Method for optimizing arrangement positions of temporary piers in construction period of cantilever of cable-stayed bridge

By introducing three-dimensional pneumatic admittance and vibration force coherence functions, the temporary pier layout position during the cantilever of cable-stayed bridge is optimized, which solves the problems of inaccurate vibration response calculation and insufficient optimization of temporary pier positions in the existing technology, and improves construction security.

CN118916958APending Publication Date: 2024-11-08SOUTHWEST JIAOTONG UNIV
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410956398.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

When calculating the vibration response of cable-stayed bridge cantilever construction period, the geometric characteristics and turbulent characteristics of the structure are ignored, and the temporary pier position is only optimized for the maximum double cantilever construction state, and the vibration response increases with the length of the cantilever is not considered. The situation leads to uncontrolled vibration response during construction, which poses safety hazards.

Method used

By preparing the pressure measurement model of the main beam section of the cable-stayed bridge, the three-dimensional pneumatic admittance function and shaking force coherence function were obtained, and introduced into the shaking frequency domain calculation method to calculate the shaking response with the development of the cantilever length during the construction period. Increase and change in vibration response of different temporary pier layout locations, optimize temporary pier locations to ensure their safety during the cantilever construction period.

Benefits of technology

The accuracy of vibration response calculation is improved, ensuring that the vibration response of the double cantilever construction state before the temporary pier is arranged is not greater than the maximum double cantilever construction state, and the safety of the cable-stayed bridge cantilever construction period is enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118916958A_ABST
    Figure CN118916958A_ABST
Patent Text Reader

Abstract

The invention discloses a method for optimizing the arrangement position of a temporary pier in the construction period of a cantilever of a cable-stayed bridge, and relates to bridge construction. The method comprises the following steps: S1, preparing a pressure measurement model of a main beam section of the cable-stayed bridge; s2, testing the pressure measurement model to obtain a three-dimensional pneumatic admittance function and a buffeting force coherence function of the pressure measurement model; s3, introducing the three-dimensional pneumatic admittance function and the buffeting force coherence function into a buffeting frequency domain calculation method of the cable-stayed bridge; s4, through a buffeting frequency domain calculation method, buffeting response increase of the cable-stayed bridge along with cantilever length development in the cantilever construction period and buffeting responses of different temporary pier arrangement positions in the maximum double-cantilever construction state are calculated; and S5, drawing a buffeting response increase relation curve of the cable-stayed bridge in the cantilever construction period along with the cantilever length development and a buffeting response change relation curve of the cable-stayed bridge in different temporary pier arrangement positions in the maximum double-cantilever construction state, and optimizing the optimal arrangement positions of the temporary piers. And the temporary pier arrangement position in the cable-stayed bridge cantilever construction period is more reasonable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a method for optimizing the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge. Background Art

[0002] A cable-stayed bridge is a structure in which the main beam and supporting tower are under compression and the cable is under tension. This feature gives it excellent spanning capacity and makes it one of the important bridge types for long-span bridges. The cantilever construction method is one of the main construction methods for long-span cable-stayed bridges. Since the stiffness, frequency and damping ratio of the cantilever construction period of a large-span cable-stayed bridge are all lower than those of the completed bridge, a larger flutter response is generated under the action of natural wind than that of the completed bridge. Especially for super-long-span cross-sea cable-stayed bridges, the three characteristics of smaller stiffness, smaller natural frequency and larger design basic wind speed make the flutter response significantly larger, making the flutter problem of the bridge one of the main control factors in the design. In addition, the construction environment of cross-sea bridges is more complex, the construction period is longer, and the flutter impact of bridge construction is more serious. Therefore, accurately calculating the flutter response of cross-sea cable-stayed bridges during construction and controlling the flutter response on this basis are important factors to ensure the safety of bridges during construction.

[0003] At present, the buffeting response of cable-stayed bridges is usually calculated based on random vibration theory and the buffeting frequency domain calculation method. The main steps are as follows: using the Sears function to convert the wind speed spectrum into the buffeting force spectrum; using the Scanlan theory to identify the aerodynamic derivatives, thereby calculating the self-excited force of the structure, and superimposing the buffeting force and the self-excited force to form the final force spectrum; using the coherence function of the pulsating wind speed to replace the coherence function of the buffeting force to calculate the joint acceptance function; based on the random vibration theory, using the frequency response function of the structure to calculate the buffeting response of the structure. Based on the above-mentioned buffeting calculation method, the position of the temporary pier is changed under the maximum double cantilever construction state, and the temporary pier layout position is optimized according to the buffeting response of the structure, so that after the temporary pier is arranged, the scheme with the minimum buffeting response under the maximum double cantilever construction state is the optimal temporary pier layout scheme.

[0004] The above-mentioned optimal arrangement scheme of existing temporary piers has the following defects:

[0005] (1) The Sears function used in the existing buffeting frequency domain calculation is based on the strip hypothesis, assuming that the characteristic size of the structure is much smaller than the turbulence integral scale, and the pulsating force is completely correlated on the entire strip. It is only an unsteady correction to the assumed constant aerodynamic force, but does not consider the influence of the geometric characteristics of the structure and the turbulence characteristics on the buffeting force; the pulsating wind coherence function replaces the buffeting force coherence function and also ignores the lateral flow of the airflow;

[0006] (2) Regarding the layout position of temporary piers, the prior art only optimizes the maximum double cantilever construction state without considering that the vibration response will increase with the length of the cantilever during the cantilever construction process. That is, the vibration response of the double cantilever construction state before the temporary piers are arranged may be greater than the vibration response of the temporary piers set in the maximum double cantilever construction state. There is a risk of collapse of the cable-stayed bridge due to the larger vibration response of the double cantilever construction state before the temporary piers are arranged.

[0007] In summary, it is necessary to design the location of temporary piers more reasonably. Summary of the invention

[0008] The purpose of the present invention is to provide a method for optimizing the layout position of temporary piers during the cantilever construction period of a cable-stayed bridge, so as to solve the problems existing in the above-mentioned prior art, make the layout position of temporary piers during the cantilever construction period of the cable-stayed bridge more reasonable, and improve the safety of the cantilever construction period of the cable-stayed bridge.

[0009] To achieve the above object, the present invention provides the following solutions:

[0010] The present invention provides a method for optimizing the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge, comprising the following steps:

[0011] S1, preparing a pressure measurement model of the main beam section of the cable-stayed bridge;

[0012] S2. Testing the pressure measurement model to obtain a three-dimensional aerodynamic admittance function and a buffeting force coherence function of the pressure measurement model;

[0013] S3, introducing the three-dimensional aerodynamic admittance function and the buffeting force coherence function into the buffeting frequency domain calculation method of the cable-stayed bridge;

[0014] S4, calculating the growth of the buffeting response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops and the buffeting response of different temporary pier arrangement positions in the maximum double cantilever construction state by the buffeting frequency domain calculation method;

[0015] S5. In the same coordinate system, draw a growth relationship curve of the vibration response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops, and a change relationship curve of the vibration response of the cable-stayed bridge at different temporary pier layout positions in the maximum double cantilever construction state. The layout position of the temporary pier is represented by the distance between the temporary pier and the bridge tower of the cable-stayed bridge, and the X-axis in the coordinate system corresponds to the change in cantilever length and the distance between the temporary pier and the bridge tower of the cable-stayed bridge. The distance between the temporary pier and the bridge tower of the cable-stayed bridge corresponding to the intersection of the growth relationship curve and the change relationship curve is the optimal layout position of the temporary pier.

[0016] Preferably, the pressure measurement model is a scaled-down model of the main beam section of the cable-stayed bridge.

[0017] Compared with the prior art, the present invention has achieved the following technical effects:

[0018] The optimization method for the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge of the present invention improves the accuracy of the calculation result of the vibration response by more accurately calculating the vibration response, and at the same time optimizes the arrangement position of the temporary piers by considering the increase of the vibration response as the cantilever length develops during the cantilever construction process and the change of the vibration response of the arrangement positions of different temporary piers in the maximum double cantilever construction state, so as to ensure that the vibration response of the double cantilever construction state before the arrangement of the temporary piers is not greater than the vibration response of the temporary piers set in the maximum double cantilever construction state, so that the arrangement position of the temporary piers during the cantilever construction period of the cable-stayed bridge is more reasonable, and the safety of the cable-stayed bridge during the cantilever construction period is improved.

[0019] Furthermore, the present invention can more accurately calculate the buffeting response during the construction period by introducing the three-dimensional aerodynamic admittance and buffeting force coherence function of the buffeting force of the main beam section of the cable-stayed bridge when calculating the buffeting response during the cantilever construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 It is a flow chart of the method for optimizing the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge according to the present invention;

[0022] Figure 2 It is the growth relationship curve of the buffeting response of the cable-stayed bridge with the development of the cantilever length during the cantilever construction period and the change relationship curve of the buffeting response of the cable-stayed bridge at different temporary pier arrangement positions in the maximum double cantilever construction state; DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0024] The purpose of the present invention is to provide a method for optimizing the layout position of temporary piers during the cantilever construction period of a cable-stayed bridge, so as to solve the problems existing in the above-mentioned prior art, make the layout position of temporary piers during the cantilever construction period of the cable-stayed bridge more reasonable, and improve the safety of the cantilever construction period of the cable-stayed bridge.

[0025] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0026] like Figure 1 to Figure 2 As shown, this embodiment provides a method for optimizing the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge, comprising the following steps:

[0027] S1. Prepare a pressure measurement model of the main beam section of the cable-stayed bridge;

[0028] S2. Testing the pressure measurement model to obtain a three-dimensional aerodynamic admittance function and a buffeting force coherence function of the pressure measurement model;

[0029] S3. Introducing the three-dimensional aerodynamic admittance function and the buffeting force coherence function into the buffeting frequency domain calculation method of the cable-stayed bridge; it should be noted that the introduction specifically refers to directly replacing the values ​​of the same functions in the buffeting frequency domain calculation method with the values ​​of the three-dimensional aerodynamic admittance function and the buffeting force coherence function obtained by the test;

[0030] S4. Calculate the growth of the buffeting response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops and the buffeting response of different temporary pier arrangement positions in the maximum double cantilever construction state by using the buffeting frequency domain calculation method;

[0031] S5. In the same coordinate system, a growth curve of the buffeting response of the cable-stayed bridge during the cantilever construction period with the development of the cantilever length and a change curve of the buffeting response of the cable-stayed bridge at different temporary pier layout positions in the maximum double cantilever construction state are drawn. The layout position of the temporary pier is represented by the distance between the temporary pier and the bridge tower of the cable-stayed bridge. The X-axis in the coordinate system corresponds to the change in cantilever length and the distance between the temporary pier and the bridge tower of the cable-stayed bridge. The distance between the temporary pier and the bridge tower of the cable-stayed bridge corresponding to the intersection of the growth curve and the change curve is the optimal layout position of the temporary pier (refer to Figure 2 ).

[0032] It should be noted that Figure 2 The solid line curve in the figure is the growth curve of the buffeting response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops. Figure 2 The dashed curve in the figure is the variation curve of the buffeting response of the cable-stayed bridge under the maximum double cantilever construction state with different temporary pier layout positions. Figure 2It can be seen that the buffeting response of the cable-stayed bridge gradually increases with the development of the cantilever length during the cantilever construction period, while the buffeting response of the cable-stayed bridge in the maximum double cantilever construction state gradually decreases with the distance between the temporary pier and the bridge tower of the cable-stayed bridge. Therefore, in order to ensure that the buffeting response of the cantilever construction state before the temporary pier is smaller than the buffeting response of the cable-stayed bridge in the maximum double cantilever construction state, and to make the buffeting response of the cable-stayed bridge in the maximum double cantilever construction state the lowest, the distance between the temporary pier and the bridge tower of the cable-stayed bridge corresponding to the intersection of the growth relationship curve and the change relationship curve is taken as the optimal layout position of the temporary pier.

[0033] In this embodiment, the pressure measurement model is tested in step S2 to obtain the three-dimensional aerodynamic admittance function and the buffeting force coherence function of the pressure measurement model by specifically performing the following steps:

[0034] Testing the pressure measurement model to obtain the three-dimensional aerodynamic admittance function and buffeting force coherence function of the pressure measurement model specifically includes the following steps:

[0035] (1) Multiple pressure measurement points are set on the pressure measurement model as required, and the pressure measurement model is placed in a wind tunnel. Then, at least two turbulent wind fields with different turbulence integral scales at the construction site of the cable-stayed bridge are simulated in the wind tunnel. The wind field characteristics of each turbulent wind field are measured using an anemometer. The wind field characteristics include the average wind speed U in the downwind direction, the turbulence degree I in the downwind direction, and the wind speed U in the downwind direction. u , Downwind Turbulence Integral Scale Vertical turbulence I w , vertical turbulence integral scale The wind speed time history of each turbulent wind field is Fourier transformed to obtain the downwind wind spectrum S u and vertical wind spectrum S w ;

[0036] (2) The pressure time history of each pressure measuring point under each turbulent wind field is measured by a pressure measuring instrument. The pressure time history of each pressure measuring point under each turbulent wind field is integrated along the main beam section of the cable-stayed bridge according to the following formula to obtain the aerodynamic time history components in three directions of the main beam section of the cable-stayed bridge under each turbulent wind field:

[0037]

[0038] Among them, F x (t) is the time history of the resistance force on the model per unit length relative to the torsion center in the body axis coordinate system, F y L(t) is the lift time history of the model per unit length relative to the torsion center in the body axis coordinate system, M(t) is the moment time history of the model per unit length relative to the torsion center in the body axis coordinate system; i is the integral length of the i-th point; α i is the angle between the internal normal of the i-th point and the horizontal plane of the bridge deck; X i With Yi is the horizontal and vertical distance between the i-th point and the bridge axis; i refers to the number of the pressure measuring point; t is the acquisition time of the pressure measuring signal; n is the total number of pressure measuring points; P i is the pressure value of the ith point;

[0039] (3) According to the formula Calculate the average value of the resistance force per unit length of the model relative to the torsion center in the body axis coordinate system According to the formula Calculate the average value of the resistance force per unit length of the model relative to the torsion center in the body axis coordinate system According to the formula Calculate the average value of the resistance force per unit length of the model relative to the torsion center in the body axis coordinate system

[0040] (4) Then, the three-force coefficient of the main beam section is obtained according to the three-force coefficient formula:

[0041]

[0042] Where C D is the three-force coefficient of resistance, C L is the lift three-force coefficient, C M is the moment tri-force coefficient; ρ is the air density, B is the width of the pressure model, H is the height of the pressure model; U is the average wind speed in the downwind direction;

[0043] (5) The derivative of the three-force coefficient of resistance C′ is obtained by taking the derivative of the three-force coefficient with respect to the wind attack angle. D , the derivative of the three-force coefficient of lift C′ L and the moment three-component force coefficient derivative C′ M ; The buffeting force resistance spectrum S is obtained by Fourier transforming the buffeting force time history D , lift force spectrum S L and torque spectrum S M ;

[0044] (6) According to the aerodynamic admittance equivalent identification method, the three-dimensional aerodynamic admittance of the main beam section is obtained: L | 2 and moment three-dimensional aerodynamic admittance |χ M | 2 , as follows:

[0045]

[0046] Then, according to the three-dimensional aerodynamic admittance fitting under the whole turbulent wind field, The three-dimensional aerodynamic admittance function in, is the vertical integration scale The ratio of the width B of the pressure model, For The three-dimensional aerodynamic admittance function of lift is related to For The related moment three-dimensional aerodynamic admittance function;

[0047] It should be noted that the inventors' research shows that the aerodynamic admittance and coherence function of the buffeting force of the bridge structure in the resistance direction are not significantly different from the parameter calculation results used in traditional calculations. Therefore, the focus of this embodiment is on the aerodynamic admittance function and coherence function of the buffeting lift and moment.

[0048] (7) The buffeting lift and buffeting moment coherence functions are obtained according to the buffeting forces of multiple pressure measuring strips by the following formula:

[0049]

[0050] In the formula is the cross-spectrum of the buffeting force of the two pressure measuring strips, Coh L is the buffeting lift coherence function, Coh M is the coherence function of the buffeting force moment; it should be noted that the spacing between any two pressure measuring strips in the multiple pressure measuring strips is different, and the purpose of setting multiple pressure measuring strips is to measure the buffeting force coherence data points of the two pressure measuring strips at different spacings; for example, the total number of pressure measuring strips is three, and the spacing between every two pressure measuring strips is different, then the buffeting force coherence data points of the two pressure measuring strips at three spacings can be obtained between the two pressure measuring strips, and then the buffeting force coherence function is a function related to the spacing between the pressure measuring strips, so the buffeting force coherence function is obtained by fitting the buffeting force coherence data of multiple groups of two-by-two pressure measuring strips;

[0051] Then, according to the coherence functions of multiple turbulent fields, the least squares method is used to fit the Related coherence functions in, is the vertical integration scale The ratio of the width B of the pressure model, For The three-dimensional aerodynamic admittance function of the buffeting lift is: For The buffeting moment is related to the three-dimensional aerodynamic admittance function.

[0052] In the optional scheme of this embodiment, it is more preferred that the pressure measurement model is a scaled-down model of the main beam section of the cable-stayed bridge.

[0053] In the optional scheme of this embodiment, it is more preferred that the pressure measuring point on the pressure measuring model is preferably set at the location where the shape of the pressure measuring model changes suddenly.

[0054] The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A method for optimizing the arrangement of temporary piers during the cantilever construction period of a cable-stayed bridge, characterized in that: The following steps are involved: S1, preparing a pressure measurement model of the main beam section of the cable-stayed bridge; S2. Testing the pressure measurement model to obtain a three-dimensional aerodynamic admittance function and a buffeting force coherence function of the pressure measurement model; S3, introducing the three-dimensional aerodynamic admittance function and the buffeting force coherence function into the buffeting frequency domain calculation method of the cable-stayed bridge; S4, calculating the growth of the buffeting response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops and the buffeting response of different temporary pier arrangement positions in the maximum double cantilever construction state by the buffeting frequency domain calculation method; S5. In the same coordinate system, draw a growth relationship curve of the vibration response of the cable-stayed bridge during the cantilever construction period as the cantilever length develops, and a change relationship curve of the vibration response of the cable-stayed bridge at different temporary pier layout positions in the maximum double cantilever construction state. The layout position of the temporary pier is represented by the distance between the temporary pier and the bridge tower of the cable-stayed bridge, and the X-axis in the coordinate system corresponds to the change in cantilever length and the distance between the temporary pier and the bridge tower of the cable-stayed bridge. The distance between the temporary pier and the bridge tower of the cable-stayed bridge corresponding to the intersection of the growth relationship curve and the change relationship curve is the optimal layout position of the temporary pier.

2. The method for optimizing the arrangement position of temporary piers during the cantilever construction period of a cable-stayed bridge according to claim 1, characterized in that: The pressure measurement model is a scaled-down model of the main beam section of the cable-stayed bridge.