Device and system for verifying control equipment of nuclear power plant
Through the nuclear power plant control equipment verification device, the network signal of the nuclear power plant simulator is converted into hard-wired signals, transmitted to the equipment under test, and the output results are analyzed, solving the problem that cannot be fully verified in the existing technology, and realizing the equipment Full working conditions are tested and verified to improve reliability and safety.
Patent Information
- Application Number
- CN202410917183.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2024-11-05
AI Technical Summary
The existing technology cannot fully verify the control equipment of nuclear power plants, resulting in online simulation and full-condition online testing in the development stage, and it is difficult to simulate on-site operating conditions to find the cause of the fault during the operation stage.
Design a nuclear power plant control equipment verification device, including a communication gateway, a host computer and a signal processing unit, by converting the network signal of the nuclear power plant simulator into a hard-wired signal, and transmitting it to the test equipment through a hard-wired interface, receiving and analyzing it The output result of the device under test is to verify whether its function is normal.
The full working conditions of nuclear power plant control equipment are realized, the correctness of equipment functions is verified in advance, and the reliability and safety of equipment are improved.
Smart Images

Figure CN118897486A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of nuclear power plant safety management, and in particular to a nuclear power plant control equipment verification device and system. Background Art
[0002] For the control equipment of nuclear power plants, the current relevant technology can only verify the instrumentation and control functions, but not the entire set of equipment, resulting in incomplete verification. For example, during the development phase of nuclear power plant control equipment, it is impossible to conduct online simulation and full-condition online testing. After the control equipment of nuclear power plants fails during the operation phase, it is difficult to simulate the on-site conditions to find the cause of the failure. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a nuclear power plant control equipment verification device and system in view of at least one of the above-mentioned defects.
[0004] The technical solution adopted by the present invention to solve its technical problem is: a nuclear power plant control equipment verification device, including a communication gateway, a host computer, and a signal processing unit;
[0005] The signal processing unit is connected to the communication gateway, the host computer is connected to the communication gateway, and the communication gateway is also used to connect the signal output end of the nuclear power plant simulator and the network interface of the device under test;
[0006] The signal processing unit is also used to connect to the hard-wired interface of the device under test, convert the network signal output by the nuclear power plant simulator into a hard-wired signal and transmit it to the device under test through the hard-wired interface, and receive the hard-wired output result calculated by the device under test, and convert it into a first output result in the form of a network signal and transmit it to the host computer through the communication gateway;
[0007] The communication gateway is also used to transmit the network signal output by the nuclear power plant simulator to the device under test through the network interface, and receive the second output result calculated by the device under test according to the network signal, and transmit it to the host computer;
[0008] The host computer is used to obtain and save the third output result calculated by the nuclear power plant simulator based on the network signal in real time through the communication network, and verify whether the function of the tested equipment is normal based on the third output result.
[0009] In the nuclear power plant control equipment verification device described in the present invention, the host computer is used to read in real time through the communication gateway the first output result and the second output result obtained by calculating the device under test based on the hard-wired signal, and use them as the total output result of the device under test, and perform consistency analysis on the total output result based on the third output result, so as to verify whether the function of the device under test is normal.
[0010] In the nuclear power plant control equipment verification device described in the present invention, the host computer is provided with a consistency judgment button, and the host computer is used to perform a consistency comparison analysis on the total output result based on the third output result when the consistency judgment button is activated, so as to verify whether the function of the equipment under test is normal.
[0011] In the nuclear power plant control equipment verification device of the present invention, the host computer includes a database for storing the third output result and the total output result, and the host computer is used to:
[0012] Based on the time point of the database, the clock of the third output result is consistent with that of the total output result;
[0013] Calculate and accumulate the absolute value of the error between the third output result and the total output result at the same time within a preset time period;
[0014] By searching a preset correspondence table between the cumulative absolute value of the error and the matching score, the corresponding matching score is output; wherein, the higher the matching score, the higher the degree of normality of the function of the device under test.
[0015] In the nuclear power plant control equipment verification device described in the present invention, the host computer is used to shift the third output result and the total output result according to the communication time, align the time point of the database so that the clocks of the third output result and the total output result are consistent.
[0016] In the nuclear power plant control equipment verification device described in the present invention, the host computer also includes a display unit, and the host computer is also used to output a time curve graph of the third output result and a time curve graph of the output result of the device under test, and display them through the display unit.
[0017] In the nuclear power plant control equipment verification device described in the present invention, the host computer is also used to configure gateway parameters for the communication gateway; the gateway parameters include at least one of the communication address, communication length, communication point table, and communication cycle of the communication gateway.
[0018] In the nuclear power plant control equipment verification device described in the present invention, the host computer is also communicatively connected to the signal processing unit via the communication gateway, and the host computer is used to monitor the input and output signals of the signal processing unit.
[0019] In addition, the present invention also provides a nuclear power plant control equipment verification system, comprising the nuclear power plant control equipment verification device as described above, a device under test and a nuclear power plant simulator;
[0020] The communication gateway is respectively connected to the signal output terminal of the nuclear power plant simulator and the network interface of the device under test, and the signal processing unit is connected to the hard-wired interface of the device under test;
[0021] The nuclear power plant simulator is used to simulate the full operating data of the nuclear power plant, and processes the network signal of the simulated functional part of the tested device to be verified through the communication gateway and the signal processing unit and transmits it to the tested device.
[0022] In the nuclear power plant control equipment verification system described in the present invention, the communication gateway communicates with the nuclear power plant simulator based on a first communication protocol, the communication gateway communicates with the device under test based on a second communication protocol, and the host computer communicates with the signal processing unit based on a third communication protocol.
[0023] The implementation of the nuclear power plant control equipment verification device and system of the present invention has the following beneficial effects: the present invention can perform full-operating condition testing and verification on the equipment under test, can verify the functional correctness of the equipment under test in advance, and further improve the reliability and safety of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:
[0025] Figure 1 It is a structural schematic diagram of a nuclear power plant control equipment verification device provided by an embodiment of the present invention;
[0026] Figure 2 It is a structural schematic diagram of a nuclear power plant control equipment verification system provided by an embodiment of the present invention;
[0027] Figure 3 is a schematic diagram of signal flow of a nuclear power plant control equipment verification system provided by some embodiments of the present invention;
[0028] Figure 4 It is a schematic diagram of the structure of a nuclear power plant control equipment verification device provided by some embodiments of the present invention. DETAILED DESCRIPTION
[0029] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described in detail with reference to the accompanying drawings.
[0030] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present invention. However, it should be clear to those skilled in the art that the present invention may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present invention.
[0031] In order to facilitate the understanding of the present invention, the present invention will be described more fully below, and the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.
[0032] It should be understood that although the terms first, second, third, etc. may be used to describe various information in the embodiments of the present invention, these information should not be limited to these terms. These terms are only used to distinguish the same type of information from each other. It is not necessarily required or implied that there is any such actual relationship or order between these entities or operations.
[0033] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention herein are only for the purpose of describing specific embodiments and are not intended to limit the present invention.
[0034] Figure 3 middle, Indicates the signal flow from network signals to hard-wired signals based on a nuclear power plant simulator. Represents the signal flow of network signals based on a nuclear power plant simulator.
[0035] During the entire life cycle of nuclear power plant control equipment, due to the complexity of the equipment composition, nuclear safety control and other conditions, it is impossible to verify the equipment under all power plant conditions, which will lead to the problem that the equipment has design defects that cannot be found. In order to solve the above problems, the present invention provides a nuclear power plant control equipment verification method.
[0036] In a preferred embodiment, reference Figure 1 and Figure 2 , the nuclear power plant control equipment verification device of this embodiment includes a communication gateway, a host computer, and a signal processing unit.
[0037] The signal processing unit is connected to the communication gateway, the host computer is connected to the communication gateway, and the communication gateway is also used to connect the signal output end of the nuclear power plant simulator and the network interface of the device under test.
[0038] The signal processing unit is also used to connect to the hard-wired interface of the device under test, convert the network signal output by the nuclear power plant simulator into a hard-wired signal and transmit it to the device under test through the hard-wired interface, and receive the hard-wired output result calculated by the device under test, and convert it into a first output result in the form of a network signal and transmit it to the host computer through the communication gateway. In other words, the signal processing unit realizes the function of converting the network data of the nuclear power plant simulator into actual data.
[0039] Specifically, network signals include digital signals and analog signals simulated by simulators. Hard-wired signals include actual digital signals and analog signals, such as input voltage signals, current signals, switch signals, etc.
[0040] The communication gateway is also used to transmit the network signal output by the nuclear power plant simulator to the device under test through the network interface, and receive the second output result calculated by the device under test based on the network signal and transmit it to the host computer.
[0041] The host computer is used to obtain and save the third output result calculated by the nuclear power plant simulator based on the network signal in real time through the communication network, and verify whether the function of the equipment under test is normal according to the third output result.
[0042] In some embodiments, the host computer is used to read in real time through the communication gateway the first output result and the second output result obtained by the device under test based on the hard-wired signal, and use them as the total output result of the device under test, and analyze the total output result based on the third output result to verify whether the function of the device under test is normal.
[0043] refer to Figure 4The working principle of the present invention is as follows: after the nuclear power plant simulator simulates the full operating data of the nuclear power plant, two types of simulation data will be obtained. The first type of simulation data is a network signal, which is transmitted to the signal processing unit through the communication gateway for processing. The signal processing unit converts the network signal into a hard interface signal and sends it to the device under test as the input signal of the device under test. The device under test calculates the first output result according to the received hard interface signal and transmits it to the host computer in real time and saves it in the database. At the same time, the device under test receives the network signal output by the nuclear power plant simulator through the communication gateway and calculates the second output result accordingly and transmits it to the host computer in real time and saves it in the database. The host computer uses the first output result and the second output result as the total output result of the device under test. The second type of simulation data is the third output result, which is calculated by the nuclear power plant simulator according to the network signal and transmitted to the host computer in real time and saved in the database. The host computer analyzes the total output result according to the third output result, thereby verifying whether the function of the device under test is normal.
[0044] It can be understood that the present invention simulates the full operating data of the power plant through the nuclear power plant simulator, and sends the input and output of the equipment part to be verified to the communication gateway. The communication gateway distributes the data to the device under test and the signal processing unit. The signal processing unit converts the digital and analog signals in the simulator into actual digital and analog signals and transmits them to the device under test. The host computer reads the input and output data of the nuclear power plant simulator and the device under test in real time through the communication gateway, compares and evaluates the consistency of the two data, and finally gives a verification conclusion.
[0045] This embodiment can perform power plant full-operation condition testing and verification on the equipment under test, and can verify the functional correctness of the equipment under test in advance, further improving the reliability and safety of the equipment.
[0046] Optionally, the host computer is provided with a consistency judgment button, and the host computer is used to perform consistency comparison analysis on the total output result based on the third output result when the consistency judgment button is activated, so as to verify whether the function of the device under test is normal. Exemplarily, when the working condition simulation is completed, click the consistency judgment button, and the host computer can perform consistency calculation on the data run by the simulator and the data calculated by the unit under test.
[0047] Based on the above embodiments, reference Figure 3 The host computer includes a database for storing the third output result and the total output result, and the host computer is used to:
[0048] Based on the time point of the database, the clocks of the third output result and the total output result are consistent. Specifically, the host computer is used to shift the third output result and the total output result according to the communication time, align the time point of the database so that the clocks of the third output result and the total output result are consistent. In other words, the data of both parties are shifted according to the communication time, the database time point is aligned, and the clocks of the data of both parties are guaranteed to be consistent.
[0049] The absolute value of the error between the third output result and the total output result at the same time in the preset time period is calculated and accumulated. In other words, the two data are compared point by point, the absolute value of the error between the simulation machine calculation result and the calculation result of the device under test at the same time is calculated and accumulated, and the variance value of the entire process data can also be calculated.
[0050] By looking up the preset correspondence table between the absolute value of the cumulative error and the matching score, the corresponding matching score is output. Among them, the lower the absolute value of the cumulative error, the higher the matching score, which means that the function of the device under test is more normal. In other words, the correspondence table can set multiple threshold intervals. The corresponding matching score can be determined by looking up the table to determine which threshold interval the absolute value of the cumulative error belongs to, so that the matching degree between the device under test and the data simulated by the simulator can be clearly known. Exemplarily, if the absolute value of the error is less than or equal to 0, it is 100 points; if the absolute value of the error is 10% of the simulator data value, it is 90 points, and so on, giving a matching score of 0 to 100 points.
[0051] In an alternative embodiment, reference Figure 2 , the host computer also includes a display unit, and the host computer is also used to output a time curve graph of the third output result and a time curve graph of the output result of the device under test, and display them through the display unit. That is to say, the host computer can also output the calculation result and the curve graph of the calculation result of the device under test and display them through the display unit to intuitively display the data. Optionally, the time curve graph of the first output result of the device under test and the time curve graph of the second output structure can be output separately, or the time curve graph of the total output result of the device under test can be displayed as a whole, so as to meet the personalized needs of users.
[0052] This embodiment can perform power plant full-operation condition testing and verification on the equipment under test, and can verify the functional correctness of the equipment under test in advance, further improving the reliability and safety of the equipment.
[0053] In an optional embodiment, the host computer is also used to configure gateway parameters for the communication gateway. The gateway parameters include communication address, communication length, communication point table, communication cycle and other parameters of the communication gateway.
[0054] In an optional embodiment, the host computer is also connected to the signal processing unit through a communication gateway, and the host computer is used to monitor the input and output signals of the signal processing unit.
[0055] In a specific implementation, the host computer can be composed of a computer, which is connected to the nuclear power plant simulator, communication gateway, signal processing unit and the device under test through the network. When the host computer runs the developed visualization software, the user can operate it through the mouse and touch screen. The technician can configure the communication address, communication length, communication point table, communication cycle and other parameters of the communication gateway through the host computer. At the same time, the signal processor unit configuration can be managed, the input and output data of the signal processing unit can be monitored, and the data and status of the current point can be displayed in real time. The host computer reads the upstream input signal of the full working condition of the device under test in the nuclear power plant simulator and the analog output signal of the device under test in real time through the gateway, and stores them in the database. The host computer reads the digital quantity / analog quantity / network data given by the signal processing unit of the actual device under test, and also reads the calculated digital quantity / analog quantity / network data of the device under test and stores them in the database. All the above data can be displayed in real time on the interface.
[0056] This embodiment can test and verify the equipment under test under all working conditions of the power plant, and can verify the functional correctness of the equipment under test in advance, further improving the reliability and safety of the equipment. It solves the problem that the control equipment of the nuclear power plant cannot be simulated online and tested under all working conditions during the development stage, and solves the problem that it is difficult to simulate the on-site working conditions to find the cause of the fault after the control equipment of the nuclear power plant fails during the operation stage.
[0057] In another preferred embodiment, Figure 2 As shown, the nuclear power plant control equipment verification system of this embodiment includes the nuclear power plant control equipment verification device, the equipment under test and the nuclear power plant simulator as in the above-mentioned embodiment.
[0058] The communication gateway is connected to the signal output terminal of the nuclear power plant simulator and the network interface of the device under test respectively, and the signal processing unit is connected to the hard wiring interface of the device under test.
[0059] The nuclear power plant simulator is used to simulate the full operating data of the nuclear power plant. The network signals of the simulated functional parts of the equipment under test to be verified are processed and transmitted to the equipment under test through the communication gateway and signal processing unit.
[0060] The signal processing unit is also used to connect to the hard-wired interface of the device under test, convert the network signal output by the nuclear power plant simulator into a hard-wired signal and transmit it to the device under test. In other words, the signal processing unit realizes the function of converting the network data of the nuclear power plant simulator into actual data.
[0061] Specifically, network signals include digital signals and analog signals simulated by simulators. Hard-wired signals include actual digital signals and analog signals, such as input voltage signals, current signals, switch signals, etc.
[0062] The host computer obtains the third output result calculated by the nuclear power plant simulator based on the network signal in real time through the communication network and saves it, and verifies whether the function of the tested equipment is normal according to the third output result.
[0063] In some embodiments, the host computer reads and saves the total output result calculated by the device under test based on the hard-wired signal and the network signal in real time through the communication gateway, and analyzes the total output result based on the third output result to verify whether the function of the device under test is normal.
[0064] The working principle of the present invention is: after the nuclear power plant simulator simulates the full working condition data of the nuclear power plant, two kinds of simulation data will be obtained. The first kind of simulation data is a network signal, which is transmitted to the signal processing unit through the communication gateway for processing. The signal processing unit converts the network signal into a hard interface signal and sends it to the device under test as the input signal of the device under test. The device under test calculates the first output result according to the received hard interface signal and transmits it to the host computer in real time and saves it in the database. At the same time, the device under test receives the network signal output by the nuclear power plant simulator through the communication gateway and calculates the second output result accordingly and transmits it to the host computer in real time and saves it in the database. The host computer uses the first output result and the second output result as the total output result of the device under test. The second kind of simulation data is the third output result, which is calculated by the nuclear power plant simulator according to the network signal and transmitted to the host computer in real time and saved in the database. The host computer analyzes the total output result according to the third output result, thereby verifying whether the function of the device under test is normal.
[0065] It can be understood that the present invention simulates the full operating data of the power plant through the nuclear power plant simulator, and sends the input and output of the equipment part to be verified to the communication gateway. The communication gateway distributes the data to the device under test and the signal processing unit. The signal processing unit converts the digital and analog signals in the simulator into actual digital and analog signals and transmits them to the device under test. The host computer reads the input and output data of the nuclear power plant simulator and the device under test in real time through the communication gateway, compares and evaluates the consistency of the two data, and finally gives a verification conclusion.
[0066] This embodiment can test and verify the equipment under test under all working conditions of the power plant, and can verify the functional correctness of the equipment under test in advance, further improving the reliability and safety of the equipment. It solves the problem that the control equipment of the nuclear power plant cannot be simulated online and tested under all working conditions during the development stage, and solves the problem that it is difficult to simulate the on-site working conditions to find the cause of the fault after the control equipment of the nuclear power plant fails during the operation stage.
[0067] In an optional embodiment, the communication gateway communicates with the nuclear power plant simulator based on a first communication protocol, the communication gateway communicates with the device under test based on a second communication protocol, and the host computer communicates with the signal processing unit based on a third communication protocol.
[0068] It can be understood that the communication gateway has a standard RJ45 network port, which is connected to the switch through a network cable, so that the communication gateway, nuclear power plant simulator, and the device under test are in the same network segment, and the gateway and the simulator, and the gateway and the device under test can communicate. In terms of communication protocols, the communication gateway and the nuclear power plant simulator can communicate through one of the communication protocols TCP / IP, UDP, MQTT, Modbus-TCP, Modbus-RTU, and OPC. The communication gateway and the device under test can communicate through one of the communication protocols TCP / IP, UDP, Modbus-TCP, Modbus-RTU, Ethernet / IP, and MQTT. The signal processing unit and the host computer can communicate through one of the communication protocols TCP / IP, Modbus-TCP, Ethernet / IP, and OPC.
[0069] This embodiment can perform power plant full-operation condition testing and verification on the equipment under test, and can verify the functional correctness of the equipment under test in advance, further improving the reliability and safety of the equipment.
[0070] The host computer of the present invention includes a processor for providing computing and control capabilities to support the operation of the entire nuclear power plant control equipment verification device. It should be understood that in the embodiment of the present application, the processor can be a central processing unit (CPU), and the processor can also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components, etc. Among them, the general-purpose processor can be a microprocessor or the processor can also be any conventional processor, etc.
[0071] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0072] The steps of the method or algorithm described in conjunction with the embodiments disclosed herein may be implemented directly using hardware, a software module executed by a processor, or a combination of the two. The software module may be placed in a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.
[0073] It can be understood that the above embodiments only express the preferred implementation modes of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the patent scope of the present invention. It should be pointed out that, for ordinary technicians in this field, the above technical features can be freely combined without departing from the concept of the present invention, and several deformations and improvements can be made, which all belong to the protection scope of the present invention. Therefore, all equivalent changes and modifications made to the scope of the claims of the present invention should belong to the coverage of the claims of the present invention.
Claims
1. A nuclear power plant control equipment verification device, It is characterized in that Including communication gateway, host computer, signal processing unit; The signal processing unit is connected to the communication gateway, the host computer is connected to the communication gateway, and the communication gateway is also used to connect the signal output end of the nuclear power plant simulator and the network interface of the device under test; The signal processing unit is also used to connect to the hard-wired interface of the device under test, convert the network signal output by the nuclear power plant simulator into a hard-wired signal and transmit it to the device under test through the hard-wired interface, and receive the hard-wired output result calculated by the device under test, and convert it into a first output result in the form of a network signal and transmit it to the host computer through the communication gateway; The communication gateway is also used to transmit the network signal output by the nuclear power plant simulator to the device under test through the network interface, and receive the second output result calculated by the device under test according to the network signal, and transmit it to the host computer; The host computer is used to obtain and save the third output result calculated by the nuclear power plant simulator based on the network signal in real time through the communication gateway, and verify whether the function of the tested equipment is normal based on the third output result.
2. The nuclear power plant control equipment verification device according to claim 1, It is characterized in that The host computer is used to read the first output result and the second output result of the device under test in real time through the communication gateway, and use them as the total output result of the device under test, and perform consistency analysis on the total output result based on the third output result, so as to verify whether the function of the device under test is normal.
3. The nuclear power plant control equipment verification device according to claim 2, It is characterized in that The host computer is provided with a consistency judgment button, and the host computer is used to perform a consistency comparison analysis on the total output result based on the third output result when the consistency judgment button is activated, so as to verify whether the function of the device under test is normal.
4. The nuclear power plant control equipment verification device according to claim 2 or 3, It is characterized in that The host computer includes a database for storing the third output result and the total output result, and the host computer is used for: Based on the time point of the database, the clock of the third output result is consistent with that of the total output result; Calculate and accumulate the absolute value of the error between the third output result and the total output result at the same time within a preset time period; By searching a preset correspondence table between the cumulative absolute value of the error and the matching score, the corresponding matching score is output; wherein, the higher the matching score, the higher the degree of normality of the function of the device under test.
5. The nuclear power plant control equipment verification device according to claim 4, It is characterized in that The host computer is used to perform shift processing on the third output result and the total output result according to the communication time, and align the time point of the database so that the clock of the third output result and the clock of the total output result are consistent.
6. The nuclear power plant control equipment verification device according to claim 1, It is characterized in that The host computer further includes a display unit, and the host computer is further configured to output a time curve graph of the third output result and a time curve graph of the output result of the device under test, and display them through the display unit.
7. The nuclear power plant control equipment verification device according to claim 1, It is characterized in that The host computer is also used to configure gateway parameters for the communication gateway; the gateway parameters include at least one of the communication address, communication length, communication point table, and communication cycle of the communication gateway.
8. The nuclear power plant control equipment verification device according to claim 1, It is characterized in that The host computer is also connected to the signal processing unit through the communication gateway to monitor the input and output signals of the signal processing unit.
9. A nuclear power plant control equipment verification system, It is characterized in that It comprises a nuclear power plant control equipment verification device as claimed in any one of claims 1 to 8, a device under test and a nuclear power plant simulator; The communication gateway is respectively connected to the signal output terminal of the nuclear power plant simulator and the network interface of the device under test, and the signal processing unit is connected to the hard-wired interface of the device under test; The nuclear power plant simulator is used to simulate the full operating data of the nuclear power plant, and processes the network signal of the simulated functional part of the tested device to be verified through the communication gateway and the signal processing unit and transmits it to the tested device.
10. The nuclear power plant control equipment verification system according to claim 9, It is characterized in that The communication gateway communicates with the nuclear power plant simulator based on a first communication protocol, the communication gateway communicates with the device under test based on a second communication protocol, and the host computer communicates with the signal processing unit based on a third communication protocol.
Citation Information
Cited By
Communication method and device for analog machine test, equipment, medium and program product
CN119788558A
Nuclear power control station periodic test method and related equipment
CN120578147A