Bridge substructure integral pouring construction method

Through the integrated casting construction method, combined with the steel cofferdam and formwork support frame, the problems of long construction intervals between the bearing and pier columns and low material use efficiency are solved, and the rapid, safe and economical construction of the bridge lower structure is achieved, and the construction is improved. Efficiency and integrity.

CN118911027APending Publication Date: 2024-11-08CCCC SECOND HARBOR ENGINEERING CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411207126.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the existing bridge lower structure construction methods, there are large intervals between the construction of the bearing and pier columns, and the material use and processing efficiency are low, which affects the overall construction efficiency and quality.

Method used

The integrated pouring construction method is adopted, and the combination of steel cofferdam, formwork support frame and fixing frame can achieve simultaneous pouring of the bearing and pier columns, reducing construction intervals, improving construction efficiency, and using layered pouring and string casting technology Control the concrete pouring height to ensure structural stability.

Benefits of technology

It realizes rapid, safe and economical construction of the bearing and pier columns, reduces material consumption, improves construction efficiency and integrity, and ensures structural reliability and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911027A_ABST
    Figure CN118911027A_ABST
Patent Text Reader

Abstract

The invention discloses an integral pouring construction method for a bridge substructure. Comprising the following steps that an original ground is leveled and rolled, a pile foundation is constructed, a foundation pit is supported by conducting lofting, inserting, driving and sinking on a steel cofferdam, the foundation pit is excavated in a layered mode, and after the foundation pit is excavated to the position below an inner supporting system by a certain distance, the inner supporting system is installed; excavating to the bottom of the foundation pit, and pouring cushion concrete; after the pile foundation is inspected to be qualified, a bearing platform is constructed; processing and binding pier column steel bars, transporting the pier column steel bars to a site, integrally hoisting, welding and fixing the pier column steel bars and the bearing platform steel bars, and then mounting the pier column steel templates according to a single block; concrete pouring of the bearing platform is carried out, after pouring is completed, the horizontal bearing platform top formwork is closed, and then concrete pouring of the pier column is carried out. Overall pouring of the bearing platform and the pier column is achieved, the structure is reliable, operation is convenient, the construction period is greatly shortened, and the integrity of the bearing platform and the pier column is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of civil engineering bridge substructure construction, and in particular relates to an integral casting construction method for a bridge substructure. Background Art

[0002] At present, for the substructure of a concrete bridge constructed with steel cofferdams, pile foundation construction is generally carried out first, followed by steel cofferdam construction, and then abutment and pier construction.

[0003] The types of steel cofferdams are mainly divided into steel sheet piles, steel pipe piles, steel box casings and steel hanging box cofferdams. Among them, steel plate (pipe) pile cofferdams are generally used for onshore caps. When the caps and pier bodies are cast in place, steel formwork is used. The pier construction can only be carried out after the cap construction is completed. The construction interval is not less than 2 days and not more than 10 days. When the caps and pier bodies are prefabricated, lifting machinery is required to put the caps and piers in place, and vertical connections are set up by means of steel strands, pre-buried grouting sleeves, etc., to ensure that the caps and piers are tightly connected.

[0004] After the pouring of the cap in the above-mentioned cast-in-place construction method is completed, it is necessary to wait until the concrete strength meets the design requirements before the pier column reinforcement can be tied; when the prefabricated construction method is adopted, high requirements are placed on the quality of the prefabricated components and the accuracy of the production equipment. Summary of the invention

[0005] The purpose of the present invention is to solve the shortcomings of the above-mentioned background technology and provide a method for integrally casting the substructure of a bridge, thereby improving the efficiency of the construction of the abutment and piers and reducing the input and consumption of construction materials.

[0006] The technical solution adopted by the present invention is: a method for integrally pouring a bridge substructure, comprising the following steps:

[0007] S1: Level and roll the original ground, and construct the pile foundation. Support the foundation pit by staking out, inserting and sinking the steel cofferdam. Excavate the foundation pit in layers. After excavating to a certain distance below the internal support system, install the internal support system.

[0008] S2: Excavate to the bottom of the foundation pit, pour cushion concrete, cut the pile head, and after the pile foundation is inspected and qualified, carry out the construction of the cap. The construction of the cap includes tying the cap steel bars, adding concrete pads, and installing the cap side formwork;

[0009] S3: Hoist the formwork support frame into the pedestal, and then hoist the formwork fixing frame above the pedestal, so that the steel sections at both ends of the formwork fixing frame are fixed on the steel cofferdam;

[0010] S4: Process and tie the pier column steel bars, transport the pier column steel bars to the site, hoist them as a whole, weld and fix the pier column steel bars to the cap steel bars, fix the template back ribs set on the column steel template to the telescopic fixed axis of the template fixing frame, and then install the pier column steel template as a single piece;

[0011] S5: Carry out integral concrete pouring: first pour the concrete of the pedestal. After the pouring is completed, close the horizontal pedestal top formwork, and then pour the concrete of the pier column.

[0012] Furthermore, the template fixing frame includes a steel section and a telescopic fixing shaft arranged on the inner circumference of the steel section, and is transported to the site after the template fixing frame is spliced ​​in the back field.

[0013] Furthermore, the internal support system includes purlins, angle braces, and braces. The purlins are fixed to the circumference of the inner wall of the steel cofferdam, the two ends of the angle braces are fixed to the purlins on two adjacent surfaces of the inner wall of the steel cofferdam, and the two ends of the braces are fixed to the purlins on two opposite surfaces of the inner wall of the steel cofferdam.

[0014] Furthermore, the lowest level of the inner support system of the steel cofferdam is 30 cm to 40 cm higher than the top level of the pedestal to ensure smooth installation of the pedestal top formwork.

[0015] Furthermore, the pouring of the cap concrete and the pier column concrete is carried out in layers, and the thickness of each layer shall not exceed 30cm.

[0016] Furthermore, the pier column concrete is poured through a string tube to ensure that the concrete pouring height does not exceed 2m.

[0017] Furthermore, the formwork support frame is a support frame structure that supports the pier column steel formwork.

[0018] Furthermore, it also includes: after the overall pouring is completed, covering it with geotextile and sprinkling water for curing, and the curing period is not less than 7 days.

[0019] Furthermore, installing the side formwork of the pedestal includes: setting a support rod between the side formwork of the pedestal and the steel cofferdam, and setting a pull rod between the side formwork of the pedestal and the top of the steel bars of the pedestal.

[0020] Furthermore, the installation of the pier column steel formwork is fixed by using a formwork support frame and a formwork fixing frame, the adjacent upper and lower segment pier column steel formwork is fixed by bolts, and the pier column steel formwork on the same layer is fixed by setting tension screws at the diagonals of the pier column.

[0021] The present invention realizes the integral casting of the pedestal and the pier column, has a reliable structure, is easy to operate, greatly saves the construction period, ensures the integrity of the pedestal and the pier column, and at the same time the steel formwork, support frame and fixing frame used can be recycled, with significant practical effect.

[0022] The specific beneficial effects of the present invention are as follows:

[0023] 1. Good safety performance. The steel cofferdam, fixed frame, support frame, steel formwork and other structures have clear force, and finite element software is used for simulation analysis to ensure the stability and safety of the structure during the construction process.

[0024] 2. High construction efficiency. The components of the steel cofferdam, the steel bars of the foundation, the steel bars of the pier column, etc. can all be processed in the back field. The front field only needs to carry out the processes such as steel sheet pile sinking, internal support installation, and steel bar installation. The back field processing is not restricted by the environment and weather, and can realize all-weather operation with high construction efficiency.

[0025] 3. Good economic benefits. There are wide channels for obtaining materials such as steel sheet piles, steel sections, and steel pipes, and the materials can be used in a cyclical manner.

[0026] 4. Wide application range. When the foundation pit of the cap adopts steel cofferdam, this construction method can be used to speed up the construction progress and improve the integrity of the cap and pier. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a cross-sectional view of the foundation pit of the steel cofferdam of the present invention;

[0028] Figure 2 is a plan layout diagram of the present invention;

[0029] Figure 3 It is the integral casting cross-sectional view of the present invention;

[0030] Figure 4 It is a structural schematic diagram of the template fixing frame of the present invention.

[0031] Among them, 1-original ground; 2-pile foundation; 3-steel cofferdam; 4-foundation pit; 5-purlin; 6-angle brace; 7-bracing; 8-cushion concrete; 9-cap; 901-cap steel bar; 902-concrete pad; 903-cap side formwork; 904-cap top formwork; 10-formwork support frame; 11-formwork fixing frame; 1101-steel; 1102-telescopic fixed shaft; 12-pier; 1201-pier steel bar; 1202-pier steel formwork; 1203-formwork back rib; 1204-tension screw. DETAILED DESCRIPTION

[0032] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments to facilitate a clear understanding of the present invention, but they do not constitute a limitation on the present invention.

[0033] like Figure 1-4 As shown, the present invention comprises the following steps:

[0034] S1: The original ground 1 is leveled and rolled, and the pile foundation 2 is constructed. The foundation pit 4 is supported by staking out, inserting and sinking the steel cofferdam 3. The foundation pit 4 is excavated in layers. After the excavation is 50 cm below the inner support system, the inner support system is installed.

[0035] S2: excavate to the bottom of the foundation pit 4, pour cushion concrete 8, cut the pile head of the pile foundation 2 by the ring cutting method, check whether the pile foundation 2 is qualified, and after the pile foundation 2 is qualified, construct the cap 9. The construction of the cap 9 includes tying the cap steel bars 901, adding concrete pads 902, and installing the cap side template 903;

[0036] S3: hoist the formwork support frame 10 into the pedestal 9, and then hoist the formwork fixing frame 11 above the pedestal 9, so that the steel sections 1101 at both ends of the formwork fixing frame 11 are fixed on the steel cofferdam 3;

[0037] S4: Processing and tying the pier column steel bars 1201, transporting the pier column steel bars 1201 to the site, hoisting them as a whole, welding and fixing the pier column steel bars 1201 and the cap steel bars 901, fixing the template back ribs 1203 provided on the column steel template 1202 and the telescopic fixed shaft 1102 of the template fixing frame 11, and then installing the pier column steel template 1202 as a single piece;

[0038] S5: pouring concrete as a whole: first pouring concrete of the cap 9, after the pouring is completed, closing the horizontal cap top formwork 904, and then pouring concrete of the pier 12 using a conduit;

[0039] S6: After the overall pouring is completed, cover it with geotextile and sprinkle water for curing. The curing period is not less than 7 days.

[0040] In some optional embodiments, the template fixing frame 11 includes a steel section 1101 and a telescopic fixing shaft 1102 arranged on the inner circumference of the steel section 1101, and the template fixing frame 11 is transported to the site after being spliced ​​in the back field.

[0041] In some optional embodiments, the internal support system includes a purlin 5, an angle brace 6, and a brace 7. The purlin 5 is fixed to the circumference of the inner wall of the steel cofferdam 3, the two ends of the angle brace 6 are fixed to the purlin 5 on two adjacent surfaces of the inner wall of the steel cofferdam 3, and the two ends of the brace 7 are fixed to the purlin 5 on two opposite surfaces of the inner wall of the steel cofferdam 3.

[0042] The lowest level of the inner support system of the steel cofferdam 3 is 30-40cm higher than the top level of the cap 9 to ensure smooth installation of the cap top formwork. The concrete of the cap 9 and the pier 12 are poured in layers, and the thickness of each layer shall not exceed 30cm. The concrete of the pier 12 is poured through a string tube to ensure that the concrete pouring height does not exceed 2m.

[0043] In some optional embodiments, the formwork support frame 10 is a support frame structure that supports the pier column steel formwork 1202.

[0044] The installation of the cap side formwork 903 includes: setting a support rod between the cap side formwork 903 and the steel cofferdam 3, and setting a tie rod between the cap side formwork 903 and the top of the cap steel bar 901. Before installing the cap side formwork 903, its surface should be polished and cleaned to ensure that there is no dirt or rust on the surface, and then a release agent should be applied.

[0045] The installation of the pier column steel formwork 1202 is fixed by using a formwork support frame 10 and a formwork fixing frame 11. The adjacent upper and lower segment pier column steel formwork 1202 is fixed by bolts. The same layer pier column steel formwork 1202 is fixed by setting tension screws 1204 at the diagonal positions of the pier column.

[0046] In some optional embodiments, the steel cofferdam 3 is a steel sheet pile cofferdam or a steel pipe pile cofferdam.

[0047] In some optional embodiments, the formwork support frame 10 and the formwork fixing frame 11 are welded by steel sections and steel pipes, wherein a single formwork fixing frame 11 is provided with a double layer of fourteen telescopic fixed shafts 1102, and the telescopic range of a single telescopic fixed shaft is 0.8m.

[0048] Foundation pit 4 considers dry excavation construction. If the ground hydrology is higher than the bottom elevation of the cushion concrete, the precipitation well technology can be used to ensure dry construction of the foundation pit.

[0049] In order to ensure that the cap 9 and the pier 12 can be cast together, the support system in the steel cofferdam 3 does not interfere with the construction of the pier. If it interferes with the construction of the pier, the design of the steel cofferdam needs to be further optimized.

[0050] It is necessary to establish a model using finite element software based on the actual geological conditions on site and analyze various working conditions during the excavation process to ensure the safety and reliability of the steel cofferdam 3 structure.

[0051] The formwork fixing frame 11 is fixed on the steel cofferdam 3 by snap buckles. When the steel cofferdam 3 cannot provide support for the formwork fixing frame 11, a steel section can be added to the end of the formwork fixing frame 11 to provide vertical support.

[0052] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

Claims

1. A method for integrally casting a bridge substructure. Features: The following steps are involved: S1: The original ground (1) is leveled and rolled, and pile foundation (2) is constructed. The foundation pit (4) is supported by staking out, inserting and sinking the steel cofferdam (3). The foundation pit (4) is excavated in layers. After the excavation reaches a certain distance below the internal support system, the internal support system is installed. S2: excavating to the bottom of the foundation pit (4), pouring cushion concrete (8), cutting the pile head of the pile foundation (2), and after the pile foundation (2) is inspected and qualified, constructing the cap (9). The construction of the cap (9) includes tying the cap steel bars (901), adding concrete pads (902), and installing the cap side formwork (903); S3: hoisting the formwork support frame (10) into the pedestal (9), and then hoisting the formwork fixing frame (11) above the pedestal (9), so that the steel sections (1101) at both ends of the formwork fixing frame (11) are fixed on the steel cofferdam (3); S4: Processing and tying the pier column steel bars (1201), transporting the pier column steel bars (1201) to the site, hoisting the pier column steel bars (1201) and welding the pier column steel bars (1201) to the cap steel bars (901), fixing the template back ribs (1203) provided on the column steel template (1202) to the telescopic fixed shaft (1102) of the template fixing frame (11), and then installing the pier column steel template (1202) as a single piece; S5: Casting of concrete as a whole: Casting of concrete for the cap (9) is performed first. After the casting is completed, the horizontal cap top formwork (904) is closed, and then the concrete casting of the pier column (12) is performed.

2. A method for integrally casting a bridge substructure according to claim 1, Features: The template fixing frame (11) comprises a steel section (1101) and a telescopic fixing shaft (1102) arranged on the inner circumference of the steel section (1101), and is transported to the site after the template fixing frame (11) is assembled at the back site.

3. A method for integrally pouring a bridge substructure according to claim 1, Features: The inner support system comprises a purlin (5), an angle brace (6), and a brace (7); the purlin (5) is fixed to the circumference of the inner wall of the steel cofferdam (3); two ends of the angle brace (6) are fixed to the purlin (5) on two adjacent surfaces of the inner wall of the steel cofferdam (3); and two ends of the brace (7) are fixed to the purlin (5) on two opposite surfaces of the inner wall of the steel cofferdam (3).

4. A method for integrally casting a bridge substructure according to claim 1, Features: The lowest level of the inner support system of the steel cofferdam (3) is 30 cm to 40 cm higher than the top level of the pedestal (9).

5. A method for integrally casting a bridge substructure according to claim 1, Features: The concrete pouring of the cap (9) and the concrete pouring of the pier column (12) are both carried out in layers, and the thickness of each layer shall not exceed 30 cm.

6. A method for integrally casting a bridge substructure according to claim 1, Features: The concrete for pouring the pier column (12) is poured through a string tube to ensure that the concrete pouring height does not exceed 2m.

7. A method for integrally casting a bridge substructure according to claim 1, Features: The formwork support frame (10) is a support frame structure that supports the pier column steel formwork (1202).

8. The method for integrally casting a bridge substructure according to claim 1, Features: Also includes: After the overall pouring is completed, cover it with geotextile and sprinkle water for curing. The curing period is not less than 7 days.

9. The method for integrally casting a bridge substructure according to claim 1, Features: The installation of the pedestal side formwork (903) includes: setting a support rod between the pedestal side formwork (903) and the steel cofferdam (3), and setting a pull rod between the pedestal side formwork (903) and the top of the pedestal reinforcement (901).

10. The method for integrally casting a bridge substructure according to claim 1, Features: The installation of the pier column steel formwork (1202) is fixed by a formwork support frame (10) and a formwork fixing frame (11), the adjacent upper and lower segment pier column steel formworks (1202) are fixed by bolts, and the pier column steel formworks (1202) on the same layer are fixed by tension screws (1204) at the diagonal positions of the pier columns.

Citation Information

Cited By

  • Deepwater cofferdam facilitating installation of Y-shaped pier support and construction method of deepwater cofferdam

    CN122344898A

  • Deep water cofferdam facilitating installation of y-shaped pier support and construction method thereof

    CN122344898B