Power distribution system active and reactive coupling flexible operation domain model and observation method

By establishing a flexible operating domain model for the coupling of active and reactive power in the power distribution system, the problem of adaptability boundary characterization for a high proportion of new energy power distribution system under the uncertainty of active and reactive power was solved, and the accurate characterization of net load and safe and economical operation of the system were achieved.

CN118899840APending Publication Date: 2024-11-05TIANJIN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411009037.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

In existing technologies, high-proportion renewable energy power distribution systems struggle to accurately characterize adaptation boundaries when faced with uncertainties in active and reactive power, potentially leading to the neglect of certain over-limit scenarios and impacting the safe and economical operation of the system.

Method used

A flexible operating domain model for active and reactive power coupling in a power distribution system is established. By combining linear algebra and basic feasible solution theory with affine methods, the boundary of the flexible operating domain for active and reactive power coupling is solved. Considering network constraints and the adjustment capability of flexible resources, polyhedral linearization technology is used to handle capacity constraints, and a high-dimensional geometric space is constructed to reflect the spatiotemporal coupling relationship.

Benefits of technology

It enables accurate characterization of the uncertainty of net load in the power distribution system, ensuring that the system can adapt to active and reactive power fluctuations under safe and economical operation, avoid over-limit scenarios, and improve the system's flexible supply capacity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118899840A_ABST
    Figure CN118899840A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution system active and reactive coupling flexible operation domain model and an observation method. Firstly, an active and reactive coupling flexible operation domain model of the power distribution system is constructed; secondly, obtaining a form of an active and reactive coupling flexible operation domain boundary by using linear algebra and a basic feasible solution theory; and finally, solving a part of flexible operation domain corresponding to each basic feasible solution through an optimization method, and obtaining a complete active and reactive coupling flexible operation domain through union set operation. The effectiveness of the provided model and method is verified through a 4-node system. According to the method, the adaptive boundary of the power distribution system to the net load uncertainty of each node can be depicted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of distribution network operation, and relates to the establishment of an active and reactive coupling flexible operation domain model of a distribution system, and a solution and observation method for the active and reactive coupling flexible operation domain. Background Art

[0002] The output of wind, solar and other renewable energy power generation is highly probabilistic due to the weather, and the various load demands and responses are also affected by user behavior and have certain uncertainties. This requires that a high proportion of renewable energy distribution systems can still maintain safe and economical operation under the influence of the above uncertain factors. The configuration scale and location of flexible resources and their utilization status at a specific moment will affect the system's adaptability to these uncertain factors.

[0003] In response to the above problems, scholars at home and abroad have proposed the concept of flexible operation domain of distribution system. Considering resource regulation capability as flexibility supply, and considering uncertain disturbances in system operation as flexibility demand, the balance of flexibility supply and demand focuses on the envelope capability of flexibility supply to flexibility demand. Therefore, it is necessary to quantify this envelope capability. There is a certain uncertainty in the active and reactive power of the net load of the node, and the two are not completely correlated. The distribution system has the ability to adapt to active and reactive uncertainties, but existing research pays more attention to the ability to adapt to active uncertainty. In fact, only focusing on active power and ignoring the adaptation boundary of reactive uncertainty may ignore certain over-limit scenarios. It is necessary to study a method for accurately characterizing the actual boundary (active and reactive coupling flexible operation domain) of adapting to active and reactive uncertainty in order to avoid the above problems. The present invention discloses a model and observation method of active and reactive coupling flexible operation domain of distribution system, considering the active and reactive coupling regulation capability of distribution network network constraints and converter interface grid-connected resources (energy storage, SOP), studying the modeling and observation analysis method of active-reactive coupling flexible operation domain, and realizing the description of system flexibility supply capability. Summary of the invention

[0004] In order to solve the above problems, the present invention proposes a distribution system active and reactive coupling flexible operation domain model and observation method.

[0005] The present invention solves the technical problem by adopting the following technical solutions:

[0006] A distribution system active and reactive coupling flexible operation domain model and observation method, the specific steps are as follows:

[0007] Step 1: Under the premise of maintaining safe operation, a distribution system active and reactive coupling flexible operation domain model is established. The model is expressed by the following formula:

[0008] Ω fle ={(P F,Q F )H(P F ,Q F )≤0},

[0009] Among them, Ω fle represents the set of net load fluctuation power that each node can adapt to in each period, P F Represents the vector of net load active power fluctuation that each node can adapt to, Q F Represents the vector of net load reactive power fluctuation that each node can adapt to, H represents P F and Q F The constraints satisfied.

[0010] Among them, the expression of the boundary of the active and reactive coupling flexible operation domain is:

[0011] H(P F ,Q F )=0;

[0012] Step 2: Using linear algebra and basic feasible solution theory, obtain the form of the boundary of the active and reactive coupling flexible operation domain;

[0013] Step 3: Solve the partial flexible operation domain corresponding to each solution through optimization method, and obtain the complete active and reactive coupling flexible operation domain through union operation.

[0014] Furthermore, the Step 1 specifically includes:

[0015] The target variable for flexibility in this application is defined as the net load fluctuation power P that each target node can adapt to under the influence of flexible adjustment capability: F ,Q F , under the constraints of safe and economic operation of the system, these power injections are balanced with the power of flexible resources and net loads:

[0016] F(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net ,P F ,Q F )=0

[0017] G(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net )≤0

[0018] The first formula represents all equivalent relationships, including power flow equations, node injection power expressions, etc. The second formula represents all inequality relationships, including network security constraints of node voltage and branch power, and the flexible adjustment range of various dispatchable resources. V is the vector composed of the voltage of each node, P branch ,Q branch is the vector of active and reactive power of each branch, P resource ,Q resource is the vector of active and reactive power of each flexible resource, P net ,Q net It is the vector composed of the net active and reactive power of each node.

[0019] Due to the time coupling and decentralized access to flexible resources, including energy storage systems and branch power constraints, the flexibility representation variables at different locations and time periods It is coupled;

[0020] The active and reactive coupling flexible operation domain is defined as a high-dimensional geometric space to reflect this spatiotemporal coupling relationship.

[0021] Ω fle ={(P F ,Q F )H(P F ,Q F )≤0}

[0022] Ω fle The variables in are part of the original variables, and the original variable space is in the subspace P F ,Q F Projection on.

[0023] Furthermore, the method of obtaining the boundary of the active and reactive coupling flexible operation domain in step 2 includes:

[0024] The S21 line capacity constraint and SOP capacity constraint are linearized, and the line capacity and SOP capacity constraints are transformed using polyhedron linearization technology;

[0025] S22 organizes all constraints on boundary known variables into a set of equations and inequalities, which contains the target variables of the flexible operation domain;

[0026] S23 uses linear algebra and basic feasible solution theory to solve all basic feasible solutions of the linear programming problem corresponding to the system of equations and the system of inequalities described in S22;

[0027] S24 constructs an analytical expression for the active and reactive coupling flexible operation domain corresponding to each basic feasible solution.

[0028] Furthermore, the S22 is specifically as follows: all the known variables about the boundary The constraints are organized as and In the form of, forming a system of equations and inequalities;

[0029] Based on the affine method, the target variable is obtained An affine relationship between the constrained variables, including voltage, branch power, and flexible resource regulation power, and then combining the affine relationship with the upper and lower bounds of the constrained variables to obtain a feasible range of the target variable;

[0030] The details are as follows:

[0031] For time period t, the solution of the feasible region is expressed as: there are some variables with known boundaries, denoted as and The relevant equations and inequalities are summarized below:

[0032]

[0033] Where Φ and Γ are parameter matrices, ε t is a vector of constant parameters.

[0034] Furthermore, the step S23 is specifically: using linear algebra methods to solve and All basic feasible solutions of the corresponding linear programming problem, get the boundary known variables and the target variable The affine relationship between

[0035] The basic feasible solution is a solution to a linear programming problem with a minimum set of non-zero variables. For linear programming problems, first of all, standardization is required, and the following auxiliary variables are introduced:

[0036]

[0037] In the formula, and From for For a variable in Another border is , it may correspond to the upper bound or the lower bound. Therefore, and is a selection result. This application refers to it as the mth selection method, so the original equation and Arranged into the following matrix form:

[0038]

[0039] in,

[0040]

[0041] On this basis, the lth basic feasible solution of the linear programming problem corresponding to the above equation is discussed as follows:

[0042]

[0043] In the formula, Yes t The two complement each other to form a complete basic feasible solution. For all variables z t ;

[0044] For the lth basic feasible solution, there is the following equality relationship:

[0045]

[0046] In the formula, Φ a,l is Φ The corresponding part of the matrix;

[0047] Therefore, under certain conditions, the basic feasible solution is derived and The mapping relationship between The value range of feasible range.

[0048] Further deduction shows that

[0049]

[0050] It can be seen from this that a certain choice and The feasible domain obtained by a basic feasible solution is a local feasible domain, which is only a part of the overall feasible domain. It is necessary to list all m and l to obtain feasible domain.

[0051] Further, the step S24 is specifically as follows: constructing an analytical expression of the active and reactive coupling flexible operation domain corresponding to each basic feasible solution:

[0052] The feasible domain is The upper and lower bounds of The energy storage system power is determined by There is temporal coupling between the upper and lower bounds of the variables; The time coupling model is used to obtain the flexible operation domain expression;

[0053] According to the above analysis, Considering the time coupling characteristics of this expression, its feasible domain is expressed as:

[0054]

[0055] In the formula,

[0056] For each m and l, the above The feasible domain of is accurate because it is derived from the affine relationship. Considering all m and l, the active and reactive power flexible operation domain is expressed as follows:

[0057]

[0058] Furthermore, the Step 3 specifically includes:

[0059] because The calculation process is complicated. After deriving the expression Then, the optimal power flow is used to obtain

[0060]

[0061] Then the expression of the active and reactive coupling flexible operation domain is obtained as follows:

[0062]

[0063] An electronic device comprises a processor and a memory, wherein the memory is used to store instructions, and the processor is used to execute the instructions stored in the memory so that the electronic device executes any one of the methods described above.

[0064] A computer-readable storage medium storing instructions, when the instructions are executed, performs any of the above methods

[0065] The advantages and positive effects of the present invention are:

[0066] The method of the present application can characterize the adaptation boundary of the distribution system to the uncertainty of the net load of each node, and the effectiveness of the proposed model and method is verified through a 4-node system. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] In order to more clearly illustrate the technical solution of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0068] Figure 1 A flow chart for solving a distribution system active and reactive coupling flexible operation domain model and an observation method in the present invention;

[0069] Figure 2 A flowchart for solving step 2 in claim 1 of the present invention;

[0070] Figure 3 This is a schematic diagram of the network structure of a 4-node system in this implementation case;

[0071] Figure 4 This is a schematic diagram of the active and reactive coupling flexible operation domain of node 1 in this implementation case;

[0072] Figure 5 This is a schematic diagram of the active and flexible operation domain of node 1 and node 2 in this implementation case; DETAILED DESCRIPTION

[0073] In order to make the structure and advantages of the present invention more clear, the structure of the present invention will be further described below in conjunction with the accompanying drawings.

[0074] Combined with Figure 1 The overall solution process of the solution flow chart of the active and reactive coupling flexible operation domain model and observation method of the power distribution system proposed by the present invention is described in detail, and the specific steps are as follows:

[0075] Step 1: Propose a distribution system active and reactive coupling flexible operation domain model, that is, under the premise of maintaining safe operation, each node in each period can adapt to the net load fluctuation power (target variable) of the set. Specifically include:

[0076] The target variable for flexibility in this application is defined as the net load fluctuation power that each target node can adapt to under the influence of flexible adjustment capability. Under the constraints of system safe and economic operation, these power injections are balanced with the power of flexible resources and net load.

[0077] F(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net ,P F ,Q F )=0

[0078] G(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net )≤0

[0079] The first formula represents all equivalent relationships, including power flow equations, node injection power expressions, etc. The second formula represents all inequality relationships, including network security constraints of node voltage and branch power, and the flexible adjustment range of various dispatchable resources. V is the vector composed of the voltage of each node, P branch ,Q branch is the vector of active and reactive power of each branch, P resource ,Q resource is the vector of active and reactive power of each flexible resource, P net ,Q net It is the vector composed of the net active and reactive power of each node.

[0080] Due to the temporal coupling and decentralized access to flexible resources, such as energy storage systems, as well as branch power constraints, the flexibility representation variables δ t F This paper defines the flexible operation domain of active and reactive coupling as a high-dimensional geometric space to reflect this spatiotemporal coupling relationship.

[0081] Ω fle ={(P F ,Q F )H(P F ,Q F )≤0}

[0082] Ω fle The variables in P are part of the original variables, that is, the original variable space is in P F ,Q F Projection onto (subspace).

[0083] The flexibility resources in this application mainly include SOP and energy storage. The SOP operation model is as follows:

[0084] P SOP,i,t +P SOP,j,t =0

[0085]

[0086] The energy storage operation model is as follows:

[0087]

[0088] in,

[0089] Step 2: Solve the equations using linear algebra and basic feasible solution theory to obtain the boundary expression of the active and reactive coupling flexible operation domain, including linearization of line capacity constraints and SOP capacity constraints; organize all constraints on the known variables on the boundary into equations and inequalities, which contain the target variables of the flexible operation domain; use linear algebra and basic feasible solution theory to solve all basic feasible solutions of the linear programming problem corresponding to the above equations and inequalities to obtain the boundary of the active and reactive coupling flexible operation domain;

[0090] Specifically include:

[0091] 1) Line capacity constraints and SOP capacity constraints are linearized

[0092] In order to accurately constrain active and reactive power, the line capacity and SOP capacity constraints are transformed using polyhedron linearization technology.

[0093]

[0094] where x n and n is an auxiliary variable; μ is the relaxation coefficient.

[0095] You can eliminate n equality constraints and n variables x n , then about the variable P SOPi , Q SOPi , S SOPi The three-dimensional second-order cone constraint will be approximately equivalent to the variable P SOPi , Q SOPi , S SOPi ,x0,y n A set of linear inequality constraints (n=0,1,...,L).

[0096] The calculation method of μ is as follows:

[0097]

[0098] When L is selected as 8, μ≈1.88×10 -5 In this case, the polyhedron linearization accuracy is almost 100%, and the processed linear constraints are roughly equivalent to the original second-order conic constraints.

[0099] 2) All about The constraints are organized as and , forming a system of equations and inequalities.

[0100] Based on the affine method, the target variable is obtained The affine relationship between the target variable and the constrained variable (such as voltage, branch power, and flexible resource adjustment power). Then, the feasible range of the target variable is obtained by combining the affine relationship and the upper and lower bounds of the constrained variable. The core idea is briefly described as follows:

[0101] For time period t, the solution of the feasible domain can be expressed as: there are some variables with known boundaries (constrained variables), denoted as and and The relevant equations and inequalities can be summarized as follows:

[0102]

[0103] Where Φ and Γ are parameter matrices, ε t is a vector of constant parameters.

[0104] 3) Solve using linear algebra methods and All basic feasible solutions of the corresponding linear programming problem are obtained and The affine relationship between .

[0105] The basic feasible solution is a solution to a linear programming problem with a minimum set of non-zero variables. For linear programming problems, first of all, standardization is required and the following auxiliary variables are introduced:

[0106]

[0107] In the formula, and From for For a variable in Another border is , it may correspond to the upper bound or the lower bound. Therefore, and is a selection result. This paper calls it the mth selection method, so the original equation and Arranged into the following matrix form:

[0108]

[0109] in,

[0110]

[0111] On this basis, the lth basic feasible solution of the linear programming problem corresponding to the above equation is discussed as follows:

[0112]

[0113] In the formula, Yes t The two complement each other to form a complete basic feasible solution. For all variables z t .

[0114] Discuss the basic feasible solution The way to obtain Φ is to set the rank of Φ to S (the number of equations). The number of is N, then z t The number of is 2N and the rank of J is N+S, The number of variables in is N+S, The number of variables in is NS. Next, we discuss how to obtain the basic feasible solution in two cases:

[0115] 1) When performing variable selection, if from z t Select NS variables from All from Then the corresponding The rank is N+S, so the selected and It meets the requirements of a basic feasible solution and is a basic feasible solution;

[0116] 2) If from z t Select NS variables from Not all from And there are from Yes, then the corresponding The rank is less than N+S, so the selected and It does not meet the requirements of a basic feasible solution and is not a basic feasible solution. and The situation is checked and the set of basic feasible solutions Ω is obtained. b .

[0117] For the lth basic feasible solution, there is the following equality relationship:

[0118]

[0119] In the formula, Φ a,l is Φ The corresponding part of the matrix.

[0120] Therefore, we can derive the and The mapping relationship between . Based on this basic feasible solution and The value range of feasible range.

[0121] Further deduction

[0122]

[0123] It can be seen from this that a certain choice and The feasible domain obtained by a basic feasible solution is a local feasible domain, which is only a part of the overall feasible domain. It is necessary to list all m and l to obtain feasible domain.

[0124] 4) Construct the analytical expression of the active and reactive coupling flexible operation domain corresponding to each basic feasible solution

[0125] The feasible domain is The upper and lower bounds of The energy storage system power is determined by There is temporal coupling between the upper and lower bounds of the variables. The time coupling model can obtain the flexible operation domain expression of active and reactive coupling with time and space coupling.

[0126] According to the above analysis, Considering the time coupling characteristics of this expression, its feasible domain can be expressed as:

[0127]

[0128] In the formula,

[0129] For each m and l, the above The feasible domain of is accurate because it is derived from the affine relationship. Therefore, considering all m and l, the active and reactive coupling flexible operation domain can be expressed as follows:

[0130]

[0131] Step 3: Determine the parameters in the boundary expression of the active and reactive coupling flexible operation domain of the distribution system. Solve the partial flexible operation domain corresponding to each basic feasible solution through optimization method, and obtain the complete active and reactive coupling flexible operation domain through union operation. Specifically include:

[0132] because The calculation process is complicated. After deriving the expression Then, the optimal power flow can be used to obtain

[0133]

[0134] Then the expression of the active and reactive coupling flexible operation domain is obtained as follows:

[0135]

[0136] The effectiveness of the proposed model and method is demonstrated on the example system. This paper uses a 4-node system to test the model and observation method of the flexible operation domain. A 3MW SOP is installed between feeders F1 and F2, and node 1 is connected to a 1MW energy storage. The line capacity is 7.8MW. The system diagram is attached. Figure 3 , now we analyze the active and reactive coupling flexible operation domain of node 1 and node 2.

[0137] First, construct the active and reactive power flexible operation domain according to the above steps. The specific process of step 2 is shown in the attached Figure 2 .

[0138] Analyze the boundary of the active and reactive coupling flexible operation domain of node 1 under the combined action of SOP and energy storage, as shown in the attached figure. Figure 4 shown.

[0139] Analyze the boundary between the active and flexible operation domain of node 1 and the active and flexible operation domain of node 2 under the combined effect of SOP and energy storage. Figure 5 shown.

[0140] The present application also provides an electronic device, which may include: at least one processor and at least one memory.

[0141] The processor may include one or more processing cores. The processor uses various interfaces and lines to connect various parts of the entire server, and executes various functions of the server and processes data by running or executing instructions, programs, code sets or instruction sets stored in the memory, and calling data stored in the memory.

[0142] Optionally, the processor can be implemented in at least one hardware form of digital signal processing (DSP), field programmable gate array (FPGA), and programmable logic array (PLA). The processor can integrate one or a combination of a central processing unit (CPU), a graphics processing unit (GPU), and a modem. Among them, the CPU mainly processes the operating system, user interface, and application programs; the GPU is responsible for rendering and drawing the content to be displayed on the display; and the modem is used to process wireless communications. It is understandable that the above-mentioned modem may not be integrated into the processor, but may be implemented separately through a chip.

[0143] Among them, the memory may include a random access memory (RAM) or a read-only memory (Read-Only Memory). Optionally, the memory includes a non-transitory computer-readable storage medium. The memory can be used to store instructions, programs, codes, code sets or instruction sets. The memory may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as a touch function, a sound playback function, an image playback function, etc.), instructions for implementing the above-mentioned various method embodiments, etc.; the data storage area may store data involved in the above-mentioned various method embodiments, etc. The memory may also be optionally at least one storage device located away from the aforementioned processor. The memory as a computer storage medium may include an operating system, a network communication module, a user interface module, and an application program for a method for diagnosing a fault of a worm gearbox.

[0144] The present application also provides a computer-readable storage medium, which stores instructions. When executed by one or more processors, the electronic device executes one or more of the methods described in the above embodiments.

[0145] In addition, each functional unit in the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0146] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, which is stored in a memory and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned memory includes: various media that can store program codes, such as USB flash drives, mobile hard drives, magnetic disks or optical disks.

[0147] The above descriptions are merely embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A distribution system active and reactive coupling flexible operation domain model and observation method, characterized in that: The specific steps are as follows: Step 1: Under the premise of maintaining safe operation, a distribution system active and reactive coupling flexible operation domain model is established. The model is expressed by the following formula: Ω fle ={(P F ,Q F )H(P F ,Q F )≤0}, Among them, Ω fle Represents the set of net load fluctuation power that each node can adapt to in each period, P F Represents the vector of net load active power fluctuation that each node can adapt to, Q F Represents the vector of net load reactive power fluctuation that each node can adapt to, H represents P F and Q F The constraints satisfied. Among them, the expression of the boundary of the active and reactive coupling flexible operation domain is: H(P F ,Q F )=0; Step 2: Using linear algebra and basic feasible solution theory, obtain the form of the boundary of the active and reactive coupling flexible operation domain; Step 3: Solve the partial flexible operation domain corresponding to each solution through optimization method, and obtain the complete active and reactive coupling flexible operation domain through union operation.

2. According to claim 1, a distribution system active and reactive coupling flexible operation domain model and observation method, characterized in that: The Step 1 specifically includes: The target variable for flexibility in this application is defined as the net load fluctuation power P that each target node can adapt to under the influence of flexible adjustment capability: F ,Q F , under the constraints of safe and economic operation of the system, these power injections are balanced with the power of flexible resources and net loads: F(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net ,P F ,Q F )=0 G(V,P branch ,Q branch ,P resource ,Q resource ,P net ,Q net )≤0 The first formula represents all equivalent relationships, including power flow equations, node injection power expressions, etc. The second formula represents all inequality relationships, including network security constraints of node voltage and branch power, and the flexible adjustment range of various dispatchable resources. V is the vector composed of the voltage of each node, P branch ,Q branch is the vector of active and reactive power of each branch, P resource ,Q resource is the vector of active and reactive power of each flexible resource, P net ,Q net It is the vector composed of the net active and reactive power of each node. Due to the time coupling and decentralized access to flexible resources, including energy storage systems and branch power constraints, the flexibility representation variables at different locations and time periods It is coupled; The active and reactive coupling flexible operation domain is defined as a high-dimensional geometric space to reflect this spatiotemporal coupling relationship. Ω fle ={(P F ,Q F )H(P F ,Q F )≤0} Ω fle The variables in are part of the original variables, and the original variable space is in the subspace P F ,Q F Projection on.

3. According to claim 1, a distribution system active and reactive coupling flexible operation domain model and observation method, characterized in that: The method of step 2, obtaining the form of the boundary of the active and reactive coupling flexible operation domain, comprises: The S21 line capacity constraint and SOP capacity constraint are linearized, and the line capacity and SOP capacity constraints are transformed using polyhedron linearization technology; S22 organizes all constraints on boundary known variables into a set of equations and inequalities, which contains the target variables of the flexible operation domain; S23 uses linear algebra and basic feasible solution theory to solve all basic feasible solutions of the linear programming problem corresponding to the system of equations and the system of inequalities described in S22; S24 constructs an analytical expression for the active and reactive coupling flexible operation domain corresponding to each basic feasible solution.

4. According to claim 3, a distribution system active and reactive coupling flexible operation domain model and observation method is characterized in that: The S22 is specifically: all the known variables about the boundary are The constraints are organized as and In the form of, forming a system of equations and inequalities; Based on the affine method, the target variable is obtained An affine relationship between the constrained variables, including voltage, branch power, and flexible resource regulation power, and then combining the affine relationship with the upper and lower bounds of the constrained variables to obtain a feasible range of the target variable; The details are as follows: For time period t, the solution of the feasible region is expressed as: there are some variables with known boundaries, denoted as and The relevant equations and inequalities are summarized below: Where Φ and Γ are parameter matrices, ε t is a vector of constant parameters.

5. According to claim 3, a distribution system active and reactive coupling flexible operation domain model and observation method is characterized in that: The step S23 is specifically: using linear algebra method to solve and All basic feasible solutions of the corresponding linear programming problem, get the boundary known variables and the target variable The affine relationship between The basic feasible solution is a solution to a linear programming problem with a minimum set of non-zero variables. For linear programming problems, first of all, standardization is required, and the following auxiliary variables are introduced: In the formula, and From for For a variable in Another border is , it may correspond to the upper bound or the lower bound. Therefore, and is a selection result. This application refers to it as the mth selection method, so the original equation and Arranged into the following matrix form: in, On this basis, the lth basic feasible solution of the linear programming problem corresponding to the above equation is discussed as follows: In the formula, Yes t The two complement each other to form a complete basic feasible solution. For all variables For the lth basic feasible solution, there is the following equality relationship: In the formula, Φ a,l is Φ The corresponding part of the matrix; Therefore, under certain conditions, the basic feasible solution is derived and The mapping relationship between The value range of feasible range. Further deduction shows that It can be seen from this that a certain choice and The feasible domain obtained by a basic feasible solution is a local feasible domain, which is only a part of the overall feasible domain. It is necessary to list all m and l to obtain feasible domain.

6. According to claim 3, a distribution system active and reactive coupling flexible operation domain model and observation method is characterized in that: The step S24 is specifically as follows: constructing an analytical expression of the active and reactive coupling flexible operation domain corresponding to each basic feasible solution The feasible domain is The upper and lower bounds of The energy storage system power is determined by There is temporal coupling between the upper and lower bounds of the variables; The time coupling model is used to obtain the flexible operation domain expression; According to the above analysis, Considering the time coupling characteristics of this expression, its feasible domain is expressed as: In the formula, A=[I,L] T ; For each m and l, the above The feasible domain of is accurate because it is derived from the affine relationship. Considering all m and l, the active and reactive power flexible operation domain is expressed as follows:

7. According to claim 1, a distribution system active and reactive coupling flexible operation domain model and observation method, characterized in that: The Step 3 specifically includes: because The calculation process is complicated. After deriving the expression Then, the optimal power flow is used to obtain Then the expression of the active and reactive coupling flexible operation domain is obtained as follows:

8. An electronic device, comprising a processor and a memory, wherein the memory is used to store instructions, and the processor is used to execute the instructions stored in the memory, so that the electronic device executes the method according to any one of claims 1 to 7.

9. A computer-readable storage medium storing instructions, wherein when the instructions are executed, the method according to any one of claims 1 to 7 is executed.