TACS system time-limited permission signal opening method based on train safety envelope extension

By automatically expanding the train operation envelope in the TACS system and opening the allowable signal of the signal in a limited time, the problem that the TACS system cannot safely detect the signal passing through the signal, ensuring that the signal allows the signal to be turned off before the train passes, avoiding safety risks. Improves system availability and security.

CN118907190APending Publication Date: 2024-11-08CASCO SIGNAL LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411174085.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-08

Smart Images

  • Figure CN118907190A_ABST
    Figure CN118907190A_ABST
Patent Text Reader

Abstract

The invention relates to a TACS system time-limited permission signal opening method based on train safety envelope expansion, and the method comprises the steps: automatically expanding a train operation envelope after a trackside controller WTC obtains a line resource, and triggering the trackside controller WTC to apply for a permission signal for opening a current signal machine in a limited time for a degraded train; and the allowing signal is closed before the degraded train body completely passes through the signal machine. Compared with the prior art, the method has the advantages that display upgrading of other following trains is avoided, and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a train signal control system, in particular to a time-limited permission signal opening method of a TACS system based on train safety envelope expansion. Background Art

[0002] In a train operation control system based on continuous two-way train-ground communication (CBTC system for short), trains rely on movement authorization information calculated by ground equipment to operate. Train operation in CBTC mode does not rely on trackside signal display, but most CBTC projects will add an interlocking backup mode. When the train is downgraded to the interlocking backup mode, the driver needs to obtain the driving permission through the display of the trackside signal to control the train operation. In the backup mode, the interlocking subsystem obtains information such as the occupancy status of the front section, the route status, and the train operation mode through secondary detection equipment such as axle counters to control the display of the trackside signal.

[0003] The CBTC system uses ground equipment as the core of train control, has many trackside equipment, and has low communication efficiency between the train and the ground, which limits the efficiency and reliability of train operation. Compared with the CBTC system, the train autonomous operation system (TACS system) based on vehicle-to-vehicle communication uses vehicle-to-vehicle equipment as the control core, and the train autonomously calculates the mobile authorization. The train performs autonomous operation control based on the resources applied for, obtains the safe position of other trains through vehicle-to-vehicle communication to achieve train interval protection, gets rid of the dependence on traditional secondary detection equipment such as axle counters, reduces the number of trackside equipment, and improves the efficiency and reliability of train operation.

[0004] After the TACS train is downgraded, the driver still needs to control the train operation according to the display of the trackside signal. After the trackside signal opens the permission signal, due to the lack of secondary detection equipment such as axle counters, the TACS system cannot safely detect the downgraded train passing the signal and cannot close the permission signal opened for it in time. The permission signal may be misinterpreted by the driver of another downgraded train following behind, causing safety issues in the signal display upgrade.

[0005] After searching, Chinese patent publication number CN113044084A discloses a signal display method for TACS system, which specifically discloses that the method realizes the display control of trackside signal by processing line resource allocation, and the display method is a normal lighting display method or a normal lighting off display method, which gets rid of the way of controlling the signal display according to route information, and the signal display logic is simpler and more direct, which improves the efficiency of operation. However, the existing patent does not consider the safety problem of TACS system opening a limited-time permission signal for downgraded trains in the absence of secondary detection equipment, causing display upgrades for other following trains. Summary of the invention

[0006] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and provide a TACS system time-limited permission signal opening method based on train safety envelope extension.

[0007] The purpose of the present invention can be achieved by the following technical solutions:

[0008] According to the first aspect of the present invention, a method for opening a TACS system limited-time permission signal based on the extension of the train safety envelope is provided. The method automatically expands the train operation envelope after the trackside controller WTC obtains the line resources, triggers the trackside controller WTC to apply for the permission signal of the current signal to be opened within a limited time for the downgraded train, and closes the permission signal before the downgraded train body completely passes the signal.

[0009] As a preferred technical solution, the method specifically comprises the following steps:

[0010] Step S1, after the train loses the train-to-ground communication during operation, the trackside onboard controller WTC inherits the train safety envelope calculated by the onboard controller CC for the train;

[0011] Step S2, the automatic train monitoring system ATS automatically reissues the running task before the train is downgraded to the trackside train controller WTC that takes over the train, and extends the train safety envelope to the prohibition signal before the end of the task;

[0012] Step S3: The driver drives the train to approach and stop before the prohibition signal, completing the current operation task, and the automatic train monitoring system ATS issues the next train operation task;

[0013] Step S4, the trackside train controller WTC applies for line resources according to the newly issued operation task;

[0014] Step S5, the trackside train controller WTC calculates the guarantee of no vehicle occupation between the current signal and the next signal in the same direction;

[0015] Step S6, the trackside train controller WTC applies to the trackside resource manager WRC for opening the permission signal of the current signal within a limited time;

[0016] Step S7, the trackside resource manager WRC drives the target controller OC to light up the permission light of the current signal within a limited time range;

[0017] Step S8: The driver drives the train through the current signal within a limited time range.

[0018] As a preferred technical solution, in step S1, after the trackside onboard controller WTC takes over the onboard controller CC, it completes the application for releasing line resources and issuing signal lighting instructions for the train.

[0019] As a preferred technical solution, in step S2, the trackside train controller WTC applies to the trackside resource manager WRC for required line resources according to the train mission, and after obtaining all required line resources, extends the train safety envelope to the prohibition signal before the mission end.

[0020] As a preferred technical solution, in step S4, the trackside train controller WTC applies to the trackside resource manager WRC for line resources from the current signal to the next signal in the same direction according to the newly issued operation task.

[0021] As a preferred technical solution, in step S5, the trackside train controller WTC establishes vehicle-to-vehicle communication with other trains on the entire line, obtains safety positioning information of other trains, and then calculates the guarantee that there is no vehicle occupying the line between the current signal and the next signal in the same direction.

[0022] As a preferred technical solution, in step S6, after the trackside train controller WTC obtains all the required line resources, it extends the end point of the train safety envelope from the current prohibited signal to the next signal in the same direction, and combines the guarantee that there is no other train occupying the protection section of the current signal to apply to the trackside resource manager WRC for the permission signal to open the current signal within a limited time.

[0023] As a preferred technical solution, the limited time in step S6 is the shortest time required for the train to accelerate from stationary to the maximum speed limit of manual vehicle operation, until the tail of the train clears the current signal after the safety envelope of the downgraded train is expanded.

[0024] As a preferred technical solution, in step S7, the trackside resource manager WRC drives the target controller OC to light up the permission light of the current signal within a limited time range according to the time-limited permission signal opening request of the trackside train controller WTC.

[0025] As a preferred technical solution, in step S8, the driver drives the train through the current signal after visually observing the permission light. When the specified time is up, the trackside resource manager WRC drives the target controller OC to change the prohibition light of the current signal.

[0026] According to a second aspect of the present invention, there is provided an electronic device, comprising a memory and a processor, wherein a computer program is stored in the memory, and the method described above is implemented when the processor executes the program.

[0027] According to a third aspect of the present invention, there is provided a computer-readable storage medium having a computer program stored thereon, wherein the program implements the method described above when executed by a processor.

[0028] Compared with the prior art, the present invention has the following advantages:

[0029] 1) The present invention enables the TACS system to open a limited-time permission signal for a downgraded train in the absence of secondary detection equipment, ensuring that the permission signal is closed before the downgraded train body completely passes the signal, thereby avoiding display upgrades for other following trains;

[0030] 2) The invention automatically expands the train safety operation envelope after the trackside controller WTC obtains line resources, triggering the trackside controller WTC to apply for the train to open the permission signal of the current signal within a limited time. The whole process does not require manual intervention and is automatically completed by the system, thereby improving availability;

[0031] 3) The necessary condition for the invention to allow the signal to be opened within a limited time is that all line resources within the current signal protection zone have been allocated and no vehicle is occupying the zone, thus fully ensuring the safety of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 This is the TACS system architecture diagram;

[0033] Figure 2 This is a schematic diagram of extending the train safety envelope to S1 for train TU1 according to an embodiment of the present invention;

[0034] Figure 3 This is a schematic diagram of establishing train-to-train communication between WTC and train TU2 to obtain train positioning information according to an embodiment of the present invention;

[0035] Figure 4 This is a schematic diagram of the trackside resource manager WRC sending a command to the target controller OC to drive the signal S1 to light up the permission light in an embodiment of the present invention;

[0036] Figure 5 This is a schematic diagram of the trackside resource manager WRC sending a command to the target controller OC to drive the signal S1 to light up the prohibition light in an embodiment of the present invention;

[0037] Figure 6 This is a schematic diagram of the trackside resource manager WRC sending an instruction to the target controller OC to drive the signal S1 to light up the prohibition light according to an embodiment of the present invention. DETAILED DESCRIPTION

[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0039] The method for opening a TACS system limited-time permission signal based on train safety envelope expansion described in the present invention can effectively solve the safety problem that the TACS system cannot safely detect that a downgraded train occupies the downstream section of the signal, cannot timely close the permission signal opened for the following train, and causes a display upgrade for the following train.

[0040] As attached Figure 1 As shown in the figure, the TACS system mainly includes the automatic train monitoring system ATS, the trackside resource manager WRC and the train onboard controller CC, the onboard backup positioning system BLS, the trackside train controller WTC, and the target controller OC. Among them, the automatic train monitoring system ATS is responsible for supervising and controlling the operation of the train, and has the functions of tracking train operation, issuing train operation tasks, alarm and event reporting, and train operation adjustment. The trackside resource manager WRC has the functions of train sequence management, line resource allocation and recovery, signal and switch control, trackside equipment status collection and drive, etc. The onboard controller CC autonomously calculates and plans the driving path and planned operation curve according to the train operation task, applies for and releases resources from the trackside resource manager WRC, negotiates with other trains to use resources, actively controls the train, and realizes the train safety protection function and the train automatic driving function. The trackside train controller WTC is mainly responsible for managing and tracking faulty trains, taking over faulty trains to apply for and release resources. The target controller OC mainly realizes the status collection and drive of trackside equipment, including the drive and status collection of signal machines. The on-board backup positioning system BLS mainly provides the corresponding train ID and train location information to the trackside train controller based on the acquired transponder information to realize the location tracking of the downgraded train. The train operation mode of the TACS system includes TACS mode and manual mode. When the train is in a state of complete on-board safety protection, it is considered to be in TACS mode. When the train is not in a state of complete on-board safety protection and is manually involved in safety protection, it is considered to be in manual mode.

[0041] As attached Figure 2-6 As shown, the method for opening the signal within a limited time based on the TACS system based on the train safety envelope extension is as follows:

[0042] 101) Train TU1 and train TU2 are tracked and run between stations in manual mode after being degraded due to a fault in the train-to-ground communication. The trackside train controller WTC_A of train TU1 applies to WRC for line resources to signal S1 for train TU1. After all the required resources are obtained, TU1 extends the train safety envelope to S1. Figure 2 As shown;

[0043] 102) The driver drives train TU1 to approach and stop at the upstream of signal S1. The automatic train monitoring system ATS sends the train operation task in the same direction as signal S1 to the trackside train controller WTC. The trackside train controller WTC applies for the line resources from signal S1 to signal S2 from the trackside resource manager WRC, and establishes train-to-train communication with train TU2 to obtain the train positioning information, as shown in the attached figure. Figure 3 As shown;

[0044] 103) After the train obtains all the line resources between signal S1 and signal S2, the trackside train controller WTC extends the train safety envelope of TU1 to S2. Combined with the guarantee that there is no other train occupying the signal protection zone, the trackside train controller WTC applies to the trackside resource manager WRC to open the S1 permission signal for 15 seconds. The trackside resource manager WRC sends a command to the target controller OC to drive the signal S1 permission light to light up. Figure 4 As shown;

[0045] 104) After the driver visually sees the permission signal, he drives train TU1 to approach and pass the signal. The onboard backup positioning system BLS reads the downstream Beacon of signal S1 and updates the positioning information of train TU1 to the trackside train controller WTC. The trackside train controller WTC applies to the trackside resource manager WRC to turn off the S1 permission signal. The trackside resource manager WRC sends a command to the target controller OC to drive the signal S1 prohibition light to light up. Figure 5 shown.

[0046] 105) With a small probability, when the driver drives train TU1 to approach and pass signal S1, the onboard backup positioning system BLS does not read the downstream Beacon of signal S1. Before the train TU1 completely clears the signal S1, the 15s countdown ends and the trackside resource manager WRC sends a command to the target controller OC to drive the signal S1 prohibition light to light up. Figure 6 shown.

[0047] The above is an introduction to the method embodiment. The following is a further explanation of the scheme of the present invention through electronic equipment and storage medium embodiments.

[0048] The electronic device of the present invention includes a central processing unit (CPU), which can perform various appropriate actions and processes according to computer program instructions stored in a read-only memory (ROM) or loaded from a storage unit into a random access memory (RAM). In the RAM, various programs and data required for device operation can also be stored. The CPU, ROM and RAM are connected to each other via a bus. An input / output (I / O) interface is also connected to the bus.

[0049] Multiple components in the device are connected to the I / O interface, including: input units, such as keyboards, mice, etc.; output units, such as various types of displays, speakers, etc.; storage units, such as disks, optical disks, etc.; and communication units, such as network cards, modems, wireless communication transceivers, etc. The communication unit allows the device to exchange information / data with other devices through computer networks such as the Internet and / or various telecommunication networks.

[0050] The processing unit performs the various methods and processes described above, such as the method of the present invention. For example, in some embodiments, the method of the present invention can be implemented as a computer software program, which is tangibly contained in a machine-readable medium, such as a storage unit. In some embodiments, part or all of the computer program can be loaded and / or installed on the device via a ROM and / or a communication unit. When the computer program is loaded into RAM and executed by the CPU, one or more steps of the method of the present invention described above can be performed. Alternatively, in other embodiments, the CPU can be configured to perform the method of the present invention by any other appropriate means (e.g., by means of firmware).

[0051] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.

[0052] The program code for implementing the method of the present invention can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine as a stand-alone software package and partially on a remote machine, or entirely on a remote machine or server.

[0053] In the context of the present invention, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or equipment, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0054] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed by the present invention, and these modifications or replacements should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.

Claims

1. A method for opening a TACS system limited-time permission signal based on train safety envelope expansion, characterized in that: The method automatically expands the train operation envelope after the trackside controller WTC obtains line resources, triggers the trackside controller WTC to apply for the downgraded train to open the permission signal of the current signal within a limited time, and closes the permission signal before the downgraded train body completely passes the signal.

2. According to claim 1, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: The method specifically comprises the following steps: Step S1, after the train loses the train-to-ground communication during operation, the trackside onboard controller WTC inherits the train safety envelope calculated by the onboard controller CC for the train; Step S2, the automatic train monitoring system ATS automatically reissues the running task before the train is downgraded to the trackside train controller WTC that takes over the train, and extends the train safety envelope to the prohibition signal before the end of the task; Step S3: The driver drives the train to approach and stop before the prohibition signal, completing the current operation task, and the automatic train monitoring system ATS issues the next train operation task; Step S4, the trackside train controller WTC applies for line resources according to the newly issued operation task; Step S5, the trackside train controller WTC calculates the guarantee of no vehicle occupation between the current signal and the next signal in the same direction; Step S6, the trackside train controller WTC applies to the trackside resource manager WRC for opening the permission signal of the current signal within a limited time; Step S7, the trackside resource manager WRC drives the target controller OC to light up the permission light of the current signal within a limited time range; Step S8: The driver drives the train through the current signal within a limited time range.

3. According to claim 2, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: In step S1, after the trackside onboard controller WTC takes over the onboard controller CC, it completes the application for releasing line resources and issuing signal lighting instructions for the train.

4. According to claim 2, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: In step S2, the trackside train controller WTC applies for the required line resources from the trackside resource manager WRC according to the train mission, and after obtaining all the required line resources, extends the train safety envelope to the prohibition signal before the mission end.

5. According to claim 2, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: In step S4, the trackside train controller WTC applies to the trackside resource manager WRC for line resources between the current signal and the next signal in the same direction according to the newly issued operation task.

6. According to claim 2, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: In step S5, the trackside train controller WTC establishes vehicle-to-vehicle communication with other trains on the entire line, obtains safety positioning information of other trains, and then calculates the guarantee that there is no vehicle occupying the space between the current signal and the next signal in the same direction.

7. According to claim 6, a TACS system time-limited permission signal opening method based on train safety envelope expansion is characterized in that: In step S6, after the trackside train controller WTC obtains all the required line resources, it extends the end point of the train safety envelope from the current prohibited signal to the next signal in the same direction, and combines the guarantee that there is no other train occupying the protection section of the current signal to apply to the trackside resource manager WRC for the permission signal to open the current signal within a limited time.

8. According to claim 2, a method for opening a TACS system limited-time permission signal based on train safety envelope expansion is characterized in that: The limited time in step S6 is the shortest time required for the train to accelerate from rest to the maximum speed limit of manual vehicle operation, until the rear of the train clears the current signal after the safety envelope of the downgraded train is expanded.

9. According to claim 2, a method for opening a TACS system limited-time permission signal based on train safety envelope expansion is characterized in that: In step S7, the trackside resource manager WRC drives the target controller OC to light up the permission light of the current signal within a limited time range according to the time-limited permission signal opening request of the trackside train controller WTC.

10. The method for opening a TACS system limited-time permission signal based on train safety envelope expansion according to claim 2, characterized in that: In step S8, the driver drives the train through the current signal after visually observing the permission light. When the limited time is over, the trackside resource manager WRC drives the target controller OC to change the prohibition light of the current signal.

11. An electronic device comprising a memory and a processor, wherein a computer program is stored in the memory, wherein: When the processor executes the program, the method according to any one of claims 1 to 10 is implemented.

12. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the method according to any one of claims 1 to 10 is implemented.

Citation Information

Cited By

  • Degradation train control method and device based on train safety positioning and medium