Composite material car roof assembling tool and method

By designing composite roof assembly tooling, including support, positioning and compression devices, the problem of composite roof assembly is solved, precise positioning and high-quality connection of the roof is achieved, and assembly accuracy and product quality are improved.

CN118906477APending Publication Date: 2024-11-08CRRC QINGDAO SIFANG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411397059.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The prior art lacks assembly tooling suitable for composite roofs, making it difficult to achieve precise positioning and high-quality connection of composite roofs.

Method used

A composite roof assembly tool is designed, including support devices, positioning devices, prototyping compression devices and hoisting devices, for supporting, positioning and pressing various parts of the roof, and through these devices, the roof accuracy of the roof is achieved. Assembly.

Benefits of technology

It realizes precise positioning and high-quality connection of each component on the roof of the composite material, improving assembly accuracy and product quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118906477A_ABST
    Figure CN118906477A_ABST
Patent Text Reader

Abstract

The invention discloses a composite material car roof assembling tool and method.The composite material car roof assembling tool comprises a first supporting device used for supporting an end arc top, a middle arc top and an air conditioner platform of a car roof; the positioning device is arranged opposite to the first supporting device and used for positioning the end arc top, the middle arc top and the air conditioner platform on the first supporting device; the profiling pressing device is used for pressing the joint of the end arc top and the air conditioner platform and the joint of the air conditioner platform and the middle arc top; and the jacking device is arranged opposite to the first supporting device and used for lifting the end arc tops or the middle arc tops before the end arc tops and the middle arc tops are connected with the air conditioner platform so as to treat the connecting areas and lowering the end arc tops or the middle arc tops after treatment. Positioning of all the parts of the composite material car roof, process treatment of the connecting positions of all the parts and pressing of the connecting positions of the car roof parts through the profiling pressing device can be achieved, assembling of the composite material car roof can be achieved, and the assembling precision and the product quality of the composite material car roof are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of composite vehicle roof assembly, and more specifically, to a composite vehicle roof assembly tool. In addition, the present invention also relates to a composite vehicle roof assembly method using the composite vehicle roof assembly tool to assemble the composite vehicle roof. Background Art

[0002] At present, rail transit vehicle bodies are mainly made of metal materials such as carbon steel, stainless steel and aluminum alloy. In the relevant technologies, body assembly tools and process methods are also mainly applicable to metal bodies. However, with the need for lightweight high-speed trains, composite materials such as glass fiber and carbon fiber reinforced composite materials are gradually being used in rail vehicles. However, there is currently no assembly tool for composite roofs.

[0003] Therefore, how to provide an assembly tool that can adapt to the assembly of composite material roofs is a problem that urgently needs to be solved by those skilled in the art. Summary of the invention

[0004] In view of this, an object of the present invention is to provide a composite material vehicle roof assembly tool, which can realize the assembly of the composite material vehicle roof.

[0005] Another object of the present invention is to provide a composite material roof assembly method for assembling a composite material roof using the composite material roof assembly tool, which can realize the assembly of the composite material roof.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A composite material roof assembly tool, comprising:

[0008] A first supporting device is used to support the end arc top, the middle arc top and the air conditioning platform of the roof;

[0009] A positioning device, arranged relative to the first supporting device, used to position the end arc top, the middle arc top and the air conditioning platform on the first supporting device respectively;

[0010] A contour pressing device, used for pressing the connection between the end arc top and the air conditioning platform and the connection between the air conditioning platform and the middle arc top;

[0011] The lifting device is arranged relative to the first supporting device, and is used to lift the end arc top or the middle arc top before connecting the end arc top and the middle arc top to the air-conditioning platform respectively, so as to process the connection area, and lower the end arc top or the middle arc top after processing.

[0012] Optionally, the positioning device includes two transverse center positioning mechanisms, which are respectively arranged on both sides of the width direction of the first supporting device and correspond to the center position of the length direction of the first supporting device;

[0013] The transverse center positioning mechanism is provided with a transverse positioning plate, and the transverse positioning plate is used to indicate the transverse center line of the roof to define the position of the transverse center line of the middle arc top.

[0014] Optionally, the positioning device comprises:

[0015] A first longitudinal positioning mechanism is provided at one end of the first supporting device in the length direction, the first longitudinal positioning mechanism comprises a second column and a first wire pulling device provided on the second column, the first wire pulling device comprises a winding wheel, a thin wire and a first positioning wheel;

[0016] A second longitudinal positioning mechanism is arranged at the other end in the length direction of the first supporting device. The second longitudinal positioning mechanism includes a third column, a second positioning wheel and a wire binding ring. The thin wire is wound out from the winding wheel, passes through the first positioning wheel to the second positioning wheel, and is fixed to the wire binding ring. The thin wire is used to mark the longitudinal center line of the roof to define the positions of the end arc top, the middle arc top and the longitudinal center line of the air-conditioning platform.

[0017] Optionally, the positioning device comprises:

[0018] Four end positioning mechanisms are respectively arranged at the two ends in the length direction and the two sides in the width direction of the first supporting device, and are used to position the end arc tops.

[0019] Optionally, the first supporting device comprises:

[0020] Two foundation longitudinal beams arranged in parallel;

[0021] A plurality of support column assemblies are arranged on the foundation longitudinal beam, and the support column assemblies include:

[0022] The fifth pillar;

[0023] A first support block, disposed on the top of the fifth column, for supporting the end arc top, the middle arc top or the air conditioning platform;

[0024] The first rotating clamping assembly is rotatably disposed on the top of the fifth column and is used to clamp or loosen the end arc top, the middle arc top or the air conditioning platform.

[0025] Optionally, the contour pressing device comprises:

[0026] two sixth columns arranged in parallel;

[0027] A profiled beam connected between two of the sixth columns;

[0028] The spiral compression components are arranged at intervals along the length direction of the profiled beam and are used to compress the connection between the end arc top and the air conditioning platform or the connection between the air conditioning platform and the middle arc top.

[0029] Optionally, the lifting device comprises:

[0030] The seventh pillar;

[0031] A first lifting mechanism, provided on the seventh column;

[0032] A movable plate connected to the first lifting mechanism;

[0033] A second support block is provided on the movable plate and is used to support the end arc top, the middle arc top or the air conditioning platform;

[0034] The second rotary clamping assembly is rotatably disposed on the movable plate and is used for clamping or loosening the end arc top, the middle arc top or the air conditioning platform.

[0035] Optionally, it also includes:

[0036] A hanging frame provided with hanging ears;

[0037] A second supporting device, used to support the hanging frame;

[0038] The vehicle roof fixing tool is used to fix the vehicle roof.

[0039] Optionally, the roof fixing tooling comprises:

[0040] The arc-shaped template assembly is arranged on the hanging frame, including an arc-shaped template, a second lifting mechanism connected to the arc-shaped template, and two clamping mechanisms respectively arranged at both ends of the arc-shaped template, wherein the clamping mechanism is used to apply pressure to the top of the roof to fine-tune the curvature of the roof so that the curvature of the roof is the same as the curvature of the arc-shaped template.

[0041] Optionally, the roof fixing tooling comprises:

[0042] Two through-length longitudinal beams connected to the hanging frame, arranged in parallel along the length direction of the roof, and used to be located below the roof;

[0043] A cross brace assembly connected to the through-length longitudinal beam, used to support the end arc top, the middle arc top and the air conditioning platform, and the cross brace assembly can be extended and retracted in a direction close to or away from the roof to support different products;

[0044] The contoured top beam assembly is connected to the full-length longitudinal beam and can be extended and retracted in a direction close to or away from the roof to support different products. It is arranged below the curved beam connecting the end arc top and the air-conditioning platform and below the curved beam connecting the middle arc top and the air-conditioning platform.

[0045] Optionally, the roof fixing tooling comprises:

[0046] Two air-conditioning outlet hanging beams are connected between the hanging frame and the full-length longitudinal beam and are respectively located at the air-conditioning outlet positions of the two air-conditioning platforms on the roof.

[0047] A composite material roof assembly method is applied to any one of the composite material roof assembly tools mentioned above, and the composite material roof assembly method comprises:

[0048] The air-conditioning platform is hoisted to the first supporting device, and the air-conditioning platform is positioned by using the positioning device. After the air-conditioning platform is positioned, the air-conditioning platform is pressed and fixed;

[0049] Lifting the middle arc top to the first supporting device, and positioning the middle arc top using the positioning device;

[0050] The contour pressing device is used to press the overlapping position between the middle arc top and the air conditioning platform;

[0051] Lifting the end arc top to the first supporting device, and positioning the end arc top using the positioning device;

[0052] The contour pressing device is used to press the overlapping position between the end arc top and the air conditioning platform;

[0053] Pressing the end arc top tightly;

[0054] Mark the first position of the profiling pressing device at the middle arc top, remove the profiling pressing device at the overlapping position of the middle arc top and the air-conditioning platform, use the jacking device to lift the middle arc top to be away from the surface of the air-conditioning platform, process the connection position of the middle arc top and the air-conditioning platform, use the jacking device to lower the middle arc top, press the profiling pressing device at the overlapping position of the middle arc top and the air-conditioning platform, so that the profiling pressing device is located at the first position;

[0055] Riveting the middle arc top to the air conditioning platform;

[0056] Mark the second position of the profiling pressing device at the end arc top, remove the profiling pressing device at the overlapping position of the end arc top and the air conditioning platform, use the jacking device to lift the end arc top to be away from the surface of the air conditioning platform, process the connection position of the end arc top and the air conditioning platform, use the jacking device to lower the end arc top, press the profiling pressing device at the overlapping position of the end arc top and the air conditioning platform, so that the profiling pressing device is located at the second position;

[0057] The end arc top is riveted to the air conditioning platform.

[0058] Optionally, the composite material roof assembly tool further comprises a hanging frame, a second supporting device and a roof fixing tool, and the composite material roof assembly method further comprises:

[0059] After the roof is assembled, the arc-shaped template formed by the roof fixing tooling is adjusted to the highest position and locked by using the second lifting mechanism formed by the roof fixing tooling;

[0060] The second supporting device is arranged on both sides of the roof;

[0061] Lifting the hanging frame onto the second supporting device, and connecting the hanging frame to the second supporting device;

[0062] The through-length longitudinal beam composed of the roof fixing tooling is arranged below the roof, and the through-length longitudinal beam is connected to the hanging frame;

[0063] Adjusting the clamping mechanism of the arc-shaped template assembly formed by the roof fixing tooling so that the roof fits the arc-shaped template of the arc-shaped template assembly, and locking the arc-shaped template;

[0064] Adjusting the height of the cross brace assembly and the profiled top beam assembly of the roof fixing tooling so that the cross brace assembly and the profiled top beam assembly are respectively fitted with the bottom of the roof;

[0065] By lifting the lifting frame, the roof is lifted to the vehicle body assembly platform.

[0066] The composite material roof assembly tool provided by the present invention has the following beneficial effects:

[0067] The first supporting device has supporting points for supporting the end arc top, the middle arc top and the air conditioning platform respectively, so that the end arc top, the middle arc top and the air conditioning platform can be placed on the first supporting device; the positioning device can position the end arc top, the middle arc top and the air conditioning platform respectively, so that the end arc top, the middle arc top and the air conditioning platform have accurate positions on the first supporting device respectively, thereby ensuring the assembly accuracy of the end arc top and the middle arc top connected to the air conditioning platform respectively; the contour pressing device can press the connection between the end arc top and the air conditioning platform and the connection between the air conditioning platform and the middle arc top, thereby ensuring the connection quality of the connection between the end arc top and the air conditioning platform and the connection quality of the connection between the air conditioning platform and the middle arc top. In addition, before connecting the end arc top and the middle arc top to the air conditioning platform respectively, the end arc top or the middle arc top is raised by the lifting device to process the connection area between the end arc top and the middle arc top and the air conditioning platform respectively, which is conducive to ensuring the reliability of the connection between the end arc top and the middle arc top and the air conditioning platform respectively.

[0068] It can be seen that the composite roof assembly tooling can realize the positioning of the various components of the composite roof, the process treatment of the joints of the various components, and the use of the contoured pressing device to press the joints of the roof components, thereby realizing the assembly of the composite roof and improving the assembly accuracy and product quality of the composite roof.

[0069] The composite material vehicle roof assembly method provided by the present invention is applied to the composite material vehicle roof assembly tool and has the same beneficial effects as the composite material vehicle roof assembly tool. BRIEF DESCRIPTION OF THE DRAWINGS

[0070] In order to more clearly illustrate the technical solutions in the embodiments of the present invention or related technologies, the drawings required for use in the embodiments or related technical descriptions are briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0071] Figure 1 A schematic diagram of the structure of a composite material roof assembly tool provided in a specific embodiment of the present invention;

[0072] Figure 2 It is a structural schematic diagram of the transverse center positioning mechanism;

[0073] Figure 3 is a structural schematic diagram of a first longitudinal positioning mechanism;

[0074] Figure 4 is a structural schematic diagram of a second longitudinal positioning mechanism;

[0075] Figure 5 is a structural schematic diagram of the end positioning mechanism;

[0076] Figure 6 The structural diagram of the foundation longitudinal beam;

[0077] Figure 7 It is a structural schematic diagram of the support column assembly;

[0078] Figure 8 It is a structural schematic diagram of the profiling pressing device;

[0079] Fig. 9 It is a structural schematic diagram of the jacking device;

[0080] Fig.10 It is a structural schematic diagram of the roof transfer tooling;

[0081] Fig.11 It is a schematic diagram of the structure of the roof fixing tooling;

[0082] Fig.12 is a schematic structural diagram of a second supporting device;

[0083] Fig.13 This is a schematic diagram of the structure when the air conditioning platform is installed on the composite roof assembly tooling;

[0084] Fig.14 It is a schematic diagram of the structure when the middle arc top is installed on the composite roof assembly tooling;

[0085] Fig.15 It is a structural schematic diagram of the contour pressing device pressing the overlapping position of the middle arc top and the air conditioning platform;

[0086] Fig.16 It is a schematic diagram of the structure in which the arc-shaped template assembly presses the top of the roof;

[0087] Fig.17 It is a schematic diagram of the structure after the roof transfer tool is connected to the roof installed on the composite material roof assembly tool;

[0088] Fig.18 for Fig.17 Left view of .

[0089] Reference numerals:

[0090] 1-first support device; 11-foundation longitudinal beam; 12-support column assembly; 121-fifth column; 122-first support block; 123-first rotary clamping assembly; 13-tooling pressure head; 2-positioning device; 21-lateral center positioning mechanism; 211-lateral positioning plate; 212-first column; 22-first longitudinal positioning mechanism; 221-second column; 222-first wire pulling device; 2221-winding wheel; 2222-fine wire; 2223-first positioning wheel; 23-second longitudinal positioning mechanism; 231-third column, 232-second positioning wheel; 233-binding ring; 24-end positioning mechanism; 241-fourth column; 242-end The first part is a positioning plate; 3-profile clamping device; 31-sixth column; 32-profile beam; 33-screw clamping assembly; 4-lifting device; 41-seventh column; 42-first lifting mechanism; 43-movable plate; 44-second support block; 45-second rotary clamping assembly; 5-hanging frame; 6-second supporting device; 61-eighth column; 62-positioning column; 7-roof fixing tooling composition; 71-arc template assembly; 711-arc template; 712-second lifting mechanism; 713-clamping mechanism; 72-through-length longitudinal beam; 73-cross brace assembly; 74-profile top beam assembly; 75-air conditioning outlet hanging beam; 8-air conditioning platform; 9-middle arc top; 10-end arc top. DETAILED DESCRIPTION

[0091] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0092] The core of the present invention is to provide a composite material roof assembly tool, which can realize the assembly of the composite material roof. Another core of the present invention is to provide a composite material roof assembly method using the composite material roof assembly tool to assemble the composite material roof, which can realize the assembly of the composite material roof.

[0093] Please refer to Figure 1The embodiment of the present invention provides a composite material roof assembly tool, including a first supporting device 1, a positioning device 2, a contour pressing device 3 and a jacking device 4, wherein the first supporting device 1 is used to support the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 of the roof; the positioning device 2 is arranged relative to the first supporting device 1, and is used to position the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 on the first supporting device 1 respectively; the contour pressing device 3 is used to press the connection between the end arc top 10 and the air-conditioning platform 8 and the connection between the air-conditioning platform 8 and the middle arc top 9; the jacking device 4 is arranged relative to the first supporting device 1, and is used to raise the end arc top 10 or the middle arc top 9 before connecting the end arc top 10 and the middle arc top 9 to the air-conditioning platform 8 respectively, so as to process the connection area, and lower the end arc top 10 or the middle arc top 9 after the processing.

[0094] It can be understood that the first supporting device 1 has supporting points for supporting the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 respectively, so that the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 can be placed on the first supporting device 1; the positioning device 2 can position the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 respectively, so that the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 have precise positions on the first supporting device 1 respectively, thereby ensuring the assembly accuracy of the end arc top 10 and the middle arc top 9 connected to the air-conditioning platform 8 respectively; the contoured clamping device 3 can clamp the connection between the end arc top 10 and the air-conditioning platform 8 and the connection between the air-conditioning platform 8 and the middle arc top 9, thereby ensuring the connection quality of the connection between the end arc top 10 and the air-conditioning platform 8 and the connection quality of the connection between the air-conditioning platform 8 and the middle arc top 9. In addition, before connecting the end arc top 10 and the middle arc top 9 to the air-conditioning platform 8 respectively, the end arc top 10 or the middle arc top 9 is raised by using the jacking device 4 to process the connection areas between the end arc top 10 and the middle arc top 9 and the air-conditioning platform 8 respectively, which is beneficial to ensure the reliability of the connection between the end arc top 10 and the middle arc top 9 and the air-conditioning platform 8 respectively.

[0095] It can be seen that the composite roof assembly tooling can realize the positioning of the various components of the composite roof, the process treatment of the joints of the various components, and can use the contour pressing device 3 to press the joints of the roof components, thereby realizing the assembly of the composite roof and improving the assembly accuracy and product quality of the composite roof.

[0096] It should be noted that the present embodiment does not limit the specific structure of the positioning device 2 , as long as the end arc top 10 , the middle arc top 9 and the air conditioning platform 8 can be positioned on the first supporting device 1 .

[0097] Please combine Figure 1 and Figure 2In some embodiments, the positioning device 2 includes two transverse center positioning mechanisms 21, which are respectively arranged on both sides of the width direction of the first supporting device 1 and correspond to the center position of the length direction of the first supporting device 1; the transverse center positioning mechanism 21 is provided with a transverse positioning plate 211, and the transverse positioning plate 211 is used to indicate the transverse center line of the roof to limit the position of the transverse center line of the middle arc top 9.

[0098] It should be noted that, in the embodiment of the present invention, the transverse center line refers to the center line parallel to the width direction of the roof, corresponding to the center position of the length direction of the roof. In this embodiment, two transverse center positioning mechanisms 21 are used to locate the transverse center line of the roof. When installing the middle arc top 9, the center line of the middle arc top 9 and the center line on the transverse positioning plate 211 of the transverse center positioning mechanism 21 are aligned on the same straight line, thereby defining the position of the transverse center line of the middle arc top 9 and ensuring the installation accuracy of the middle arc top 9.

[0099] It is understandable that if Figure 2 As shown, the transverse center positioning mechanism 21 includes a first column 212, and a transverse positioning plate 211 is arranged on the top of the first column 212, so that the transverse positioning plate 211 is supported at a suitable position through the first column 212 to facilitate the positioning of the transverse center line of the middle arc top 9.

[0100] In addition, in order to facilitate the positioning of the longitudinal center lines of the roof components, please combine Figure 1 , Figure 3 and Figure 4 In some embodiments, the positioning device 2 includes a first longitudinal positioning mechanism 22 and a second longitudinal positioning mechanism 23. The first longitudinal positioning mechanism 22 is arranged at one end of the first supporting device 1 in the length direction. The first longitudinal positioning mechanism 22 includes a second column 221 and a first wire pulling device 222 arranged on the second column 221. The first wire pulling device 222 includes a winding wheel 2221, a thin wire 2222 and a first positioning wheel 2223; the second longitudinal positioning mechanism 23 is arranged at the other end of the first supporting device 1 in the length direction. The second longitudinal positioning mechanism 23 includes a third column 231, a second positioning wheel 232 and a wire binding ring 233. The thin wire 2222 is wound out from the winding wheel 2221, passes through the first positioning wheel 2223 to the second positioning wheel 232, and is fixed to the wire binding ring 233. The thin wire 2222 is used to mark the longitudinal center line of the roof to define the positions of the longitudinal center lines of the end arc top 10, the middle arc top 9 and the air-conditioning platform 8.

[0101] It should be noted that, in the embodiment of the present invention, the longitudinal center line refers to the center line parallel to the length direction of the roof, corresponding to the center position of the width direction of the roof.

[0102] In this embodiment, a first longitudinal positioning mechanism 22 and a second longitudinal positioning mechanism 23 are respectively arranged at both ends of the first supporting device 1 in the length direction. At the center position corresponding to the width direction of the roof, a thin line 2222 is drawn along the length direction of the roof. The thin line 2222 is used to indicate the longitudinal center line of the roof. When the roof is assembled, the longitudinal center lines of the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 are respectively made to coincide with the thin line 2222 or the longitudinal center lines of the end arc top 10, the middle arc top 9 and the air-conditioning platform 8 are respectively located in the same longitudinal section of the roof as the thin line 2222, so as to realize precise assembly of the roof.

[0103] In addition, in order to ensure the position accuracy of the two end arc tops 10, please combine Figure 1 and Figure 5 In some embodiments, the positioning device 2 includes four end positioning mechanisms 24, which are respectively arranged at the two ends in the length direction and the two sides in the width direction of the first supporting device 1, and are used to position the end arc top 10. That is to say, when installing the end arc top 10, the end of the end arc top 10 is abutted against the end positioning mechanism 24 of the end of the corresponding end, and the two sides of the end arc top 10 are respectively abutted against the end positioning mechanism 24 of the side of the corresponding end, so as to achieve the installation and limitation of the end arc top 10 and ensure the accuracy of the roof assembly. It can be understood that the end positioning mechanism 24 includes a fourth column 241 and an end positioning plate 242 arranged on the fourth column 241, and the fourth column 241 is used to support the end positioning plate 242 at a suitable position so that the end positioning plate 242 abuts against the end arc top 10 to limit the position.

[0104] In addition, the above embodiment does not limit the specific structure of the first supporting device 1, as long as the first supporting device 1 can support various components of the roof.

[0105] Please combine Figure 1 , Figure 6 and Figure 7 In some embodiments, the first supporting device 1 includes two parallel basic longitudinal beams 11 and a plurality of supporting column assemblies 12. The supporting column assembly 12 is arranged on the basic longitudinal beam 11. The supporting column assembly 12 includes a fifth column 121, a first supporting block 122 and a first rotating clamping assembly 123. The first supporting block 122 and the first rotating clamping assembly 123 are respectively arranged on the top of the fifth column 121. The first supporting block 122 is used to support the end arc top 10, the middle arc top 9 or the air-conditioning platform 8; the first rotating clamping assembly 123 is rotatably arranged on the top of the fifth column 121, and is used to clamp or loosen the end arc top 10, the middle arc top 9 or the air-conditioning platform 8.

[0106] It is understandable that the basic longitudinal beam 11 is the foundation of the composite material roof assembly tooling, and the other parts of the composite material roof assembly tooling are arranged on the basic longitudinal beam 11, and the basic longitudinal beam 11 plays a supporting role. The fifth column 121 is arranged on the basic longitudinal beam 11, and is used to support the first support block 122 and the first rotating clamping assembly 123 at a suitable position. During assembly, the end arc top 10, the middle arc top 9 or the air conditioning platform 8 are placed on the first support block 122, and the end arc top 10, the middle arc top 9 or the air conditioning platform 8 are compressed by the first rotating clamping assembly 123, so that the end arc top 10, the middle arc top 9 and the air conditioning platform 8 are installed on the first supporting device 1 respectively.

[0107] It should be noted that, in some embodiments, the number of supporting column assemblies 12 is twenty-four, wherein four supporting column assemblies 12 are respectively arranged corresponding to the two end arc tops 10, that is, four supporting column assemblies 12 support one end arc, eight supporting column assemblies 12 are correspondingly arranged corresponding to the middle arc top 9, that is, the middle arc top 9 is jointly supported by eight supporting column assemblies 12, and four supporting column assemblies 12 are respectively arranged corresponding to the two air-conditioning platforms 8, that is, four supporting column assemblies 12 jointly support one air-conditioning platform 8.

[0108] The first rotary clamping assembly 123 is rotatably disposed at the top of the fifth column 121, that is, by rotating the first rotary clamping assembly 123, the first rotary clamping assembly 123 can be made close to or away from the first support block 122. When the first rotary clamping assembly 123 is close to the first support block 122, the first rotary clamping assembly 123 presses the end arc top 10, the middle arc top 9 or the air-conditioning platform 8 against the first support block 122. When the first rotary clamping assembly 123 is away from the first support block 122, it is convenient to place the end arc top 10, the middle arc top 9 or the air-conditioning platform 8 on the first support block 122, or to conveniently remove the assembled roof.

[0109] This embodiment does not limit the specific manner in which the first rotary clamping assembly 123 is rotatably disposed on the top of the fifth column 121 , as long as it can ensure that the first rotary clamping assembly 123 can be rotated toward the first support block 122 or rotated away from the first support block 122 .

[0110] In addition, the above embodiments do not limit the specific structure of the contour pressing device 3, as long as the contour pressing device 3 can press the connection between the end arc top 10 and the air conditioning platform 8 and the connection between the air conditioning platform 8 and the middle arc top 9.

[0111] Please refer to Figure 8In some embodiments, the contour pressing device 3 includes two parallel sixth columns 31, a contour beam 32 and a spiral pressing assembly 33. The contour beam 32 is connected between the two sixth columns 31. The spiral pressing assembly 33 is arranged at intervals along the length direction of the contour beam 32, and is used to press the connection between the end arc top 10 and the air conditioning platform 8 or the connection between the air conditioning platform 8 and the middle arc top 9. It can be understood that the number of contour pressing devices 3 corresponds to the number of connections between the various components of the roof. For example, in some embodiments, the number of contour pressing devices 3 is four, and the four contour pressing devices 3 are respectively arranged at the connection between the two air conditioning platforms 8 and the two ends of the middle arc top 9, the connection between the first air conditioning platform 8 and the corresponding first end arc top 10, and the connection between the second air conditioning platform 8 and the corresponding second end arc top 10. It is understandable that the shape of the profiling beam 32 is the same as the shape of the corresponding connection. When the profiling clamping device 3 is installed at each connection, each spiral clamping assembly 33 can be screwed to the corresponding connection. The spiral clamping assembly 33 is arranged at intervals along the length direction of the profiling beam 32, which is conducive to subjecting the connection to sufficient clamping force and improving the force balance. By pressing the connection between the end arc top 10 and the air conditioning platform 8 or the connection between the air conditioning platform 8 and the middle arc top 9 with the spiral clamping assembly 33, the bonding quality of the connection structure of each connection can be ensured, and the reliability of the connection between the end arc top 10 and the air conditioning platform 8 and the air conditioning platform 8 and the middle arc top 9 can be improved.

[0112] It should be noted that the above embodiment does not limit the specific structure of the jacking device 4 , as long as the jacking device 4 can lift the end arc top 10 , the middle arc top 9 or the air-conditioning platform 8 .

[0113] Please refer to Fig. 9In some embodiments, the jacking device 4 includes a seventh column 41, a first lifting mechanism 42, a movable plate 43, a second support block 44 and a second rotary clamping assembly 45. The first lifting mechanism 42 is arranged on the seventh column 41, and the first lifting mechanism 42 is connected to the movable plate 43. The second support block 44 is arranged on the movable plate 43 for supporting the end arc top 10, the middle arc top 9 or the air-conditioning platform 8; the second rotary clamping assembly 45 is rotatably arranged on the movable plate 43 for clamping or loosening the end arc top 10, the middle arc top 9 or the air-conditioning platform 8. That is to say, in this embodiment, the first lifting mechanism 42 is actuated to drive the movable plate 43 to rise and fall, and then the movable plate 43 drives the second support block 44 and the second rotating clamping assembly 45 to rise and fall together. The second support block 44 can support the end arc top 10, the middle arc top 9 or the air-conditioning platform 8, and the second rotating clamping assembly 45 presses the end arc top 10, the middle arc top 9 or the air-conditioning platform 8 against the second support block 44. Therefore, when the first lifting mechanism 42 is actuated, it can drive the end arc top 10, the middle arc top 9 or the air-conditioning platform 8 to rise or fall together, so that the connection between the end arc top 10 and the air-conditioning platform 8 or the connection between the middle arc top 9 and the air-conditioning platform 8 can be staggered, which is convenient for surface treatment or gluing of the connection.

[0114] In some embodiments, the number of jacking devices 4 is eight, two end arc tops 10 correspond to two jacking devices 4 respectively, and one middle arc top 9 corresponds to four jacking devices 4, that is, during the assembly process, two jacking devices 4 are used to lift the end arc tops 10 so as to perform surface treatment or glue application on the connection between the end arc tops 10 and the air conditioning platform 8. After the surface treatment or glue application, the end arc tops 10 are lowered so that the connection between the end arc tops 10 and the air conditioning platform 8 is overlapped and pressed. Similarly, four jacking devices 4 are used to lift the middle arc top 9 so as to perform surface treatment or glue application on the connection between the middle arc top 9 and the air conditioning platform 8. After the surface treatment or glue application, the middle arc top 9 is lowered so that the connection between the middle arc top 9 and the air conditioning platform 8 is overlapped and pressed.

[0115] In addition, after the roof is assembled, in order to facilitate the lifting of the assembled roof, please refer to Fig.10 In some embodiments, the composite material roof assembly tooling also includes a roof transfer tooling, and the roof transfer tooling includes a hanging frame 5, a second supporting device 6, and a roof fixing tooling assembly 7. The hanging frame 5 is provided with a lifting lug so that the entire roof transfer tooling can be lifted by a lifting tool through the lifting lug. In some embodiments, four pairs of lifting lugs are provided on the upper surface of the hanging frame 5 along the length direction. The hanging frame 5 serves as the basis of the roof transfer tooling, and the roof fixing tooling assembly 7 is connected to the hanging frame 5. When the assembled roof is transported, the weight of the roof transfer tooling and the weight of the roof are borne by the hanging frame 5. This embodiment does not limit the specific structure of the hanging frame 5. In some embodiments, the hanging frame 5 is a frame structure with high rigidity.

[0116] The second supporting device 6 is used to support the hanging frame 5. The specific structure of the second supporting device 6 is not limited in this embodiment as long as it can play the role of supporting the hanging frame 5. Fig.12 As shown, in some embodiments, the second supporting device 6 includes a plurality of eighth columns 61 and a positioning column 62 disposed on the top of the eighth column 61, and the positioning column 62 cooperates with the positioning hole on the hanging frame 5 to limit the position, so as to realize the precise positioning of the hanging frame 5. In addition, a plurality of screws are disposed around the top of the eighth column 61, and the screws serve to connect the hanging frame 5 and the eighth column 61. In some embodiments, the number of the eighth columns 61 is eight, that is, the hanging frame 5 is supported by eight eighth columns 61.

[0117] In addition, the above embodiment does not limit the specific structure of the roof fixing tool assembly 7, as long as it can play the role of supporting and fixing the assembled roof.

[0118] like Fig.11 As shown, in some embodiments, the roof fixing tooling assembly 7 includes an arc-shaped template assembly 71, which is arranged on the hanging frame 5. The arc-shaped template assembly 71 includes an arc-shaped template 711, a second lifting mechanism 712 connected to the arc-shaped template 711, and two clamping mechanisms 713 respectively arranged at both ends of the arc-shaped template 711. The clamping mechanism 713 is used to apply pressure to the top of the roof to fine-tune the curvature of the roof so that the curvature of the roof is the same as the curvature of the arc-shaped template 711. It can be understood that, in theory, the curvature design of the arc template 711 is the same as the theoretical curvature of the roof arc top. This embodiment uses the second lifting mechanism 712 to drive the arc template 711 to rise and fall, so as to achieve height adjustment of the arc template 711, so that the arc template 711 can fit the roof arc top; in addition, this embodiment uses two clamping mechanisms 713 to squeeze the two ends of the roof arc top respectively, which can adjust the curvature of the roof arc top and adjust the deformation of the arc top, so that the arc top can better fit the arc template 711, so as to ensure that the roof shape remains stable during transportation and avoid deformation of the roof during transportation.

[0119] In addition, if Fig.11As shown, in some embodiments, the vehicle roof fixing tooling assembly 7 includes two full-length longitudinal beams 72, a cross brace assembly 73 and a profiled top beam assembly 74. The two full-length longitudinal beams 72 are respectively connected to the hanging frame 5 and are arranged in parallel along the length direction of the vehicle roof, and are used to be located below the vehicle roof; the cross brace assembly 73 and the profiled top beam assembly 74 are respectively connected to the two full-length longitudinal beams 72, and the cross brace assembly 73 is used to support the end arc top 10, the middle arc top 9 and the air conditioning platform 8. The cross brace assembly 73 can be extended in the direction close to or away from the vehicle roof to support different products; the profiled top beam assembly 74 can be extended in the direction close to or away from the vehicle roof to support different products, and the profiled top beam assembly 74 is arranged below the curved beam connecting the end arc top 10 and the air conditioning platform 8 and below the curved beam connecting the middle arc top 9 and the air conditioning platform 8. In other words, the full-length longitudinal beam 72, the cross brace assembly 73 and the profiled top beam assembly 74 are located below the assembled vehicle roof to support the assembled vehicle roof. It should be noted that the specific method of connecting the full-length longitudinal beam 72 with the hanging frame 5 is not limited in this embodiment, as long as the connection between the full-length longitudinal beam 72 and the hanging frame 5 can be achieved. In some embodiments, the number of the cross brace components 73 is eight, and the two end arcs correspond to two cross brace components 73 respectively, and one middle arc top 9 corresponds to four cross brace components 73, so that eight cross brace components 73 are used to support the assembled roof together. It should be noted that the cross brace component 73 can be extended and retracted in the direction close to or away from the roof to support different products, that is, the position of the cross brace component 73 in this embodiment is adjustable, so that the cross brace component 73 can be adapted to support products of different forms by adjusting the position of the cross brace component 73. Similarly, in some embodiments, the number of the imitation top beam components 74 is eight, and the eight imitation top beam components 74 are distributed under the curved beam at the connection between the end arc top 10 and the air conditioning platform 8 and under the curved beam at the connection between the middle arc top 9 and the air conditioning platform 8, so as to play a supporting role at the connection, making the supporting role more reliable. In addition, the contoured top beam assembly 74 can be extended or retracted in a direction closer to or away from the roof to support different products. That is, the position of the contoured top beam assembly 74 in this embodiment is adjustable, so that the contoured top beam assembly 74 can be adapted to support products of different shapes by adjusting the position of the contoured top beam assembly 74.

[0120] To further improve the stability of the transfer, please continue to refer to Fig.11 In some embodiments, the vehicle roof fixing tooling assembly 7 includes two air conditioning opening hanging beams 75, which are connected between the hanging frame 5 and the full-length longitudinal beam 72, and the two air conditioning opening hanging beams 75 are respectively located at the air conditioning opening positions of the two air conditioning platforms 8 on the vehicle roof. In other words, the present embodiment utilizes the two air conditioning opening hanging beams 75 to connect the hanging frame 5 and the full-length longitudinal beam 72, so that the hanging frame 5 and the full-length longitudinal beam 72 are connected as one body, which is convenient for overall lifting and ensures the stability of the vehicle roof transportation.

[0121] In addition to the above-mentioned composite material roof assembly tool, the present invention also provides a composite material roof assembly method applied to the composite material roof assembly tool disclosed in the above-mentioned embodiment, and the composite material roof assembly method includes:

[0122] like Fig.13 As shown, the air-conditioning platform 8 is hoisted to the first supporting device 1, and the positioning device 2 is used to position the air-conditioning platform 8. After the air-conditioning platform 8 is positioned, the air-conditioning platform 8 is pressed and fixed. That is to say, during assembly, the air-conditioning platform 8 is first hoisted to the first supporting device 1. In some embodiments, the air-conditioning platform 8 is positioned along the vehicle width direction according to the positioning surfaces on both sides of the first supporting device 1, and the deviation between the center line of the air-conditioning platform 8 and the longitudinal center line of the roof is checked to ensure that the deviation is no more than 2 mm. The air-conditioning platform 8 is positioned along the length direction of the roof according to the distance between the opening center line of the air-conditioning platform 8 and the transverse center line of the roof. After the air-conditioning platform 8 is positioned, the tooling press head 13 is used to press and fix the air-conditioning platform 8.

[0123] Then, if Fig.14 As shown, the middle arc top 9 is installed, hoisted to the first supporting device 1, and positioned by the positioning device 2. In some embodiments, the middle arc top 9 is positioned along the vehicle width direction according to the positioning surfaces on both sides of the first supporting device 1. The middle arc top 9 is positioned along the vehicle length direction according to the distance between the center line of the middle arc top 9 and the transverse center line of the vehicle body.

[0124] Then, if Fig.15 As shown, the contour pressing device 3 is installed to the overlapping position of the middle arc top 9 and the air conditioning platform 8, and the contour pressing device 3 presses the overlapping position of the middle arc top 9 and the air conditioning platform 8.

[0125] The end arc top 10 is installed, hoisted to the first support device 1, and positioned by the positioning device 2. In some embodiments, the end arc top is positioned along the vehicle width direction according to the positioning surfaces on both sides of the first support device 1. The end arc top 10 is positioned along the length direction of the roof according to the distance between the end arc top 10 and the transverse center line of the vehicle body and the total length of the roof, and the total length of the roof is controlled. The difference of the diagonal lines of the roof is detected, and the diagonal difference is controlled within a certain range.

[0126] The contour pressing device 3 is pressed to press the overlapping position of the end arc top 10 and the air conditioning platform 8.

[0127] The end arc top 10 is pressed tightly.

[0128] The first position of the profiling clamping device 3 is marked on the middle arc top 9, the profiling clamping device 3 at the overlap position of the middle arc top 9 and the air conditioning platform 8 is removed, the middle arc top 9 is lifted up to the surface of the air conditioning platform 8 by the jacking device 4, the connection position of the middle arc top 9 and the air conditioning platform 8 is processed (for example, structural adhesive is applied), the middle arc top 9 is lowered by the jacking device 4, and the profiling clamping device 3 is pressed at the overlap position of the middle arc top 9 and the air conditioning platform 8, so that the profiling clamping device 3 is located in the first position. That is to say, after the middle arc top 9 is dropped, the profiling clamping device 3 is installed to ensure that the profiling clamping device 3 is consistent with the clamping position marked before.

[0129] The middle arc top 9 is riveted to the air conditioning platform 8. For example, in some embodiments, after the structural adhesive is cured, a drill bit and a countersinking head special for composite materials are used to drill and countersink the rivet holes, and finally the riveting is completed as required.

[0130] The second position of the profiling clamping device 3 is marked on the end arc top 10, the profiling clamping device 3 at the overlap position of the end arc top 10 and the air conditioning platform 8 is removed, the end arc top 10 is lifted by the jacking device 4 to be separated from the surface of the air conditioning platform 8, the connection position of the end arc top 10 and the air conditioning platform 8 is processed (for example, structural adhesive is applied), the end arc top 10 is lowered by the jacking device 4, and the profiling clamping device 3 is pressed against the overlap position of the end arc top 10 and the air conditioning platform 8, so that the profiling clamping device 3 is located in the second position. That is to say, after the end arc top 10 is dropped, the profiling clamping device 3 is installed to ensure that the profiling clamping device 3 is consistent with the clamping position marked before.

[0131] The end arc top 10 is riveted to the air conditioning platform 8. In some embodiments, after the structural adhesive is cured, a drill bit and a countersinking head specially made for composite materials are used to drill and countersink the rivet holes, and finally the riveting is completed as required.

[0132] In addition, in some embodiments, after the end arc top 10 is riveted to the air conditioning platform 8, other components of the roof can be installed.

[0133] After the roof is assembled, in order to facilitate the transfer of the assembled roof to the vehicle body assembly station, please refer to Fig.16 and Fig.17 In some embodiments, the composite material roof assembly tool further includes a hanging frame 5, a second supporting device 6 and a roof fixing tool assembly 7, and the composite material roof assembly method further includes:

[0134] After the roof is assembled, the arc-shaped template 711 of the roof fixing tool assembly 7 is adjusted to the highest position and locked by using the second lifting mechanism 712 of the roof fixing tool assembly 7. Fig.16 As shown, this is to prevent the roof transfer tooling from falling and damaging the roof panel.

[0135] The second supporting device 6 is arranged on both sides of the vehicle roof.

[0136] The hanging frame 5 is hoisted onto the second supporting device 6 , and the hanging frame 5 is connected to the second supporting device 6 .

[0137] The full-length longitudinal beam 72 of the roof fixing tooling assembly 7 is arranged below the roof, and the full-length longitudinal beam 72 is connected to the hanging frame 5. In some embodiments, the hanging frame 5 and the full-length longitudinal beam 72 are connected by the air conditioning port hanging beam 75 at the air conditioning port position of the air conditioning platform 8.

[0138] The pressing mechanism 713 of the arc-shaped template assembly 71 is adjusted so that the vehicle roof fits the arc-shaped template 711 of the arc-shaped template assembly 71 , and the arc-shaped template 711 is locked.

[0139] The heights of the cross brace assembly 73 and the profiled top beam assembly 74 of the vehicle roof fixing tooling assembly 7 are adjusted so that the cross brace assembly 73 and the profiled top beam assembly 74 are respectively fitted with the bottom of the vehicle roof.

[0140] By lifting the lifting frame 5, the roof is lifted to the vehicle body assembly platform, thereby completing the smooth lifting of the assembled roof.

[0141] It can be understood that during the lifting process, the full-length longitudinal beam 72 can support the carbon fiber roof, and the arc-shaped template 711 can ensure that the roof does not deform.

[0142] It should also be noted that, in this specification, relational terms such as first and second, etc. are merely used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations.

[0143] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0144] The composite material roof assembly tooling and method provided by the present invention are introduced in detail above. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method and core ideas of the present invention. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the present invention, the present invention can also be improved and modified in a number of ways, and these improvements and modifications also fall within the scope of protection of the present invention.

Claims

1. A composite material roof assembly tool, characterized in that: include: A first supporting device (1) is used to support the end arc top (10), the middle arc top (9) and the air conditioning platform (8) of the vehicle roof; a positioning device (2), arranged relative to the first supporting device (1), and used to position the end arc top (10), the middle arc top (9) and the air conditioning platform (8) on the first supporting device (1), respectively; A contour pressing device (3) for pressing the connection between the end arc top (10) and the air conditioning platform (8) and the connection between the air conditioning platform (8) and the middle arc top (9); A lifting device (4) is arranged relative to the first supporting device (1), and is used to lift the end arc top (10) or the middle arc top (9) before connecting the end arc top (10) and the middle arc top (9) to the air conditioning platform (8) respectively, so as to process the connection area, and to lower the end arc top (10) or the middle arc top (9) after the processing.

2. The composite material roof assembly tool according to claim 1, characterized in that: The positioning device (2) comprises two transverse center positioning mechanisms (21), the two transverse center positioning mechanisms (21) being respectively arranged on both sides of the first supporting device (1) in the width direction and corresponding to the center position of the first supporting device (1) in the length direction; The transverse center positioning mechanism (21) is provided with a transverse positioning plate (211), and the transverse positioning plate (211) is used to indicate the transverse center line of the roof, so as to define the position of the transverse center line of the middle arc top (9).

3. The composite material roof assembly tool according to claim 1, characterized in that: The positioning device (2) comprises: a first longitudinal positioning mechanism (22) disposed at one end of the first supporting device (1) in the length direction, the first longitudinal positioning mechanism (22) comprising a second column (221) and a first wire pulling device (222) disposed on the second column (221), the first wire pulling device (222) comprising a winding wheel (2221), a thin wire (2222) and a first positioning wheel (2223); A second longitudinal positioning mechanism (23) is arranged at the other end of the first supporting device (1) in the length direction, the second longitudinal positioning mechanism (23) comprising a third upright column (231), a second positioning wheel (232) and a wire binding ring (233), the thin wire (2222) is wound from the winding wheel (2221), passes through the first positioning wheel (2223) to the second positioning wheel (232), and is fixed to the wire binding ring (233), the thin wire (2222) is used to mark the longitudinal center line of the roof, so as to define the positions of the longitudinal center lines of the end arc top (10), the middle arc top (9) and the air conditioning platform (8).

4. The composite material roof assembly tool according to claim 1, characterized in that: The positioning device (2) comprises: Four end positioning mechanisms (24) are respectively arranged at both ends in the length direction and both sides in the width direction of the first supporting device (1) and are used to position the end arc top (10).

5. The composite material roof assembly tool according to claim 1, characterized in that: The first supporting device (1) comprises: Two basic longitudinal beams (11) arranged in parallel; A plurality of support column assemblies (12) are arranged on the base longitudinal beam (11), and the support column assemblies (12) include: Fifth pillar (121); A first support block (122) is disposed on the top of the fifth column (121) and is used to support the end arc top (10), the middle arc top (9) or the air conditioning platform (8); The first rotary clamping assembly (123) is rotatably disposed on the top of the fifth column (121) and is used to clamp or loosen the end arc top (10), the middle arc top (9) or the air conditioning platform (8).

6. The composite material roof assembly tool according to claim 1, characterized in that: The contour pressing device (3) comprises: Two sixth columns (31) arranged in parallel; A profiled beam (32) connected between the two sixth columns (31); Screw compression assemblies (33) are arranged at intervals along the length direction of the profiled beam (32) and are used to compress the connection between the end arc top (10) and the air conditioning platform (8) or the connection between the air conditioning platform (8) and the middle arc top (9).

7. The composite material roof assembly tool according to claim 1, characterized in that: The lifting device (4) comprises: Seventh pillar (41); A first lifting mechanism (42) is provided on the seventh column (41); A movable plate (43) connected to the first lifting mechanism (42); A second support block (44) is provided on the movable plate (43) and is used to support the end arc top (10), the middle arc top (9) or the air conditioning platform (8); The second rotary clamping assembly (45) is rotatably disposed on the movable plate (43) and is used to clamp or loosen the end arc top (10), the middle arc top (9) or the air conditioning platform (8).

8. The composite material roof assembly tool according to any one of claims 1 to 7, characterized in that: Also includes: A hanging frame (5) provided with hanging ears; A second supporting device (6), used for supporting the hanging frame (5); The vehicle roof fixing tool component (7) is used to fix the vehicle roof.

9. The composite material roof assembly tool according to claim 8, characterized in that: The roof fixing tooling component (7) comprises: The arc-shaped template assembly (71) is arranged on the hanging frame (5), comprising an arc-shaped template (711), a second lifting mechanism (712) connected to the arc-shaped template (711), and two clamping mechanisms (713) respectively arranged at two ends of the arc-shaped template, wherein the clamping mechanisms (713) are used to apply pressure to the top of the roof to fine-tune the curvature of the roof so that the curvature of the roof is the same as the curvature of the arc-shaped template (711).

10. The composite material roof assembly tool according to claim 8, characterized in that: The roof fixing tooling component (7) comprises: Two through-length longitudinal beams (72) connected to the hanging frame (5), arranged in parallel along the length direction of the roof, and used to be located below the roof; a cross brace assembly (73) connected to the through-length longitudinal beam (72) and used to support the end arc top (10), the middle arc top (9) and the air conditioning platform (8); the cross brace assembly (73) can be extended and retracted in a direction approaching or away from the vehicle roof to support different products; The contoured top beam assembly (74) is connected to the through-length longitudinal beam (72) and can be extended and retracted in a direction close to or away from the vehicle roof to support different products. The contoured top beam assembly (74) is disposed below the curved beam connecting the end arc top (10) and the air conditioning platform (8) and below the curved beam connecting the middle arc top (9) and the air conditioning platform (8).

11. The composite material roof assembly tool according to claim 8, characterized in that: The roof fixing tooling component (7) comprises: Two air conditioning outlet hanging beams (75) are connected between the hanging frame (5) and the through-length longitudinal beam (72), and are respectively located at the air conditioning outlet positions of the two air conditioning platforms (8) on the roof.

12. A composite material roof assembly method, characterized in that: The composite material roof assembly tool used in any one of claims 1 to 11, wherein the composite material roof assembly method comprises: The air-conditioning platform (8) is hoisted onto the first supporting device (1), and the air-conditioning platform (8) is positioned using the positioning device (2); after the air-conditioning platform (8) is positioned, the air-conditioning platform (8) is pressed and fixed; Lifting the middle arc top (9) to the first supporting device (1), and positioning the middle arc top (9) using the positioning device (2); The contour pressing device (3) is used to press the overlapping position between the middle arc top (9) and the air conditioning platform (8); Lifting the end arc top (10) to the first supporting device (1), and positioning the end arc top (10) using the positioning device (2); The contour pressing device (3) is used to press the overlapping position between the end arc top (10) and the air conditioning platform (8); Pressing the end arc top (10) tightly; Marking the first position of the profiling pressing device (3) at the middle arc top (9), removing the profiling pressing device (3) at the overlapping position of the middle arc top (9) and the air conditioning platform (8), lifting the middle arc top (9) by using the jacking device (4) to be away from the surface of the air conditioning platform (8), processing the connection position between the middle arc top (9) and the air conditioning platform (8), lowering the middle arc top (9) by using the jacking device (4), pressing the profiling pressing device (3) at the overlapping position of the middle arc top (9) and the air conditioning platform (8), so that the profiling pressing device (3) is located at the first position; Riveting the middle arc top (9) to the air conditioning platform (8); The second position of the profiling pressing device (3) is marked at the end arc top (10), the profiling pressing device (3) at the overlapping position of the end arc top (10) and the air conditioning platform (8) is removed, the end arc top (10) is lifted by the jacking device (4) to be separated from the surface of the air conditioning platform (8), the connection position between the end arc top (10) and the air conditioning platform (8) is processed, the end arc top (10) is lowered by the jacking device (4), and the profiling pressing device (3) is pressed at the overlapping position of the end arc top (10) and the air conditioning platform (8), so that the profiling pressing device (3) is located at the second position; The end arc top (10) is riveted to the air conditioning platform (8).

13. The composite material roof assembly method according to claim 12, characterized in that: The composite material vehicle roof assembly tool further comprises a hanging frame (5), a second supporting device (6) and a vehicle roof fixing tool component (7), and the composite material vehicle roof assembly method further comprises: After the roof is assembled, the arc-shaped template (711) of the roof fixing tool assembly (7) is adjusted to the highest position and locked using the second lifting mechanism (712) of the roof fixing tool assembly (7); The second supporting device (6) is arranged on both sides of the vehicle roof; Lifting the hanging frame (5) onto the second supporting device (6), and connecting the hanging frame (5) to the second supporting device (6); The through-length longitudinal beam (72) of the vehicle roof fixing tooling assembly (7) is arranged below the vehicle roof, and the through-length longitudinal beam (72) is connected to the hanging frame (5); Adjusting the clamping mechanism (713) of the arc-shaped template assembly (71) of the vehicle roof fixing tool assembly (7) so that the vehicle roof fits the arc-shaped template (711) of the arc-shaped template assembly (71), and locking the arc-shaped template (711); Adjusting the heights of the cross brace assembly (73) and the contoured top beam assembly (74) of the vehicle roof fixing tooling assembly (7) so that the cross brace assembly (73) and the contoured top beam assembly (74) are respectively fitted to the bottom of the vehicle roof; By hoisting the hoisting frame (5), the roof is hoisted to the vehicle body assembly position.