Novel power transmission line iron tower pile foundation

By designing the threaded connection between spiral piles and the bearing substrate and high-pressure cement slurry injection in the tower pile foundation of the transmission line, a stable rectangular base is formed, which solves the problem of not reaching the holding layer and complex construction in the prior art, and improves the construction efficiency and support stability.

CN118911187AInactive Publication Date: 2024-11-08YUNNAN XUHENG ELECTRIC POWER EQUIPMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411309620.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The tower pile foundation of the existing transmission line cannot directly reach the predetermined holding layer, and the construction process is complex, with complex processes such as mud wall protection and hole cleaning, which affects the construction efficiency and effect.

Method used

A new type of power transmission line tower pile foundation including a bearing substrate, a construction device, a sealing device and a detection device is designed. Through the threaded connection between the spiral pile and the bearing substrate, the steel plate is driven downward, and the special cement slurry is injected into high pressure to form a solid The grouting body, combined with the spiral pile, forms a rectangular base, has strong support stability, and avoids excessive injection through temperature and pressure detection.

Benefits of technology

The auger drill rod can reach the holding layer deep underground, reduce the complex process of traditional drilling piles, improve construction efficiency and effect, form a stable rectangular base, high support strength, and avoid excessive expansion and material leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911187A_ABST
    Figure CN118911187A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of power transmission line iron tower piles, and discloses a novel power transmission line iron tower pile foundation which comprises a bearing base plate, a blocking device is arranged on the surface of the bearing base plate, a construction device is arranged on the top of the bearing base plate, and a detection device is arranged on the surface of the blocking device. According to the novel power transmission line iron tower pile foundation, the construction device is arranged, the spiral pile is aligned to the threaded groove in the bearing base plate and then screwed downwards, the reinforcing steel bar plate is driven to move downwards synchronously, specially-made cement grout is injected, the cement grout is diffused to soil around the pile under the pressure effect, a firm grouting body is formed and tightly combined with the spiral pile, and therefore the foundation is formed. According to the device, the spiral drill rod can penetrate into the ground and can directly reach a preset supporting layer, the spiral drill rod is pushed downwards while rotating, complex procedures such as mud wall protection and hole cleaning needed by a traditional cast-in-situ bored pile are reduced, and the effect is good when the device is used.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of power transmission line iron tower piles, in particular to a novel power transmission line iron tower pile foundation. Background Art

[0002] Since the foundation of the transmission tower needs to withstand large horizontal tension of the ground wire, horizontal wind load of the ground wire, and wind load on the transmission tower body, it has high requirements for horizontal bearing capacity and often needs to increase the diameter of the pile foundation, resulting in a large volume of foundation concrete. However, the downward pressure bearing capacity requirement of the transmission line tower foundation is relatively low, and does not require an overly large cross-section to meet the pile body bearing capacity requirements.

[0003] The prior art discloses a hollow pile foundation for a power transmission line tower with a publication number of CN203498854U, which solves the defects of complex construction process, large amount of concrete materials and environmental pollution compared with the prior art. The above device includes a steel cage and a cylindrical pile cast with the steel cage, and also includes a column connector, a cap and a column. The cap is arranged on the cylindrical pile, and the column is arranged on the cap. The lower part of the column connector is anchored in the column and the cap. The cylindrical pile is provided with a cavity, and the lower part of the cylindrical pile is provided with an expansion head. The above device effectively simplifies the construction difficulty, reduces the concrete consumption, and reduces the construction waste.

[0004] The above-mentioned new type of transmission line iron tower pile foundation effectively simplifies the construction difficulty, reduces the consumption of concrete, and reduces construction waste. The expanded head part at the bottom of the foundation is designed as a concrete solid structure, which expands the contact area with the base foundation and improves the downward pressure bearing capacity. The cylindrical pile is designed as a hollow structure to reduce the consumption of concrete. It has the characteristics of energy saving and environmental protection, convenient construction, and simple structure. However, the above-mentioned transmission line iron tower pile foundation does not have a rotary drill rod deep underground, and cannot directly reach the predetermined bearing layer. The spiral drill rod does not push downward while rotating. There are complex processes such as mud wall protection and hole cleaning required by traditional bored piles. The effect is not good during use, and this needs to be improved. Summary of the invention

[0005] The object of the present invention is to provide a novel transmission line iron tower pile foundation to solve the problems raised in the above background technology.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a new type of transmission line tower pile foundation, comprising a supporting base plate, a sealing device is arranged on the surface of the supporting base plate, a construction device is arranged on the top of the supporting base plate, and a detection device is arranged on the surface of the sealing device.

[0007] The construction device includes an intermediate connecting horizontal plate, a steel bar plate, a spiral pile, a bottom receiving plate, a discharge trough hole, a top supporting plate, a connecting seat, a connecting strip plate, a connecting bolt and a limiting thin plate. A threaded groove is provided inside the supporting base plate, and the threaded groove is adapted to the spiral pile. The spiral pile is threadedly connected to the inside of the supporting base plate, and the discharge trough hole is provided at the bottom end of the front side of the spiral pile. The interior of the spiral pile is hollow. The bottom receiving plate is fixedly connected to the bottom of the supporting base plate. A connecting hole body with the same aperture as the threaded groove is provided inside the bottom receiving plate. The spiral pile is threadedly connected to the inside of the bottom receiving plate. The intermediate connecting horizontal plate is fixedly connected to the top surface of the spiral pile. The steel bar plate is fixedly connected to the side of the intermediate connecting horizontal plate. The connecting seat is fixedly connected to the top of the steel bar plate. The limiting thin plate is fixedly connected to the top of the supporting base plate.

[0008] Preferably, the blocking device includes a connecting frame, a mounting seat, a mounting bolt and a blocking rectangular plate, the connecting frame is fixedly connected to the front side of the supporting substrate, the mounting seat is slidably connected to the surface of the connecting frame, and the mounting bolt is threadedly connected to the inside of the connecting frame.

[0009] Preferably, the detection device includes a temperature detection device, a temperature conduction plate and a pressure detection sensor, the temperature detection device is fixedly connected to the front side of the sealing rectangular plate, and the temperature conduction plate is fixedly connected to the front side of the sealing rectangular plate.

[0010] Preferably, a connecting screw hole is provided inside the connecting strip, and a threaded slot hole having a hole diameter equal to that of the connecting screw hole is provided inside the top end supporting plate.

[0011] Preferably, the connecting bolts are threadedly connected to the inside of the connecting seat, the connecting strips and the top support plate. The connecting bolts are used to install the connecting seat, the connecting strips and the top support plate. Installing the top support plate inside the installing connecting seat serves to increase the supporting area.

[0012] Preferably, the top support plate is inserted into the interior of the connecting seat, and the connecting strip is fixedly connected to the top of the connecting seat.

[0013] Preferably, the right side of the temperature detection device is connected to the left side of the temperature conducting plate, and the pressure detection sensor is fixedly connected to the front side of the sealing rectangular plate.

[0014] Preferably, the mounting bolts are threadedly connected to the inside of the mounting seat, and the blocking rectangular plate is fixedly connected to the side of the mounting seat. The installation of the front mounting seat and the blocking rectangular plate can be completed by screwing in the mounting bolts. The mounting seats and blocking rectangular plates on the four sides are installed to form a rectangular frame. Special cement slurry is injected under high pressure and dried to form a rectangular base, which has strong support stability.

[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. The new transmission line iron tower pile foundation is provided with a construction device. The spiral pile is aligned with the threaded groove inside the bearing base plate and then twisted downward, driving the steel plate to move downward synchronously, and continuously moving to the limit thin plate on the top of the bearing base plate, and then stopping when it cannot be turned over further. At this time, the spiral pile is extended into the ground, and then a special cement slurry is injected by high pressure. The cement slurry diffuses to the soil around the pile under pressure to form a solid grouting body, which is tightly combined with the spiral pile to jointly bear the load of the upper iron tower. Due to the formation of the above-mentioned rectangular frame, a rectangular base is finally formed, and the support has strong stability, so that the device can set the rotary drill rod deep into the ground, which can directly reach the predetermined bearing layer. The spiral drill rod is pushed downward while rotating, reducing the complex processes such as mud wall protection and hole cleaning required for traditional bored piles, and the effect is good when used.

[0016] 2. The new transmission line tower pile foundation is equipped with a blocking device. Four mounting seats and the side blocking rectangular plates are first installed, and a rectangular frame is formed with the connecting frame. When a special cement slurry is injected into the mounting bolts under high pressure, a rectangular base can be finally formed. The supporting strength is high and it is suitable for use with construction equipment.

[0017] 3. The new transmission line tower pile foundation is equipped with a detection device, which uses a temperature detection device and a temperature conductive plate to detect the temperature, and uses a pressure detection sensor to detect the internal pressure. When the pressure setting value is detected, the feeding is stopped. At this time, the bottom has been injected, avoiding the tilting and leakage of the sealing rectangular plate caused by excessive injection and expansion. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall three-dimensional bottom-up structure of the present invention; Figure 2 For the present invention Figure 1 The enlarged structural diagram at A in the middle; Figure 3 It is a schematic diagram of the overall three-dimensional front view structure of the present invention; Figure 4 For the present invention Figure 3 The enlarged structural diagram at B in the middle; Figure 5 It is a schematic diagram of the overall three-dimensional side structure of the present invention.

[0019] In the figure: 1. supporting substrate; 2. blocking device; 201. connecting frame; 202. mounting seat; 203. mounting bolts; 204. blocking rectangular plate; 3. construction device; 301. middle connecting horizontal plate; 302. steel plate; 303. screw pile; 304. bottom receiving plate; 305. discharge slot hole; 306. top supporting plate; 307. connecting seat; 308. connecting strip; 309. connecting bolts; 310. limiting thin plate; 4. detection device; 401. temperature detection device; 402. temperature conducting plate; 403. pressure detection sensor. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0021] See also Figure 1-5 , the present invention provides the following technical solutions: A novel transmission line iron tower pile foundation comprises a bearing base plate 1, a sealing device 2 is arranged on the surface of the bearing base plate 1, a construction device 3 is arranged on the top of the bearing base plate 1, and a detection device 4 is arranged on the surface of the sealing device 2.

[0022] The construction device 3 includes an intermediate connecting horizontal plate 301, a steel bar plate 302, a screw pile 303, a bottom receiving plate 304, a discharge slot hole 305, a top supporting plate 306, a connecting seat 307, a connecting strip plate 308, a connecting bolt 309 and a limiting thin plate 310. A threaded groove is provided inside the supporting base plate 1, and the threaded groove is adapted to the screw pile 303. The screw pile 303 is threadedly connected to the inside of the supporting base plate 1. The discharge slot hole 305 is provided at the bottom end of the front side of the screw pile 303. The interior of the screw pile 303 is hollow. The bottom receiving plate 304 is fixedly connected to the bottom of the supporting base plate 1. A connecting hole body with the same aperture as the threaded groove is provided inside the bottom receiving plate 304. The screw pile 303 is threadedly connected to the inside of the bottom receiving plate 304. The intermediate connecting horizontal plate 301 is fixedly connected to the top of the surface of the screw pile 303. The steel plate 302 is fixedly connected to the side of the middle connecting cross plate 301, the connecting seat 307 is fixedly connected to the top of the steel plate 302, the limiting thin plate 310 is fixedly connected to the top of the supporting base plate 1, the connecting strip 308 is provided with a connecting screw hole, the top supporting plate 306 is provided with a threaded slot hole with the same aperture as the connecting screw hole, the connecting bolt 309 is threadedly connected to the inside of the connecting seat 307, the connecting strip 308 and the top supporting plate 306, the setting of the connecting bolt 309 is used to install the connecting seat 307, the connecting strip 308 and the top supporting plate 306, and the top supporting plate 306 is installed inside the installing connecting seat 307 to increase the supporting area, the top supporting plate 306 is inserted into the inside of the connecting seat 307, and the connecting strip 308 is fixedly connected to the top of the connecting seat 307.

[0023] The blocking device 2 includes a connecting frame 201, a mounting seat 202, a mounting bolt 203 and a blocking rectangular plate 204. The connecting frame 201 is fixedly connected to the front of the supporting substrate 1, the mounting seat 202 is slidably connected to the surface of the connecting frame 201, the mounting bolt 203 is threadedly connected to the inside of the connecting frame 201, the mounting bolt 203 is threadedly connected to the inside of the mounting seat 202, and the blocking rectangular plate 204 is fixedly connected to the side of the mounting seat 202. The mounting seat 202 and the blocking rectangular plate 204 on the front can be installed by screwing in the mounting bolt 203. The mounting seats 202 and the blocking rectangular plate 204 on the four sides are installed to form a rectangular frame. High-pressure injection of special cement slurry is dried to form a rectangular base, and the support has strong stability.

[0024] The detection device 4 includes a temperature detection device 401, a heat conducting plate 402 and a pressure detection sensor 403. The temperature detection device 401 is fixedly connected to the front side of the sealing rectangular plate 204, the heat conducting plate 402 is fixedly connected to the front side of the sealing rectangular plate 204, the right side of the temperature detection device 401 is connected to the left side of the heat conducting plate 402, and the pressure detection sensor 403 is fixedly connected to the front side of the sealing rectangular plate 204.

[0025] When in use, it is necessary to first install the four mounting seats 202 and the side blocking rectangular plates 204, and cooperate with the connecting frame 201 to form a rectangular frame. When the special cement slurry is injected into the mounting bolts 203 under high pressure, a rectangular base can be finally formed with high supporting strength. When installing, first install the front mounting seat 202. When installing, align the groove inside the mounting seat 202 with the connecting frame 201 and insert it, and slide the blocking rectangular plate 204 backward against the side of the connecting frame 201 until the screw hole inside the connecting frame 201 is aligned with the screw hole inside the mounting seat 202. Then screw the mounting bolts 203 in to complete the installation of the front mounting seat 202 and the blocking rectangular plate 204. The blocking rectangular plates 204 on the four sides are installed in the same way to form a rectangular frame, which is convenient for the subsequent injection of cement slurry. Then the screw pile 303 can be aligned with the threaded groove inside the supporting substrate 1 and then screwed downward to drive the steel The rib plate 302 moves downward synchronously, and continues to move to the limiting thin plate 310 on the top of the supporting substrate 1, and then stops when it can no longer flip. At this time, the spiral pile 303 extends into the ground, and then the special cement slurry is injected under high pressure through the spiral pile 303. The cement slurry diffuses to the soil around the pile under pressure to form a solid grouting body, which is tightly combined with the spiral pile 303 to jointly bear the load of the upper iron tower. Due to the formation of the above-mentioned rectangular frame, it finally dries to form a rectangular base with strong support stability, and the cement slurry will contact the side of the sealing rectangular plate 204 close to the inner wall. The temperature is detected by the temperature detection device 401 and the heat conducting plate 402, and the internal pressure is detected by the pressure detection sensor 403. When the pressure setting value is detected, the feeding is stopped. At this time, the bottom has been injected, avoiding the tilting and leakage of the sealing rectangular plate 204 caused by excessive injection and expansion.

[0026] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A novel transmission line tower pile foundation, comprising a bearing base plate (1), Features: A blocking device (2) is provided on the surface of the carrier substrate (1), a construction device (3) is provided on the top of the carrier substrate (1), and a detection device (4) is provided on the surface of the blocking device (2); The construction device (3) comprises an intermediate connecting horizontal plate (301), a steel bar plate (302), a screw pile (303), a bottom receiving plate (304), a discharge slot hole (305), a top supporting plate (306), a connecting seat (307), a connecting strip plate (308), a connecting bolt (309) and a limiting thin plate (310); a thread groove is provided inside the supporting base plate (1), the thread groove is adapted to the screw pile (303); the screw pile (303) is threadedly connected to the inside of the supporting base plate (1); the discharge slot hole (305) is provided at the bottom end of the front face of the screw pile (303); The bottom receiving plate (304) is designed to be hollow inside, and is fixedly connected to the bottom of the supporting base plate (1). A connecting hole having a diameter equal to that of the thread groove is provided inside the bottom receiving plate (304). The spiral pile (303) is threadedly connected to the inside of the bottom receiving plate (304). The middle connecting horizontal plate (301) is fixedly connected to the top of the surface of the spiral pile (303). The steel bar plate (302) is fixedly connected to the side of the middle connecting horizontal plate (301). The connecting seat (307) is fixedly connected to the top of the steel bar plate (302). The limiting thin plate (310) is fixedly connected to the top of the supporting base plate (1).

2. A new type of transmission line tower pile foundation according to claim 1, Features: The blocking device (2) comprises a connecting frame (201), a mounting seat (202), a mounting bolt (203) and a blocking rectangular plate (204); the connecting frame (201) is fixedly connected to the front surface of the supporting substrate (1); the mounting seat (202) is slidably connected to the surface of the connecting frame (201); and the mounting bolt (203) is threadedly connected to the inside of the connecting frame (201).

3. A new type of transmission line tower pile foundation according to claim 2, Features: The detection device (4) comprises a temperature detection device (401), a thermal conductive plate (402) and a pressure detection sensor (403); the temperature detection device (401) is fixedly connected to the front side of the blocking rectangular plate (204); and the thermal conductive plate (402) is fixedly connected to the front side of the blocking rectangular plate (204).

4. A new type of transmission line tower pile foundation according to claim 3, Features: A connecting screw hole is provided inside the connecting strip plate (308), and a threaded slot hole having a hole diameter equal to that of the connecting screw hole is provided inside the top end supporting plate (306).

5. A new type of transmission line tower pile foundation according to claim 4, Features: The connecting bolt (309) is threadedly connected to the inside of the connecting seat (307), the connecting strip (308) and the top end supporting plate (306).

6. A new type of transmission line tower pile foundation according to claim 5, Features: The top end support plate (306) is inserted into the interior of the connection seat (307), and the connection strip plate (308) is fixedly connected to the top of the connection seat (307).

7. A new type of transmission line tower pile foundation according to claim 6, Features: The right side of the temperature detection device (401) is connected to the left side of the temperature conducting plate (402), and the pressure detection sensor (403) is fixedly connected to the front side of the blocking rectangular plate (204).

8. A new type of transmission line tower pile foundation according to claim 7, Features: The mounting bolt (203) is threadedly connected to the interior of the mounting seat (202), and the blocking rectangular plate (204) is fixedly connected to the side of the mounting seat (202).