Small-oil-discharge replacement method of neutral bushing for converter transformer
By using oil level maintenance tooling and guide rod limit tooling during the replacement of the converter rheology neutral point casing, the problems of exposed air and guide rod drop are solved, and faster and safer casing replacement is achieved. Avoid the necessity of overall oil discharge and full vacuum oil injection.
Patent Information
- Application Number
- CN202411065414.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-08-05
AI Technical Summary
During the replacement of the neutral point casing of the converter rheology, the "straw hat" structure of the mesh-side high-pressure casing is easily exposed, resulting in the need to discharge the oil as a whole before performing a full vacuum injection, which is inefficient and has safety hazards.
The oil level maintenance tooling and guide rod limit tooling are adopted to prevent the straw hat structure from being exposed and guide rod falling. The casing is replaced without affecting the oil level through step-by-step operations to avoid overall oil discharge and full vacuum oil injection.
It significantly shortens the replacement time, avoids exposed straw hat structure and damage to guide rods, improves replacement efficiency and safety, and saves a lot of construction periods.
Smart Images

Figure CN118920336A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of substation maintenance, and in particular to a method for replacing small oil drain of a neutral point bushing for a commutation transformer. Background Art
[0002] Many converter transformer neutral point bushings use ABB glue-impregnated paper dry bushings. It has been found many times that the silicone rubber shed of the dry bushing and the internal epoxy resin tube at the corresponding position have obvious cracks, and the neutral point bushing needs to be replaced.
[0003] observe Figure 1 When the converter transformer is operating normally, the left neutral point bushing is full of oil, and the body is also full of oil. At this time, the "straw hat" structure of the grid-side high-voltage bushing is soaked in oil; when replacing the neutral point bushing of the converter transformer, since the paper insulation grading ring of the "straw hat" structure of the grid-side high-voltage bushing is higher than the neutral point bushing mounting flange surface, the straw hat structure will inevitably be exposed. However, according to the requirements of the ABB manufacturer, after the insulating parts of the converter transformer are exposed, the oil must be drained as a whole before full vacuum oil filling; at the same time, since the current-carrying guide rod of the neutral point bushing is heavy, people need to enter to assist in the disassembly and assembly of the bushing. Therefore, the converter transformer is drained as a whole and then oiled. The whole process takes about 15 days; not only is the replacement efficiency slow, but there are also safety hazards. Summary of the invention
[0004] In order to speed up the replacement of the neutral point bushing of a converter transformer, the present application provides a method for replacing the neutral point bushing of a converter transformer by draining oil.
[0005] The present application provides a method for replacing the small oil drain of the neutral point bushing for a converter transformer, which adopts the following technical solution:
[0006] A method for replacing the small oil drain of a neutral point bushing for a converter transformer, which uses a guide rod limiting tool and an oil level keeping tool, wherein the oil level keeping tool is used to prevent the straw hat structure from being exposed, and the guide rod limiting tool is used to prevent the guide rod from falling; the guide rod limiting tool comprises two limiting rods, each of which is provided with a semicircular notch, and the two limiting rods can be spliced by a screw rod, and the two notches are spliced together to form a through hole;
[0007] The oil level maintenance tool comprises a cylinder, the bottom surface of which is provided with a mounting flange, the bottom side wall is provided with an oil filling and draining valve, the middle side wall is provided with an oil level maintenance valve, and the top side wall is provided with a hanging point;
[0008] Replacing the casing involves the following steps:
[0009] S1. Clean the machines and work points;
[0010] S2. Install the oil level monitoring device: close the gate valve from the main body to the oil pillow pipeline, and install a transparent pipe at the gas next to the pressure regulating switch to the elevated seat on the side of the network;
[0011] S3. Remove the casing cap, install the casing professional lifting device, install the oil level maintaining tooling, and inject a certain amount of oil into the cylinder;
[0012] S4. Lift the casing. When the guide rod leaks out, install the guide rod limit tooling.
[0013] S5. Continue to slowly lift the casing until the top of the guide rod is completely exposed, then remove the guide rod traction rope, lift off the old casing, and place a sealing gasket in the casing flange hole;
[0014] S6. Lift the new casing and install the traction rope;
[0015] S7. Slowly lower the new casing. When it reaches a certain height, remove the guide rod limit fixture.
[0016] S8. Hold the traction rope tightly, install the new sleeve and copper rod, and complete the exhaust of the new sleeve;
[0017] S9. After draining the oil, remove the oil level maintaining tooling and complete the cleaning work; then open the oil pillow to the main body valve and restore the converter to the operating state.
[0018] Optionally, the step S1 specifically includes: cleaning the tooling, hooks, hangers, sleeves and flange surfaces with alcohol and cotton gauze; and cleaning the tools that need to be used in oil with oil.
[0019] Optionally, connect the mounting flange on the oil level maintaining tooling to the flat-top flange surface with bolts, connect the oil filling and draining valve to the flange of the gas relay next to the converter transformer voltage regulating switch, and connect the oil level maintaining valve to the oil tank; fill oil into the cylinder, if the height difference between the straw hat structure and the flat top of the converter transformer is h, the oil level in the cylinder is 1.5h; after the oil filling is completed, shake the casing slightly, and proceed to the subsequent steps after the oil level stabilizes.
[0020] Optionally, the casing lifting in step S4 is specifically as follows: keep the oil pillow pipeline valve slightly open to allow the oil to slowly overflow from the casing flange, and slowly lift the neutral point casing; after the bottom of the casing leaves the flat top, close the oil pillow pipeline gate valve, lift the bottom of the casing until the sealing plate is completely separated from the flat top, check the oil level status in the tooling again, and use the flange mouth sealing plate to seal the casing flange hole.
[0021] Optionally, the installation of the guide rod limiting tooling in step S4 is specifically as follows: assembling two limiting rods, both limiting rods are mounted on the cylinder body, allowing the guide rod to pass through the through hole on the limiting rod, and installing a clamp on the guide rod.
[0022] Optionally, step S6 specifically includes: hanging the new casing to the upper part of the guide rod, passing one end of the traction rope through the guide rod hole of the new casing, and connecting the other end with a special bolt, which is screwed into the threaded hole at the top of the guide rod.
[0023] Optionally, step S7 is specifically as follows: slowly lower the casing, and when it reaches a height of 600 mm, tighten the traction rope to prevent the guide rod from being pressed down, remove the guide rod limit fixture and flange hole sealing plate, install the sealing gasket, and pay attention to the oil level to maintain the oil level in the fixture and the oil level of the riser on the mesh side.
[0024] Optionally, step S8 specifically includes: after the casing is lowered into place, install the flange bolts and tighten them evenly; then slowly open the oil pillow to the main body valve, and after observing oil coming out from the guide rod at the top of the neutral point casing, close the oil pillow to the main body valve and install the general cap of the new casing.
[0025] In summary, this application includes the following beneficial technical effects:
[0026] The present application sets an oil level maintaining tool so that the "straw hat" structure of the grid-side high-voltage bushing is always wrapped by the converter transformer oil when the bushing is removed, thereby preventing the straw hat structure from being exposed; therefore, in the subsequent bushing replacement process, there is no need to drain the oil of the converter transformer as a whole and then perform full vacuum oil filling, which saves a lot of time; at the same time, when replacing the bushing, a guide rod limiting tool is used, and when replacing the bushing, the guide rod copper bar is fixed to prevent the lead from being damaged by downward pressure. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a rough overall structural diagram of the current converter transformer;
[0028] Figure 2 This is an overall structural diagram of a tooling used in a method for replacing a small oil drain of a neutral point bushing for a converter transformer in the present application;
[0029] Figure 3 This is the overall structural diagram of the oil level maintenance tooling of this application;
[0030] Figure 4 It is the overall structural diagram of the guide rod limiting tooling of this application.
[0031] Description of reference numerals:
[0032] 1. Guide rod; 2. Oil level holding tool; 201. Cylinder; 202. Mounting flange; 203. Oil filling and discharge valve; 204. Oil level holding valve; 205. Lifting point; 3. Guide rod limit tool; 301. Limit rod; 302. Clamp; 303; Screw. DETAILED DESCRIPTION
[0033] The following is combined with Figure 1-4 This application is described in further detail.
[0034] The embodiment of the present application discloses a method for replacing the neutral point bushing of a converter transformer by draining small amounts of oil. The method uses an oil level maintaining tool 2 and a guide rod 1 limiting tool. The guide rod 1 limiting tool includes two limiting rods 301. The limiting rods 301 are provided with semicircular notches. The two limiting rods 301 can be spliced by a screw 303, and the two notches are spliced together to form a through hole. The oil level maintaining tool 2 includes a cylinder 201. The bottom surface of the cylinder 201 is provided with a mounting flange 202, the bottom side wall is provided with an oil filling and draining valve 203, the middle side wall is provided with an oil level maintaining valve 204, and the top is provided with a hanging point 205.
[0035] The method comprises the following steps:
[0036] S1. Clean the machines and work points;
[0037] S11. Tool cleaning: Use alcohol and cotton gauze to wipe the inner wall and flange surface of the tool to ensure that it is clean and free of impurities; use alcohol and cotton gauze to wipe the crossarm, clamp, fixing bolts, etc.
[0038] S12. Cleaning of machinery and equipment: Wipe the hooks, slings, etc. with alcohol, and wrap the surfaces of large and small hooks with plastic cloth; use clean lifting ropes and pull ropes; use oil to clean tools that need to be used in oil.
[0039] S13. Casing cleaning: Wipe the silicone rubber shed of the casing with alcohol and cotton gauze, and wrap the surface of the casing with plastic cloth.
[0040] S14, Flange cleaning: To prevent impurities and rust on the surface of the screw holes, screw rods, and nuts from dissolving in the oil after the casing flange bolts are removed, the bolts must be replaced and the screw holes must be cleaned before the installation tool is oiled. Replace the diagonal bolts No. 1 and No. 5, No. 3 and No. 7, and the grounding bolts first, and then replace the diagonal bolts No. 2 and No. 6, No. 4 and No. 8 to prevent oil leakage. After removing the old bolts, blow the screw holes with high-pressure air, and then clean the screw holes with dough to ensure that the screw holes are clean and free of impurities, and tighten the bolts after replacement.
[0041] Since the gap between the casing flange surface and the CT flange surface is small and difficult to clean, it is necessary to blow the gap with high-pressure air during the removal of the bolts; then use cotton gauze to clean the casing and CT flange surfaces, and then use dough to stick the flange surfaces to ensure that there are no tiny impurities remaining on the flange surfaces.
[0042] S15. Cleaning after the tooling is installed: Remove 8 bolts from the CT flange surface at the following intervals, hoist the tooling, install it with a long screw, and clean the sealing gasket; after the tooling is installed, clean the internal parts of the tooling with oil, rinse twice, and drain the oil to ensure that there are no impurities at the working point.
[0043] S2. Install oil level monitoring device: close the gate valve of the pipeline from the main body to the oil pillow, and install a transparent tube from the gas beside the pressure regulating switch to the net side riser to observe the oil level in the net side riser to prevent the "straw hat" structure from being exposed. ;
[0044] S3. Remove the casing general cap to prevent the oil seeping from here from flowing into the tooling along the casing surface, install a clean casing special hoist to prevent contamination by impurities and install the casing professional hoist, install the oil level maintaining tooling, connect the mounting flange on the oil level maintaining tooling with the flat-top flange surface through bolts, connect the oil filling and draining valve to the gas relay flange next to the converter transformer pressure regulating switch, connect the oil level maintaining valve to the external oil tank, and then inject a certain amount of oil into the cylinder; considering that the "straw hat" structure is 200mm higher than the flat top of the converter transformer, during the replacement of the casing, in order to ensure the normal work, prevent the oil level fluctuation from causing the oil level of the grid side riser to drop, resulting in the "straw hat" being exposed, and set the oil level in the tooling to 300mm. During the casing replacement process, a dedicated person is assigned to monitor the oil level throughout the process, and the oil level is adjusted through the pressure regulating switch gas relay valve and the tooling oil level control valve to always keep the oil level in the tooling at 300mm;
[0045] After filling the tooling with oil to 300mm, remove the six bolts on the neutral point bushing flange (leave two diagonal bolts), then slowly remove the two diagonal bolts, and slightly shake the bushing to prevent a large amount of insulating oil from gushing out of the body. The bushing can be lifted only after the oil level in the tooling remains stable.
[0046] S4. Lift the casing. When the guide rod leaks out, install the guide rod limit fixture, keep the oil pillow pipeline valve slightly open, let the oil slowly overflow from the casing, and slowly lift the neutral point casing to ensure that the external insulating oil of the converter transformer will not flow back into the main body oil tank during the casing lifting process, affecting the cleanliness of the main body insulating oil; during the lifting process, arrange special personnel to be responsible for operating the casing guide rod traction device and monitoring the traction situation to prevent the guide rod from sliding down; when the bottom of the casing is lifted until the sealing plate is completely separated from the flat top, check the oil level status in the fixture again, and use the flange hole sealing plate to cover the casing flange hole;
[0047] Then assemble the two limit rods, both of which are mounted on the cylinder, so that the guide rod passes through the through hole on the limit rod, and at the same time install a clamp on the guide rod; continue to slowly lift the casing until the top of the guide rod is completely exposed, remove the guide rod traction rope, lift off the old casing, and place a sealing gasket on the casing flange.
[0048] S5. Continue to slowly lift the casing until the top of the guide rod is completely exposed, then remove the guide rod traction rope, lift off the old casing, and place a sealing gasket in the casing flange hole;
[0049] S6. Lift the new casing and install the traction rope. Lift the new casing to the upper part of the guide rod. Pass one end of the traction rope through the guide rod hole of the new casing and connect the other end with a special bolt. Screw the special bolt into the threaded hole at the top of the guide rod.
[0050] S7. Slowly lower the casing. When it reaches a height of 600 mm, tighten the traction rope to prevent the guide rod from being pressed down. Remove the guide rod limit fixture and flange hole sealing plate, install the sealing gasket, and pay attention to the oil level in the fixture and the oil level of the riser on the mesh side.
[0051] S8. After the casing is lowered into place, install the flange bolts and tighten them evenly; then slowly open the oil pillow to the body valve, and after observing the oil coming out from the top guide rod of the neutral point casing, close the oil pillow to the body valve to complete the casing exhaust, and then install the general cap of the new casing;
[0052] S9. After draining the oil, remove the oil level maintaining tooling and complete the cleaning work; then open the oil pillow to the main body valve and restore the converter to the operating state.
[0053] In the embodiment of the present application, a method for replacing the neutral point bushing of a converter transformer by draining the oil is used. Due to the setting of the oil level maintaining tooling, the "straw hat" structure of the grid-side high-voltage bushing is always wrapped by the converter transformer oil when the bushing is removed, thereby preventing the straw hat structure from being exposed; therefore, in the subsequent bushing replacement process, there is no need to drain the oil of the converter transformer as a whole and then perform full vacuum oil filling, which saves a lot of time; at the same time, when replacing the bushing, a guide rod limiting tooling is used, and when replacing the bushing, the guide rod copper bar is fixed to prevent the lead from being damaged by downward pressure.
[0054] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for replacing the small oil drain of the neutral point bushing for a converter transformer, characterized in that: The guide rod limiting tool and the oil level holding tool are applied. The oil level holding tool is used to prevent the straw hat structure from being exposed, and the guide rod limiting tool is used to prevent the guide rod from falling. The guide rod limiting tool comprises two limiting rods, and a semicircular notch is provided on the limiting rod. The two limiting rods can be spliced by a screw rod, and the two notches are spliced to form a through hole. The oil level maintenance tool comprises a cylinder, the bottom surface of which is provided with a mounting flange, the bottom side wall is provided with an oil filling and draining valve, the middle side wall is provided with an oil level maintenance valve, and the top is provided with a hanging point; Replacing the casing involves the following steps: S1. Clean the machines and work points; S2. Install the oil level monitoring device: close the gate valve from the main body to the oil pillow pipeline, and install a transparent pipe at the gas next to the pressure regulating switch to the elevated seat on the side of the network; S3. Remove the casing cap, install the casing professional lifting device, install the oil level maintaining tooling, and inject a certain amount of oil into the cylinder; S4. Lift the casing, and when the guide rod leaks out, install the guide rod limit fixture; S5. Continue to slowly lift the casing until the top of the guide rod is completely exposed, then remove the guide rod traction rope, lift off the old casing, and place a sealing gasket in the casing flange hole; S6. Lift the new casing and install the traction rope; S7. Slowly lower the new casing. When it reaches a certain height, remove the guide rod limit fixture. S8. Hold the traction rope tightly, install the new sleeve and copper rod, and complete the exhaust of the new sleeve; S9. After draining the oil, remove the oil level maintaining tooling and complete the cleaning work; then open the oil pillow to the main body valve and restore the converter to the operating state.
2. A method for replacing the small oil drain of a neutral point bushing for a converter transformer according to claim 1, characterized in that The step S1 specifically includes: cleaning the tooling, the hook and hanger, the sleeve and each flange surface with alcohol and cotton gauze; and cleaning the tools that need to be used in oil with oil.
3. A method for replacing the small oil drain of the neutral point bushing for a converter transformer according to claim 2, characterized in that The step S3 is specifically as follows: connecting the mounting flange on the oil level holding fixture to the flat-top flange surface by bolts, connecting the oil filling and draining valve to the flange of the gas relay next to the converter transformer voltage regulating switch, and connecting the oil level holding valve to the oil tank; filling oil into the cylinder, if the height difference between the straw hat structure and the flat top of the converter transformer is h, the oil level in the cylinder is 1.5h; after the oil filling is completed, slightly shake the casing, and proceed to the subsequent steps after the oil level stabilizes.
4. A method for replacing the small oil drain of a neutral point bushing for a converter transformer according to claim 3, characterized in that The specific steps of lifting the casing in step S4 are as follows: keep the oil pillow pipeline valve slightly open to allow the oil to slowly overflow from the casing flange and slowly lift the neutral point casing; after the bottom of the casing leaves the flat top, close the oil pillow pipeline gate valve, lift the bottom of the casing until the sealing plate is completely separated from the flat top, check the oil level in the tooling again, and seal the casing flange hole with a flange hole sealing plate.
5. A method for replacing the small oil drain of the neutral point bushing for a converter transformer according to claim 4, characterized in that The installation of the guide rod limiting tooling in step S4 is specifically as follows: assembling two limiting rods, both limiting rods are mounted on the cylinder, the guide rod passes through the through hole on the limiting rod, and a clamp is installed on the guide rod.
6. A method for replacing the small oil drain of a neutral point bushing for a converter transformer according to claim 5, characterized in that Step S6 specifically includes: hanging the new casing to the upper part of the guide rod, passing one end of the traction rope through the guide rod hole of the new casing, and connecting the other end with a special bolt, which is screwed into the threaded hole at the top of the guide rod.
7. A method for replacing the small oil drain of the neutral point bushing for a converter transformer according to claim 6, characterized in that Step S7 is as follows: slowly lower the casing, and when it reaches a height of 600 mm, tighten the traction rope to prevent the guide rod from being pressed down, remove the guide rod limit fixture and flange hole sealing plate, install the sealing gasket, and pay attention to the oil level to maintain the oil level in the fixture and the oil level of the mesh side riser.
8. A method for replacing the small oil drain of a neutral point bushing for a converter transformer according to claim 7, characterized in that Step S8 specifically includes: after the casing is lowered into place, the flange bolts are installed and tightened evenly; then the oil pillow is slowly opened to the main body valve, and after oil is observed to flow out from the top guide rod of the neutral point casing, the oil pillow is closed to the main body valve, and the general cap of the new casing is installed.
Citation Information
Patent Citations
Method for dismounting large transformer bushing without oil discharging
CN103996984A
Oil-oil bushing cable outlet transformer test method without head removing
CN104062526A
Construction method for quickly dismounting transformer directly connected with GIS equipment
CN112152130A
Method for replacing switching gear box of converter transformer
CN115458312A
Centralized substation equipment
JP6576508B1