Waterproof construction method for foundation raft in deep foundation ponding area
By excavating water collection and water collection puddles in deep foundation water accumulation areas and installing steel cage nets and pumping pipes, the problem of water accumulation during construction is solved, the construction efficiency and quality is improved, maintenance costs are reduced, and maintenance costs are enhanced Structural strength of the foundation raft.
Patent Information
- Application Number
- CN202411072287.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-08
AI Technical Summary
In the construction of foundation raft slabs in deep foundation water accumulation areas, traditional drainage methods are inefficient, which makes it difficult to ensure construction efficiency and quality, and requires frequent maintenance, which cannot effectively deal with the continuous water accumulation problem in the water collection pit.
By digging water collection holes and water collection holes at the construction site, installing steel cage nets and water extraction pipes, extracting water accumulation, and pouring water barriers and waterproof layers in the water collection holes to form a pit structure in the pit to ensure the water collection holes The side walls and bottoms are dry, improving waterproofing and construction efficiency.
It effectively solves the problem of water accumulation affecting construction, improves the construction efficiency and quality of foundation raft slabs, reduces the later maintenance costs, enhances the structural strength of foundation raft slabs, and reduces the construction risks caused by groundwater.
Smart Images

Figure CN118911174A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building waterproof construction, and in particular to a foundation raft waterproof construction method in a deep foundation waterlogging area. Background Art
[0002] Buildings usually need to have a foundation raft at the bottom. The foundation raft is used to support the building and prevent it from sinking. The structure and construction process of the foundation raft need to consider the geological conditions of the location where it is located. The construction of the foundation raft in the deep foundation water accumulation area is the construction process of constructing the foundation raft in the area with a lot of water accumulation in the soil, and the construction depth of the foundation raft is deep. During the construction of the foundation raft in the deep foundation sump area, due to factors such as geological conditions, groundwater and construction precipitation, water accumulation often occurs in the sump. These accumulated waters will be continuously generated and difficult to be discharged at one time. The continuous water accumulation in the sump will seriously restrict the efficiency and quality of the subsequent cushion casting and waterproofing layer construction. The traditional drainage method has the problems of low efficiency and frequent maintenance in dealing with the construction of the foundation raft in the deep foundation sump area, and it is difficult to meet the actual construction needs. Summary of the invention
[0003] In view of this, in order to deal with the construction difficulties of low construction efficiency and frequent maintenance caused by water accumulation during the construction of the foundation raft in the deep foundation sump area, the construction efficiency and quality of the foundation raft in the deep foundation sump area are improved. The present invention provides 1. A waterproof construction method for the foundation raft in the deep foundation water accumulation area, characterized in that it comprises the following steps: S1: Determine the construction location of the foundation raft, dig a sump at the construction location, dig a water collection pit at the bottom of the sump, and let the accumulated water seeping from the side wall of the sump flow into the sump; S2: Waterproof the side walls and bottom of the sump; S3: A steel cage is buried in the water collection pit, and the two sides of the steel cage support the side walls of the water collection pit; a pumping pipe is installed in the steel cage; and the accumulated water in the water collection pit is pumped out through the pumping pipe; S4: Pour a water-proof cushion layer inside the sump and on the side walls of the sump, and seal the upper end of the pumping pipe; S5: Cast the foundation raft slab on the waterproof cushion layer in the sump.
[0004] Furthermore, the cross section of the sump in step S1 is a trapezoidal cross section that is wider at the top and narrower at the bottom.
[0005] Furthermore, gravel layers are laid on both sides of the water collection pit in step S1.
[0006] Furthermore, the steel cage mesh in step S3 is a rectangular cage mesh structure, and the steel cage mesh is also wrapped with a dense filter mesh.
[0007] Furthermore, in step S2, the process of waterproofing the sidewalls and bottom of the sump is as follows: bricks are laid on the sidewalls of the sump to form a brick membrane slope, and a waterproof membrane is laid on the surface of the brick membrane slope.
[0008] Furthermore, after laying the waterproof coiled material once on the slope surface of the brick membrane in step S2, the waterproof coiled material is baked so that it is tightly attached to the slope surface of the brick membrane.
[0009] Furthermore, the water pumping pipe in step S3 is a seamless steel pipe, and the lower end of the seamless steel pipe is welded to the steel cage.
[0010] Furthermore, the process of pumping out the accumulated water in the water collection pit through the pumping pipe is to place the pumping pump into the steel cage along the cavity of the seamless steel pipe, and start the pumping pump to pump out the water in the steel cage.
[0011] Furthermore, in step S5, the process of pouring the foundation raft slab in the sump is as follows: the pouring of the foundation raft slab is completed in two steps, firstly pouring a lower foundation layer in the sump; performing secondary waterproofing treatment on the upper surface of the lower foundation layer to obtain a secondary waterproof layer; and pouring an upper foundation layer on the secondary waterproof layer.
[0012] Furthermore, the secondary waterproof layer is located in the sump, and the upper end of the upper foundation layer extends out of the ground beyond the sump.
[0013] The beneficial effects of the waterproof construction method of a foundation raft in a deep foundation water accumulation area of the present invention are as follows: by adopting the above construction method, a water collection pit is dug in the water collection pit to form a pit-in-pit structure, so that the accumulated water continuously seeping from the inner wall of the water collection pit during the construction process can be gathered into the water collection pit in real time, avoiding the problem of water accumulation in the water collection pit affecting the construction, thereby improving the construction efficiency of the foundation raft. In addition, the water collection pit can keep the side wall and bottom of the water collection pit relatively dry, which is convenient for the construction of the primary waterproof layer, improves the water-stopping effect of the primary waterproof membrane, avoids the problem of frequent maintenance of the foundation raft in the later stage, and reduces the later maintenance cost of the foundation raft. The above construction method buries a steel cage mesh in the water collection pit, and then pours concrete to form a reinforced concrete support at the bottom of the foundation raft, improves the structural strength of the foundation raft, and reduces the construction risk of the foundation raft caused by the underground water discharge problem. The bottom and the inside of the foundation raft are respectively paved with a primary waterproof membrane and a secondary waterproof membrane, and the secondary waterproof structure can effectively prevent the penetration of water from the ground to the top and bottom, ensuring the quality of the foundation raft concrete pouring. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a flow chart of a method for waterproofing a foundation raft slab in a deep foundation waterlogging area according to an embodiment of the present invention.
[0015] Figure 2It is a cross-sectional view of a foundation raft construction structure constructed by a foundation raft waterproofing construction method for a deep foundation waterlogging area according to an embodiment of the present invention.
[0016] In the above figure: 1-foundation raft, 11-upper foundation layer, 12-lower foundation layer, 2-sump, 21-brick membrane slope, 22-primary waterproof layer, 23-waterproof cushion layer, 3-sump, 31-gravel layer, 4-steel cage, 41-pump pipe, 5-secondary waterproof layer. DETAILED DESCRIPTION
[0017] To make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described below with reference to the accompanying drawings.
[0018] Please refer to Figure 1 and Figure 2 , Figure 1 This is a flow chart of a waterproof construction method for a foundation raft in a deep foundation waterlogging area according to the present invention. Figure 2 The cross-sectional view of the foundation raft structure constructed by the construction method. The foundation raft 1 construction structure includes a sump 2, a water collection pit 3 is also provided at the bottom of the sump 2, a steel cage 4 is provided in the sump 3, a primary waterproof layer 22 is provided on the side wall and bottom of the sump 3, a waterproof cushion layer 23 is cast on the primary waterproof layer 22, the foundation raft 1 is cast on the waterproof cushion layer 23, and the foundation raft 1 fills the entire sump 2. The foundation raft 1 structure forms a reinforced concrete support structure with a steel cage 4 at the bottom of the sump 2, and forms a waterproof structure of a primary waterproof layer and a waterproof cushion layer 23 on the side wall of the sump 2, so that after the construction of the foundation raft is completed, the bottom water accumulation erosion ability can be effectively avoided, the construction quality of the foundation raft 1 is improved, its service life is extended, and its subsequent maintenance cost is reduced.
[0019] The specific process of the waterproof construction method of the foundation raft slab in the deep foundation waterlogging area of the present invention is as follows: S1: Determine the construction position of the foundation raft 1, excavate a sump 2 at the construction position, and excavate a drainage pit 3 at the bottom 2 of the sump; wherein there is a lot of accumulated water and seepage water in the soil at the construction position. After the drainage pit 3 is excavated at the bottom of the sump 2, the accumulated water seeping from the side wall of the sump 2 will flow into the drainage pit 3 along the side wall of the sump 2.
[0020] In this embodiment, the cross-section of the sump 2 in step S1 is a trapezoidal cross-section that is wide at the top and narrow at the bottom, so as to ensure that a slope surface is formed on the side wall of the sump 2, so that all the water seeping out of the soil body can flow into the sump 3; the sump 3 in step S1 is also paved with gravel layers 31 on both sides, and the cross-section of the gravel layer 31 is an inverted triangle structure. The gravel layer 31 has a filtering effect on the water seeping out of the soil body, preventing soil particles in the soil body from flowing into the sump 3 with the accumulated water, thereby causing the problem of soil accumulation in the sump 3. S2: Perform a waterproofing treatment on the side wall and the bottom of the sump 2 to obtain a waterproof layer 22; the specific process is to first lay bricks along the slope of the sump 2, and build all the bricks into an integral structure to form a brick membrane slope 21, the brick membrane slope 21 is supported on the slope of the sump 2 to ensure that the brick membrane slope 21 does not collapse (the slope of the sump 2 has a supporting effect on the brick membrane slope 21), and the surface of the brick membrane slope 21 after building has the advantages of being dry and flat; then on the completed brick membrane slope A primary waterproofing membrane is laid on the surface of the slope 21 (the primary waterproofing layer 22 is the primary waterproofing membrane). The primary waterproofing membrane can be an asphalt waterproofing membrane and a polymer waterproofing membrane. When the waterproofing membrane is laid, the primary waterproofing membrane is pressed tightly against the surface of the brick membrane slope 21. After the waterproofing membrane is laid, the primary waterproofing membrane is baked to soften the waterproofing membrane and tightly adhere to the surface of the brick membrane slope 21. This avoids bulging between the primary waterproofing membrane and the surface of the brick membrane slope 21, thereby improving the waterproofing effect of the waterproofing membrane.
[0021] S3: A steel cage 4 is buried in the sump. It can be understood that the sump is a strip-shaped groove with a rectangular cross-section. In the present embodiment, the steel cage 4 is a rectangular cage structure. Both sides of the steel cage 4 support the side walls of the sump 3, and the steel cage 4 is also wrapped with a dense filter mesh. The dense filter mesh can further ensure that the accumulated water flowing into the steel cage 4 is clean.
[0022] Then, a pumping pipe 41 is installed in the steel cage mesh 4, wherein the pumping pipe 41 is a seamless steel pipe, and the pumping pipe 41 is vertically fixed on the steel cage mesh 4, and the lower end of the pumping pipe 41 extends into the steel cage mesh 4, and the lower end of the pumping pipe 41 is welded to the steel cage mesh 4, and the upper end of the pumping pipe 41 exceeds the height of the water collection pit 3; the accumulated water in the water collection pit 3 is pumped out through the pumping pipe 41. The above-mentioned pumping process is as follows: placing a pump along the seamless steel pipe into the steel cage 4, starting the pump to pump out the water in the steel cage 4, and taking the pump out of the pumping pipe 41 after the pumping is completed.
[0023] S4: Cast a waterproof cushion layer 23 in the sump 3 and on the side wall of the sump, and seal the upper end of the pumping pipe 41; the specific process is to first cast a waterproof cushion layer 23 with a concrete structure on the surface of the primary waterproof membrane on the side wall of the sump, and the waterproof cushion layer 23 extends to the top of the steel cage 4 in the backwater pit, so that the bottom and side walls of the sump are both concrete structures, and then inject concrete slurry into the upper end of the pumping pipe 41, and the concrete slurry fills the steel cage 4 from the pumping pipe 41 downwards, so as to form a reinforced concrete support structure in the backwater pit, and then install a cover body on the upper end of the pumping pipe 41, and weld the cover body to the upper end of the pumping pipe 41 to seal the pumping pipe 41; finally, check the sealing of the cover body structure at the upper end of the pumping pipe 41 to ensure that there is no leakage. The cover body sealing the upper end of the pumping pipe 41 can prevent groundwater from penetrating upward along the inner wall of the pumping pipe 41.
[0024] S5: Casting the foundation raft 1 in the sump. In this embodiment, the foundation raft 1 includes an upper foundation layer 11 and a lower foundation layer 12, wherein the casting of the foundation raft 1 is completed in two steps: first, the lower foundation layer 12 is cast in the sump; a secondary waterproofing treatment is performed on the upper surface of the lower foundation layer 12 to obtain a secondary waterproofing layer 5; and the upper foundation layer 11 is cast on the secondary waterproofing layer 5. The secondary waterproofing layer 5 is located in the sump 3, and the upper end of the upper foundation layer 11 extends out of the ground beyond the sump. The secondary waterproofing layer 5 is a secondary waterproofing membrane, and its material is the same as that of the primary waterproofing membrane. The secondary waterproofing membrane is cast between the upper foundation layer 11 and the lower foundation layer.
[0025] By adopting the above construction method, a water collection pit 3 is excavated in the water collection pit 2 to form a pit-in-pit structure, so that the accumulated water that continuously seeps out from the inner wall of the water collection pit 2 during the construction process can be gathered into the water collection pit 3 at any time, avoiding the problem that the accumulated water in the water collection pit 3 will not gather and affect the construction, thereby improving the construction cost efficiency. In addition, the water collection pit 3 can keep the side walls and bottom of the water collection pit 3 relatively dry, which is convenient for the primary waterproof construction effect, improves the water-stopping effect of the primary waterproof membrane, and reduces the later maintenance cost of the foundation raft 1. The above construction method buries a steel cage 4 in the water collection pit 3, and then pours concrete to form a reinforced concrete support at the bottom of the foundation raft 1, improves the structural strength of the foundation raft 1, and reduces the construction risk of the foundation raft 1 caused by groundwater problems. The bottom and inside of the foundation raft 1 are respectively paved with a primary waterproof membrane and a secondary waterproof membrane, and the secondary waterproof structure can effectively prevent water from penetrating from the ground to the top and bottom, ensuring the quality of the concrete pouring of the foundation raft 1.
[0026] In this document, the directional words such as front, back, top, and bottom are defined by the positions of the components in the drawings and the positions of the components relative to each other, and are only for the sake of clarity and convenience in expressing the technical solution. It should be understood that the use of the directional words should not limit the scope of protection claimed in this application.
[0027] In the absence of conflict, the above embodiments and features in the embodiments may be combined with each other.
[0028] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for waterproofing a foundation raft in a deep foundation waterlogging area, characterized in that: The steps include: S1: Determine the construction location of the foundation raft, dig a sump at the construction location, dig a water collection pit at the bottom of the sump, and let the accumulated water seeping from the side wall of the sump flow into the sump; S2: Waterproof the side walls and bottom of the sump; S3: A steel cage is buried in the water collection pit, and the two sides of the steel cage support the side walls of the water collection pit; a pumping pipe is installed in the steel cage; and the accumulated water in the water collection pit is pumped out through the pumping pipe; S4: Pour a waterproof cushion layer inside the sump and on the side walls of the sump, and seal the upper end of the pumping pipe; S5: Cast the foundation raft slab on the waterproof cushion layer in the sump.
2. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 1, characterized in that: The cross section of the sump in step S1 is a trapezoidal cross section that is wide at the top and narrow at the bottom.
3. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 1, characterized in that: In step S1, gravel layers are also laid on both sides of the water collection pit.
4. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 1, characterized in that: The steel cage mesh in step S3 is a rectangular cage mesh structure, and the steel cage mesh is also wrapped with a filter mesh.
5. The waterproof construction method for deep foundation raft in waterlogged area according to claim 1, characterized in that: The process of waterproofing the sidewalls and bottom of the sump in step S2 is as follows: laying bricks on the sidewalls of the sump to form a brick membrane slope, and laying a waterproof membrane on the surface of the brick membrane slope.
6. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 5, characterized in that: In step S2, after laying the primary waterproofing membrane on the slope surface of the brick membrane, the secondary waterproofing membrane is baked to make it closely adhere to the slope surface of the brick membrane.
7. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 1, characterized in that: The water pumping pipe in step S3 is a seamless steel pipe, and the lower end of the seamless steel pipe is welded to the steel cage.
8. A waterproof construction method for deep foundation raft in waterlogged areas according to claim 7, characterized in that: The process of pumping out the accumulated water in the sump through the pumping pipe is to place the pumping pump into the steel cage along the cavity of the seamless steel pipe, and start the pumping pump to pump out the water in the steel cage.
9. The waterproof construction method for deep foundation raft in waterlogged area according to claim 1, characterized in that: The process of pouring the foundation raft slab in the sump in step S5: the pouring of the foundation raft slab is completed in two steps, first pouring the lower foundation layer in the sump; performing secondary waterproofing treatment on the upper surface of the lower foundation layer to obtain a secondary waterproof layer; and pouring the upper foundation layer on the secondary waterproof layer.
10. A waterproof construction method for deep foundation raft slab in waterlogged area according to claim 9, characterized in that: The secondary waterproof layer is located in the sump, and the upper end of the upper foundation layer extends out of the ground beyond the sump.
Citation Information