Vierendeel truss type superposed beam with pipeline hole
Through the fasting truss-type overlapping beam designed with inverted T-shaped structure, the problem that prefabricated overlapping beams in the prior art cannot provide temporary support is solved, and construction simplification and equipment pipeline layout are achieved, and construction efficiency and safety are improved. .
Patent Information
- Application Number
- CN202411297707.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-11-08
AI Technical Summary
The prefabricated overlapping beams of existing prefabricated garages are usually rectangular or have no ears, and cannot provide temporary support for secondary beams and floor slabs, resulting in inconvenience during construction, and openings on the beams weaken the overall stiffness and inconvenient equipment pipeline layout. .
Fastening truss-type overlapping beams designed with inverted T-shaped structures, with lifting ears at the flange for placing prefabricated overlapping plates, providing temporary support, and openings for passing through the equipment pipelines on the beams to simplify construction and improve construction. The stiffness of the beam.
Through the inverted T-shaped structure design, temporary support is provided to simplify construction, avoiding the crossing of steel bars at beam and column nodes, improving construction efficiency and safety. The equipment pipeline can utilize holes, reducing the impact on the net height of the beam bottom.
Smart Images

Figure CN118911347A_ABST
Abstract
Description
Technical Field
[0001] The invention discloses an assembled building structure, in particular to a hollow truss type composite beam with pipeline openings, belonging to the technical field of building engineering. Background Art
[0002] A prefabricated garage is a prefabricated building structure that is usually assembled on site from prefabricated components. This type of garage is usually made of steel, concrete or other durable materials. The advantages of prefabricated garages include fast construction speed, relatively low cost, easy quality control, and high flexibility. In the construction process of a prefabricated garage, design and manufacturing work are usually carried out first, and then the prefabricated components are transported to the site, and then assembled and installed by a professional construction team. Compared with traditional on-site construction, this construction method can greatly shorten the construction period and reduce the chaos and waste on the construction site. In addition, prefabricated garages can be disassembled and reassembled at a later stage, and have a certain degree of portability and reusability.
[0003] Prefabricated garages in the prior art are usually assembled from columns, beams and composite slabs. Conventional prefabricated composite beams are usually rectangular in design, with the same width as the cast-in-place part, or without ears. Temporary supports cannot be provided for secondary beams and floor slabs during the construction phase, causing many inconveniences in the construction of prefabricated garages. Conventional frame main beams are cast-in-place, with low strength of steel bars and concrete. If holes are opened on the beams, the overall stiffness of the beams will be greatly weakened, resulting in large requirements for the calculated cross-section of the beams and uncontrollable measures for strengthening the holes. If the holes on the beams are not considered, the equipment pipelines must go through the bottom of the beams. If holes are opened on the composite beams, the material strength is controlled by factory batch production, and the equipment pipelines can use the holes on the beams for layout. Summary of the invention
[0004] In view of the shortcomings of the above-mentioned prior art that the prefabricated composite beams adopt a rectangular design or have no cantilevers, and cannot provide temporary supports for secondary beams and floor slabs, the present invention provides a hollow truss composite beam with pipeline openings, which adopts an inverted T-shaped structure design and has cantilevers at the flanges. The prefabricated composite panels can be placed on the flange cantilevers to provide temporary supports for the composite panels during the construction phase.
[0005] The technical solution adopted by the present invention to solve its technical problems is: a hollow truss type composite beam with a pipeline opening, the composite beam comprising a precast lower chord of the composite beam, a cast-in-place upper chord of the composite beam and a cast-in-place vertical web member of the composite beam, the cast-in-place vertical web members of the composite beam and the cast-in-place upper chord of the composite beam are formed on the precast lower chord of the composite beam by a cast-in-place process, the precast lower chord of the composite beam, the cast-in-place vertical web members of the composite beam and the cast-in-place upper chord of the composite beam together constitute a hollow truss type composite beam, and the hollow position of the hollow truss type composite beam is provided with an opening for passing the equipment pipeline.
[0006] The technical solution adopted by the present invention to solve the technical problem further includes: The prefabricated lower chord of the composite beam includes a prefabricated lower chord body, top exposed steel bars, a steel cage, four corner steel bars, side exposed steel bars, top reinforcing steel bars and bottom reinforcing steel bars. The steel cage and the four corner steel bars are tied together to form a supporting body. Concrete is poured in the supporting body to form a prefabricated lower chord body. The top exposed steel bars are arranged in the prefabricated lower chord body, and part of them extend to the outside of the top of the prefabricated lower chord body. The top surface of the prefabricated lower chord body corresponds to two sides of the top exposed steel bars to form a cantilever ear respectively. The side exposed steel bars, the top reinforcing steel bars and the bottom reinforcing steel bars are all arranged parallel to the length direction of the prefabricated lower chord body. The side exposed steel bars and the bottom reinforcing steel bars are arranged at the bottom of the inner side of the steel cage, and the top reinforcing steel bars are arranged at the top of the inner side of the steel cage.
[0007] The prefabricated lower chord of the composite beam also includes middle reinforcing steel bars, which are arranged at the middle position inside the steel cage.
[0008] The intermediate reinforcing steel bars are arranged in more than one row, with more than one steel bar in each row.
[0009] The prefabricated lower chord body has a width of more than 200 mm and a height of more than 250 mm.
[0010] The steel cage is surrounded by a rectangular structure, and four steel bars are arranged at four corners, respectively corresponding to the four corners of the steel cage.
[0011] There are four exposed top steel bars and four top reinforcing steel bars, and the top reinforcing steel bars are arranged correspondingly to the exposed top steel bars.
[0012] There are four exposed side steel bars and one to four bottom reinforcing steel bars. The exposed side steel bars are arranged at positions corresponding to the top reinforcing steel bars, and the bottom reinforcing steel bars are arranged between adjacent exposed side steel bars. One or two bottom reinforcing steel bars are arranged between the exposed side steel bars, or no bottom reinforcing steel bars are arranged.
[0013] A keyway is provided in the middle of the end surface of the prefabricated lower chord body.
[0014] The keyway width is not less than 1 / 2 of the prefabricated part of the composite beam, and the keyway height is not less than 1 / 2 of the prefabricated part of the composite beam.
[0015] The beneficial effects of the present invention are as follows: the present invention adopts an inverted T-shaped structural design, and a lug is provided at the flange, on which the prefabricated composite plate can be placed, providing a temporary support for the composite plate during the construction phase. The present invention only needs to consider the prefabrication of the frame beam in the main force direction, avoiding the crossing of steel bars at the beam-column node, and simplifying the construction.
[0016] The present invention will be further described below in conjunction with the accompanying drawings and specific implementation methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a schematic diagram of the side structure of the prefabricated lower chord main body in the present invention.
[0018] Figure 2 It is a schematic cross-sectional structure diagram of a first embodiment of the prefabricated lower chord main body in the non-civil air defense area of the present invention.
[0019] Figure 3 This is a schematic cross-sectional structure diagram of a second embodiment of the prefabricated lower chord main body in a non-civil air defense area of the present invention.
[0020] Figure 4 It is a schematic cross-sectional structure diagram of the third embodiment of the prefabricated lower chord main body in the non-civil air defense area of the present invention.
[0021] Figure 5 It is a schematic diagram of the cross-sectional structure of the opening position of the prefabricated lower chord main body in the non-civil air defense area of the present invention.
[0022] Figure 6 This is a schematic diagram of the cross-sectional structure of the prefabricated lower chord main body in the non-civil air defense area of the present invention where no hole is opened.
[0023] Figure 7 This is a schematic diagram of the front view structure of the prefabricated lower chord main body in the non-civil defense area of the present invention.
[0024] Figure 8 It is a schematic cross-sectional structure diagram of a first embodiment of the prefabricated lower chord main body in the civil air defense area of the present invention.
[0025] Fig. 9 This is a schematic cross-sectional structure diagram of a second embodiment of the prefabricated lower chord main body in the civil air defense area of the present invention.
[0026] Fig.10 It is a schematic diagram of the cross-sectional structure of the opening position of the prefabricated lower chord main body in the civil air defense area of the present invention.
[0027] Fig.11 This is a schematic diagram of the cross-sectional structure of the prefabricated lower chord main body in the civil air defense area in the present invention at the position where the hole is not opened.
[0028] Fig.12 This is a schematic diagram of the front view structure of the prefabricated lower chord main body in the civil air defense area of the present invention.
[0029] Fig.13 It is a schematic diagram of the composite beam structure in the present invention.
[0030] In the figure, 1-precast lower chord body, 2-exposed steel bars on the top, 3-cantilever ears, 4-key slots, 5-exposed steel bars on the side, 6-steel cage, 7-corner steel bars, 8-middle reinforcing steel bars, 9-top reinforcing steel bars, 10-bottom reinforcing steel bars, 11-opening, 12-frame columns, 13-precast lower chord of composite beam, 14-cast-in-place upper chord of composite beam, 15-cast-in-place vertical web members of composite beam. DETAILED DESCRIPTION
[0031] This embodiment is a preferred implementation mode of the present invention. Other embodiments whose principles and basic structures are the same or similar to those of this embodiment are within the protection scope of the present invention.
[0032] Please refer to the attached Figure 1 To Attachment Fig.12 The present invention mainly protects a hollow truss type composite beam with a pipeline opening, the composite beam comprises a precast lower chord 13 of the composite beam, a cast-in-place upper chord 14 of the composite beam and a cast-in-place vertical web member 15 of the composite beam, the cast-in-place vertical web member 15 of the composite beam and the cast-in-place upper chord 14 of the composite beam are formed on the precast lower chord 13 of the composite beam by a cast-in-place process, the precast lower chord 13 of the composite beam, the cast-in-place vertical web member 15 of the composite beam and the cast-in-place upper chord 14 of the composite beam together constitute a hollow truss type composite beam, and an opening 11 for passing equipment pipelines is provided at the hollow position of the hollow truss type composite beam.
[0033] In this embodiment, the prefabricated lower chord of the composite beam mainly includes a prefabricated lower chord body 1, top exposed steel bars 2, a steel cage 6, four corner steel bars 7, side exposed steel bars 5, middle reinforcing steel bars 8, top reinforcing steel bars 9 and bottom reinforcing steel bars 10. The steel cage 6 and the four corner steel bars 7 are tied together to form a supporting body of the prefabricated lower chord of the composite beam in the present invention. Concrete is poured in the supporting body to form a prefabricated lower chord body 1. The top exposed steel bars 2 are arranged in the prefabricated lower chord body 1, and part of them extend to the outside of the top of the prefabricated lower chord body 1. A cantilever 3 is formed on both sides of the top surface of the prefabricated lower chord body 1 corresponding to the top exposed steel bars 2, which is used to place the prefabricated composite plate. In this embodiment, the cantilever 3 should be interpreted in a broad sense, except for the ones shown in this embodiment. In addition to the conventional cantilever structure, other side protruding structures can also be used. As long as they can be used to place and support the structure of the prefabricated plate, they should be understood as the cantilever structure in the present invention. The side exposed steel bars 5, the middle reinforcing steel bars 8, the top reinforcing steel bars 9 and the bottom reinforcing steel bars 10 are all arranged parallel to the length direction of the prefabricated lower chord body 1. The side exposed steel bars 5 and the bottom reinforcing steel bars 10 are arranged at the bottom of the inner side of the steel cage 6, the middle reinforcing steel bars 8 are arranged in the middle position of the inner side of the steel cage 6, and the top reinforcing steel bars 9 are arranged at the top of the inner side of the steel cage 6. The prefabricated lower chord body 1 is provided with more than one opening 11, which can be used for running air ducts and water and electricity pipelines, etc. The prefabricated composite beam in the present invention adopts an inverted T-shaped structure design, and the cantilever 3 of the flange can be used to place prefabricated composite plates.
[0034] In this embodiment, the width of the prefabricated lower chord main body 1 is more than 200mm. In this embodiment, it is preferably 650mm~850mm. The height is more than 250mm. In this embodiment, it is preferably 300~550mm. It can be determined according to needs. When it is used in non-civil defense areas, its width can be 800mm. When it is used in civil defense areas, its width can be 850mm. The height is preferably 450mm. If an opening 11 is opened at the corresponding position, the height of the corresponding position is preferably 350mm, that is, the opening 11 is opened on the prefabricated lower chord main body 1 with a height of 100mm.
[0035] In this embodiment, the maximum structural dimensions of the opening 11 are 1600 mm in length and 400 mm in height, which can fully meet the requirements for the passage of general water, electricity, and equipment pipelines. The main cross beams on the upper and lower sides of the opening 11 have at least a 350 mm thick concrete layer to ensure the strength of the composite beam body at the opening 11.
[0036] In this embodiment, the steel cage 6 is surrounded by a rectangular structure, and four corner steel bars 7 are provided, which are respectively provided at the four corners of the steel cage 6. The four corner steel bars 7 are preferably φ12 steel bars, that is, the diameter of the four corner steel bars 7 is preferably 12 mm.
[0037] In this embodiment, four exposed top steel bars 2 are provided, and four top reinforcing steel bars 9 are also provided. The top reinforcing steel bars 9 are provided corresponding to the exposed top steel bars 2. The top reinforcing steel bars 9 are preferably φ16 steel bars, that is, the diameter of the top reinforcing steel bars 9 is preferably 16 mm.
[0038] In the present embodiment, more than one row of intermediate reinforcing steel bars 8 are arranged, with more than one steel bar in each row. In the present embodiment, fifteen to twenty-seven intermediate reinforcing steel bars 8 can be arranged according to actual needs. Preferably, three rows are arranged, with five to nine steel bars in each row according to actual needs. The intermediate reinforcing steel bars 8 are preferably φ12.7 steel bars, that is, the diameter of the intermediate reinforcing steel bars 8 is preferably 12.7 mm.
[0039] In this embodiment, four side exposed steel bars 5 are provided, and one to four bottom reinforcing steel bars 10 are provided. The side exposed steel bars 5 are provided at positions corresponding to the top reinforcing steel bars 9, and the bottom reinforcing steel bars 10 are provided between adjacent side exposed steel bars 5. One or two bottom reinforcing steel bars 10 may be provided between the side exposed steel bars 5, or none may be provided. In this embodiment, the side exposed steel bars 5 and the bottom reinforcing steel bars 10 are preferably steel bars of φ25, that is, the diameters of the side exposed steel bars 5 and the bottom reinforcing steel bars 10 are preferably 25 mm.
[0040] In this embodiment, a key groove 4 is opened in the middle position of the end surface of the prefabricated lower chord body 1. The width of the key groove 4 is not less than 1 / 2 of the prefabricated part of the composite beam, and the height is not less than 1 / 2 of the prefabricated part of the composite beam. In this embodiment, the key groove 4 is preferably 450mm wide and 140mm high.
[0041] When the present invention is used, after the prefabricated lower chord body 1 is hoisted to the top of the prefabricated column in place on site (usually overlapped on the prefabricated column body or the corbel of the prefabricated column body or other supporting structures of the prefabricated column body), the bottom reinforcements of the continuous beam are welded to each other, and the trough plate is hoisted to the ear 3 of the prefabricated lower chord body, the next step of the construction of the cast-in-place reinforced concrete of the beam and slab can be carried out. The composite beam prefabricated lower chord is formed with a composite beam cast-in-place upper chord through a cast-in-place process. The composite beam prefabricated lower chord and the composite beam cast-in-place upper chord together constitute the composite beam body, and the composite beam body is provided with a hole 11 for passing equipment pipelines. There is no need to support the formwork for the beam and slab construction. The prefabricated prefabricated lower chord body 1 can be temporarily supported on the corbel of the prefabricated column, and the prefabricated trough plate can be temporarily supported on the ear 3 of the prefabricated prefabricated lower chord body 1. The on-site installation is relatively efficient. The sealed grooved plate is directly supported on the precast lower chord body 1 and serves as the side formwork of the composite beam, reducing the process of installing the formwork. The precast part of the precast lower chord body 1 is reserved for steel bars to be poured in situ concrete.
[0042] The present invention adopts an inverted T-shaped structural design, and a lug is provided at the flange. The precast panel can be placed on the lug of the flange to provide a temporary support for the precast panel during the construction phase. The present invention only needs to consider the prefabrication of the frame beam in the main force direction to avoid the crossing of steel bars at the beam-column node, thereby simplifying the construction. The equipment pipelines can utilize the openings to reduce the impact of the pipelines on the net height of the bottom of the beam, and the consistency of the opening position can ensure the safety of the beam. The present invention manufactures the bottom concrete of the prefabricated lower chord body 1 and the related main force-bearing steel bars and the opening reinforcement bars in a standardized manner in the factory. After the trough plate is hoisted on site, only the inner template of the opening and the force-bearing bars on the top of the beam need to be set to complete the concrete pouring.
Claims
1. A hollow truss composite beam with pipeline openings, Its characteristics are: The composite beam comprises a prefabricated lower chord (13) of the composite beam, a cast-in-place upper chord (14) of the composite beam and a cast-in-place vertical web member (15) of the composite beam. The cast-in-place vertical web members (15) of the composite beam and the cast-in-place upper chord (14) of the composite beam are formed on the prefabricated lower chord (13) of the composite beam by a cast-in-place process. The prefabricated lower chord (13) of the composite beam, the cast-in-place vertical web members (15) of the composite beam and the cast-in-place upper chord (14) of the composite beam together constitute a hollow truss composite beam. The hollow position of the hollow truss composite beam is provided with a hole (11) for passing equipment pipelines.
2. The hollow truss composite beam with pipeline openings according to claim 1, Its characteristics are: The composite beam prefabricated lower chord comprises a prefabricated lower chord body (1), top exposed steel bars (2), a steel cage (6), four corner steel bars (7), side exposed steel bars (5), top reinforcing steel bars (9) and bottom reinforcing steel bars (10). The steel cage (6) and the four corner steel bars (7) are tied together to form a supporting body. Concrete is poured in the supporting body to form a prefabricated lower chord body (1). The top exposed steel bars (2) are arranged in the prefabricated lower chord body (1) and partially extend outward from the top of the prefabricated lower chord body (1). A cantilever (3) is formed on the top surface of the prefabricated lower chord body (1) corresponding to both sides of the top exposed steel bars (2). The side exposed steel bars (5), the top reinforcing steel bars (9) and the bottom reinforcing steel bars (10) are all arranged parallel to the length direction of the prefabricated lower chord body (1). The side exposed steel bars (5) and the bottom reinforcing steel bars (10) are arranged at the inner bottom of the steel cage (6), and the top reinforcing steel bars (9) are arranged at the inner top of the steel cage (6).
3. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: The prefabricated lower chord of the composite beam further comprises an intermediate reinforcing steel bar (8), wherein the intermediate reinforcing steel bar (8) is arranged at a middle position inside the steel cage (6).
4. The hollow truss composite beam with pipeline openings according to claim 3, Its characteristics are: The intermediate reinforcing steel bars (8) are arranged in more than one row, with more than one steel bar in each row.
5. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: The prefabricated lower chord body (1) has a width of more than 200 mm and a height of more than 250 mm.
6. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: The steel cage (6) is surrounded by a rectangular structure, and four steel bars (7) are provided at four corners, which are respectively provided at positions corresponding to the four corners of the steel cage (6).
7. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: There are four top exposed steel bars (2) and four top reinforcing steel bars (9), and the top reinforcing steel bars (9) are arranged corresponding to the top exposed steel bars (2).
8. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: Four side exposed steel bars (5) are provided, and one to four bottom reinforcing steel bars (10) are provided. The side exposed steel bars (5) are provided at positions corresponding to the top reinforcing steel bars (9), and the bottom reinforcing steel bars (10) are provided between adjacent side exposed steel bars (5). One or two bottom reinforcing steel bars (10) are provided between the side exposed steel bars (5), or no bottom reinforcing steel bars (10) are provided.
9. The hollow truss composite beam with pipeline openings according to claim 2, Its characteristics are: A key groove (4) is provided in the middle of the end surface of the prefabricated lower chord body (1).
10. The hollow truss composite beam with pipeline openings according to claim 9, Its characteristics are: The keyway (4) has a width not less than 1 / 2 of the prefabricated portion of the composite beam, and a height not less than 1 / 2 of the prefabricated portion of the composite beam.