Building engineering quantity analysis and management method and system based on digital twinning

Through digital twin technology, three-dimensional models and building sub-models are constructed, the construction progress is monitored and the construction cycle is regulated, which solves the problem that the existing technology cannot effectively monitor and regulate construction efficiency, and achieves a dynamic improvement in construction efficiency.

CN118917968AInactive Publication Date: 2024-11-08NANTONG SHIPPING COLLEGE

Patent Information

Application Number
CN202411163204.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing construction project volume analysis and management methods cannot effectively monitor the construction progress, resulting in the inability to dynamically regulate construction efficiency.

Method used

Using a digital twin method, by constructing a three-dimensional digital model, the construction building is divided into building submodels, the completion progress coefficient is calculated, the construction efficiency signal is generated, and the construction cycle is judged based on the signal, so as to improve construction efficiency through dynamic regulation.

Benefits of technology

Dynamic monitoring and regulation of construction efficiency has been achieved, construction efficiency has been improved, and overall construction efficiency has been improved by adjusting the construction cycle and number of people.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118917968A_ABST
    Figure CN118917968A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building engineering quantity management, and discloses a building engineering quantity analysis and management method and system based on digital twinning, and the method comprises the following steps: 1, constructing a three-dimensional digital model of a project through employing a building information model technology; 2, dividing the three-dimensional digital model into a plurality of standard building sub-models; and step 3, obtaining building information of actual construction. According to the method, the construction periods of all the construction sub-models are obtained, the construction period deviation rate under a low construction efficiency signal and the construction period deviation rate under a high construction efficiency signal are obtained through analysis and processing, the two construction period deviation rates are subtracted, and the construction period deviation rate difference value is obtained; and finally, comparing the construction period deviation rate difference value with a construction period deviation rate difference value threshold value, and judging whether the generated construction efficiency is related to the construction period or not, so that whether the construction efficiency can be improved by correcting the construction period or not can be judged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction engineering quantity management, and in particular to a construction engineering quantity analysis management method and system based on digital twins. Background Art

[0002] The analysis and management of construction project quantities is an important basis for construction project cost and construction. Therefore, in order to ensure the scientificity and suitability of construction project cost and the smoothness of construction process, it is necessary to analyze and manage the construction project quantities.

[0003] However, although the construction volume is currently analyzed and managed during the construction process, the existing analysis and management methods cannot monitor the progress of the construction completion, and thus cannot effectively and dynamically regulate the construction efficiency. Summary of the invention

[0004] The purpose of the present invention is to provide a construction project quantity analysis and management method and system based on digital twins, so as to solve the problem that the existing analysis and management methods in the above background cannot effectively dynamically regulate the construction efficiency by monitoring the construction completion progress.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A construction engineering quantity analysis management method and system based on digital twins, comprising the following steps:

[0007] Step 1: Use building information modeling technology to construct a three-dimensional digital model of the project; Step 2: Divide the three-dimensional digital model into several standard building sub-models; Step 3: Obtain the building information of the actual construction, divide the actual construction building into several construction building sub-models, and calculate the completion progress coefficient of the construction building sub-model, and generate low construction efficiency and high construction efficiency signals through comparison and judgment; wherein, the construction building sub-model and the standard building sub-model are in a corresponding relationship; Step 4: Based on the low construction efficiency signal generated in the above steps, judge whether the low construction efficiency is related to the construction period, and generate a corrected construction period signal and a non-corrected construction period signal through the judgment result; Step 5: Based on the corrected construction period signal generated in the above steps, dynamically adjust the construction period to improve the construction efficiency.

[0008] As a further solution of the present invention: the completion progress coefficient of the construction building sub-model is obtained by processing the sub-model size deviation ratio and the sub-model shape deviation ratio;

[0009] The completion progress coefficient of the construction building sub-model = sub-model size deviation ratio Wx + sub-model shape deviation ratio Vx.

[0010] As a further solution of the present invention: the size deviation ratio of the sub-model = the length value ratio + the width value ratio + the height value ratio, and the size deviation ratio of the sub-model is recorded as Wx;

[0011] The shape deviation ratio of the sub-model = overlapping volume value / standard building sub-model, and the shape deviation ratio of the sub-model is recorded as Vx;

[0012] As a further solution of the present invention: the overlapping volume value acquisition process is:

[0013] Obtain the height value, length value and width value of the construction building sub-model, and establish an XYZ three-dimensional coordinate system, with the height of the construction building sub-model as the Z axis, the length of the construction building sub-model as the X axis, and the width of the construction building sub-model as the Y axis;

[0014] The length value, width value and height value of the standard building sub-model are respectively brought into the X-axis, Y-axis and Z-axis of the three-dimensional coordinate system, and the overlapping volume value is obtained through processing.

[0015] As a further solution of the present invention: comparing and judging the completion progress coefficient of the construction building sub-model with the completion progress coefficient threshold of the construction building sub-model;

[0016] If the completion progress coefficient of the construction building sub-model is less than the completion progress coefficient threshold of the construction building sub-model, a low construction efficiency signal is generated;

[0017] If the completion progress coefficient of the construction building sub-model is ≥ the completion progress coefficient threshold of the construction building sub-model, a high construction efficiency signal is generated.

[0018] As a further solution of the present invention: based on the above-mentioned low construction efficiency signal;

[0019] The specific analysis steps include the following process:

[0020] All construction building sub-models are numbered in sequence to obtain the construction period of all construction sub-models;

[0021] The construction cycle deviation rate under the low construction efficiency signal is obtained through analysis and processing, which is recorded as Ax;

[0022] The construction cycle deviation rate under high construction efficiency signal is obtained through analysis and processing, which is recorded as Ay.

[0023] As a further solution of the present invention: Substitute Ax and Ay into the formula Kx=Ay-Ax to obtain the construction period deviation rate difference Kx, and compare the construction period deviation rate difference K1 with the construction period deviation rate difference threshold Ky;

[0024] If Kx≤Ky, it means that the generated low construction efficiency signal has nothing to do with the construction period, and the generated signal does not correct the construction period;

[0025] If Kx>Ky, it means that the low construction efficiency signal is related to the construction cycle, and a corrected construction cycle signal is generated.

[0026] As a further solution of the present invention: based on the above-mentioned modified periodic signal;

[0027] The specific process is as follows:

[0028] Obtain a curve status diagram of the completion progress of the construction building sub-model within the construction cycle;

[0029] The completion progress value whose curve is below the standard line is marked as not meeting the standard;

[0030] The completion progress value where the curve is located above the standard line is marked as reaching the standard;

[0031] The completion progress value where the curve is above the standard line is marked as normal.

[0032] As a further solution of the present invention: obtaining the completion progress value data marked as not reaching the standard, subtracting the standard value of the single-day completion progress from the completion progress value marked as not reaching the standard, obtaining the deviation value data of the single-day completion progress marked as not reaching the standard, summing these data to obtain the total value of the deviation value, recorded as Jx;

[0033] Obtain the completion progress value data marked as normal, subtract the completion progress value marked as normal from the single-day completion progress standard value, obtain the deviation value data of the single-day completion progress marked as normal, sum these data, obtain the total value of the deviation value, and record it as Jy;

[0034] Get the total number of days Tx of the construction period, the number of days Ty that have been constructed, and the total amount of work M per worker per day;

[0035] Obtain the completion progress value data marked as reaching the target and the number of construction workers on that day, perform ratio processing on the completion progress value marked as reaching the target and the number of construction workers on that day to obtain a set of ratio data, sum and average these data, and record them as the total daily work value M of each worker;

[0036] Substitute into the formula Where Jx-Jy>0;

[0037] The value of Lx obtained by calculation is the number of additional construction workers required.

[0038] As a further solution of the present invention: a data acquisition module: acquires the size information of the construction building sub-model, including the length value, the width value and the height value, acquires the construction period of the construction sub-model, and acquires the historical construction information;

[0039] Processing module: Processing the acquired size information of the construction building sub-model to obtain the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model, and processing the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model to obtain the completion progress coefficient of the construction building sub-model;

[0040] Judgment and identification module: compares the completion progress coefficient of the construction building sub-model with the completion progress coefficient threshold of the construction building sub-model, and generates low construction efficiency and high construction efficiency signals;

[0041] Analysis and identification module: obtains low construction efficiency signals, analyzes and processes to obtain construction cycle deviation rate difference, compares the construction cycle deviation rate difference with the construction cycle deviation rate difference threshold, and generates uncorrected construction cycle signals and corrected construction cycle signals;

[0042] Construction cycle adjustment module: obtains the correction construction cycle signal and makes corrections and adjustments to the construction cycle.

[0043] Beneficial effects of the present invention:

[0044] (1) The present invention obtains architectural information of the construction building, divides the construction building into a plurality of architectural sub-models, then performs ratio processing on the length value, width value and height value of the construction building sub-model and the length value, width value and height value of the standard building sub-model respectively, adds the ratios to obtain the size deviation ratio of the sub-model, then obtains the overlap value of the volume value of the sub-model and the volume value of the standard building sub-model, performs ratio processing on the overlap value and the volume value of the standard building sub-model to obtain the shape deviation ratio of the sub-model, sums the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model, obtains the completion progress coefficient of the construction building sub-model, and then understands the efficiency of the construction according to the completion progress coefficient of the construction building sub-model;

[0045] (2) The present invention obtains the construction cycles of all construction sub-models, and obtains the construction cycle deviation rate under the low construction efficiency signal and the construction cycle deviation rate under the high construction efficiency signal through analysis and processing, and then subtracts the two construction cycle deviation rates to obtain the construction cycle deviation rate difference. Finally, the construction cycle deviation rate difference is compared with the construction cycle deviation rate difference threshold to determine whether the generated construction efficiency is related to the construction cycle, so as to determine whether the construction efficiency can be improved by correcting the construction cycle.

[0046] (3) When the construction efficiency is lower than the construction period, the total deviation of the construction progress within the construction period, the remaining construction days within the construction period, and the total daily work of the construction workers can be obtained. Then, the required additional number of construction workers can be calculated through the formula. Therefore, the overall construction efficiency can be improved to a certain extent by adjusting the number of construction workers within the construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] The present invention will be further described below in conjunction with the accompanying drawings.

[0048] Figure 1 It is a flow chart of a construction engineering quantity analysis and management method based on digital twins of the present invention;

[0049] Figure 2 It is a schematic diagram of a process for obtaining a completion progress coefficient of a construction building sub-model in a construction engineering quantity analysis and management method based on digital twins of the present invention;

[0050] Figure 3 It is a schematic diagram of a process of judging whether low construction efficiency is related to a construction period in a construction engineering quantity analysis and management method based on digital twins of the present invention;

[0051] Figure 4 It is a schematic diagram of a construction engineering quantity analysis and management system based on digital twins of the present invention. DETAILED DESCRIPTION

[0052] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0053] Embodiment 1

[0054] See also Figure 1-Figure 3 As shown, the present invention is a construction engineering quantity analysis and management method based on digital twins, comprising the following steps:

[0055] Step 1: Use building information modeling technology to build a three-dimensional digital model of the project;

[0056] Step 2: Divide the 3D digital model into several standard building sub-models;

[0057] Step 3: Obtain the building information of actual construction, divide the building under actual construction into several construction building sub-models, and calculate the completion progress coefficient of the construction building sub-model. Through comparison and judgment, generate low construction efficiency and high construction efficiency signals;

[0058] Among them, the construction building sub-model corresponds to the standard building sub-model;

[0059] If the completion progress coefficient of the construction building sub-model is less than the completion progress coefficient threshold of the construction building sub-model, a low construction efficiency signal is generated;

[0060] If the completion progress coefficient of the construction building sub-model is ≥ the completion progress coefficient threshold of the construction building sub-model, a high construction efficiency signal is generated;

[0061] Step 4: Based on the low construction efficiency signal generated in the above steps, determine whether the low construction efficiency is related to the construction period, and generate a corrected construction period signal and a non-corrected construction period signal according to the determination result;

[0062] Step 5: Based on the modified construction cycle signal generated in the above steps, the construction cycle is dynamically adjusted to improve the construction efficiency.

[0063] Embodiment 2

[0064] The completion progress coefficient of the construction building sub-model in step 3 of the above embodiment is obtained by processing the sub-model size deviation ratio and the sub-model shape deviation ratio;

[0065] The completion progress coefficient of the construction building sub-model = sub-model size deviation ratio Wx + sub-model shape deviation ratio Vx;

[0066] The process of obtaining the size deviation ratio of the sub-model is as follows:

[0067] The size deviation ratio of the sub-model = the length value ratio + the width value ratio + the height value ratio, and the size deviation ratio of the sub-model is recorded as Wx;

[0068] The length value ratio is the ratio of the length value of the construction building sub-model to the length value of the standard building sub-model;

[0069] The width value ratio is the ratio of the width value of the construction building sub-model to the width value of the standard building sub-model;

[0070] The height value ratio is the ratio of the height value of the construction building sub-model to the height value of the standard building sub-model;

[0071] The process of obtaining the shape deviation ratio of the sub-model is:

[0072] The shape deviation ratio of the sub-model = overlapping volume value / standard building sub-model, and the shape deviation ratio of the sub-model is recorded as Vx;

[0073] The overlapping volume value is the overlapping volume value of the standard building sub-model and the constructed building sub-model;

[0074] Specifically, the overlapping volume value acquisition process is:

[0075] Obtain the height value, length value and width value of the construction building sub-model, and establish an XYZ three-dimensional coordinate system, with the height of the construction building sub-model as the Z axis, the length of the construction building sub-model as the X axis, and the width of the construction building sub-model as the Y axis;

[0076] The length value, width value and height value of the standard building sub-model are respectively brought into the X-axis, Y-axis and Z-axis of the three-dimensional coordinate system, and the overlapping volume value is obtained through processing.

[0077] Embodiment 3

[0078] Based on the low construction efficiency signal generated in the first embodiment, the factors affecting the low efficiency are analyzed;

[0079] According to the formula: construction efficiency = construction volume / construction period, we can know the factors that affect construction efficiency during the construction period;

[0080] The specific analysis steps include the following process:

[0081] All construction building sub-models are numbered in sequence to obtain the construction period of all construction sub-models;

[0082] The construction periods of the construction sub-models that generate low construction efficiency signals are arranged in order from small to large numbers to form a set of data;

[0083] The expected construction period of the standard building sub-model corresponding to the construction sub-model generating the low construction efficiency signal is arranged into a set of data in ascending order of numbers;

[0084] The expected construction period is an empirical value predicted by the staff based on the construction volume, number of construction workers and weather conditions for construction;

[0085] The construction period of the construction sub-model with the same number is subtracted from the expected construction period of the standard building sub-model to obtain the absolute value of the difference, and the absolute value of the difference is compared with the expected construction period value of the standard building sub-model to obtain the construction period deviation rate under the low construction efficiency signal, which is recorded as Ax;

[0086] The construction periods of the construction sub-models that generate high construction efficiency signals are arranged in order from small to large numbers to form a set of data;

[0087] The expected construction period of the standard building sub-model corresponding to the construction sub-model generating the high construction efficiency signal is arranged into a set of data in ascending order of numbers;

[0088] Subtract the construction period of the construction sub-model with the same number from the expected construction period of the standard building sub-model to obtain the absolute value of the difference, and perform ratio processing on the absolute value of the difference and the expected construction period value of the standard building sub-model to obtain the construction period deviation rate under the high construction efficiency signal, which is recorded as Ay;

[0089] Substitute Ax and Ay into the formula Kx=Ay-Ax to obtain the construction period deviation rate difference Kx, and compare the construction period deviation rate difference K1 with the construction period deviation rate difference threshold Ky;

[0090] If Kx≤Ky, it means that the generated low construction efficiency signal has nothing to do with the construction period, and the generated signal does not correct the construction period;

[0091] If Kx>Ky, it means that the low construction efficiency signal is related to the construction cycle, and a corrected construction cycle signal is generated.

[0092] Embodiment 4

[0093] Based on the modified cycle signal generated in the above embodiment, the construction cycle is adjusted to improve the construction efficiency;

[0094] The way to adjust the construction period is to adjust the number of construction workers;

[0095] The specific process is as follows:

[0096] Obtain the daily completion progress data of the construction sub-model during the construction period, establish an XY two-dimensional plane coordinate system, take the day value of the construction period as the X-axis, and the construction efficiency as the Y-axis, and build a standard line parallel to the X-axis in the coordinate system with the standard value of the single-day completion progress;

[0097] Thus, a dot graph corresponding to the completion progress of the construction building sub-model during the construction process is obtained. According to the time sequence of the construction period, the dot graphs corresponding to the completion progress of the construction sub-model are connected from left to right with a smooth curve to obtain a curve state diagram of the completion progress of the construction building sub-model within the construction period.

[0098] The completion progress value whose curve is below the standard line is marked as not meeting the standard;

[0099] The completion progress value where the curve is located above the standard line is marked as reaching the standard;

[0100] The completion progress value where the curve is located above the standard line is marked as normal;

[0101] Obtain the completion progress value data marked as not reaching the target, subtract the standard value of the single-day completion progress from the completion progress value marked as not reaching the target, obtain the deviation value data of the single-day completion progress marked as not reaching the target, sum these data, obtain the total value of the deviation value, and record it as Jx;

[0102] Obtain the completion progress value data marked as normal, subtract the completion progress value marked as normal from the single-day completion progress standard value, obtain the deviation value data of the single-day completion progress marked as normal, sum these data, obtain the total value of the deviation value, and record it as Jy;

[0103] Get the total number of days Tx of the construction period, the number of days Ty that have been constructed, and the total amount of work M per worker per day;

[0104] Specifically, the process of obtaining the total daily workload value M of each worker is as follows:

[0105] Obtain the completion progress value data marked as reaching the target and the number of construction workers on that day, perform ratio processing on the completion progress value marked as reaching the target and the number of construction workers on that day to obtain a set of ratio data, sum and average these data, and record them as the total daily work value M of each worker;

[0106] Substitute into the formula Where Jx-Jy>0;

[0107] The value of Lx obtained by calculation is the number of additional construction workers required.

[0108] Embodiment 5

[0109] See also Figure 4 As shown, a construction engineering quantity analysis and management system based on digital twins includes:

[0110] Data acquisition module: obtains the size information of the construction building sub-model, including length, width and height, obtains the construction period of the construction sub-model, obtains historical construction information, and sends it to the cloud server platform;

[0111] Processing module: Processing the acquired size information of the construction building sub-model to obtain the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model, and processing the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model to obtain the completion progress coefficient of the construction building sub-model;

[0112] Judgment and identification module: compares the completion progress coefficient of the construction building sub-model with the completion progress coefficient threshold of the construction building sub-model, and generates low construction efficiency and high construction efficiency signals;

[0113] Analysis and identification module: obtains low construction efficiency signals, analyzes and processes to obtain construction cycle deviation rate difference, compares the construction cycle deviation rate difference with the construction cycle deviation rate difference threshold, and generates uncorrected construction cycle signals and corrected construction cycle signals;

[0114] Construction cycle adjustment module: obtains the correction construction cycle signal and makes corrections and adjustments to the construction cycle.

[0115] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A construction engineering quantity analysis and management method based on digital twins, characterized in that: The following steps are involved: Step 1: Use building information modeling technology to build a three-dimensional digital model of the project; Step 2: Divide the 3D digital model into several standard building sub-models; Step 3: Obtain the building information of actual construction, divide the building under actual construction into several construction building sub-models, and calculate the completion progress coefficient of the construction building sub-model. Through comparison and judgment, generate low construction efficiency and high construction efficiency signals; Among them, the construction building sub-model corresponds to the standard building sub-model; Step 4: Based on the low construction efficiency signal generated in the above steps, determine whether the low construction efficiency is related to the construction period, and generate a corrected construction period signal and a non-corrected construction period signal according to the determination result; Step 5: Based on the modified construction cycle signal generated in the above steps, dynamically adjust the construction cycle.

2. A construction engineering quantity analysis and management method based on digital twin according to claim 1, characterized in that: The completion progress coefficient of the construction building sub-model is obtained by processing the sub-model size deviation ratio and the sub-model shape deviation ratio; The completion progress coefficient of the construction building sub-model = sub-model size deviation ratio Wx + sub-model shape deviation ratio Vx.

3. A construction engineering quantity analysis and management method based on digital twin according to claim 2, characterized in that: The size deviation ratio of the sub-model = the length value ratio + the width value ratio + the height value ratio, and the size deviation ratio of the sub-model is recorded as Wx; The shape deviation ratio of the sub-model = overlapping volume value / standard building sub-model, and the shape deviation ratio of the sub-model is recorded as Vx.

4. A construction engineering quantity analysis and management method based on digital twin according to claim 3, characterized in that: The process of obtaining the overlapping volume value is as follows: Obtain the height value, length value and width value of the construction building sub-model, and establish an XYZ three-dimensional coordinate system, with the height of the construction building sub-model as the Z axis, the length of the construction building sub-model as the X axis, and the width of the construction building sub-model as the Y axis; The length value, width value and height value of the standard building sub-model are respectively brought into the X-axis, Y-axis and Z-axis of the three-dimensional coordinate system, and the overlapping volume value is obtained through processing.

5. The construction engineering quantity analysis and management method based on digital twin according to claim 3 is characterized in that: Compare and judge the completion progress coefficient of the construction building sub-model with the completion progress coefficient threshold of the construction building sub-model; If the completion progress coefficient of the construction building sub-model is less than the completion progress coefficient threshold of the construction building sub-model, a low construction efficiency signal is generated; If the completion progress coefficient of the construction building sub-model is ≥ the completion progress coefficient threshold of the construction building sub-model, a high construction efficiency signal is generated.

6. A construction engineering quantity analysis and management method based on digital twin according to claim 1, characterized in that: Based on the above-mentioned signal of low construction efficiency; The specific analysis steps include the following process: All construction building sub-models are numbered in sequence to obtain the construction period of all construction sub-models; The construction cycle deviation rate under the low construction efficiency signal is obtained through analysis and processing, which is recorded as Ax; The construction cycle deviation rate under high construction efficiency signal is obtained through analysis and processing, which is recorded as Ay.

7. A construction engineering quantity analysis and management method based on digital twins according to claim 6, characterized in that: Substitute Ax and Ay into the formula Kx=Ay-Ax to obtain the construction period deviation rate difference Kx, and compare the construction period deviation rate difference K1 with the construction period deviation rate difference threshold Ky; If Kx≤Ky, it means that the generated low construction efficiency signal has nothing to do with the construction period, and the generated signal does not correct the construction period; If Kx>Ky, it means that the low construction efficiency signal is related to the construction cycle, and a corrected construction cycle signal is generated.

8. A construction engineering quantity analysis and management method based on digital twin according to claim 7, characterized in that: Based on the above modified cycle signal; The specific process is as follows: Obtain a curve status diagram of the completion progress of the construction building sub-model within the construction cycle; The completion progress value whose curve is below the standard line is marked as not meeting the standard; The completion progress value where the curve is located above the standard line is marked as reaching the standard; The completion progress value where the curve is above the standard line is marked as normal.

9. A construction engineering quantity analysis and management method based on digital twins according to claim 8, characterized in that: Obtain the completion progress value data marked as not reaching the target, subtract the standard value of the single-day completion progress from the completion progress value marked as not reaching the target, obtain the deviation value data of the single-day completion progress marked as not reaching the target, sum these data, obtain the total value of the deviation value, and record it as Jx; Obtain the completion progress value data marked as normal, subtract the completion progress value marked as normal from the single-day completion progress standard value, obtain the deviation value data of the single-day completion progress marked as normal, sum these data, obtain the total value of the deviation value, and record it as Jy; Get the total number of days Tx of the construction period, the number of days Ty that have been constructed, and the total amount of work M per worker per day; Obtain the completion progress value data marked as reaching the target and the number of construction workers on that day, perform ratio processing on the completion progress value marked as reaching the target and the number of construction workers on that day to obtain a set of ratio data, sum and average these data, and record them as the total daily work value M of each worker; Substitute into the formula Where Jx-Jy>0; The value of Lx obtained by calculation is the number of additional construction workers required.

10. A construction engineering quantity analysis and management system based on digital twin, the system implements the method according to any one of claims 1 to 9, characterized in that: include: Data acquisition module: obtains the size information of the construction building sub-model, including length, width and height, obtains the construction period of the construction sub-model, and obtains historical construction information; Processing module: Processing the acquired size information of the construction building sub-model to obtain the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model, and processing the size deviation ratio of the sub-model and the shape deviation ratio of the sub-model to obtain the completion progress coefficient of the construction building sub-model; Judgment and identification module: compares the completion progress coefficient of the construction building sub-model with the completion progress coefficient threshold of the construction building sub-model, and generates low construction efficiency and high construction efficiency signals; Analysis and identification module: obtains low construction efficiency signals, analyzes and processes to obtain construction cycle deviation rate difference, compares the construction cycle deviation rate difference with the construction cycle deviation rate difference threshold, and generates uncorrected construction cycle signals and corrected construction cycle signals; Construction cycle adjustment module: obtains the correction construction cycle signal and makes corrections and adjustments to the construction cycle.

Citation Information

Patent Citations

  • Building engineering quantity analysis and management method and system based on BIM technology, and computer storage medium

    CN113343342A

  • Fabricated building construction safety risk intelligent management method based on digital twinning

    CN117195601A

  • Fabricated building construction intelligent management method and system based on digital twinning

    CN117196507A

  • Building engineering construction progress supervision system based on BIM technology

    CN117557065A

  • Construction work management system and construction work management method

    JP2021157532A

Cited By

  • Equipment management and control modeling design method and equipment based on digital twinning and medium

    CN119294140A