Quality control supervision method in communication engineering supervision

Through fiber tester and database technology, fast and accurate fault point positioning and maintenance solution selection in communication engineering are achieved, the problems of low efficiency and high cost in the existing technology are solved, and the efficiency and accuracy of communication engineering quality control are improved. .

CN118921113AActive Publication Date: 2024-11-08NINGBO WANSHI ENGINEERING MANAGEMENT CONSULTING CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410896873.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-11-08
Estimated Expiration
2044-07-05

AI Technical Summary

Technical Problem

The existing communication engineering quality control methods rely on manual testing and are inefficient, so they cannot quickly determine whether the fault point and reserved fiber length meet the needs, resulting in long maintenance time and high cost.

Method used

The fiber tester is used to monitor the fiber lines, obtain pole information and reserved fiber length through the database, calculate the fault point range, select the optimal maintenance node, use the reserved fiber coil for tensile replacement, and update the database in real time.

Benefits of technology

It improves the location accuracy and maintenance efficiency of fault points, reduces manual errors and material waste, ensures the accuracy and real-time information, and reminds and warnings to avoid delays caused by insufficient reserved fibers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118921113A_ABST
    Figure CN118921113A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of communication engineering quality control, and discloses a monitoring method for quality control in communication engineering supervision, which comprises the following steps of: testing a fault point in an optical fiber line by using an optical fiber tester, and feeding back the actual optical fiber length from the fault point to a test starting point; the actual optical fiber length comprises the optical fiber length between two adjacent telegraph poles and the reserved optical fiber length on the telegraph poles, determining a theoretical interval where a fault point exists through calculation, testing the loss value of the fault point, selecting a breakpoint according to the theoretical interval and testing the loss value of the breakpoint, and further determining the interval of the fault point by comparing the difference of the two loss values. And judging the distance between the telegraph pole and the adjacent telegraph pole to select a maintenance scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of communication engineering quality control, and in particular to a supervision method for quality control in a communication engineering. Background Art

[0002] The development of information technology and the diversification of communication channels have led to higher and higher requirements for the quality of information dissemination platforms. The importance of communication engineering has gradually become prominent in the process of information technology application. The quality of communication engineering directly determines the speed and quality of information dissemination. Communication engineering quality control is an important part of construction management, which has an important impact on improving the quality of the project and its overall performance. As the requirements for information quality gradually increase, quality issues in communication engineering have gradually attracted the attention of all sectors of society. Practice has proved that effective quality control is the most effective way to ensure the quality of communication construction projects.

[0003] At present, the quality control of communication projects is generally dominated by manual work. Communication projects are tested manually using test instruments and the test points are constantly changed. This leads to low work efficiency and long troubleshooting time. When repairing faulty optical fibers, not only is it impossible to quickly determine the best repair point, but it is also impossible to determine whether the reserved optical fiber length meets the repair needs. When the reserved optical fiber is insufficient, there is no timely warning.

[0004] In summary, communication projects are now in urgent need of a fast and efficient quality control supervision method. Summary of the invention

[0005] The present invention provides a method for supervising quality control in a communication project, which is used to promote solving the problems mentioned in the above background technology.

[0006] The present invention provides the following technical solution: a supervision method for quality control in communication engineering supervision, comprising:

[0007] S1 obtains all the information related to the electric poles, marks them, and stores the information related to the electric poles in the database;

[0008] S2 obtains the distance between two adjacent electric poles and the length of the reserved optical fiber coil on the electric poles through the database;

[0009] S3 uses a fiber optic tester to test the entire fiber optic line and monitor the actual length of the fiber optic cable from the fault point to the utility pole at the test endpoint;

[0010] S4 locates the farthest electric pole according to the fault point length fed back by the optical fiber tester, forming the first test area;

[0011] S5 forms a second test area by calculating and selecting prediction nodes for the first test area;

[0012] S6 performs error processing on the second test area to form a third test area, selects breakpoints in the third test area, determines the range of the fault point, and performs maintenance according to the endpoints on both sides of the fault point range:

[0013] S7 determines the electric poles closest to the endpoints on both sides of the fault point range, and uses its reserved optical fiber coil to stretch and replace the faulty interception section.

[0014] Optionally, the information related to all electric poles is obtained, marked, and stored in a database:

[0015] The distance between two adjacent electric poles is c.

[0016] Get the theoretical fiber length between every two adjacent poles.

[0017] The theoretical optical fiber length is the distance c between two adjacent electric poles and the reserved optical fiber length b on each electric pole.

[0018] Store the above information in the database,

[0019] Randomly select the pole at the end point of the entire optical fiber line as the starting point, and mark the poles in sequence starting from the starting point.

[0020] The pole at the end point contains only one adjacent pole and no optical fiber is reserved.

[0021] Optionally, the entire optical fiber line is tested using an optical fiber tester to monitor the actual length of the optical fiber from the fault point to the electric pole at the test endpoint:

[0022] Use a fiber optic tester to test the entire fiber optic line from the starting point.

[0023] If a fault point is found in the optical fiber, the optical fiber tester will feedback the actual length h of the optical fiber from the fault point to the starting point.

[0024] Optionally, the fault point length fed back by the optical fiber tester is located at the farthest electric pole to form a first test area:

[0025] According to the actual length h of the optical fiber at the fault point, calculate the actual distance to the pole and obtain the number of the farthest pole.

[0026] The farthest pole number can be obtained by the following formula:

[0027]

[0028] In the above formula, m is the number of poles, that is, the serial number of the farthest pole, n is the total number of poles in the communication project, h is the actual length of the optical fiber at the fault point, c is the distance between adjacent wires, b is the reserved optical fiber length of each pole, and the symbol Indicates rounding up.

[0029] The mth electric pole is selected as the termination electric pole, and the distance between the electric pole at the test endpoint and the termination electric pole is taken as the first test area.

[0030] Optionally, the second test area is formed by calculating and selecting prediction nodes from the first test area:

[0031] The theoretical position of the fault point from the m-1th pole is calculated by the following formula. The theoretical position is the straight-line distance between two adjacent poles at the same height:

[0032]

[0033] In the above formula, k represents the distance from the fault point to the theoretical position of the fault point on the m-1th pole, h is the actual length of the optical fiber at the fault point, m represents the number of the farthest pole, that is, the termination pole, n represents the total number of poles for the communication project, c represents the distance between adjacent poles, and b is the reserved optical fiber length for each pole.

[0034] Taking the m-1th electric pole as the starting point, the point with a distance k in the test direction of the optical fiber tester, i.e. the theoretical position, is selected as the predicted node, and the area between the predicted node and the m-1th electric pole is taken as the second test area.

[0035] Optionally, the second test area is error processed to form a third test area, a breakpoint is selected in the third test area, a fault point range is determined, and maintenance is performed according to endpoints on both sides of the fault point range:

[0036] The minimum error ratio between the actual length of the optical fiber at the fault point and the theoretical length of the optical fiber at the fault point is w, and the maximum error ratio is v.

[0037] Get the distance between the pole at the endpoint and the m-1 pole, recorded as x, and get the distance from the theoretical position to the m-1 pole, which is k;

[0038] Calculate the total distance Y=x+k of the optical fiber installed on the pole;

[0039] Get the maximum loss value = Y × v;

[0040] Get the minimum loss value = Y × w;

[0041] In the reverse direction of the test, select the point with the maximum loss value from the prediction node in the second test area as the first prediction node.

[0042] In the reverse direction of the test, select the point with the minimum loss value from the prediction node in the second test area as the second prediction node.

[0043] The area from the first prediction node to the second prediction node is used as the third test area.

[0044] Obtain the point with the largest optical fiber curvature value in the third test area, cut off the point with the largest optical fiber curvature value as the first breakpoint, and the optical fiber curvature value is the degree of optical fiber bending.

[0045] Start from the starting point and test the first breakpoint.

[0046] If the feedback value is less than the actual distance h of the fault point, the difference f between the feedback value and the actual distance h of the fault point is calculated. Taking the first breakpoint as the starting point, a point with a length of f is selected along the test direction as the second breakpoint to form a segment with a length of f. The difference f is stored in the set F.

[0047] If the feedback value is equal to the actual distance h from the fault point, the area between the first breakpoint and the first prediction node is selected as the pre-test area.

[0048] Take the first breakpoint as the starting point, test the fault point, the feedback value is p, select the first breakpoint in the pre-test area with a distance of p from the first prediction point and cut it off as the second breakpoint, obtain the formed interception segment length p, and store it in the set F,

[0049] The maintenance plan is selected based on the distance between the intercepted section and the m-1th pole and the mth pole and the corresponding reserved optical fiber length.

[0050] Optionally, the maintenance plan is selected by the distance between the intercepted segment and the m-1th electric pole and the mth electric pole and the corresponding reserved optical fiber length:

[0051] Get the shortest distance e1 between the endpoint of the intercepted segment and the m-1th electric pole,

[0052] Get the shortest distance e2 between the endpoint of the intercepted segment and the mth electric pole,

[0053] If e1 is greater than or equal to e2, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement. The stretching length is the length of the cut section. The reserved optical fiber length of the electric pole in the database is updated.

[0054] If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the mth electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the mth electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time.

[0055] If e1 is less than e2, the reserved optical fiber on the mth pole is selected as the maintenance point for stretching and replacement. The stretching length is the cut segment. The reserved optical fiber length of the pole in the database is updated.

[0056] If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the m-1th electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time.

[0057] The present invention has the following beneficial effects:

[0058] 1. A supervision method for quality control in the supervision of communication engineering projects, which uses a fiber optic tester to monitor the fiber optic line. When a fault is found, the actual length of the fiber optic cable from the fault point to the starting point can be fed back. The farthest pole from the theoretical position of the fault point is calculated according to the actual length of the fiber optic cable at the fault point, and the area between the farthest pole and the starting point is used as the first test area to shorten the range of the fault point. The position of the fault point between the farthest pole and the second farthest pole is calculated according to the distance between adjacent poles and the length of the reserved coil on the pole, and the area between the second farthest pole and the point is used as the second test area to further shorten the range of the fault point. According to the error range between the actual length of the fiber optic cable at the fault point and the theoretical length of the fault point, the range of the fault point is shortened to within the error range. In this way, the range of the fiber optic fault point can be accurately located, and the maintenance time and cost caused by the unclear fault point can be reduced. This can greatly reduce manual errors and improve the efficiency of determining the range of the fault point.

[0059] 2. A supervision method for quality control in the supervision of communication engineering projects, which selects the point with the largest bending degree of the optical fiber in the test area to cut it and conducts a test. If the test feedback distance is less than the actual length of the optical fiber at the fault point, a point is further selected for cutting based on the difference between the two, and the resulting intercepted segment is the final location of the fault point; if the test feedback distance is equal to the actual length of the optical fiber at the fault point, it means that the cutting point is after the fault point, and the distance from the fault point in the reverse direction is obtained by testing the test area in the reverse direction, and the distance is cut based on this, and the resulting intercepted segment is the final location of the fault point. In this way, the range of the fault point can be determined, the workload of blindly searching for the fault point is reduced, and work efficiency is improved.

[0060] 3. This method of quality control in communication engineering supervision selects the best maintenance plan by comparing the poles and reserved optical fiber lengths at the endpoints on both sides of the fault point, and uses the reserved optical fiber coils on the poles for stretching and replacement, which simplifies the maintenance process, improves maintenance efficiency, reduces material waste and maintenance time. When the reserved optical fiber length is not enough to cover the length required for maintenance, the system will issue an early warning to remind the staff to replace it in time, avoiding delays caused by insufficient reserved optical fiber.

[0061] 4. This method of quality control in the supervision of communication projects realizes the systematic management of communication projects by storing the pole information and the reserved optical fiber length in the database, and improves the efficiency of information retrieval and updating. During the maintenance process, the reserved optical fiber length of the poles in the database will be updated in real time, ensuring the accuracy and timeliness of the information.

[0062] 5. This quality control supervision method in communication engineering supervision can determine the fault point range to the greatest extent, reduce the length of the intercepted section, and save costs by calculating the error between the actual length of the optical fiber and the theoretical position of the optical fiber length. BRIEF DESCRIPTION OF THE DRAWINGS

[0063] Figure 1 It is a schematic diagram of the structure of the present invention.

[0064] Figure 2 Schematic diagram for determining the scope of the fault point. DETAILED DESCRIPTION

[0065] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0066] For example, see Figure 1-Figure 2 ,A supervision method for quality control in communication engineering supervision, comprising,

[0067] S1 obtains all the information related to the electric poles, marks them, and stores the information related to the electric poles in the database;

[0068] S2 obtains the distance between two adjacent electric poles and the length of the reserved optical fiber coil on the electric poles through the database;

[0069] S3 uses a fiber optic tester to test the entire fiber optic line and monitor the actual length of the fiber optic cable from the fault point to the utility pole at the test endpoint;

[0070] S4 locates the farthest electric pole according to the fault point length fed back by the optical fiber tester, forming the first test area;

[0071] S5 forms a second test area by calculating and selecting prediction nodes for the first test area;

[0072] S6 performs error processing on the second test area to form a third test area, selects breakpoints in the third test area, determines the range of the fault point, and performs maintenance according to the endpoints on both sides of the fault point range:

[0073] S7 determines the electric poles closest to the endpoints on both sides of the fault point range, and uses its reserved optical fiber coil to stretch and replace the faulty interception section.

[0074] The method obtains all the information related to the electric poles, marks them, and stores the information related to the electric poles in the database:

[0075] The distance between two adjacent electric poles is c.

[0076] Get the theoretical fiber length between every two adjacent poles.

[0077] The theoretical optical fiber length is the distance c between two adjacent electric poles and the reserved optical fiber length b on each electric pole.

[0078] Store the above information in the database,

[0079] By storing the pole information and reserved optical fiber length in the database, systematic management of communication projects is achieved, and the efficiency of information retrieval and updating is improved.

[0080] Randomly select the pole at the end point of the entire optical fiber line as the starting point, and mark the poles in sequence starting from the starting point.

[0081] The pole at the end point contains only one adjacent pole and no optical fiber is reserved.

[0082] The fiber optic tester is used to test the entire fiber optic line and monitor the actual length of the fiber optic cable from the fault point to the electric pole at the test endpoint:

[0083] Use a fiber optic tester to test the entire fiber optic line from the starting point.

[0084] In actual situations, there is an optical fiber connection between the optical fiber tester and the starting point. However, since the length of the optical fiber between adjacent utility poles is much longer than the length of the optical fiber between the optical fiber tester and the starting point, the effect of the optical fiber length between the starting point and the optical fiber tester on the test is ignored here.

[0085] If a fault point is found in the optical fiber, the optical fiber tester will feedback the actual length h of the optical fiber from the fault point to the starting point.

[0086] The fault point length is located at the farthest electric pole according to the feedback from the optical fiber tester, forming the first test area:

[0087] According to the actual length h of the optical fiber at the fault point, calculate the actual distance to the pole and obtain the number of the farthest pole.

[0088] The farthest pole number can be obtained by the following formula:

[0089]

[0090] In the above formula, m is the number of poles, that is, the serial number of the farthest pole, n is the total number of poles in the communication project, h is the actual length of the optical fiber at the fault point, c is the distance between adjacent wires, b is the reserved optical fiber length of each pole, and the symbol Indicates rounding up.

[0091] By calculating the farthest electric pole, the fault point can be narrowed down.

[0092] The mth electric pole is selected as the termination electric pole, and the distance between the electric pole at the test endpoint and the termination electric pole is taken as the first test area.

[0093] The second test area is formed by calculating and selecting prediction nodes from the first test area:

[0094] The theoretical position of the fault point from the m-1th pole is calculated by the following formula. The theoretical position is the straight-line distance between two adjacent poles at the same height:

[0095]

[0096] In the above formula, k represents the distance from the fault point to the theoretical position of the fault point on the m-1th pole, h is the actual length of the optical fiber at the fault point, m represents the number of the farthest pole, that is, the termination pole, n represents the total number of poles for the communication project, c represents the distance between adjacent poles, and b is the reserved optical fiber length for each pole.

[0097] Since the actual length of the optical fiber will be affected by external forces in reality, the optical fiber will be deformed, resulting in an error between the theoretical position of the optical fiber at the fault point and the actual position of the optical fiber at the fault point. Therefore, the concept of theoretical position is used here.

[0098] Taking the m-1th electric pole as the starting point, the point with a distance k in the test direction of the optical fiber tester, i.e. the theoretical position, is selected as the prediction node, and the area between the prediction node and the m-1th electric pole is selected as the second test area.

[0099] Since the difference between the actual optical fiber length and the theoretical optical fiber length is very small, and the reserved coil will not be subjected to too much external force, in this embodiment, only the area where the fault point appears between the electric poles adjacent to the farthest electric pole is considered.

[0100] See also Figure 2 , the error processing is performed on the second test area to form a third test area, a breakpoint is selected in the third test area, the fault point range is determined, and maintenance is performed according to the endpoints on both sides of the fault point range:

[0101] The minimum error ratio between the actual length of the optical fiber at the fault point and the theoretical length of the optical fiber at the fault point is w, and the maximum error ratio is v.

[0102] Get the distance between the pole at the endpoint and the m-1 pole, recorded as x, and get the distance from the theoretical position to the m-1 pole, which is k;

[0103] Calculate the total distance Y=x+k of the optical fiber installed on the pole;

[0104] Get the maximum loss value = Y × v;

[0105] Get the minimum loss value = Y × w;

[0106] In the reverse direction of the test, select the point with the maximum loss value from the prediction node in the second test area as the first prediction node.

[0107] In the reverse direction of the test, select the point with the minimum loss value from the prediction node in the second test area as the second prediction node.

[0108] The area from the first prediction node to the second prediction node is used as the third test area.

[0109] The calculation error can minimize the scope of the fault point, reduce the length of the interception section, and save costs.

[0110] By using a fiber optic tester to monitor the fiber optic line, when a fault is found, the actual length of the fiber optic cable from the fault point to the starting point can be fed back. The farthest pole from the theoretical position of the fault point is calculated based on the actual length of the fiber optic cable at the fault point, and the area between the farthest pole and the starting point is used as the first test area to shorten the range of the fault point. The position of the fault point between the farthest pole and the second farthest pole is calculated based on the distance between adjacent poles and the length of the reserved coil on the pole, and the area between the second farthest pole and the point is used as the second test area to further shorten the range of the fault point. Based on the error range between the actual length of the fiber optic cable at the fault point and the theoretical length of the fault point, the range of the fault point is shortened to within the error range. In this way, the range of the fiber optic fault point can be accurately located, reducing the maintenance time and cost caused by unclear fault points, greatly reducing manual errors, and improving the efficiency of determining the range of fault points.

[0111] Obtain the point with the largest optical fiber curvature value in the third test area, cut off the point with the largest optical fiber curvature value as the first breakpoint, and the optical fiber curvature value is the degree of optical fiber bending.

[0112] As the optical fiber is subjected to external forces, it will bend and deform to varying degrees. The greater the bending degree, the more likely it is that the fault point will occur. This can increase the probability of finding the fault point.

[0113] Start from the starting point and test the first breakpoint.

[0114] If the feedback value is less than the actual distance h of the fault point, the difference f between the feedback value and the actual distance h of the fault point is calculated. Taking the first breakpoint as the starting point, a point with a length of f is selected along the test direction as the second breakpoint to form a segment with a length of f. The difference f is stored in the set F.

[0115] Since the optical fiber must be cut to form a segment every time a fault occurs, the length of each segment is recorded through set F, and the reserved optical fiber length of the maintenance point is updated in real time according to the length of the latest segment.

[0116] If the feedback value is equal to the actual distance h from the fault point, the area between the first breakpoint and the first prediction node is selected as the pre-test area.

[0117] Take the first breakpoint as the starting point, test the fault point, the feedback value is p, select the first breakpoint in the pre-test area with a distance of p from the first prediction point and cut it off as the second breakpoint, obtain the formed interception segment length p, and store it in the set F,

[0118] By selecting the point with the largest bending degree of the optical fiber in the test area and cutting it, and then testing, if the test feedback distance is less than the actual length of the optical fiber at the fault point, further points are selected for cutting based on the difference between the two, and the resulting intercepted segment is the final location of the fault point; if the test feedback distance is equal to the actual length of the optical fiber at the fault point, it means that the cutting point is after the fault point. By testing in the reverse direction of the test area, the distance from the fault point in the reverse direction is obtained, and the distance is cut based on this. The resulting intercepted segment is the final location of the fault point. In this way, the range of the fault point can be determined, the workload of blindly searching for the fault point is reduced, and work efficiency is improved.

[0119] The maintenance plan is selected based on the distance between the intercepted section and the m-1th pole and the mth pole and the corresponding reserved optical fiber length.

[0120] Determine the poles closest to the endpoints on both sides of the fault point range, and use the reserved optical fiber coils to stretch and replace the faulty interception section:

[0121] Get the shortest distance e1 between the endpoint of the intercepted segment and the m-1th electric pole,

[0122] Get the shortest distance e2 between the endpoint of the intercepted segment and the mth electric pole,

[0123] If e1 is greater than or equal to e2, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement. The stretching length is the length of the cut section. The reserved optical fiber length of the electric pole in the database is updated.

[0124] If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the mth electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the mth electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time.

[0125] If e1 is less than e2, the reserved optical fiber on the mth pole is selected as the maintenance point for stretching and replacement. The stretching length is the cut segment. The reserved optical fiber length of the pole in the database is updated.

[0126] If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the m-1th electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time.

[0127] During the maintenance process, the reserved optical fiber length of the utility poles in the database will be updated in real time, ensuring the accuracy and timeliness of the information.

[0128] By comparing the poles and reserved optical fiber lengths at the endpoints on both sides of the fault point, the optimal maintenance plan is selected, and the reserved optical fiber coils on the poles are used for stretching and replacement, which simplifies the maintenance process, improves maintenance efficiency, reduces material waste and maintenance time. When the reserved optical fiber length is not enough to cover the length required for maintenance, the system will issue an early warning to remind the staff to replace it in time, avoiding delays caused by insufficient reserved optical fiber.

[0129] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0130] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for quality control in communication engineering supervision, characterized in that: include, S1 obtains all the information related to the electric poles, marks them, and stores the information related to the electric poles in the database; S2 obtains the distance between two adjacent electric poles and the length of the reserved optical fiber coil on the electric poles through the database; S3 uses a fiber optic tester to test the entire fiber optic line and monitor the actual length of the fiber optic cable from the fault point to the utility pole at the test endpoint; S4 locates the farthest electric pole according to the fault point length fed back by the optical fiber tester, forming the first test area; S5 forms a second test area by calculating and selecting prediction nodes for the first test area; S6 performs error processing on the second test area to form a third test area, selects breakpoints in the third test area, determines the range of the fault point, and performs maintenance according to the endpoints on both sides of the fault point range: S7 determines the electric poles closest to the endpoints on both sides of the fault point range, and uses its reserved optical fiber coil to stretch and replace the faulty interception section.

2. The method for quality control in communication engineering supervision according to claim 1, characterized in that: The method obtains all the information related to the electric poles, marks them, and stores the information related to the electric poles in the database: The distance between two adjacent electric poles is c. Get the theoretical fiber length between every two adjacent poles. The theoretical optical fiber length is the distance c between two adjacent electric poles and the reserved optical fiber length b on each electric pole. Store the above information in the database, Randomly select the pole at the end point of the entire optical fiber line as the starting point, and mark the poles in sequence starting from the starting point. The pole at the end point contains only one adjacent pole and no optical fiber is reserved.

3. The method for quality control in communication engineering supervision according to claim 1, characterized in that: The fiber optic tester is used to test the entire fiber optic line and monitor the actual length of the fiber optic cable from the fault point to the electric pole at the test endpoint: Use a fiber optic tester to test the entire fiber optic line from the starting point. If a fault point is found in the optical fiber, the optical fiber tester will feedback the actual length h of the optical fiber from the fault point to the starting point.

4. The method for quality control in communication engineering supervision according to claim 1, characterized in that: The fault point length is located at the farthest electric pole according to the feedback from the optical fiber tester, forming the first test area: According to the actual length h of the optical fiber at the fault point, calculate the actual distance to the pole and obtain the number of the farthest pole. The farthest pole number can be obtained by the following formula: In the above formula, m is the number of poles, that is, the serial number of the farthest pole, n is the total number of poles in the communication project, h is the actual length of the optical fiber at the fault point, c is the distance between adjacent wires, b is the reserved optical fiber length of each pole, and the symbol Indicates rounding up. The mth electric pole is selected as the termination electric pole, and the distance between the electric pole at the test endpoint and the termination electric pole is taken as the first test area.

5. The method for quality control in communication engineering supervision according to claim 1, characterized in that: The second test area is formed by calculating and selecting prediction nodes from the first test area: The theoretical position of the fault point from the m-1th pole is calculated by the following formula. The theoretical position is the straight-line distance between two adjacent poles at the same height: In the above formula, k represents the distance from the fault point to the theoretical position of the fault point on the m-1th pole, h is the actual length of the optical fiber at the fault point, m represents the number of the farthest pole, that is, the termination pole, n represents the total number of poles for the communication project, c represents the distance between adjacent poles, and b is the reserved optical fiber length for each pole. Taking the m-1th electric pole as the starting point, the point with a distance k in the test direction of the optical fiber tester, i.e. the theoretical position, is selected as the predicted node, and the area between the predicted node and the m-1th electric pole is taken as the second test area.

6. The method for quality control in communication engineering supervision according to claim 1, characterized in that: The error processing is performed on the second test area to form a third test area, a breakpoint is selected in the third test area, the fault point range is determined, and maintenance is performed according to the endpoints on both sides of the fault point range: The minimum error ratio between the actual length of the optical fiber at the fault point and the theoretical length of the optical fiber at the fault point is w, and the maximum error ratio is v. Get the distance between the pole at the endpoint and the m-1 pole, recorded as x, and get the distance from the theoretical position to the m-1 pole, which is k; Calculate the total distance Y=x+k of the optical fiber installed on the pole; Get the maximum loss value = Y × v; Get the minimum loss value = Y × w; In the reverse direction of the test, select the point with the maximum loss value from the prediction node in the second test area as the first prediction node. In the reverse direction of the test, select the point with the minimum loss value from the prediction node in the second test area as the second prediction node. The area from the first prediction node to the second prediction node is used as the third test area. Obtain the point with the largest optical fiber curvature value in the third test area, cut off the point with the largest optical fiber curvature value as the first breakpoint, and the optical fiber curvature value is the degree of optical fiber bending. Start from the starting point and test the first breakpoint. If the feedback value is less than the actual distance h of the fault point, the difference f between the feedback value and the actual distance h of the fault point is calculated. Taking the first breakpoint as the starting point, a point with a length of f is selected along the test direction as the second breakpoint to form a segment with a length of f. The difference f is stored in the set F. If the feedback value is equal to the actual distance h from the fault point, the area between the first breakpoint and the first prediction node is selected as the pre-test area. Take the first breakpoint as the starting point, test the fault point, the feedback value is p, select the first breakpoint in the pre-test area with a distance of p from the first prediction point and cut it off as the second breakpoint, obtain the formed interception segment length p, and store it in the set F, The maintenance plan is selected based on the distance between the intercepted section and the m-1th pole and the mth pole and the corresponding reserved optical fiber length.

7. The method for quality control in communication engineering supervision according to claim 1, characterized in that: Determine the poles closest to the endpoints on both sides of the fault point range, and use the reserved optical fiber coils to stretch and replace the faulty interception section: Get the shortest distance e1 between the endpoint of the intercepted segment and the m-1th electric pole, Get the shortest distance e2 between the endpoint of the intercepted segment and the mth electric pole, If e1 is greater than or equal to e2, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement. The stretching length is the length of the cut section. The reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the mth electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the mth electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time. If e1 is less than e2, the reserved optical fiber on the mth pole is selected as the maintenance point for stretching and replacement. The stretching length is the cut segment. The reserved optical fiber length of the pole in the database is updated. If the reserved optical fiber length b is less than the stretched length, the reserved optical fiber on the m-1th electric pole is selected as the maintenance point for stretching and replacement, and the reserved optical fiber length of the electric pole in the database is updated. If the reserved optical fiber length b on the m-1th electric pole is less than the stretched length, an early warning is issued to notify the staff to replace it in time.

Citation Information

Patent Citations

  • Method for improving locating precision of optical fiber fault location of multi-stage unequal EPON network

    CN103560825A

  • Method and device for positioning fault point in optical fiber

    CN114172567A

  • Optical fiber fault positioning method, system and device and nonvolatile storage medium

    CN116192246A

  • Optical Fiber Fault Locator

    US20120236294A1