Construction method of steel-concrete combined bridge deck slab with steel bar lattice shear connectors

By using the design of lattice shear joints with steel-concrete composite bridge panels, the problems of large labor consumption and insufficient connection in traditional construction are solved, the explosion and crack resistance of the bridge panels are improved, and rapid construction is achieved and cost-reducing effects.

CN118911014AInactive Publication Date: 2024-11-08SOUTHEAST UNIV
View PDF 11 Cites 0 Cited by

Patent Information

Application Number
CN202410972871.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional steel-concrete composite bridge decks require a lot of manpower and fatigue problems during construction. PBL shear connections are insufficient, and the crack resistance of the negative bending moment zone bridge decks is low, and the existing technology design is complex and costly. , not suitable for engineering applications.

Method used

Orthogonal opposite-concrete composite bridge panel with reinforced bar lattice shear joints are used to form orthogonal opposite-concrete steel plates through welding of flat steel plates and stiffeners, and the reinforced bar lattice shear joints are welded on them, forming a modeling plate and casting Different types of concrete layers include ordinary concrete, fiber concrete and ultra-high performance concrete. The steel bar lattice consists of lower chord steel bars, inclined steel bars and overhead steel bars. The inclined steel bars form a triangular structure to improve crack resistance.

Benefits of technology

It realizes automated production, increases the stiffness of the bridge deck, simplifies the construction process, makes up for the shortcomings of PBL connectors, improves the explosion resistance and crack resistance in the negative bending moment zone, and reduces construction difficulty and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911014A_ABST
    Figure CN118911014A_ABST
Patent Text Reader

Abstract

The invention relates to a novel orthotropic steel-concrete combined bridge deck slab with steel bar lattice shear connectors, and belongs to the technical field of bridge structures. The construction method comprises the following steps: welding to form an orthotropic steel plate; steel bar lattice shear force connecting pieces are welded to the orthotropic steel plates; building templates around the upper part of the orthotropic steel plate; and according to common concrete or fiber concrete or UHPC selected for pouring, after pouring is completed, a concrete layer is formed, and pouring concrete selected for the concrete layer is cured. According to the steel bar lattice shear connecting piece, automatic production can be achieved, the rigidity of the bridge deck slab is improved, and therefore support-free rapid construction can be achieved, and the defects of a PBL connecting piece combined bridge deck slab are overcome while the rigidity of the bottom steel plate is improved; and the technical problem of low crack capacity of a bridge deck in a hogging moment area of the steel-concrete combined continuous beam bridge can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a novel orthotropic steel-concrete composite bridge deck with a reinforced lattice shear connector, belonging to the technical field of bridge structures. Background Art

[0002] With the promotion and application of steel-concrete composite structure bridges in my country, steel plate-concrete continuous composite bridge decks are favored by people due to their strong bearing capacity, high rigidity, simple construction, good fatigue resistance and durability. In the construction of bridge decks, the bottom steel plate can play the role of formwork, eliminating the need for formwork support erection and removal work, and realizing rapid construction. At the same time, in the renovation and reconstruction of reinforced concrete bridge decks, the use of steel plate-concrete composite bridge decks can speed up the construction progress and reduce traffic impact. Therefore, steel plate-concrete composite bridge decks have broad application prospects in engineering practice. The structural weight of the orthotropic composite bridge deck is between that of the orthotropic steel bridge deck and the concrete bridge deck, and the structural height and bearing capacity are greater than those of the orthotropic steel bridge deck and the concrete deck.

[0003] Traditional shear connectors mainly include PBL and studs. Although stud shear connectors have excellent mechanical properties and ductility, they still have some disadvantages, such as requiring a lot of manpower and fatigue problems. Although the bearing capacity of the orthotropic steel-concrete composite bridge deck with PBL shear connectors is significantly greater than that of the composite bridge deck with stud shear connectors, PBL shear connectors cannot make up for the problem of insufficient connection of the composite bridge deck.

[0004] As an important transportation infrastructure, bridges are one of the key targets of terrorist bombings and military strikes. The use of orthotropic steel-concrete composite bridge decks with reinforced lattice shear connectors can significantly improve their explosion resistance. The concrete can be selected from ordinary concrete, rubber concrete, and ultra-high performance concrete of different strengths according to design requirements.

[0005] Application No. 20191046036.7 discloses a corrugated steel-rubber concrete composite bridge deck, whose design concept is a double-layer steel plate-rubber concrete composite structure.

[0006] Application No. 201610309805.3 discloses a concave weathering steel-concrete composite bridge deck, whose bottom steel plate is a concave bottom steel plate with wave peaks formed at intervals along the length of the plate surface; both of them are complex in design and high in cost, and are not convenient for engineering applications.

[0007] Application No. 201110314503.2 discloses a steel-concrete composite continuous beam bridge that is crack-resistant in the negative bending zone. The design concept is to use high-strength concrete and prestressed tendons in the negative bending zone. However, since the continuous composite steel-concrete bridge deck is only provided with prestressed tendons in the negative bending zone, the construction is difficult and the cost is high.

[0008] Application No. 201810098694.5 discloses an explosion-proof and impact-proof steel bridge deck pavement structure and pavement method. The design idea is to arrange a multi-layer protection system, but due to the complex design and high cost, it is not convenient for engineering application.

[0009] Application No. 201410743551.7 discloses a steel bridge deck paving structure and paving method using flexible connectors, but the structure does not take into account the explosion-proof performance of the bridge deck.

[0010] Application No. 201510946264.0 discloses a steel bridge deck pavement structure and pavement method with explosion-proof performance, which does not consider improving the explosion-proof performance of the bridge deck by providing shear connectors and concrete pavement layers. Summary of the invention

[0011] The present invention provides a novel orthotropic steel-concrete composite bridge deck with reinforced lattice shear connectors. It effectively solves the technical problems of bolts requiring a large amount of manpower and fatigue, insufficient connection of PBL shear connectors, and effectively solves the low cracking capacity of bridge decks in negative bending moment areas and improves their explosion resistance. The research has important engineering significance.

[0012] The present invention adopts the following technical solution:

[0013] The construction method of the steel-concrete composite bridge deck with steel bar lattice shear connectors of the present invention; the construction steps are as follows:

[0014] Step 1: Use flat steel plates and stiffening ribs to weld to form orthotropic steel plates;

[0015] Step 2: welding the steel bar lattice shear connector on the orthotropic steel plate;

[0016] Step 3: Build a template around the upper part of the orthotropic steel plate;

[0017] Step 4: Select ordinary concrete, fiber concrete or UHPC concrete according to the engineering design;

[0018] When ordinary concrete or fiber concrete is used, the template height in step 3 is 10-15 cm;

[0019] When using UHPC concrete, the formwork height in step 3 is less than 6 cm;

[0020] Step 5: According to the ordinary concrete, fiber concrete or UHPC concrete selected for pouring, a concrete layer is formed after pouring is completed, and the poured concrete selected for the concrete layer is cured.

[0021] The steel-concrete composite bridge deck construction method with reinforced lattice shear connectors of the present invention; the stiffening ribs welded in step 1 are open ribs or U-shaped stiffening ribs; the open ribs or U-shaped stiffening ribs are erected on a bracket;

[0022] Several brackets are placed parallel to each other, and several open ribs or U-shaped stiffening ribs are placed on each bracket;

[0023] The placement length of several mutually parallel brackets is equal to the length of the flat steel plate;

[0024] The flat steel plate is mounted and welded to the open rib or U-shaped stiffening rib to form an orthotropic steel plate.

[0025] The construction method of the steel-concrete composite bridge deck with reinforced lattice shear connectors of the present invention;

[0026] The steel bar lattice shear connector comprises a lower chord steel bar, an inclined steel bar, and an upper chord steel bar.

[0027] The lower chord steel bars are composed of a plurality of crisscrossed steel bars; the lower chord steel bars are arranged on the upper end surface of the flat steel plate of the orthotropic steel plate;

[0028] The upper chord steel bar is composed of a plurality of crisscrossed steel bars; the upper chord steel bar is located above the lower chord steel bar;

[0029] The inclined steel bars are a triangular structure formed by combining two steel bars, and the inclined steel bars are arranged between the lower chord steel bars and the upper chord steel bars.

[0030] The construction method of the steel-concrete composite bridge deck with a steel lattice shear connector of the present invention; the angle of the inclined steel bars of the triangular structure is 30°-75°.

[0031] The invention discloses a method for constructing a steel-concrete composite bridge deck with a steel lattice shear connector; the oblique steel bars are arranged in a single row in a straight line along the length direction of the lower chord steel bars and the upper chord steel bars; and a plurality of rows of oblique steel bars are arranged between the lower chord steel bars and the upper chord steel bars (8).

[0032] The construction method of the steel-concrete composite bridge deck with steel bar lattice shear connectors of the present invention; the spacing between the inclined steel bars in the single-row arranged inclined steel bars is 100mm-300mm.

[0033] The construction method of the steel-concrete composite bridge deck with reinforced lattice shear connectors of the present invention;

[0034] The steel bar lattice shear connector comprises a lower chord steel bar, an arc-shaped steel bar, and an upper chord steel bar;

[0035] The lower chord steel bars are composed of a plurality of crisscrossed steel bars; the lower chord steel bars are arranged on the upper end surface of the flat steel plate of the orthotropic steel plate;

[0036] The arc top of the arc-shaped steel bar faces upward, and the bottom end is fixed on the lower chord steel bar;

[0037] The upper chord steel bar is composed of a plurality of crisscrossed wave-shaped steel bars; the upper chord steel bar is fixed to the arc top of the arc-shaped steel bar.

[0038] The invention discloses a method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector; the arc-shaped steel bars are arranged in a single row in a straight line along the length direction of the lower chord steel bars; the crest of the wavy upper chord steel bars is connected to the top of the arc of the arc-shaped steel bars; and the trough of the upper chord steel bars is located between the arc-shaped steel bars adjacent in the vertical and horizontal directions.

[0039] The construction method of the steel-concrete composite bridge deck with steel bar lattice shear connectors of the present invention; the spacing between the arc-shaped steel bars in the arc-shaped steel bars arranged in a single row is 100mm-300mm.

[0040] Beneficial Effects

[0041] The steel-concrete composite bridge deck construction method with steel lattice shear connectors of the present invention can realize automatic production of the steel lattice shear connectors, increase the rigidity of the bridge deck, and thus realize fast construction without support. At the same time, the steel skeleton is pre-buried in the bridge deck concrete, and the bridge deck remains integral, without destroying the integrity of the bridge deck concrete. While improving the rigidity of the bottom steel plate, it makes up for the shortcomings of the PBL connector composite bridge deck; it can also be prefabricated in the factory and assembled on site. In addition, it can also solve the technical problem of low cracking capacity of the bridge deck in the negative bending moment zone of the steel-concrete composite continuous beam bridge.

[0042] In the construction method of the steel-concrete composite bridge deck with steel lattice shear connectors described in the present invention, the steel lattice shear connectors are composed of upper chord steel bars, lower chord steel bars and oblique steel bars. The number of steel lattices, the diameter of the upper chord steel bars or the lower chord steel bars, the inclination angle, bending angle, height and diameter of the oblique steel bars can be set according to design requirements; the concrete layer can use ordinary concrete, rubber concrete and ultra-high performance concrete according to design requirements, and a steel mesh can be added to the negative bending moment area to further improve the crack resistance of the negative bending moment.

[0043] The structure of the steel lattice shear connector based on the triangular structure can be further improved into a curved wave shape, further improving the bending moment crack resistance of the steel mesh. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 It is a stereoscopic diagram of a novel orthotropic steel-concrete composite bridge deck with a reinforced lattice shear connector provided by the present invention;

[0045] Figure 2It is a front view of a novel orthotropic steel-concrete composite bridge deck with a reinforced lattice shear connector provided by the present invention;

[0046] Figure 3 It is a top view of a novel orthotropic steel-concrete composite bridge deck with a reinforced lattice shear connector provided by the present invention;

[0047] Figure 4 is a vertical view of the orthotropic steel plate provided by the present invention;

[0048] Figure 5 It is a vertical view of the steel bar lattice shear connector provided by the present invention;

[0049] Figure 6 It is a vertical view of the corrugated steel bar lattice shear connector provided by the present invention;

[0050] In the figure: 1 is an orthotropic steel plate, 2 is a steel lattice shear connector, 3 is a concrete layer, 4 is a flat steel plate, 5 is a stiffening rib, 6 is a lower chord steel bar, 7 is an inclined steel bar, 8 is an upper chord steel bar, and 9 is an arc steel bar. DETAILED DESCRIPTION

[0051] To make the purpose and technical solution of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the embodiment of the present invention. Obviously, the described embodiment is only a part of the embodiment of the present invention, not all of the embodiments.

[0052] The construction method of the steel-concrete composite bridge deck with steel bar lattice shear connectors of the present invention; the construction steps are as follows:

[0053] Step 1: using a flat steel plate and stiffening ribs to weld to form an orthotropic steel plate 1;

[0054] Step 2: welding the steel bar lattice shear connector 2 on the orthotropic steel plate 1;

[0055] Step 3: Build a template around the upper part of the orthotropic steel plate 1; the height of the template and the wooden template is selected according to the design requirements;

[0056] Step 4: pour concrete layers on the orthotropic steel plates and steel lattice. Different types of concrete are selected according to the design and explosion-proof requirements. When ordinary concrete or fiber concrete is used for the composite slab, the original 20-30 cm concrete slab is reduced to 10-15 cm. When ultra-high performance concrete (UHPC) is used for the composite slab, the thickness can be less than 6 cm, and the problem of insufficient tensile performance of conventional concrete can be solved.

[0057] Step 5: According to the selected ordinary concrete, fiber concrete or UHPC concrete for pouring, a concrete layer 3 is formed after pouring is completed, and the poured concrete selected for the concrete layer 3 is cured.

[0058] When prefabricating the bridge deck, steel bars should be reserved around the concrete layer to facilitate connection with other composite bridge decks.

[0059] like Figure 1 , Figure 2 , Figure 3 , Figure 4 As shown: the stiffening rib welded in step 1 is an open rib or a U-shaped stiffening rib; the open rib or the U-shaped stiffening rib is mounted on the bracket;

[0060] Several brackets are placed parallel to each other, and several open ribs or U-shaped stiffening ribs are placed on each bracket;

[0061] The placement length of several mutually parallel brackets is equal to the length of the flat steel plate;

[0062] The flat steel plate is mounted on the open rib or the U-shaped stiffening rib and welded to each other to form an orthotropic steel plate 1.

[0063] like Figure 5 As shown: the steel lattice shear connector includes a lower chord steel bar 6, an inclined steel bar 7, and an upper chord steel bar 8.

[0064] The lower chord steel bar 6 is composed of a plurality of crisscrossed steel bars; the lower chord steel bar 6 is arranged on the upper end surface of the flat steel plate of the orthotropic steel plate 1;

[0065] The upper chord steel bar 8 is composed of a plurality of crisscrossed steel bars; the upper chord steel bar 8 is located above the lower chord steel bar 6; the oblique steel bars 7 are arranged in a single row in a straight line along the length direction of the lower chord steel bars 6 and the upper chord steel bars 8; and a plurality of rows of oblique steel bars 7 are arranged between the lower chord steel bars 6 and the upper chord steel bars 8.

[0066] The inclined steel bar 7 is a triangular structure formed by combining two steel bars, and the inclined steel bar 7 is arranged between the lower chord steel bar 6 and the upper chord steel bar 8. The angle of the inclined steel bar 7 of the triangular structure is 30°-75°. The spacing between the inclined steel bars 7 in the single row is 100mm-300mm.

[0067] like Figure 6 As shown: the steel bar lattice shear connector includes a lower chord steel bar 6, an arc-shaped steel bar 9, and an upper chord steel bar 8. The lower chord steel bar 6 is composed of a plurality of crisscrossed steel bars; the lower chord steel bar 6 is arranged on the upper end surface of the flat steel plate of the orthotropic steel plate 1; the arc top of the arc-shaped steel bar 9 faces upward, and its bottom end is fixed on the lower chord steel bar 6; the upper chord steel bar 9 is composed of a plurality of crisscrossed wavy steel bars; the upper chord steel bar 9 is fixed to the arc top of the arc-shaped steel bar 9.

[0068] The arc-shaped steel bars 9 are arranged in a single row in a straight line along the length direction of the lower chord steel bars 6; the wave crest of the wavy upper chord steel bars 8 is connected to the arc top of the arc-shaped steel bars 9; the wave trough of the upper chord steel bars 8 is located between the vertically and horizontally adjacent arc-shaped steel bars 9. The spacing between the arc-shaped steel bars 9 in the single row is 100mm-300mm.

[0069] Based on the above ideal embodiments of the present invention, the relevant staff can make various changes and modifications without departing from the technical concept of the present invention through the above description. The technical scope of the present invention is not limited to the contents of the specification, and its technical scope must be determined according to the scope of the claims.

Claims

1. Construction method of steel-concrete composite bridge deck with reinforced lattice shear connectors; Features :The construction steps are as follows: Step 1: Using a flat steel plate and stiffening ribs to weld to form an orthotropic steel plate (1); Step 2: welding a steel bar lattice shear connector (2) onto the orthotropic steel plate (1); Step 3: Building a template around the upper part of the orthotropic steel plate (1); Step 4: Select ordinary concrete, fiber concrete or UHPC concrete according to the engineering design; When ordinary concrete or fiber concrete is used, the template height in step 3 is 10-15 cm; When using UHPC concrete, the formwork height in step 3 is less than 6 cm; Step 5: According to the selected ordinary concrete, fiber concrete or UHPC concrete for pouring, a concrete layer (3) is formed after pouring is completed, and the poured concrete selected for the concrete layer (3) is cured.

2. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 1; characterized in that: The stiffening rib welded in step 1 is an open rib or a U-shaped stiffening rib; the open rib or the U-shaped stiffening rib is mounted on a bracket; Several brackets are placed parallel to each other, and several open ribs or U-shaped stiffening ribs are placed on each bracket; The placement length of several mutually parallel brackets is equal to the length of the flat steel plate; The flat steel plate is mounted on the open rib or the U-shaped stiffening rib and welded to each other to form an orthotropic steel plate (1).

3. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 1; characterized in that: The steel bar lattice shear connector comprises a lower chord steel bar (6), an inclined steel bar (7), and an upper chord steel bar (8). The lower chord steel bars (6) are composed of a plurality of steel bars arranged in a crisscross pattern; the lower chord steel bars (6) are arranged on the upper end surface of the flat steel plate of the orthotropic steel plate (1); The upper chord steel bar (8) is composed of a plurality of steel bars arranged in a crisscross pattern; the upper chord steel bar (8) is located above the lower chord steel bar (6); The inclined steel bar (7) is a triangular structure formed by combining two steel bars, and the inclined steel bar (7) is arranged between the lower chord steel bar (6) and the upper chord steel bar (8).

4. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 3; characterized in that: The angle of the inclined steel bars (7) of the triangular structure is 30°-75°.

5. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 3; characterized in that: The oblique steel bars (7) are arranged in a single row in a straight line along the length direction of the lower chord steel bars (6) and the upper chord steel bars (8); and a plurality of rows of oblique steel bars (7) are arranged between the lower chord steel bars (6) and the upper chord steel bars (8).

6. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 5, characterized in that: The spacing between the inclined steel bars (7) arranged in a single row is 100 mm to 300 mm.

7. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 1, characterized in that: The steel bar lattice shear connector comprises a lower chord steel bar (6), an arc-shaped steel bar (9), and an upper chord steel bar (8). The lower chord steel bars (6) are composed of a plurality of steel bars arranged in a crisscross pattern; the lower chord steel bars (6) are arranged on the upper end surface of the flat steel plate of the orthotropic steel plate (1); The arc top of the arc-shaped steel bar (9) faces upward, and the bottom end is fixed on the lower chord steel bar (6); The upper chord steel bar (9) is composed of a plurality of crisscrossed wave-shaped steel bars; the upper chord steel bar (9) is fixed to the arc top of the arc-shaped steel bar (9).

8. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 5, characterized in that: The arc-shaped steel bars (9) are arranged in a single row in a straight line along the length direction of the lower chord steel bars (6); the wave crest of the wave-shaped upper chord steel bars (8) is connected to the arc top of the arc-shaped steel bars (9); and the wave trough of the upper chord steel bars (8) is located between the arc-shaped steel bars (9) adjacent in the vertical and horizontal directions.

9. The method for constructing a steel-concrete composite bridge deck with a reinforced lattice shear connector according to claim 5, characterized in that: The spacing between the arc-shaped steel bars (9) arranged in a single row is 100 mm to 300 mm.

Citation Information

Patent Citations

  • Anti-cracking steel-concrete combined continuous girder bridge of negative moment region

    CN102505624A

  • Steel bridge deck pavement structure and pavement method

    CN104452586A

  • Anti-knocking steel box beam bridge deck paving structure and paving method

    CN105401519A

  • Concave rib weathering resistant steel-concrete combination bridge deck

    CN105780649A

  • Anti-explosion anti-shock steel deck pavement structure and pavement method

    CN108086153A