side of the coal seam M2 and the inner dump is 50m. When the horizontal mining working side of the coal seam M2 advances a certain distance and the inner dump can be built, the bottom line of the lowest step slope of the horizontal mining working side of the coal seam M2 and the bottom line of the lowest step slope of the inner dump should maintain a safety distance of 50m. Figure 8 shown.
[0070] Step 7: When the top elevation of the inner dump reaches the bottom elevation of coal seam M1, determine the initial trench opening position of M1 horizontal mining working side;
[0071] In this embodiment, there are only two coal layers. When the top elevation of the inner dump develops to the bottom elevation of coal seam M1 +666, the initial trench opening position of the horizontal mining working side of coal seam M1 is determined as follows: Fig. 9 As shown in the figure, according to the mining equipment operating parameters, the length of the opening trench is determined to be 35m, and the width of the opening trench is 40m. Fig.10 As shown. A mining face is established beside the section ditch according to the mining parameters of the M1 horizontal mining working face of the coal seam. During the advancement of the M1 horizontal mining working face of the coal seam, mining belts are mined one by one. Each mining belt is mined to extend the working line by one mining width. The bottom line of the lowest step slope of the M1 horizontal mining working face of the coal seam should be kept at a safe distance of 40m from the bottom line of the step slope of the +666 elevation of the inner dump. Fig.11 shown.
[0072] Step 8: After forming the shape of the horizontal mining working side and the internal dump of each coal seam, adopt a zoning disposal method to determine the disposal and transportation path of the waste materials generated by the horizontal mining working side of each coal seam.
[0073] In this embodiment, after the coal seam M1 horizontal mining working side, the coal seam M2 horizontal mining working side and the inner dump are formed, the three develop in coordination, that is, the three advance at the same speed, such as Fig.12 As shown. The zoning discharge method is adopted. The waste materials generated by the horizontal mining working side of the coal seam M2 are mainly discharged to the waste steps below the elevation of +666 in the inner waste dump through the end side. The waste materials generated by the horizontal mining working side of the coal seam M1 are discharged to the waste steps above the elevation of +666 in the inner waste dump through the end side. When the inner discharge space below the elevation of +666 is not enough to accommodate the waste materials generated by the horizontal mining working side of the coal seam M2, the car can go up through the end side to the inner discharge steps above the elevation of +666 for waste discharge operations, as shown in the figure. Fig.13 If there are more than two coal seams in the composite slope, the zoning dumping method should be that the dumping materials generated by the horizontal mining working side of each coal seam are dumped to the inner dumping yard step between the floor elevation of the coal seam and the floor elevation of the previous coal seam.
[0074] In summary, the open-pit mine strong drainage steep slope mining method provided by the present invention provides clear guidance for the open-pit mine strong drainage steep slope mining operation in terms of mining parameters, mining process and operating equipment, and based on the slope stability coefficient F sThe safe distance between the horizontal mining working side of each coal seam and the internal dump has been determined, which can effectively improve the coal resource recovery rate, optimize the production process and economic benefits while ensuring the safety and stability of the slope. In addition, a zoning disposal method is adopted to determine the disposal and transportation routes of the waste materials generated by the horizontal mining working side of each coal seam, thereby improving the efficiency of the disposal operation.
[0075] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A method for mining steep slopes in open-pit mines. It is characterized in that The following steps are involved: S1, according to the open-pit coal mining design, obtain the step form and mining parameters of the horizontal working side, end side and inner dump slope of each coal seam in the composite coal seam; S2, determine the mining process based on the length of the working line and the distance between the horizontal mining work area and the inner dump; S3, determining the operating equipment used for mining based on the mining parameters and mining process; S4, based on the distance between the horizontal mining working side and the inner dump of each coal seam, design a variety of distance combination schemes, and use numerical simulation software to calculate the slope stability coefficient F from the lowest coal seam to the surface in various distance combination schemes s , select the distance combination scheme that meets the set conditions as the optimal design scheme for the safe distance between the horizontal mining working side and the internal dump of each coal seam; S5, determine the initial trench position and trench size of each coal seam horizontal mining working section, dig the trench according to the coal seam trend, and establish a mining working face beside the trench to carry out mining operations; S6. After the horizontal mining working side and internal dump of each coal seam are formed, a zoned disposal method is adopted to determine the disposal and transportation routes of the waste materials generated by the horizontal mining working side of each coal seam.
2. The open-pit mine steep wall mining method according to claim 1, It is characterized in that In S2, the mining process is determined according to the length of the working line and the transportation distance between the horizontal mining working area and the inner dump, which specifically includes: Taking into account the length of the working line and the transportation distance between the horizontal mining working area and the inner dumping yard, a suitable open-pit mining process is selected from the single-bucket excavator-truck mining process, the bucket wheel excavator-belt conveyor process and the semi-continuous mining process.
3. The open-pit mine steep slope mining method according to claim 1, It is characterized in that The S3, based on the mining parameters and mining process, determines the operating equipment used for mining, specifically including: Select appropriate operating equipment based on the mining process, step mining parameters and in combination with the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015).
4. The open-pit mine strong drainage steep wall mining method according to claim 1, It is characterized in that In S4, the setting condition specifically refers to: |F s -K|≤0.005 Among them, K is the slope safety reserve coefficient.
5. The open-pit mine steep slope mining method according to claim 4, It is characterized in that In S4, the slope safety reserve coefficient K is: the slope safety reserve coefficient when mining the lowest coal seam is determined based on the service life of the slope and the "Design Code for Open-Pit Mines in Coal Industry" (GB50197-2015).
6. The open-pit mine steep slope mining method according to claim 1, It is characterized in that In S5, the initial trench opening position of each coal seam horizontal mining working side is determined, specifically using the following method: The composite coal seams are numbered from top to bottom, with the top coal seam numbered M 1 , the second coal seam is numbered M 2 , ... until the lowest N coal seam is numbered M N , N is a positive integer ≥ 2; When the top elevation of the inner dump reaches the coal seam M N-i When the floor elevation is determined, the coal seam M N-i The initial trench opening position of the horizontal mining working group, where i is a positive integer ≥1 and ≤N-1; Repeat the previous step, when the top elevation of the inner dump reaches the coal seam M 1 When the floor elevation is determined, the coal seam M 1 The initial trench opening position for horizontal mining work.
7. The open-pit mine steep wall mining method according to claim 1, It is characterized in that In S5, a mining face is established beside the ditch channel to carry out mining operations, which specifically includes: Beside the opening ditch, a mining face is established according to the mining parameters of the horizontal mining working face of each coal seam. In the process of advancing the horizontal mining working face of each coal seam, the mining belts are mined one by one. Every time a mining belt is mined, the working line is extended by one mining width.
8. The open-pit mine steep wall mining method according to claim 1, It is characterized in that The S5 also includes: the bottom line of the lowest step slope of each coal seam horizontal mining working side is kept at a set safety distance from the bottom line of the step slope at the top elevation of the inner spoil dump.
9. The open-pit mine steep wall mining method according to claim 1, It is characterized in that In S6, after the horizontal mining working side and the internal dumping ground of each coal seam are formed, a zoned dumping method is adopted to determine the dumping and transportation path of the dumped materials generated by the horizontal mining working side of each coal seam, specifically including: After the horizontal mining working area and the internal dump of each coal seam are formed, coordinated development is carried out with set coordinated development steps, the same advancement speed is maintained, the top elevation of the internal dump is used as the zoning standard, and the disposal operation is carried out using a zoning disposal method.
Citation Information
Patent Citations
Method for optimizing soil discharging parameters of inner dump of open pit coal mine
CN110096787A
Method for determining advanced mining step pitch of transverse mining working side of soft rock opencast coal mine
CN113128044A
Method for determining stoping width of high-position coal seam of composite coal seam strip mine
CN113742949A
Construction method for constructing dumping site in strip mine beneficial to end slope mining safety
CN116006181A
Method for determining composite coal seam strip mine waste and coal seam replacement step pitch