Layering and grouping scheduling control method for power distribution network and computer device

By connecting energy storage units to form a group according to the distance threshold in the distribution network and scheduling of electricity within the group, the problem of large energy loss during power scheduling is solved, and the energy utilization rate and scheduling efficiency are improved.

CN118920522APending Publication Date: 2024-11-08HAIBEI POWER SUPPLY COMPANY STATE GRID QINGHAI ELECTRIC POWER +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410960706.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

The existing distribution network layered energy storage system has problems such as large energy loss and low utilization efficiency when scheduling power.

Method used

By connecting the energy storage units to form a group according to the distance threshold range and performing electricity scheduling within the group, priority is given to the use of the closest energy storage units and power generation units for power scheduling, avoiding unnecessary energy transfer and ensuring that during the power scheduling process The lowest energy loss.

Benefits of technology

It effectively reduces the energy loss during the power scheduling process, improves the energy utilization rate and power scheduling efficiency of the distribution network, and avoids the situation of multiple power transfers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118920522A_ABST
    Figure CN118920522A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of power distribution network control, and particularly relates to a hierarchical grouping scheduling control method for a power distribution network and a computer device, and the method comprises the following steps: connecting each energy storage unit with other energy storage units existing in a distance threshold range of the energy storage unit to form a group of the energy storage unit; when the electric quantity of a certain energy storage unit is lower than the lower limit of the electric quantity of the level, the power generation unit connected with the energy storage unit and / or other energy storage units in the energy storage unit cluster are controlled to dispatch electric energy to the energy storage unit; and when the electric quantity of a certain energy storage unit is higher than the upper limit of the electric quantity of the grade, controlling the energy storage unit to dispatch electric energy to other energy storage units in the group of the energy storage unit. Each energy storage unit forms a group according to the distance, and electric energy scheduling is performed in the group according to the hierarchy, so that the loss in the electric energy scheduling process is minimum, and the energy utilization rate of the power distribution network and the electric energy transmission efficiency are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of distribution network control, and in particular relates to a distribution network hierarchical and grouped dispatching control method and a computer device. Background Art

[0002] The development of distribution network related technologies has become mature. Traditional distribution network dispatching and control methods mainly include power optimization dispatching and grid balance control. Dispatching strategies are formulated through optimization algorithms according to actual energy consumption conditions. However, these methods may have problems such as low flexibility of dispatching strategies or insufficient dynamic dispatching capabilities, which may easily lead to undesirable conditions such as difficulty in timely response during peak energy consumption periods and difficulty in local consumption of electricity transmission.

[0003] In order to solve this problem, the Chinese invention patent with authorization announcement number CN108233398B proposed a layered energy storage system and control method. When there is demand from the power grid, the power of the centralized energy storage system at the centralized control layer is preferentially dispatched. If the demand cannot be met, the power of the distributed energy storage system at the convergence layer is dispatched. If the power demand of the power grid still cannot be met, the power of the distributed power grid system at the autonomous layer is dispatched. However, this solution does not take into account the problem of energy loss. When power is dispatched between energy storage systems that are far apart, a large energy loss will be generated, resulting in a large energy loss in this solution and low energy utilization efficiency. Summary of the invention

[0004] The object of the present invention is to provide a distribution network hierarchical and grouped dispatching control method and a computer device to solve the technical problem of large losses incurred during the dispatching of electric energy in a hierarchical energy storage system.

[0005] In order to solve the above technical problems, the present invention provides a distribution network hierarchical and grouped dispatching control method, comprising the following steps:

[0006] Connect each energy storage unit to other energy storage units within a distance threshold range of the energy storage unit to form a group of the energy storage unit;

[0007] When the power of a certain energy storage unit is lower than the lower limit of the power level, control the power generation unit connected to it and / or other energy storage units in the energy storage unit group to dispatch power to it;

[0008] When the power level of a certain energy storage unit is higher than the upper limit of the power level, the energy storage unit is controlled to dispatch power to other energy storage units in its group.

[0009] Furthermore, the method of connecting the energy storage unit with other energy storage units within the distance threshold range of the energy storage unit is as follows: grading the energy storage units, and connecting the energy storage units with the upper-level energy storage units, the same-level energy storage units, and the lower-level other energy storage units within the distance threshold range of the energy storage units to form a group of the energy storage units; the method of controlling other energy storage units within the energy storage unit group to dispatch electric energy to the energy storage unit includes: when the power of a certain energy storage unit is lower than the lower limit of the power of the level, controlling other energy storage units of the same level within the group whose power is above the lower limit of the power of the level to transmit electric energy to the energy storage unit; if there are no other energy storage units of the same level within the group whose power is above the lower limit of the power of the level, controlling the upper-level energy storage units within the group whose power is above the corresponding lower limit to transmit electric energy to the energy storage units; if there are no upper-level energy storage units within the group whose power is above the corresponding lower limit, controlling the lower-level energy storage control units whose power is above the corresponding lower limit to transmit electric energy to the energy storage units.

[0010] Furthermore, the method of connecting the energy storage unit to other energy storage units within the distance threshold range thereof is as follows: grading the energy storage units, connecting the energy storage unit to the upper-level energy storage unit, the same-level energy storage unit and the lower-level other energy storage units within the distance threshold range thereof to form a group of the energy storage unit; the method of controlling the energy storage unit to dispatch electric energy to other energy storage units within its group includes: when the power of the energy storage control unit is higher than the power upper limit of the level, controlling it to transmit electric energy to other energy storage units of the same level within the group whose power is below the corresponding power upper limit; if there are no other energy storage units of the same level within the group whose power is below the corresponding power upper limit, controlling it to transmit electric energy to the upper-level energy storage unit within the group whose power is below the corresponding power upper limit; if there are no upper-level energy storage units within the group whose power is below the corresponding power upper limit, controlling it to transmit electric energy to the lower-level energy storage control unit whose power is below the corresponding power upper limit.

[0011] Furthermore, the energy storage unit is connected to the power generation units within the corresponding distance threshold range. When the power level of a certain energy storage unit is lower than the lower limit of the power level, if the power generation unit connected to the energy storage unit still has surplus power, the power generation unit will be preferentially controlled to transmit power to it. If the power generation units connected to the energy storage unit have no surplus power, other energy storage units in the energy storage unit group will be controlled to transmit power to it.

[0012] Furthermore, the method of connecting the energy storage unit with other energy storage units within its own distance threshold range is as follows: the energy storage unit is divided into three levels: a primary energy storage unit, a secondary energy storage unit and a tertiary energy storage unit; the primary energy storage unit is connected to other primary energy storage units within the second distance threshold range around it, and to secondary energy storage units within the third distance threshold range around it; the secondary energy storage unit is connected to other secondary energy storage units within the fourth distance threshold range around it, and to tertiary energy storage units within the fifth distance threshold range around it; the tertiary energy storage unit is connected to other tertiary energy storage units within the sixth distance threshold range around it;

[0013] The distance threshold corresponding to the connection between the primary energy storage unit and the power generation unit is the first distance threshold, the distance threshold corresponding to the connection between the secondary energy storage unit and the power generation unit is the fourth distance threshold, and the distance threshold corresponding to the connection between the tertiary energy storage unit and the power generation unit is the sixth distance threshold;

[0014] The first distance threshold < the second distance threshold < the third distance threshold < the fourth distance threshold < the fifth distance threshold < the sixth distance threshold.

[0015] Furthermore, the calculation method of the lower limit of electricity of a certain level is: first, the historical power data of the energy storage unit of this level is used to obtain the daily change curve of the energy storage power of the energy storage unit of this level, and then the curve is integrated to obtain the rated electricity of the energy storage unit of this level; the minimum value of the rated electricity of this level is the lower limit of electricity of this level.

[0016] Furthermore, the calculation method of the upper limit of electricity consumption of a certain level is as follows: first, the historical power data of the energy storage unit of this level is used to obtain the daily change curve of the energy storage power of the energy storage unit of this level, and then the curve is integrated to obtain the rated electricity consumption of the energy storage unit of this level; the maximum value of the rated electricity consumption of this level is the upper limit of electricity consumption of this level.

[0017] Furthermore, when controlling other energy storage units of the same level within the group whose electric quantity is above the lower limit of electric quantity of the level to transmit electric energy to it, controlling the upper-level energy storage unit within the group whose electric quantity is above the corresponding lower limit to transmit electric energy to it, and controlling the next-level energy storage control unit whose electric quantity is above the corresponding lower limit to transmit electric energy to it, the energy storage unit closest to the energy storage unit is preferentially controlled to transmit electric energy to the energy storage unit.

[0018] Furthermore, when controlling it to transmit electric energy to other energy storage units of the same level within the group whose electric power is below the corresponding upper limit, controlling it to transmit electric energy to the upper-level energy storage unit within the group whose electric power is below the corresponding upper limit, and controlling it to transmit electric energy to the next-level energy storage control unit whose electric power is below the corresponding upper limit, the energy storage unit is preferentially controlled to transmit electric energy to the energy storage unit closest to the energy storage unit.

[0019] Furthermore, the method for classifying all energy storage units in the distribution network is as follows: the energy storage units are classified according to their voltage levels, energy storage units of the same voltage level are at the same level, and energy storage units with higher voltage levels have higher levels.

[0020] The present invention is an improved invention creation, and its beneficial effects are as follows: the distribution network hierarchical and grouped dispatching control method of the present invention connects the energy storage unit with other surrounding energy storage units according to the distance to form a group, when the power of a certain energy storage unit is lower than the lower limit of the power of the level, the power generation unit connected to it and / or other energy storage units in the energy storage unit group are controlled to dispatch electric energy to it; when the power of a certain energy storage unit is higher than the upper limit of the power of the level, the energy storage unit is controlled to dispatch electric energy to other energy storage units in its group, and a group of the energy storage unit is formed within a certain range around the energy storage unit, and electric energy is dispatched within the group, which ensures that the distance between the two parties is not too far during dispatch, and there will be no situation where the power is transferred multiple times and finally reaches the required energy storage unit, so that the energy loss in the dispatching process is minimized, and the energy utilization rate of the distribution network and the power dispatching efficiency can be improved.

[0021] To solve the above technical problems, the present invention also provides a computer device, including a processor, a memory and a computer program stored in the memory, wherein the processor executes the computer program to implement the method steps described in the distribution network hierarchical and grouped dispatching control method of the present invention.

[0022] The present invention is an improved invention creation, and its beneficial effects are as follows: the computer device of the present invention, when executing a computer program, connects the energy storage unit with other surrounding energy storage units according to the distance to form a group, and when the power of a certain energy storage unit is lower than the lower limit of the power of the level, controls the power generation unit connected to it and / or other energy storage units in the energy storage unit group to dispatch electric energy to it; when the power of a certain energy storage unit is higher than the upper limit of the power of the level, controls the energy storage unit to dispatch electric energy to other energy storage units in its group, forms a group of the energy storage unit within a certain range around the energy storage unit, and dispatches electric energy within the group, ensuring that the distance between the two parties is not too far during dispatch, and that the power is not transferred multiple times to finally reach the required energy storage unit, so that the energy loss in the dispatch process is minimized, and the energy utilization rate of the distribution network and the efficiency of electric energy dispatch can be improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 is a flow chart of a distribution network hierarchical and grouped dispatching control method according to a method embodiment of the present invention;

[0024] Figure 2 It is a schematic diagram of the connection relationship of the energy storage units of the method embodiment of the present invention. DETAILED DESCRIPTION

[0025] In the computer device of the present invention, when the processor executes the computer program, the energy storage unit is connected with other surrounding energy storage units according to the distance to form a group, and each energy storage unit is connected with other surrounding upper-level energy storage units, same-level energy storage units and lower-level energy storage units to form the group of the energy storage unit. When the power of a certain energy storage unit is lower than the lower limit of the power of the level, the other energy storage units in the energy storage unit group are controlled to dispatch electric energy to it; when the power of a certain energy storage unit is higher than the upper limit of the power of the level, the energy storage unit is controlled to dispatch electric energy to other energy storage units in its group, and the group of the energy storage unit is formed within a certain range around the energy storage unit. Electric energy is dispatched within the group, which ensures that the distance between the two parties is not too far during dispatch, and that the electric energy is not transferred multiple times to finally reach the required energy storage unit, so that the energy loss in the dispatch process is minimized, and the energy utilization rate of the distribution network and the efficiency of electric energy dispatch can be improved.

[0026] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention is further described in detail below with reference to the accompanying drawings and embodiments.

[0027] Method Example:

[0028] The distribution network hierarchical and grouped dispatching control method of the present invention divides the energy storage units in the distribution network into several levels. In this embodiment, the energy storage units are divided into primary energy storage units (330KV), secondary energy storage units (110KV) and tertiary energy storage units (35KV) according to their voltage levels. As other implementations, they can be analyzed according to the actual voltage levels, or they can be classified according to the capacity of the energy storage units. For ease of understanding, the following description is based on three levels of energy storage units.

[0029] In this embodiment, each energy storage unit includes an energy storage device, a communication device, an energy transmission device and a transformer device. The energy storage device is used to store electrical energy and output electrical energy when appropriate. The energy storage form can be chemical energy storage or mechanical energy storage. The communication device is used to send corresponding request signals to the corresponding energy storage unit and power generation unit, using conventional anti-interference communication equipment. The energy transmission device is used to achieve energy transmission, using conventional high-load energy transmission equipment. The transformer device is used to adjust the voltage of the electrical energy received by the energy storage unit to a voltage that it can adapt to.

[0030] like Figure 1 As shown, the distribution network hierarchical grouping dispatching control method of the present invention has the following main steps:

[0031] Step 1: Lay out and connect the energy storage unit.

[0032] An iterative algorithm is used to deploy multiple primary energy storage units in the target area, multiple secondary energy storage units in the target area, and multiple tertiary energy storage units on the edge line of the target area.

[0033] Each energy storage unit is connected to the energy storage unit of the previous level, the energy storage unit of the same level, and the energy storage unit of the next level within the distance threshold range to form a group of the energy storage unit. Each energy storage unit forms its own group. There are multiple energy storage units forming as many groups as needed. The groups can overlap with each other, that is, one energy storage unit can belong to different groups. The connection method in this embodiment is specifically as follows:

[0034] The primary energy storage unit is connected to the power generation units with the same voltage level as its surrounding units whose distance does not exceed the first distance threshold, to other primary energy storage units with a distance not exceeding the second distance threshold, and to the secondary energy storage units with a distance not exceeding the third distance threshold.

[0035] The secondary energy storage unit is connected to other secondary energy storage units whose distances around it do not exceed the fourth distance threshold, and is connected to tertiary energy storage units whose distances around it do not exceed the fifth distance threshold. The secondary energy storage unit is also connected to power generation units of the same voltage level whose distances around it do not exceed the fourth distance threshold.

[0036] The three-level energy storage unit is connected to other three-level energy storage units around it whose distance does not exceed the sixth distance threshold. The three-level energy storage unit is also connected to power generation units of the same voltage level whose distance does not exceed the sixth distance threshold.

[0037] Specific connection relationships such as Figure 2 The above distances and distance thresholds are the actual distances traveled by the connection lines.

[0038] When the projections of the connection lines cross during the interconnection process, the connection lines with longer projection lengths are discarded. The first distance threshold < the second distance threshold < the third distance threshold < the fourth distance threshold < the fifth distance threshold < the sixth distance threshold.

[0039] When the power generation unit generates energy, it transmits the energy to its own energy-consuming equipment; when the energy generated by the power generation unit exceeds the energy required by its own energy-consuming equipment, the energy is transmitted to the connected energy storage unit; when the energy-consuming unit issues an energy request, the energy is transmitted from the energy storage unit connected to the energy-consuming unit to the energy-consuming unit.

[0040] Gurobi, CPLEX, MATLAB / Simulink and other optimization algorithm software can be used to determine the optimal energy storage unit layout location and quantity. The specific iterative algorithm has been applied for a software patent and will not be described in detail in the present invention.

[0041] Step 2: Calculate the upper and lower limits of power for energy storage units of different levels.

[0042] According to historical data, the annual load variation curve and other characteristics of the target area are obtained. According to the annual load variation curve and other characteristics of the target area, the applicable period of the rated energy storage level is determined. According to the daily load variation curve characteristics of the current period, the rated energy storage calculation formula is used to obtain the rated energy upper limit, buffer zone and rated energy lower limit corresponding to the current rated energy storage level; the rated energy storage calculation formula is:

[0043]

[0044] where f i (t) is the daily variation curve of the applicable period of the current rated energy storage level, e -jωt and e iωt is an orthogonal basis, j and i are imaginary parts, ω is the energy consumption change frequency, t is time, n is the number of days in the applicable period of the current rated energy storage level, and the frequency components CM with the same or similar characteristics are extracted; the buffer zone D is:

[0045] D=[F t |max,f i (t)|max];

[0046] The rated energy storage calculation formula is to perform Fourier transformation on the daily variation curve and inverse Fourier transformation on the extracted result. The maximum and minimum values ​​of the rated energy storage calculation formula are the upper and lower limits of the rated power.

[0047] The historical daily variation curve f of the primary energy storage unit i (t) is substituted into the rated energy storage calculation formula. The maximum value of the formula is the upper limit of the first-level energy, and the minimum value is the lower limit of the first-level energy. i (t) is substituted into the rated energy storage calculation formula. The maximum value of the formula is the upper limit of the secondary energy, and the minimum value is the lower limit of the secondary energy. i (t) is substituted into the rated energy storage calculation formula. The maximum value of the formula is the upper limit of the third level of energy, and the minimum value is the lower limit of the third level of energy.

[0048] Step 3: Combine the calculated upper and lower limits of energy storage at different levels to adopt different strategies for different levels of energy storage units to control power dispatch.

[0049] Although different levels of energy storage units have different power dispatch strategies, the priority is how to minimize the loss during the power dispatch process. Therefore, the dispatch strategies of energy storage units of different levels all follow the principle of minimum loss during the power dispatch process. For example, power is only dispatched within the same group, and when dispatching within the same group, priority is given to dispatching within the same group. This is because groups within the same group are directly connected and do not need to be dispatched through multiple transfers, which minimizes energy loss; and because energy storage units of the same level have the same voltage level, the loss when dispatching each other is also minimal. In addition, the dispatch strategy should also prioritize power dispatch to higher-level energy storage units as much as possible.

[0050] Based on the above ideas, the following scheduling strategy is formed:

[0051] When the power level of a certain energy storage unit is lower than the lower limit of the power level of that level, other energy storage units of the same level in the group whose power levels are above the lower limit of the power level are controlled to transmit power to it; if there are no other energy storage units of the same level in the group whose power levels are above the lower limit of the power level of that level, the energy storage units of the upper level in the group whose power levels are above the corresponding lower limit of the power level are controlled to transmit power to it; if there are no energy storage units of the upper level in the group whose power levels are above the corresponding lower limit of the power level, the energy storage control units of the lower level whose power levels are above the corresponding lower limit of the power level are controlled to transmit power to it.

[0052] When the power of the energy storage control unit is higher than the power upper limit of the level, it is controlled to transmit electric energy to other energy storage units of the same level in the group whose power is below the corresponding power upper limit; if there are no other energy storage units of the same level in the group whose power is below the corresponding power upper limit, it is controlled to transmit electric energy to the upper-level energy storage unit in the group whose power is below the corresponding power upper limit; if there is no upper-level energy storage unit in the group whose power is below the corresponding power upper limit, it is controlled to transmit electric energy to the next-level energy storage control unit whose power is below the corresponding power upper limit.

[0053] The following is a detailed description of the three levels of energy storage units:

[0054] The power dispatch strategy of the primary energy storage unit is as follows:

[0055] When the energy storage of a first-level energy storage unit is lower than the first-level power lower limit, a request for increasing energy reception is sent to the connected power generation unit. If the power generation unit still has surplus energy, the request is accepted to increase the power transmitted to the first-level energy storage unit; when the power generation units that receive the request for increasing energy reception have no surplus energy and refuse the request for increasing energy reception, the request for energy reception is sent to other first-level energy storage units that are connected to the first-level energy storage unit and have energy storage not lower than the first-level power lower limit; after the other first-level energy storage units that receive the request for energy reception accept the request, the energy is transmitted from the other first-level energy storage units that accept the request to the first-level energy storage unit; when there are no other first-level energy storage units in the group whose energy storage is not lower than the first-level power lower limit or the other first-level energy storage units that receive the request for energy reception all refuse the request for energy reception, the request for energy reception is sent to the second-level energy storage unit that is connected to the first-level energy storage unit and has energy storage above the second-level power lower limit, and energy is transmitted from the second-level energy storage unit that receives the request for energy reception to the first-level energy storage unit.

[0056] When the energy transmitted to the primary energy storage unit exceeds the energy transmitted to the energy-consuming unit, the excess energy is converted into a storable form and stored in the primary energy storage unit; when the energy storage of a primary energy storage unit reaches the primary power upper limit, an energy transmission request is sent to other primary energy storage units that are connected to the primary energy storage unit and have not reached the primary power upper limit; after obtaining permission, energy is transmitted from the primary energy storage unit to other primary energy storage units that have issued permission; when there are no other primary energy storage units in the group that have not reached the primary power upper limit or other primary energy storage units that have received the energy transmission request all reject the energy transmission request, an energy transmission request is sent to the secondary energy storage unit connected to the primary energy storage unit and whose energy storage is lower than the secondary power upper limit, and energy is transmitted from the primary energy storage unit to the secondary energy storage unit that accepts the energy transmission request.

[0057] The power dispatch strategy of the secondary energy storage unit is as follows:

[0058] When the energy storage of a secondary energy storage unit reaches the secondary power upper limit, an energy transmission request is sent to other secondary energy storage units that are connected to the secondary energy storage unit and have not reached the secondary power upper limit. After obtaining permission, energy is transmitted from the secondary energy storage unit to the other secondary energy storage units that issued the permission. When there are no other secondary energy storage units that have not reached the secondary power upper limit in the group or all secondary energy storage units that have received the energy transmission request reject the energy transmission request, an energy transmission request signal is sent to the primary energy storage unit that is connected to the secondary energy storage unit and has not reached the primary power upper limit. After obtaining permission, energy is transmitted from the secondary energy storage unit to the primary energy storage unit that issued the permission. When there are no primary energy storage units that have not reached the primary power upper limit in the group or all primary energy storage units that have received the energy transmission request reject the energy transmission request, an energy transmission request is sent to the tertiary energy storage unit that has not reached the tertiary power upper limit connected to the secondary energy storage unit, and energy is transmitted from the secondary energy storage unit to the tertiary energy storage unit that receives the energy transmission request.

[0059] When the energy storage of a secondary energy storage unit is lower than the lower limit of the secondary power quantity, an energy receiving request is sent to other secondary energy storage units connected to the secondary energy storage unit and whose energy storage is not lower than the lower limit of the secondary power quantity. When the other secondary energy storage units receiving the energy receiving request give permission, energy is transferred from the other secondary energy storage units giving permission to the secondary energy storage unit; when there are no other secondary energy storage units connected to the secondary energy storage unit and whose energy storage is not lower than the lower limit of the secondary power quantity or the other secondary energy storage units receiving the energy receiving request reject the energy receiving request, an energy receiving request is sent to a connected primary energy storage unit and whose energy storage is not lower than the lower limit of the primary power quantity. After obtaining permission, energy is transferred from the primary energy storage unit that issued the permission to the secondary energy storage unit; when there are no first-level energy storage units connected and whose energy storage is not lower than the lower limit of the first-level power quantity or the first-level energy storage units receiving the energy receiving request all reject the energy receiving request, an energy receiving request is sent to a third-level energy storage unit connected to the second-level energy storage unit and whose energy storage is not lower than the lower limit of the third-level power quantity, and energy is transferred from the third-level energy storage unit that receives the energy receiving request to the second-level energy storage unit. Conventional anti-interference communication equipment is used to send requests, and conventional high-voltage energy transmission equipment is used for energy transmission.

[0060] The power dispatch strategy of the three-level energy storage unit is as follows:

[0061] When the energy storage of a certain level 3 energy storage unit exceeds the level 3 power upper limit, an energy transmission request is sent to other level 3 energy storage units connected to the level 3 energy storage unit and whose energy storage does not reach the level 3 power upper limit. After obtaining permission, the energy is transmitted from the level 3 energy storage unit to the level 3 energy storage unit that issued the permission. When other level 3 energy storage units that are not connected to the level 3 energy storage and have not reached the level 3 power upper limit or the level 3 energy storage units that have received the energy transmission request reject the energy transmission request, an energy transmission request is sent to the level 2 energy storage unit that is connected to the level 3 energy storage unit and whose energy storage does not reach the level 2 power upper limit. After obtaining permission, the energy is transmitted from the level 3 energy storage unit to the level 2 energy storage unit that issued the permission. Conventional anti-interference communication equipment is used for sending requests, and conventional high-voltage energy transmission equipment is used for energy transmission.

[0062] When using the above-mentioned dispatching strategy of the three levels of energy storage units for electric energy dispatching, there may be a situation where more than two energy storage control systems of the same level accept energy transmission requests from one energy storage control system at the same time. At this time, the energy storage control system that issues the energy transmission request gives priority to supplying power to the energy storage control system that is closest to the energy storage control system that accepts the energy transmission request, so that the loss during the energy transmission process is lower; similarly, there may be a situation where two energy storage control systems of the same level receive energy receiving requests from one energy storage control system at the same time. At this time, the energy storage unit closest to the energy storage unit that issues the energy receiving request is given priority to supply power to it.

[0063] Through the above-mentioned method steps and dispatching strategy, the distribution network hierarchical and grouped dispatching control method of the present invention can maintain the power balance of all energy storage units in the distribution network as much as possible. When the power of a certain energy storage unit is too low, other energy storage units are dispatched to transmit power to it. When the power of a certain energy storage unit is too high, power is transmitted to other energy storage units, thereby avoiding the imbalance situation that the power of some energy storage units in the distribution is too high and the power of other energy storage units is too low. At the same time, in the process of power dispatching, the dispatching strategy of the present invention is used for dispatching, which reduces unnecessary power loss, ensures the minimum power loss in the dispatching process, and enhances the power utilization rate of the distribution network.

[0064] Device Example:

[0065] The computer device of the present invention includes a processor, a memory, and a computer program stored in the memory, and the processor executes the computer program to implement the steps of the distribution network hierarchical and grouped dispatching control method as described in the method embodiment of the present invention. The specific steps, principles, and beneficial effects of the control method have been described in detail in the method embodiment, and will not be repeated in this embodiment.

[0066] The processor may be a microprocessor MCU, a programmable logic device FPGA or other processing device. The memory may be various memories, such as RAM, ROM or the like.

Claims

1. A distribution network hierarchical and grouped dispatching control method, characterized in that: The following steps are involved: Connect each energy storage unit to other energy storage units within a distance threshold range of the energy storage unit to form a group of the energy storage unit; When the power of a certain energy storage unit is lower than the lower limit of the power level, control the power generation unit connected to it and / or other energy storage units in the energy storage unit group to dispatch power to it; When the power level of a certain energy storage unit is higher than the upper limit of the power level, the energy storage unit is controlled to dispatch power to other energy storage units in its group.

2. The distribution network hierarchical and grouped dispatching control method according to claim 1 is characterized in that: The method of connecting an energy storage unit to other energy storage units within a distance threshold range thereof is as follows: grading the energy storage units, and connecting the energy storage units to the upper-level energy storage units, the same-level energy storage units, and the lower-level other energy storage units within the distance threshold range thereof to form a group of the energy storage units; the method of controlling other energy storage units within the energy storage unit group to dispatch electric energy to the energy storage unit comprises: when the power of a certain energy storage unit is lower than the power lower limit of the level, controlling other energy storage units of the same level within the group whose power is above the power lower limit of the level to transmit electric energy to the energy storage unit; if there are no other energy storage units of the same level within the group whose power is above the power lower limit of the level, controlling the upper-level energy storage units within the group whose power is above the corresponding power lower limit to transmit electric energy to the energy storage units; if there are no upper-level energy storage units within the group whose power is above the corresponding power lower limit, controlling the lower-level energy storage control units whose power is above the corresponding power lower limit to transmit electric energy to the energy storage units.

3. The distribution network hierarchical and grouped dispatching control method according to claim 1, characterized in that: The method of connecting an energy storage unit to other energy storage units within a distance threshold range thereof is as follows: grading the energy storage units, connecting the energy storage units to the upper-level energy storage units, the same-level energy storage units, and other lower-level energy storage units within the distance threshold range thereof to form a group of the energy storage units; the method of controlling the energy storage unit to dispatch electric energy to other energy storage units within its group includes: when the power of the energy storage control unit is higher than the upper power limit of the level, controlling it to transmit electric energy to other energy storage units of the same level within the group whose power is below the corresponding upper power limit; if there are no other energy storage units of the same level within the group whose power is below the corresponding upper power limit, controlling it to transmit electric energy to the upper-level energy storage unit within the group whose power is below the corresponding upper power limit; if there are no upper-level energy storage units within the group whose power is below the corresponding upper power limit, controlling it to transmit electric energy to the lower-level energy storage control unit whose power is below the corresponding upper power limit.

4. The distribution network hierarchical and grouped dispatching control method according to claim 1, characterized in that: The energy storage unit is connected to the power generation units within the corresponding distance threshold range. When the power level of a certain energy storage unit is lower than the lower limit of the power level, if the power generation unit connected to the energy storage unit still has surplus power, the power generation unit will be controlled to transmit power to it first. If the power generation units connected to the energy storage unit have no surplus power, other energy storage units in the energy storage unit group will be controlled to transmit power to it.

5. The distribution network hierarchical and grouped dispatching control method according to claim 4 is characterized in that: The method for connecting an energy storage unit to other energy storage units within its own distance threshold range is as follows: the energy storage units are divided into three levels: primary energy storage unit, secondary energy storage unit and tertiary energy storage unit; the primary energy storage unit is connected to other primary energy storage units within the second distance threshold range around it, and to secondary energy storage units within the third distance threshold range around it; the secondary energy storage unit is connected to other secondary energy storage units within the fourth distance threshold range around it, and to tertiary energy storage units within the fifth distance threshold range around it; the tertiary energy storage unit is connected to other tertiary energy storage units within the sixth distance threshold range around it; The distance threshold corresponding to the connection between the primary energy storage unit and the power generation unit is the first distance threshold, the distance threshold corresponding to the connection between the secondary energy storage unit and the power generation unit is the fourth distance threshold, and the distance threshold corresponding to the connection between the tertiary energy storage unit and the power generation unit is the sixth distance threshold; The first distance threshold < the second distance threshold < the third distance threshold < the fourth distance threshold < the fifth distance threshold < the sixth distance threshold.

6. The distribution network hierarchical and grouped dispatching control method according to claim 2, characterized in that: The calculation method for the lower limit of electricity of a certain level is: first, the historical power data of the energy storage unit of this level is used to obtain the daily change curve of the energy storage power of the energy storage unit of this level, and then the curve is integrated to obtain the rated electricity of the energy storage unit of this level; the minimum value of the rated electricity of this level is the lower limit of electricity of this level.

7. The distribution network hierarchical and grouped dispatching control method according to claim 3 is characterized in that: The calculation method of the upper limit of electricity consumption of a certain level is as follows: first, the historical power data of the energy storage unit of this level is used to obtain the daily change curve of the energy storage power of the energy storage unit of this level, and then the curve is integrated to obtain the rated electricity consumption of the energy storage unit of this level; the maximum value of the rated electricity consumption of this level is the upper limit of electricity consumption of this level.

8. The distribution network hierarchical and grouped dispatching control method according to claim 2, characterized in that: When controlling other energy storage units of the same level within the group whose electric quantity is above the lower limit of the electric quantity of the level to transmit electric energy to it, controlling the upper-level energy storage unit within the group whose electric quantity is above the corresponding lower limit of the electric quantity to transmit electric energy to it, and controlling the next-level energy storage control unit whose electric quantity is above the corresponding lower limit of the electric quantity to transmit electric energy to it, the energy storage unit closest to the energy storage unit is preferentially controlled to transmit electric energy to the energy storage unit.

9. The distribution network hierarchical and grouped dispatching control method according to claim 3, characterized in that: When controlling it to transmit electric energy to other energy storage units of the same level within the group whose electric power is below the corresponding upper limit, controlling it to transmit electric energy to the upper-level energy storage unit within the group whose electric power is below the corresponding upper limit, and controlling it to transmit electric energy to the next-level energy storage control unit whose electric power is below the corresponding upper limit, the energy storage unit is preferentially controlled to transmit electric energy to the energy storage unit closest to the energy storage unit.

10. A computer device comprising a processor, a memory and a computer program stored in the memory, characterized in that: The processor executes the computer program to implement the steps of the distribution network hierarchical and grouped dispatching control method described in any one of claims 1-9.