Overall closure construction device and method for side-span steel beams of oversized-span cable-stayed bridge
By combining the design of the hoisting frame assembly, the ground hook support assembly and the bridge assembly, the problem of insufficient protection in the construction of the steel beam of the side span of the cable-stayed bridge is solved, and the stability and precise integration of the bridge are achieved to ensure the construction Safety and efficiency.
Patent Information
- Application Number
- CN202411015838.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-08
AI Technical Summary
In the prior art, the integrated joint construction device of the overspan cable-stayed bridge side-span steel beam lacks a protective structure and cannot effectively deal with the risk of loose hook drop in special circumstances.
A construction device including a hoist frame assembly, a ground hook support assembly and a bridge assembly was designed. Through the bottom cylinder, a telescopic connection hook lock and a laser device, the stability and protection of the bridge during the construction process is ensured, and Use jack and scale dual observation to achieve accurate dragon closure.
It improves the protection of the bridge and the stability between the crane and the bridge, ensures the safety and accuracy of the construction process, and realizes efficient jointing of side span steel beams.
Smart Images

Figure CN118911017A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of side span closure construction, and in particular to a device and method for integral closure construction of side span steel beams of a super-large span cable-stayed bridge. Background Art
[0002] The existing method of assembling the side span joint is to divide the entire bridge deck into multiple small sections, and then assemble the side spans. Although this method is suitable for large-span and heavy-load bridges and can reduce the impact of expansion joints on vehicle traffic, it is difficult to control and adjust the accuracy, stability and sealing of the interfaces of various parts of the bridge deck during the specific construction process. Therefore, a method for jack-pushing and sliding side span jointing of large-span cable-stayed bridges is needed.
[0003] A steel box girder lifting equipment with automatic leveling function disclosed in the Chinese utility model patent application disclosure CN114348860A, although the lifting block installed at the lifting point of the steel box girder is clamped by the lifting mechanism, the vertical adjustment mechanism includes a lifting box, a dynamometer and a cable drum, and the cable drum is installed on one side of the lifting box, but the overall structure lacks protection for the bridge and lacks a protective structure to deal with special circumstances that may cause the loose hook to fall. Therefore, the present application provides a construction device and method for the integral jointing of the side span steel beams of an ultra-large span cable-stayed bridge to meet the needs. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a device and method for integrally closure construction of the side span steel beams of a super-large span cable-stayed bridge to solve the problem that the existing integral structure lacks protection for the bridge and lacks a protective structure to deal with special circumstances resulting in loose hooks and falling.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0006] A device and method for integrally closure construction of side span steel beams of a super-large span cable-stayed bridge, comprising a crane frame assembly 1 and two ground hook support assemblies 2, wherein the lower sides of the crane frame assembly 1 are respectively connected with hook assemblies 3, the connection between the two crane frame assemblies 1 and the hook assemblies 3 passes through the ground hook support assemblies 2, the bottoms of all the hook assemblies 3 are connected with a bridge assembly 4, and bottom cylinders 5 are respectively provided on the left front and rear sides of the center of the bottom surface of the bridge assembly 4, and each of the left and right sides of the bottom cylinder 5 are respectively connected with a retractable connecting hook lock 6, and the other end of each of the retractable connecting hook locks 6 is connected to a splicing fixing frame 7. The surface of the bridge component 4 includes a bridge 401, the top surface of the bridge 401 is provided with ears 402 at four corners, the top surface of the bridge 401 is provided with concave and convex splicing grooves 403 in an arranged manner at the left and right edges, the bottom surface of the bridge 401 is provided with semicircular grooves 404 at the front and rear sides, the front and rear surfaces of the bridge 401 are provided with a plurality of strap grooves 405 in an arranged manner, the bottom surface of the bridge 401 is provided with supporting wooden boards 406 at the front and rear edges, and the top surface of each supporting wooden board 406 is provided with a laser instrument 407 at the left and right edges.
[0007] Optionally, the crane frame assembly 1 includes a main support frame 101, a PC remote control terminal 103 is provided on the left surface of the main support frame 101, a hook support frame 102 is connected to the right side of the main support frame 101, and a hook cable winding drum 104 is provided on the top surface of the hook support frame 102 at the front and rear ends respectively.
[0008] Optionally, the ground hook support assembly 2 includes an I-beam 201, and retractable fixing columns 202 are respectively provided on the left and right edges of the bottom surface of the I-beam 201, and several position scales 203 are respectively arranged on the front and rear edges of the top surface of the I-beam 201.
[0009] Optionally, an elliptical slide groove 204 is provided at the center of the top surface of the I-beam 201 , the inner surface of the elliptical slide groove 204 is covered with a sliding chain 205 , and a circular slider 206 is provided inside the sliding chain 205 .
[0010] Optionally, the hook assembly 3 includes a hook fixing body 301, a steel cable connecting column 302 is provided on the top of the hook fixing body 301, telescopic columns 303 are provided on the left and right sides of the bottom surface of the hook fixing body 301, and a steel cable connecting hole 304 is opened on one side surface of each telescopic column 303 near the bottom edge.
[0011] Optionally, a hook 305 is connected to the bottom of each telescopic column 303, a rotating shaft 306 passes through the center of the hook 305, a buckle 307 is connected to one side of the rotating shaft 306, a hinge 308 is connected to one side of the buckle 307, and a connecting rod 309 is connected to one end of the hinge 308.
[0012] Optionally, a cable drum 310 is provided at the center of the bottom surface of the hook fixing body 301 , and the surface of the cable drum 310 is covered with an anti-falling cable 311 , and the left and right sides of the anti-falling cable 311 are respectively connected to a fall brake 312 .
[0013] Optionally, an L-shaped connecting plate 313 is provided at the center of one side surface of the hook fixing body 301, close to the left and right sides respectively, and a plurality of telescopic connecting rods 314 are arranged at the bottom of the L-shaped connecting plate 313, and a right-angle limit block 315 is provided at the eighth part of all the telescopic connecting rods 314, and a strap 316 is connected to one side of the right-angle limit block 315.
[0014] Optionally, the side span closure steps are respectively the following steps:
[0015] Step 1: The double cantilever of the beam-erecting crane lifts the Z75-76 and Z14-15 steel beam segments. After the high bolts are tightened and the circumferential seam welding is completed, the beam-erecting crane loosens the structure but does not remove the hook.
[0016] Step 2: Arrange the lifting device under the Z16 node of the steel beam. When lifting the Z15Z16 steel beam segment, remove the support slide and groove the upper slide beam at the same time.
[0017] Step 3: Measure the linear shape of the side span steel beam continuously for 24 hours, analyze the status of the steel beam, lift the top at the Z16 node according to the monitoring instruction, and adjust the posture of the side span joint in coordination with the arrangement of the 7# and 8# pier tops. Strictly control the synchronization of the lifting, lateral and longitudinal movement of the side span steel beam, and use double observation of the jack stroke and scale to ensure that the deviation is ≤5mm.
[0018] Optionally, the specific steps of adjusting the side span joint connection are as follows:
[0019] Step 1: Use 8 vertical 1500t jacks and 4 2000t jacks at piers 7# and 8# to adjust the elevation of the Z0-Z13 inter-section steel beams. At the same time, use the 400t jack at the Z16 node to adjust the elevation of the steel beams on the short-distance side to make the elevations of the two consistent. Then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams 600mm toward the middle span side.
[0020] Step 2: Use a total of 6 transverse 300t jacks at piers 7# and 8# to adjust the Z0-Z13 inter-section steel beams to the transverse design position, and then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams longitudinally 416mm to the mid-span side.
[0021] Step 3: The overall longitudinal displacement of the Z0-Z13 inter-section steel beam is estimated to be 100 mm, and the end posture of the Z0-Z13 inter-section steel beam is fine-tuned according to the sensitivity analysis to achieve precise closure.
[0022] Optionally, the auxiliary crane pulling side span steel beam device uses the steps;
[0023] Step 1: First, place multiple ground hook support assemblies 2 on the surface of the bridge body at both ends to adjust the overall height according to the height of the bottom steel beam, and pass the hook assembly 3 from the circular slider 206 to the bottom to hook the bridge assembly 4 using two hook assemblies 3.
[0024] Step 2: Use splicing fixing frames 7 to splice and fix along the bridge deck on the surfaces of the bridge bodies at both ends. Use bottom support cylinders 5 and retractable connecting hook locks 6 to place them at the bottom of the bridge assembly 4 at the bottom. The retractable connecting hook locks 6 are connected to the surface of the splicing fixing frames 7 to provide bottom support for the bottom of the bridge assembly 4. If the upper device is placed incorrectly and the hook is loosened, the bridge assembly 4 will fall immediately and cause an accident.
[0025] Step 3: Fix for the third time at the bottom of the L-shaped connecting plate 313 in the structure of the two hook components 3 by passing the bandage 316 through the bandage groove 405 opened at the bottom of the bridge component 4.
[0026] Step 4: The laser instrument 407 is connected to the PC remote control terminal 103. The laser instrument 407 can be irradiated upward to aim at the part of the bridge component 4 that needs to be docked. If an offset occurs, the PC remote control terminal 103 will record the data in real time for timely adjustment.
[0027] Compared with the prior art, the present invention has at least the following beneficial effects:
[0028] In the above scheme, a plurality of ground hook support assemblies are first placed on the surface of the bridge bodies at both ends to adjust the overall height according to the height of the bottom steel beam, and the hook assembly is passed through the circular slider to the bottom and the bridge assembly is hooked by two hook assemblies. The surfaces of the bridge bodies at both ends are fixed by splicing along the bridge deck using a splicing fixing frame, and the bottom of the bridge assembly is placed at the bottom of the bridge assembly using a bottom-covering cylinder and a retractable connecting hook lock. The retractable connecting hook lock is connected to the surface of the splicing fixing frame to provide a bottom-covering support for the bottom of the bridge assembly. If the upper device is placed incorrectly and the hook is loosened, the bridge assembly will fall immediately and cause an accident. A bandage is used to pass through the bandage groove opened at the bottom of the bridge assembly at the bottom of the L-shaped connecting plate in the structure of the two hook assemblies for the third fixation. The laser instrument is connected to the PC remote control terminal, and the laser instrument can be irradiated upward to aim at the part of the bridge assembly that needs to be docked when it rises. If an offset occurs, the PC remote control terminal will record the data in real time for timely adjustment. In addition, the circular slider can be used to use a sliding chain to move left and right on the surface of the ground hook support assembly to change the direction.
[0029] The side span Z0-1~Z12-13 segment steel beams are connected into a whole, and the double cantilever of the beam erecting crane is used to erect the Z75-76 and Z14-15 segment steel beams. After the high bolts of the Z14-15 segment steel beams are tightened and the circumferential seam welding is completed, the beam erecting crane is unhooked, the Z16 node is lifted, and the Z0-13 inter-segment steel beam is adjusted to move longitudinally toward the middle span to achieve joint connection and butt connection. Before joint connection, the linear shape of the side span steel beam is continuously measured for 24 hours to determine the adjustment value of the steel beam. According to the monitoring instructions, the adjustment measures of the 7# and 8# pier tops and the Z16 node arrangement are used to adjust the mileage, axis, and elevation deviation of the steel beam to achieve the butt connection and butt connection of the side span steel beam, and then the high bolts are tightened and welding construction is carried out.
[0030] In summary, the present invention has the advantages of improving the protection of the bridge and the stability between the crane and the bridge. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] The accompanying drawings, which are incorporated herein and constitute a part of the specification, illustrate embodiments of the invention and, together with the description, further serve to explain the principles of the invention and to enable those skilled in the relevant art to make and use the invention.
[0032] Figure 1 It is a three-dimensional structural diagram of the overall closure construction device for the side span steel beam of a super-large span cable-stayed bridge;
[0033] Figure 2 It is a schematic diagram of the three-dimensional structure of the auxiliary fixing device for the integral closure of the side span steel beam of the super-large span cable-stayed bridge;
[0034] Figure 3 It is a schematic diagram of the structure of the splicing fixing frame;
[0035] Figure 4 It is a schematic diagram of the bridge component structure;
[0036] Figure 5 It is a schematic diagram of the structure of the hanging frame assembly;
[0037] Figure 6 It is a schematic diagram of the structure of the ground hook support assembly;
[0038] Figure 7 It is a schematic diagram of the hook assembly structure;
[0039] Figure 8 It is a schematic diagram of the structure of the hook fixing body;
[0040] Fig. 9 It is a schematic diagram of the hook structure;
[0041] Fig.10 It is a schematic diagram of the cable disc structure;
[0042] Fig.11 It is a schematic diagram of the L-shaped connecting plate structure;
[0043] Fig.12 It is a schematic diagram of the plan structure of the side span closure steps;
[0044] Fig.13 Intent to express the sensitivity of the side span joint of the steel beam of the main channel bridge;
[0045] Fig.14 This is a schematic diagram of the displacement data of the closure mouth under the action of the counterweight;
[0046] Fig.15 This is a schematic diagram of the displacement of the closure mouth under the action of the counterweight;
[0047] Fig.16 This is a schematic diagram of the displacement data of the closure mouth under the effect of temperature;
[0048] Fig.17 This is a schematic diagram of the displacement of the closing mouth under the action of temperature;
[0049] Fig.18 This is a schematic diagram of the closure construction device;
[0050] Fig.19 Schematic diagram of the side span closure steps.
[0051] [reference numerals]
[0052] 1. Crane frame assembly; 101. Main support frame; 102. Hook support frame; 103. PC remote control terminal; 104. Hook cable reel; 2. Ground hook support assembly; 201. I-beam; 202. Telescopic fixed column; 203. Position scale; 204. Oval slide; 205. Sliding chain; 206. Round slider; 3. Hook assembly; 301. Hook fixed body; 302. Cable connecting column; 303. Telescopic column; 304. Cable connecting hole; 305. Hook; 306. Rotating Axis; 307, buckle; 308, hinge; 309, connecting rod; 310, cable drum; 311, anti-fall cable; 312, fall brake; 313, L-shaped connecting plate; 314, telescopic connecting rod; 315, right-angle limit block; 316, binding strap; 4, bridge assembly; 401, bridge; 402, lifting ear; 403, concave and convex splicing groove; 404, semicircular groove; 405, binding strap groove; 406, supporting wooden board; 407, laser instrument; 5, bottom cylinder; 6, telescopic connecting hook lock; 7, splicing fixing frame.
[0053] As shown in the figure, in order to clearly implement the structure of the embodiment of the present invention, specific structures and devices are marked in the figure, but this is only for illustrative purposes and is not intended to limit the present invention to the specific structure, device and environment. According to specific needs, ordinary technicians in this field can adjust or modify these devices and environments, and the adjustments or modifications made are still included in the scope of the attached claims. DETAILED DESCRIPTION
[0054] In the following, in conjunction with the accompanying drawings and specific embodiments, a device and method for integrally closure construction of the side span steel beam of a super-large span cable-stayed bridge provided by the present invention are described in detail. At the same time, it is explained here that in order to make the embodiments more detailed, the following embodiments are the best and preferred embodiments, and those skilled in the art may also adopt other alternative methods for implementation of some known technologies; and the accompanying drawings are only for a more specific description of the embodiments, and are not intended to specifically limit the present invention.
[0055] It should be noted that the references to "one embodiment", "an embodiment", "an exemplary embodiment", "some embodiments" and the like in the specification indicate that the embodiments described may include specific features, structures or characteristics, but not every embodiment may include the specific features, structures or characteristics. In addition, when a specific feature, structure or characteristic is described in conjunction with an embodiment, it should be within the knowledge of a person skilled in the art to implement such feature, structure or characteristic in conjunction with other embodiments (whether or not explicitly described).
[0056] In general, a term can be understood, at least in part, from its use in context. For example, depending, at least in part, on the context, the term "one or more" as used herein can be used to describe any feature, structure, or characteristic in the singular sense, or can be used to describe a combination of features, structures, or characteristics in the plural sense. Additionally, the term "based on" can be understood as not necessarily intended to convey an exclusive set of factors, but can instead, depending, at least in part, on the context, allow for the presence of other factors that are not necessarily explicitly described.
[0057] It will be understood that the meanings of “on,” “over,” and “above” in the present invention should be interpreted in the broadest manner, so that “on” not only means “directly on” something, but also includes the meaning of being “on” something with intervening features or layers therebetween, and “on” or “over” not only means “on” or “above” something, but also includes the meaning of being “on” or “above” something with no intervening features or layers therebetween.
[0058] Additionally, spatially relative terms such as "under," "beneath," "lower," "above," "upper," and the like may be used herein for descriptive convenience to describe the relationship of one element or feature to another element or features, as shown in the accompanying drawings. Spatially relative terms are intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the accompanying drawings. The device may be oriented in other ways, and the spatially relative descriptors used herein may be similarly interpreted accordingly.
[0059] like Figure 1-Figure 5As shown, an embodiment of the present invention provides an overall joint construction device and method for the side span steel beam of a super-large span cable-stayed bridge, including a crane frame assembly 1 and two ground hook support assemblies 2, the lower sides of the crane frame assembly 1 are respectively connected with hook assemblies 3, the connection between the two crane frame assemblies 1 and the hook assemblies 3 passes through the ground hook support assembly 2, the bottom of all the hook assemblies 3 are connected with a bridge assembly 4, the bottom surface of the bridge assembly 4 is provided with a bottom support cylinder 5 on the left front and rear sides of the center, each bottom support cylinder 5 is connected with a retractable connecting hook lock 6 on the left and right sides, and the other end of each retractable connecting hook lock 6 is connected to the surface of a splicing fixing frame 7, the bridge assembly 4 includes a bridge 401, and the top surface of the bridge 401 is provided with lifting ears 402 at four corners. The top surface of bridge 401 is provided with concave and convex splicing grooves 403 in an arranged manner near the left and right edges, the bottom surface of bridge 401 is provided with semicircular grooves 404 near the front and rear sides, the front and rear surfaces of bridge 401 are provided with several binding grooves 405 in an arranged manner, the bottom surface of bridge 401 is provided with supporting wooden boards 406 near the front and rear edges, and the top surface of each supporting wooden board 406 is provided with laser instruments 407 near the left and right edges, the crane frame assembly 1 includes a main support frame 101, the left surface of the main support frame 101 is provided with a PC remote control terminal 103, the right side of the main support frame 101 is connected to a hook support frame 102, and the top surface of the hook support frame 102 is provided with a hook cable winding drum 104 near the front and rear ends.
[0060] Two semicircular grooves 404 opened at the bottom of the bridge 401 are adapted to the bottom cylinder 5, and the retractable connecting hook locks 6 on both sides of the bottom cylinder 5 are fixed between the splicing fixing frame 7 and the bottom cylinder 5. After the top crane accidentally loosens the hook, it prevents the bridge 401 from falling directly and causing an accident. It serves as a layer of protection and fixation. When the bridge 401 falls, the retractable connecting hook locks 6 will hold the bridge 401 in mid-air.
[0061] By connecting the laser instrument 407 to the PC remote control terminal 103, the laser instrument 407 can be irradiated upward to aim at the part of the bridge component 4 that needs to be docked. If an offset occurs, the PC remote control terminal 103 will record the data in real time for timely adjustment.
[0062] like Figure 6-Figure 12As shown, in this embodiment, the ground hook support assembly 2 includes an I-beam 201, and retractable fixing columns 202 are respectively provided at the left and right edges of the bottom surface of the I-beam 201, and a plurality of position scales 203 are arranged at the front and rear edges of the top surface of the I-beam 201, and an elliptical slide groove 204 is provided at the center of the top surface of the I-beam 201. The inner surface of the elliptical slide groove 204 is covered with a sliding chain 205, and a circular slider 206 is provided inside the sliding chain 205. The hook assembly 3 includes a hook fixing body 301, and a steel cable connecting column 302 is provided at the top of the hook fixing body 301, and telescopic columns 303 are respectively provided at the left and right sides of the bottom surface of the hook fixing body 301, and a steel cable connecting hole 304 is provided at the bottom edge of each telescopic column 303. A hook 305 is connected to the bottom of each telescopic column 303, a rotating shaft 306 runs through the center of the hook 305, a buckle 307 is connected to one side of the rotating shaft 306, a hinge 308 is connected to one side of the buckle 307, and a connecting rod 309 is connected to one end of the hinge 308. A steel cable drum 310 is provided at the center of the bottom surface of the hook fixing body 301, and the surface of the steel cable drum 310 is covered with an anti-falling steel cable 311, and the left and right sides of the anti-falling steel cable 311 are respectively connected to falling brakes 312, and L-shaped connecting plates 313 are respectively provided at the center of one side surface of the hook fixing body 301, and a plurality of telescopic connecting rods 314 are arranged at the bottom of the L-shaped connecting plate 313, and a right-angle limit block 315 is provided at the eighth part of all the telescopic connecting rods 314, and a strap 316 is connected to one side of the right-angle limit block 315.
[0063] The third fixation is performed by passing the bandage 316 through the bandage groove 405 opened at the bottom of the bridge component 4 through the bottom of the L-shaped connecting plate 313 in the structure of the hook component 3, and the hook 305 is fixed to the surface of the ear 402 in the form of a buckle. The hinge 308 is bent to drive the buckle to pull out of the inside of the hook 305, and the opening is opened to buckle on the surface of the ear 402.
[0064] The hooks 305 on both sides are pulled by the fall brake 312 to prevent the hooks 305 from falling accidentally. When falling quickly, the fall brake 312 will use the steel cable to pull the hooks 305 on both sides.
[0065] like Figure 1-Figure 17 As shown, in this embodiment, the side span closure steps are respectively the following steps:
[0066] Step 1: The double cantilever of the beam-erecting crane lifts the Z75-76 and Z14-15 steel beam segments. After the high bolts are tightened and the circumferential seam welding is completed, the beam-erecting crane loosens the structure but does not remove the hook.
[0067] Step 2: Arrange the lifting device under the Z16 node of the steel beam. When lifting the Z15Z16 steel beam segment, remove the support slide and groove the upper slide beam at the same time.
[0068] Step 3: Measure the linear shape of the side span steel beam continuously for 24 hours, analyze the status of the steel beam, lift the top at the Z16 node according to the monitoring instruction, and adjust the posture of the side span joint in coordination with the arrangement of the 7# and 8# pier tops. Strictly control the synchronization of the lifting, lateral and longitudinal movement of the side span steel beam, and use double observation of the jack stroke and scale to ensure that the deviation is ≤5mm.
[0069] In this embodiment, the specific steps of adjusting the side span joint connection are as follows:
[0070] Step 1: Use 8 vertical 1500t jacks and 4 2000t jacks at piers 7# and 8# to adjust the elevation of the Z0-Z13 inter-section steel beams. At the same time, use the 400t jack at the Z16 node to adjust the elevation of the steel beams on the short-distance side to make the elevations of the two consistent. Then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams 600mm toward the middle span side.
[0071] Step 2: Use a total of 6 transverse 300t jacks at piers 7# and 8# to adjust the Z0-Z13 inter-section steel beams to the transverse design position, and then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams longitudinally 416mm to the mid-span side.
[0072] Step 3: The overall longitudinal displacement of the Z0-Z13 inter-section steel beam is estimated to be 100 mm, and the end posture of the Z0-Z13 inter-section steel beam is fine-tuned according to the sensitivity analysis to achieve precise closure.
[0073] In this embodiment, the auxiliary crane pulling side span steel beam device uses the following steps:
[0074] Step 1: First, place multiple ground hook support assemblies 2 on the surface of the bridge body at both ends to adjust the overall height according to the height of the bottom steel beam, and pass the hook assembly 3 from the circular slider 206 to the bottom to hook the bridge assembly 4 using two hook assemblies 3.
[0075] Step 2: Use splicing fixing frames 7 to splice and fix along the bridge deck on the surfaces of the bridge bodies at both ends. Use bottom support cylinders 5 and retractable connecting hook locks 6 to place them at the bottom of the bridge assembly 4 at the bottom. The retractable connecting hook locks 6 are connected to the surface of the splicing fixing frames 7 to provide bottom support for the bottom of the bridge assembly 4. If the upper device is placed incorrectly and the hook is loosened, the bridge assembly 4 will fall immediately and cause an accident.
[0076] Step 3: Fix for the third time at the bottom of the L-shaped connecting plate 313 in the structure of the two hook components 3 by passing the bandage 316 through the bandage groove 405 opened at the bottom of the bridge component 4.
[0077] Step 4: The laser instrument 407 is connected to the PC remote control terminal 103. The laser instrument 407 can be irradiated upward to aim at the part of the bridge component 4 that needs to be docked. If an offset occurs, the PC remote control terminal 103 will record the data in real time for timely adjustment.
[0078] In this embodiment, the steps for arranging the top of pier 7# are as follows:
[0079] 1) Vertical adjustment: The total weight of the Z0-1~Z12-13 steel beam segments is 10594t, the fulcrum reaction force of the single truss of pier 7# is 3689t, and it is equipped with 4 1500t jacks for lifting, and the double trusses are equipped with 8 1500t jacks in total.
[0080] 2) Longitudinal adjustment: For the longitudinal movement of the steel beam, only the longitudinal jack is installed at the 7# pier. The dynamic friction coefficient between the sliding surface MGE plate and the stainless steel plate is calculated as 0.1, and the required horizontal thrust is 1060t. The longitudinal pushing of the whole bridge is equipped with 4 650t jacks.
[0081] 3) Lateral adjustment: The horizontal thrust for lateral adjustment of the steel beam is 738t. Four 300t jacks are installed under the support point of the single truss of Pier 7#, and a total of eight 300t jacks are installed for the double trusses, four of which are installed downstream and four are installed upstream.
[0082] In this embodiment, the steps for arranging the top of pier 8# are as follows:
[0083] 1) Vertical adjustment: The total weight of the Z0-1~Z12-13 steel beam segments is 10594t, the fulcrum reaction force of the 8# pier single truss is 1608t, equipped with 2 2000t jacks for lifting, and the double trusses are equipped with 4 2000t jacks in total.
[0084] 2) Lateral adjustment: The dynamic friction coefficient between the sliding surface MGE plate and the stainless steel plate is 0.1, so the required lateral horizontal thrust is 321.6t. Two 300t jacks are installed under the support point of the single girder of 8# pier, and a total of four 300t jacks are configured for the double girder, two to the downstream side and two to the upstream side.
[0085] To ensure smooth closure, the sensitivity of the closure mouth elevation parameters under the maximum cantilever state before the side span closure is analyzed through the closure mouth sensitivity analysis. The displacement of the main beam under the action of adding 10t, 50t, and 100t counterweights at the front end of the main beam is calculated. The calculation results are shown in the figure. Fig.14 and Fig.15 As shown in the table, z is the vertical displacement, with upward as positive; △Z is the displacement value relative to the model coordinates. The temperature effect is used to calculate the displacement of the front end of the main beam when the structural temperature changes between -15℃ and 15℃. The calculation results are shown in Fig.16 and Fig.17As shown in the table, z is the vertical displacement, with upward as positive; △Z is the displacement value relative to the model coordinates, and then the sensitivity measures, the side span closure adjustment measures mainly utilize the movement of the 200t truck crane or the temperature effect to complete the high bolt tightening and weld welding construction at the closure mouth, the side span beam crane moves to the 8# pier, and the 27# and 28# inclined cables are symmetrically hung and tensioned in the side middle span.
[0086] like Fig.18 and Fig.19 As shown in the figure, 11 sections of steel beams from Z0-1 to Z20-21 are lifted and slid onto the sliding bracket by floating crane, and Z0-1 to Z12-13 are welded into a whole. Four sections from Z14-15 to Z20-21 are erected by beam erection crane on the sliding bracket. The interface between Z13 and Z14 is the side span joint opening. After the Z14-15 section steel beam is connected with the Z16-17 section, the beam erection crane is unhooked, and the side span Z0-Z13 section steel beam is longitudinally moved to the middle span side to carry out the side span joint construction.
[0087] The technical solution provided by the present invention is to first place a plurality of ground hook support assemblies 2 on the surface of the bridge bodies at both ends to adjust the overall height according to the height of the bottom steel beam, and pass the hook assembly 3 from the circular slider 206 to the bottom to hook the bridge assembly 4 using two hook assemblies 3, and use the splicing fixing frame 7 to fix the surface of the bridge bodies at both ends along the bridge deck, and place the bottom of the bridge assembly 4 at the bottom with the bottom of the bridge assembly 4 using the bottom support cylinder 5 and the retractable connecting hook lock 6, and the retractable connecting hook lock 6 is connected to the surface of the splicing fixing frame 7 to provide a bottom support for the bottom of the bridge assembly 4, and if the upper device is placed and the hook is loosened by mistake, the bridge assembly 4 will fall immediately and cause an accident, and the bandage 316 is used to pass through the bandage groove 405 opened at the bottom of the bridge assembly 4 at the bottom of the L-shaped connecting plate 313 in the structure of the two hook assemblies 3 for the third fixation, and the laser instrument 407 is connected to the PC remote control terminal 103, and the laser instrument 407 can be irradiated upward to In order to align the bridge assembly 4 with the part that needs to be docked when it rises, if there is an offset, the PC remote control terminal 103 will record the data in real time for timely adjustment. In addition, the circular slider 206 can be used to use the sliding chain 205 to move left and right on the surface of the ground hook support assembly 2 to change the direction, and then the side span Z0-1~Z12-13 segment steel beams are connected into a whole, and the beam crane double cantilever erects the Z75-76 and Z14-15 segment steel beams, and the Z14-15 segment steel beams are connected to the ground hook support assembly 2. After the high bolts of the steel beams are tightened and the circumferential seam welding is completed, the hook of the beam erection crane is released, the Z16 node is lifted, and the Z0-13 inter-section steel beams are adjusted to move longitudinally toward the middle span to achieve joint connection and butt connection. Before joint connection, the linear shape of the side span steel beams is measured continuously for 24 hours to determine the adjustment value of the steel beams. According to the monitoring instructions, the adjustment measures of the 7# and 8# pier tops and the Z16 node arrangement are used to adjust the mileage, axis, and elevation deviations of the steel beams to achieve the butt connection and butt connection of the side span steel beams, and then the high bolts are tightened and the welding construction is carried out.
[0088] The present invention covers any substitution, modification, equivalent method and scheme made on the essence and scope of the present invention. In order to make the public have a thorough understanding of the present invention, specific details are described in detail in the following preferred embodiments of the present invention, but those skilled in the art can fully understand the present invention without the description of these details. In addition, in order to avoid unnecessary confusion about the essence of the present invention, well-known methods, processes, procedures, components and circuits are not described in detail.
[0089] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A construction device for integrally closing the side span steel beams of a super-long span cable-stayed bridge, characterized in that: It includes a hanging frame assembly and two ground hook support assemblies, the lower sides of the hanging frame assembly are respectively connected with hook assemblies, the connection between the two hanging frame assemblies and the hook assemblies passes through the ground hook support assembly, the bottom of all the hook assemblies is connected with a bridge assembly, the bottom surface of the bridge assembly is provided with bottom-covering cylinders on the left front and back sides of the center, each of the bottom-covering cylinders is respectively connected with a retractable connecting hook lock on the left and right sides, and the other end of each of the retractable connecting hook locks is connected to the surface of the splicing fixing frame; The bridge assembly includes a bridge, the top surface of the bridge is provided with hanging ears at four corners, the top surface of the bridge is provided with concave and convex splicing grooves in an arranged manner at the left and right edges, the bottom surface of the bridge is provided with semicircular grooves at the front and rear sides, the front and rear surfaces of the bridge are provided with a plurality of binding grooves in an arranged manner, the bottom surface of the bridge is provided with supporting wooden boards at the front and rear edges, and the top surface of each of the supporting wooden boards is provided with laser instruments at the left and right edges.
2. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1 is characterized in that: The crane frame assembly includes a main support frame, a PC remote control terminal is provided on the left surface of the main support frame, a hook support frame is connected to the right side of the main support frame, and a hook cable winding drum is provided on the top surface of the hook support frame near the front and rear ends respectively.
3. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1 is characterized in that: The ground hook support assembly includes an I-beam, and retractable fixing columns are respectively provided on the left and right edges of the bottom surface of the I-beam, and several position scales are respectively arranged on the front and rear edges of the top surface of the I-beam.
4. The device for integrally closure of side span steel beams of a super-long span cable-stayed bridge according to claim 3 is characterized in that: An elliptical slide groove is provided at the center of the top surface of the I-beam, the inner surface of the elliptical slide groove is covered with a sliding chain, and a circular sliding block is provided inside the sliding chain.
5. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1 is characterized in that: The hook assembly includes a hook fixing body, a steel cable connecting column is provided on the top of the hook fixing body, telescopic columns are provided on the left and right sides of the bottom surface of the hook fixing body, and a steel cable connecting hole is opened on one side surface of each telescopic column near the bottom edge.
6. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 5 is characterized in that: The bottom of each telescopic column is connected with a hook, the center of the hook is penetrated by a rotating shaft, one side of the rotating shaft is connected with a buckle, one side of the buckle is connected with a hinge, and one end of the hinge is connected with a connecting rod.
7. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 5 is characterized in that: A steel cable disc is provided at the center of the bottom surface of the hook fixing body, the surface of the steel cable disc is covered with an anti-falling steel cable, and the left and right sides of the anti-falling steel cable are respectively connected with a falling brake.
8. The device for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 5 is characterized in that: An L-shaped connecting plate is provided at the center of one side surface of the hook fixing body, close to the left and right sides respectively, and a plurality of telescopic connecting rods are arranged at the bottom of the L-shaped connecting plate. A right-angle limit block is provided at the eighth part of all the telescopic connecting rods, and a strap is connected to one side of the right-angle limit block.
9. The method for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1 is characterized in that: The side span closure steps are respectively as follows: Step 1: The double cantilever of the beam-erecting crane lifts the Z75-76 and Z14-15 steel beam segments. After the high bolts are tightened and the circumferential seam welding is completed, the beam-erecting crane loosens the structure but does not remove the hook. Step 2: Arrange the lifting device under the Z16 node of the steel beam. When lifting the Z15Z16 steel beam segment, remove the support slide and groove the upper slide beam at the same time. Step 3: Measure the linear shape of the side span steel beam continuously for 24 hours, analyze the status of the steel beam, lift the top at the Z16 node according to the monitoring instruction, and adjust the posture of the side span joint in coordination with the arrangement of the 7# and 8# pier tops. Strictly control the synchronization of the lifting, lateral and longitudinal movement of the side span steel beam, and use double observation of the jack stroke and scale to ensure that the deviation is ≤5mm.
10. The method for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1, characterized in that: The specific steps of the side span joint connection and docking adjustment are as follows: Step 1: Use 8 vertical 1500t jacks and 4 2000t jacks at piers 7# and 8# to adjust the elevation of the Z0-Z13 inter-section steel beams. At the same time, use the 400t jack at the Z16 node to adjust the elevation of the steel beams on the short-distance side to make the elevations of the two consistent. Then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams 600mm toward the middle span side. Step 2: Use a total of 6 transverse 300t jacks at piers 7# and 8# to adjust the Z0-Z13 inter-section steel beams to the transverse design position, and then use the 4 longitudinal 650t jacks arranged at pier 7# to synchronously move the steel beams longitudinally 416mm to the mid-span side. Step 3: The overall longitudinal displacement of the Z0-Z13 inter-section steel beam is estimated to be 100 mm, and the end posture of the Z0-Z13 inter-section steel beam is fine-tuned according to the sensitivity analysis to achieve precise closure.
11. The method for integrally closing the side span steel beams of a super-long span cable-stayed bridge according to claim 1 is characterized in that: The steps of using the auxiliary crane to pull the side span steel beam device; Step 1: First, place multiple ground hook support assemblies on the surface of the bridge body at both ends to adjust the overall height according to the height of the bottom steel beam, and pass the hook assembly from the circular slider to the bottom to hook the bridge assembly with two hook assemblies. Step 2: Use splicing fixing frames to fix the bridge bodies at both ends along the bridge deck. Use bottom-supporting cylinders and retractable connecting hooks to place the bottom of the bridge assembly at the bottom of the bridge assembly. The retractable connecting hooks are connected to the surface of the splicing fixing frames to provide bottom support for the bottom of the bridge assembly. If the upper device is placed incorrectly and the hook is loosened, the bridge assembly will fall immediately and cause an accident. Step 3: Use a bandage to pass through the bandage groove at the bottom of the bridge assembly to fix it for the third time at the bottom of the L-shaped connecting plate in the two hook assembly structures. Step 4: Connect the laser instrument to the PC remote control terminal. The laser instrument can be shone upward to aim at the part of the bridge component that needs to be docked. If an offset occurs, the PC remote control terminal will record the data in real time for timely adjustment.
Citation Information
Patent Citations
Steel box girder hoisting equipment with automatic leveling function
CN114348860A