Top coal caving working face entry retaining floor heave gangue treatment method

By combining a conveyor and a waste rock dumper, the bottom bulging waste rock is directly transported to the goaf area, solving the soil pollution and roadway impact caused by the treatment of bottom bulging waste rock after leaving the goaf, and realizing an environmentally friendly and efficient treatment process.

CN118911699APending Publication Date: 2024-11-08HUATING COAL GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411058425.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The treatment of gangue at the bottom of the roadway after leaving the roadway open causes soil pollution and affects the use of the roadway. Traditional treatment methods are complicated and the gangue has low strength, making them difficult to treat effectively.

Method used

By using a combination of conveyors and dumpers, the bottom gangue is transported directly to the goaf, simplifying the processing and avoiding surface accumulation.

Benefits of technology

It achieves environmentally friendly treatment of bottom gangue, simplifies the treatment process, avoids surface pollution, and meets the new demands of energy development.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911699A_ABST
    Figure CN118911699A_ABST
Patent Text Reader

Abstract

The invention discloses a top coal caving working face entry retaining floor heave gangue treatment method, which is characterized in that floor heave gangue is discharged to a goaf beside a gob-side entry retaining roadway of a goaf, the gangue does not need to be lifted up to a well, the floor heave gangue does not need to be made into concrete slurry or a mixture and then is filled, and the floor heave gangue does not need to be lifted up to the well, is not discharged and does not need to be slurried. The disposal process is simplified.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of gangue treatment in gob-side lane retaining of coal mines, and in particular relates to a method for treating bulging gangue at the bottom of a lane retaining in a top coal caving working face. Background Art

[0002] The application of tunneling along the goaf of fully mechanized caving working faces is becoming more and more mature in China. When the working face is excavated, it is generally excavated along the bottom plate or a small amount of bottom coal is left. After the tunnel is left, under the action of mine pressure, the tunnel will have different degrees of floor heave. For mines with poor geological conditions, the amount of floor heave is even greater after the tunnel is left along the goaf, and the amount of floor heave can reach more than 1m, seriously affecting the normal use of the tunnel. In terms of the problem of floor heave, most mines still use traditional methods to transport the bottom heave gangue out of the mine. As solid waste generated in the process of tunneling along the goaf, the gangue accumulates on the surface, which will not only cause great damage to the soil environment such as soil erosion, surface subsidence, and land desertification, but also cause dust and air pollution. Some scientific and technological workers also believe that the bottom swell gangue can be crushed and then added with cement and other fine aggregates and water to make a concrete mixture as the filling material for the flexible formwork wall beside the roadway, but this will add multiple processes. At the same time, the bottom swell gangue itself has low strength and generally contains a large amount of mud, so the strength of the concrete mixture is low. Therefore, in order to solve the problem of handling the bottom swell gangue in the goaf-retained roadway, the bottom swell gangue can be filled into the goaf of the goaf. Summary of the invention

[0003] The purpose of the present invention is to provide a method for treating swollen gangue at the bottom of a roadway retained in a top coal caving working face, which is used for treating swollen gangue at the bottom of a roadway retained in a top coal caving working face.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is: a method for treating bulging gangue at the bottom of a roadway in a top coal caving working face, which is specifically implemented according to the following steps:

[0005] Step 1: Install a conveyor in the floor heave section of the gob-side tunnel, dig up the floor heave section, load the floor heave gangue into the conveyor, and then transfer it to the scraper conveyor at the rear of the fully mechanized caving working face;

[0006] Step 2, lift the head area of ​​the scraper conveyor, and use a bottom-discharging scraper trough as the scraper trough provided in the area, and set an openable and closable discharge port in the scraper trough.

[0007] Step 3: Arrange a rock dumper between the tunnel retaining wall and the rock retaining support, and the feeding port of the rock dumper is located below the discharging port of the scraper conveyor.

[0008] Step 4: The bottom swelled gangue falls through the discharge port of the scraper conveyor to the feeding port of the dumping machine below.

[0009] Step 5: Throw the bottom bulge gangue into the goaf between the tunnel wall and the end of the gangue retaining support through the gangue thrower.

[0010] Step 6. After the waste rock dumping is completed, move the conveyor and waste rock dumper as the working face advances, and repeat steps 1 to 5.

[0011] As a preferred technical solution of the present invention, step 2 is replaced by lifting the tail area of ​​the scraper conveyor and adopting a bottom-discharging scraper trough as the scraper trough arranged in this area.

[0012] As a preferred technical solution of the present invention, the conveyor can be a belt conveyor or a scraper conveyor.

[0013] As a preferred technical solution of the present invention, the gangue thrower is a small-sized gangue thrower.

[0014] As a preferred technical solution of the present invention, the feed port of the gangue thrower is lower than the discharge port thereof.

[0015] The beneficial effects of the present invention are as follows: a method for treating swollen bottom gangue in a retained lane of a top coal caving working face of the present invention piles up gangue along the boundary between the retained lane wall and the goaf, removes the swollen bottom gangue in the retained lane, and does not discharge the gangue to the surface; a conveyor is used to transport the gangue to the goaf through a scraper conveyor at the rear of the fully-mechanized caving working face and a gangue thrower, thereby providing a new method for treating swollen bottom gangue in a retained lane of a top coal caving working face. Compared with the traditional method for cleaning bottom bulging gangue, the method of the present invention does not need to lift the gangue to the well for treatment, and does not need to make the bottom bulging gangue into concrete slurry or mixed material for filling treatment. It simplifies the disposal process, makes the treatment of bottom bulging gangue in the lane left in the top coal caving working face more environmentally friendly, meets the new needs of my country's energy development and reform, and can be widely used in the field of treatment of bottom bulging gangue in the lane left in the top coal caving working face. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0017] Figure 1 It is a schematic plan view of a method for treating swollen gangue at the bottom of a roadway retained in a top coal caving working face according to the present invention.

[0018] Figure 2 It is a cross-sectional view of a method for treating swollen gangue at the bottom of a roadway retained in a top coal caving working face according to the present invention.

[0019] Figure 3 The present invention is a schematic diagram of the equipment position relationship of a method for treating bulging gangue at the bottom of a roadway retained in a top coal caving working face.

[0020] In the figure: 1. Goaf, 2. Scraper conveyor, 3. Gangue thrower, 4. Gangue retaining support, 5. Lane retaining wall, 6. Conveyor, 7. Bottom bulge, 8. Discharge port, 9. Coal mining face advancement direction, 10. Lane retaining tunnel. DETAILED DESCRIPTION

[0021] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.

[0022] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0023] Example 1

[0024] like Figure 1 As shown, a method for treating swollen gangue at the bottom of a roadway in a top coal caving working face of the present invention is specifically implemented according to the following steps:

[0025] Step 1, installing a conveyor 6 in the floor heave section of the gob-side tunnel 10, excavating the floor heave section, loading the floor heave gangue 7 into the conveyor 6 and then transporting it to the scraper conveyor 2 at the rear of the fully mechanized caving working face;

[0026] Step 2, lifting the head area of ​​the scraper conveyor 2, the scraper trough provided in this area adopts a bottom-discharging scraper trough, and an openable and closable discharge port 8 is provided in the scraper trough;

[0027] Step 3, arranging a rock dumper 3 between the lane retaining wall 5 and the rock retaining support 4, wherein the feeding port of the rock dumper 3 is located below the discharging port of the scraper conveyor 2;

[0028] Step 4, the bottom swelled gangue 7 falls through the discharge port 8 of the scraper conveyor 2 to the feed port of the gangue thrower 3 below;

[0029] Step 5, throwing the bottom bulge 7 to the goaf 1 at the end of the tunnel wall 5 and the slag retaining support 4 through the slag throwing machine 3;

[0030] Step 6, after the waste rock dumping is completed, the conveyor 6 and the waste rock dumper 3 are moved forward along with the working face, and steps 1 to 5 are repeated.

[0031] Combination Figure 2 and Figure 3The present invention provides a method for treating bottom heaving gangue in a top coal caving working face. In the process of retaining a roadway in the actual fully mechanized caving along the gob, a conveyor 6 can be installed in the bottom heaving section of the roadway. The conveyor can be a belt conveyor or a scraper conveyor. The bottom heaving gangue 7 generated by the bottom heaving in the roadway 10 is transferred to the scraper conveyor 2 at the rear of the working face via the conveyor 6. The scraper conveyor 2 needs to be properly modified, its head (or tail) section is properly lifted, and the scraper trough in this area is changed to a bottom unloading type, that is, a discharging port that can be opened and closed is set on the scraper trough. When the rear scraper conveyor transports coal, the discharging port is closed, and when the gangue is transferred, the discharging port is opened. A small waste rock thrower 3 is set at the bottom of the discharge port of the rear scraper conveyor. The small waste rock thrower 3 is also located between the waste rock retaining bracket 4 and the cast flexible formwork wall. Generally, the gap is 800-1200mm, the space is sufficient, and the length of the machine body does not exceed the length of the waste rock retaining bracket. The transferred bottom heave waste rock is unloaded to the feeding port of the small waste rock thrower 3 through the discharge port 8 on the scraper trough of the rear scraper conveyor 2, and the waste rock 7 generated by the bottom heave is thrown into the goaf 1 by the small waste rock thrower 3.

[0032] Example 2

[0033] like Figures 1 to 3 As shown, a method for treating swollen gangue at the bottom of a roadway in a top coal caving working face of the present invention is specifically implemented according to the following steps:

[0034] Step 1, installing a conveyor 6 in the floor heave section of the gob-side tunnel 10, excavating the floor heave section, loading the floor heave gangue 7 into the conveyor 6 and then transporting it to the scraper conveyor 2 at the rear of the fully mechanized caving working face;

[0035] Step 2, lifting the tail area of ​​the scraper conveyor 2, the scraper trough provided in this area adopts a bottom-discharging scraper trough, and an openable and closable discharge port 8 is provided in the scraper trough;

[0036] Step 3, arranging a rock dumper 3 between the lane retaining wall 5 and the rock retaining support 4, wherein the feeding port of the rock dumper 3 is located below the discharging port of the scraper conveyor 2;

[0037] Step 4, the bottom swelled gangue 7 falls through the discharge port 8 of the scraper conveyor 2 to the feed port of the gangue thrower 3 below;

[0038] Step 5, throwing the bottom bulge 7 to the goaf 1 at the end of the tunnel wall 5 and the slag retaining support 4 through the slag throwing machine 3;

[0039] Step 6, after the waste rock dumping is completed, the conveyor 6 and the waste rock dumper 3 are moved forward along with the working face, and steps 1 to 5 are repeated.

[0040] Example 3

[0041] like Figure 2As shown, in a method for treating bottom bulging gangue in a laneway retained in a top coal caving working face of the present invention, the feed port of the gangue thrower is lower than its discharge port, so as to facilitate the transportation of the bottom bulging gangue 7.

[0042] The above description shows and describes several preferred embodiments of the invention, but as mentioned above, it should be understood that the invention is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the invention concept described herein through the above teachings or the technology or knowledge of the relevant field. Changes and modifications made by those skilled in the art should be within the scope of protection of the claims attached to the invention without departing from the spirit and scope of the invention.

Claims

1. A method for treating swollen gangue at the bottom of a roadway in a top coal caving working face, characterized in that: Follow the steps below to implement it: Step 1: Install a conveyor in the floor heave section of the gob-side tunnel, dig up the floor heave section, load the floor heave gangue into the conveyor, and then transfer it to the scraper conveyor at the rear of the fully mechanized caving working face; Step 2, lift the head area of ​​the scraper conveyor, and use a bottom-discharging scraper trough as the scraper trough provided in the area, and set an openable and closable discharge port in the scraper trough; Step 3, arranging a rock dumper between the lane retaining wall and the rock retaining support, wherein the feeding port of the rock dumper is located below the discharging port of the scraper conveyor; Step 4, the bottom swelled gangue falls through the discharge port of the scraper conveyor to the feeding port of the gangue thrower below; Step 5, throwing the bottom bulge gangue into the goaf between the tunnel wall and the end of the gangue retaining support through the gangue throwing machine; Step 6. After the waste rock dumping is completed, move the conveyor and waste rock dumper as the working face advances, and repeat steps 1 to 5.

2. The method for treating bulging gangue at the bottom of a roadway in a top coal caving working face according to claim 1, characterized in that: Step 2 is replaced by lifting the tail area of ​​the scraper conveyor and using a bottom-discharging scraper trough as the scraper trough set in this area.

3. The method for treating bulging gangue at the bottom of a roadway in a top coal caving working face according to claim 1, characterized in that: The conveyor may be a belt conveyor or a scraper conveyor.

4. The method for treating bulging gangue at the bottom of a roadway in a top coal caving working face according to claim 1, characterized in that: The slag throwing machine is a small slag throwing machine.

5. The method for treating bulging gangue at the bottom of a roadway in a top coal caving working face according to claim 4, characterized in that: The feed inlet of the gangue thrower is lower than the discharge outlet thereof.