Modularized construction method for dry moving bed desulfurization tower
Through the modular construction method, decomposition and prefabricating the desulfurization tower module, the limit plate and multi-point formal installation method are used for lifting and welding, which solves the problems of welding deformation, large aerial workload and low construction efficiency of the dry-mobile mobile bed desulfurization tower, and realizes the problem of welding deformation, large aerial workload and low construction efficiency of the dry-mobile mobile bed desulfurization tower. A safe and efficient construction process.
Patent Information
- Application Number
- CN202411335875.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2024-11-12
AI Technical Summary
The traditional formal method of dry-mobile mobile bed desulfurization tower has problems such as welding deformation, large amount of high altitude work, poor safety and low construction efficiency.
The desulfurization tower is decomposed into multiple modules for prefabrication and hoisting, and the limiting plate and multi-point formal installation method are used to ensure the accurate installation and welding of the modules, reduce high-altitude operations, and improve safety and construction efficiency.
It has realized the transformation of high-altitude operations into ground assembly, shortened installation time, reduced safety hazards, improved installation quality and economic benefits, and solved the problems of welding deformation and low construction efficiency.
Smart Images

Figure CN118926753A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of chemical industry, and in particular to a modular construction method for a dry moving bed desulfurization tower. Background Art
[0002] At present, the pollutants emitted into the atmosphere in my country come from sulfides and nitrogen oxides emitted by industries, so the core of air pollution control is to control sulfur dioxide and nitrogen oxides from industrial enterprises, that is, desulfurization and denitrification. In recent years, the state has strengthened supervision and inspection of environmental protection, and has made environmental protection projects a key national project. Under the premise of major policies, treatment processes for flue gas desulfurization have emerged like "mushrooms after rain", including wet, dry, semi-dry, ammonia and other processes.
[0003] Since dry moving bed desulfurization tower is often used in coke oven supporting environmental protection, it is generally a device added on the basis of the original coking plant. Therefore, when constructing a dry moving bed desulfurization tower, its main construction difficulty is the complex construction environment. The traditional upright installation method has the problems of welding deformation, large amount of high-altitude operations, poor safety and low construction efficiency. Summary of the invention
[0004] In order to solve the problems of welding deformation, large amount of high-altitude work, poor safety and low construction efficiency in the traditional upright installation method of a dry moving bed desulfurization tower, the present invention proposes a modular construction method for a dry moving bed desulfurization tower.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a modular construction method of a dry moving bed desulfurization tower, comprising the following steps: S1—Module decomposition: According to the drawings, the desulfurization tower shell is decomposed into 6 modules, namely MK-1, MK-2, MK-3, MK-4, MK-5 and Mk-6. Among them, MK-1 to Mk-4 are "L"-shaped modules, and MK-5 and MK-6 are "well"-shaped modules; S2—Module prefabrication: Cut and prefabricate the MK-1, MK-2, MK-3, MK-4, MK-5, and MK-6 modules in sequence, and transport the modules to the construction site after prefabrication; S3—Module hoisting: hoist 6 modules in the order of Mk-1, MK-2, MK-3, MK-4, MK-5, and Mk-6; S4- Top plate hoisting: hoist the desulfurization tower top plate into place as a whole, set the limit plate, spot weld the extended part of the limit plate to the 6 modules, and remove the limit block after the top plate is fully welded; S5—Assembly welding: firstly, the plates and profiles are spliced. The components are assembled after the parts are assembled, welded and corrected. After welding, the slag and spatter on the weld surface are cleaned and the appearance quality of the weld is checked. S6—Module alignment and leveling: With the help of tools such as theodolite, magnetic plumb bob, and level ruler, ensure that the geometric dimensions, verticality, and horizontality of each installation part are within the allowable deviation range, and weld and fix them in time after confirming the level; S7—Desulfurization agent filling: The desulfurization agent filling sequence is carried out according to the drawings. The cloth bags are placed under the filling hopper. When filling the desulfurization agent, all the desulfurization agents of one tower are filled first. After adjusting and determining the final filling quantity in each desulfurization tank, multiple desulfurization tanks are filled at the same time. S8—Insulation material construction: first install the insulation nails and brackets, then install the insulation layer, and finally install the protective layer.
[0006] Furthermore, in the step S1-module decomposition: the Mk-1 module is the southwest shell of the desulfurization tower, the MK-2 module is the northwest shell, the MK-3 module is the southeast shell, the MK-4 module is the northwest shell, the MK-5 module is the middle-west shell, and the Mk-6 module is the middle-east shell, and the MK-1, MK-2, MK-3, MK-4, MK-5 and Mk-6 modules are all integral prefabricated parts.
[0007] Furthermore, in the step S2-module prefabrication: (1) After the desulfurization tower wall panels are cut, the geometric dimensions and flatness must be strictly checked, marked, and stored and fixed on a flat and uniform mold to strictly prevent deformation; (2) When butt joints are used for the splicing of reinforcing ribs, a gasket should be added and the weld must be fully penetrated. Lap joints are not allowed. T-joints between radial ribs and latitudinal ribs should use double-sided continuous fillet welds, and double-sided intermittent welds should be used between reinforcing ribs and wall panels. The weld length and weld leg height must meet the requirements of the drawings. (3) Lofting and numbering materials should reserve welding shrinkage allowances during production and installation as well as machining allowances such as cutting, planing and milling according to process requirements; (4) The layout platform must be kept flat, and there must be no weld nodules or dirt on the steel plate surface; (5) All steel components must be laid out in full size before production, and only after verification can they be cut and prefabricated; (6) Before gas cutting, clean the rust and dirt on the surface of the steel cutting area, and clean the slag and spatter left by gas cutting after gas cutting; the cutting speed should be uniform to prevent tempering. After cutting, there should be no obvious cracks, slag inclusions, stratification and edge defects larger than 1mm at the fracture.
[0008] Furthermore, in the step S3-module hoisting: Special lifting equipment and chain hoisting group are used to complete the lifting of the structural module using multi-point upright lifting technology. During the module lifting process, a tail rope is set to ensure the stability of the module during the lifting process; (1) Before lifting, confirm that the embedded bolts of the foundation have been completed and calibrated, and complete the process handover procedures with the installation professionals; (2) The site meets the lifting requirements and has been leveled; (3) The main truck crane lifts the module and stops lifting when it is 10-20cm away from the transport truck. Check the crane, foundation hoisting equipment, and module for any abnormalities. (4) The main crane slowly lifts the module, and when the bottom of the module exceeds the top of the foundation, the main arm begins to rotate westward to the position. During the rotation of the main arm, the direction of the module is controlled by a tail rope to avoid collision with the hoisting main arm, equipment foundation, steel structure frame, and other structures; (5) The fitter places the module on the foundation, aligns it, and then removes the hook from the crane to complete the installation of the module; (6) When hoisting, first hoist the desulfurization tower module on the west side, and then install the desulfurization tower module on the east side; (7) Install the wind rope in time after the module is in place; (8) Finally, complete the uninstalled beams and auxiliary components.
[0009] Furthermore, in the step S3-module hoisting: (1) After the MK-1, MK-2, MK-3, MK-4, MK-5 and MK-6 modules are installed in place, install the bottom filler beam and bottom plate of the desulfurization tower. After the installation is completed, install the bottom steel funnel. The steel funnel is prefabricated as a whole; (2) Complete the beams and wall panels between modules (MK1 / 2 / 3 / 4) in the order of modules, and complete the beams, wall panels and shutters between modules (MK5, MK6) and wall panels.
[0010] Furthermore, in the step S5-assembly welding: (1) Before assembly, the module must be inspected and qualified; the rust, burrs, dirt, etc. within 30 to 50 mm on each side of the connection contact surface and along the edge of the weld must be cleaned; (2) More than 75% of the top contact surface is in close contact. Check with a 0.3mm feeler gauge and the inserted area is less than 25%, and the edge gap shall not be greater than 0.8mm; (3) The allowable deviation of the installation welding groove angle is ±5°, and the allowable deviation of the blunt edge is ±1mm; (4) When welding, avoid welding on the parent material outside the weld bead, stagger the joints between layers of multi-layer welding, and avoid using welding rods with peeling coating or rusty core; (5) The welding sequence of component joints should be symmetrically expanded from the middle to the surrounding areas in the plane, and the vertical sequence can be adopted to facilitate process coordination, facilitate construction, and ensure welding quality; (6) The order of welding principles is: try to use symmetrical welding method to minimize welding deformation and shrinkage; weld the part with large shrinkage first, and weld the part with small shrinkage later; pay attention to slag removal during welding and thoroughly remove weld root defects; balance the heating amount during welding; (7) For butt and fillet welds that require full penetration, such as T-joints, cross joints, and fillet joints, the weld leg size shall not be less than t / 4 (t is the thickness of the vertical steel plate); (8) The corners of fillet welds should be welded continuously around the corners, and the distance between the arc start and end points and the weld end should be greater than 10.0 mm; for continuous welds without arc starting and lead-out plates at the ends of fillet welds, the distance between the arc start and end points and the weld end should be greater than 10.0 mm, and the arc pit should be filled; (9) Multi-layer welding should be performed continuously. Each layer of weld should be cleaned and inspected in time after welding, and defects should be removed before welding. (10) For concave fillet welds, the transition between the weld metal and the base material shall be smooth; for concave fillet welds, no cut marks shall be left on the surface.
[0011] Furthermore, in the step S7—desulfurizing agent loading: (1) Before loading the desulfurizer, it is necessary to enter the tower to check and confirm the internal components: 1) The shutters have been installed and fully welded around the edges without any gaps; 2) The shutter grille is intact and undamaged, correctly installed, and firmly crimped; (2) After filling, confirm that the material specifications of the distributor wire mesh are correct, and after it is firmly installed, add the formal gasket to seal the tower cover.
[0012] Furthermore, in step S8—insulation material construction: (1) Insulation nails and bracket installation The hook nails are welded firmly, the longer supports meet the expansion requirements, the insulation nails are welded firmly, the spacing is even, the length is consistent, and the installation is vertical. The spacing and length of the bracket legs are even. The insulation nails and brackets are welded at the same time when the modules are prefabricated.
[0013] (2) Insulation layer installation The insulation layer is constructed layer by layer, with staggered seams in single layers and pressed seams between layers. Self-locking pressure plates are added to the hooks and pressed tightly against the insulation layer. The exposed part of the hooks is bent upwards 90 degrees and embedded into the insulation layer.
[0014] (3) Installation of protective layer When installing corrugated plates in the full length direction, use a whole corrugated plate and it must be overlapped for installation; for vertically installed corrugated plates, the blind rivets must be installed in the same position, in a straight line horizontally and vertically, with a deviation of no more than 2mm; the corrugated plates must retain sufficient expansion joints; when installing the horizontal top corrugated plate, leave a 1% water flow slope; use mechanical cutting when cutting the outer protective plate.
[0015] The present invention has the following beneficial effects: The use of modular construction technology to convert a large number of high-altitude operations into ground assembly operations can shorten the time for modular equipment production and installation to 1 / 6 of that of traditional processes. At the same time, it greatly reduces high-altitude operations, reduces safety hazards, and effectively solves the problem of easy deformation of welding during the installation process of non-standard equipment welding groups. At the same time, it saves overall installation costs, saves time and effort, improves the safety factor of the non-standard equipment module lifting process, ensures the installation quality, and achieves good economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a process flow chart of the modular construction method of the dry moving bed desulfurization tower of the present invention. DETAILED DESCRIPTION
[0017] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0018] like Figure 1 As shown, this embodiment provides a modular construction method for a dry moving bed desulfurization tower, which is characterized by comprising the following steps: S1—Module decomposition: According to the drawings, the desulfurization tower shell is decomposed into 6 modules, namely MK-1, MK-2, MK-3, MK-4, MK-5 and Mk-6. Among them, MK-1 to Mk-4 are "L"-shaped modules, and MK-5 and MK-6 are "well"-shaped modules; S2—Module prefabrication: Cut and prefabricate the MK-1, MK-2, MK-3, MK-4, MK-5, and MK-6 modules in sequence, and transport the modules to the construction site after prefabrication; S3—Module hoisting: hoist 6 modules in the order of Mk-1, MK-2, MK-3, MK-4, MK-5, and Mk-6; S4- Top plate hoisting: hoist the desulfurization tower top plate into place as a whole, set the limit plate, spot weld the extended part of the limit plate to the 6 modules, and remove the limit block after the top plate is fully welded; S5—Assembly welding: firstly, the plates and profiles are spliced. The components are assembled after the parts are assembled, welded and corrected. After welding, the slag and spatter on the weld surface are cleaned and the appearance quality of the weld is checked. S6—Module alignment and leveling: With the help of tools such as theodolite, magnetic plumb bob, and level ruler, ensure that the geometric dimensions, verticality, and horizontality of each installation part are within the allowable deviation range, and weld and fix them in time after confirming the level; S7—Desulfurization agent filling: The desulfurization agent filling sequence is carried out according to the drawings. The cloth bags are placed under the filling hopper. When filling the desulfurization agent, all the desulfurization agents of one tower are filled first. After adjusting and determining the final filling quantity in each desulfurization tank, multiple desulfurization tanks are filled at the same time. S8—Insulation material construction: first install the insulation nails and brackets, then install the insulation layer, and finally install the protective layer.
[0019] Specifically, this embodiment takes a 5.5-meter rammed coke oven flue gas desulfurization, denitrification and dust removal double desulfurization tower as an example to illustrate the modular construction method of the above-mentioned dry moving bed desulfurization tower: Among them, the size of a single desulfurization tower is 8312mm*9832mm*17560mm, the installation elevation is +3400mm, and the unit weight is 361t. The desulfurization tower is the core equipment of the desulfurization system. It is an on-site manufactured and installed equipment. The desulfurization tower consists of three parts: equipment shell, shutters, and desulfurizer. This is a coke oven supporting environmental protection project. It is an additional device for the original coking plant. The main construction difficulty is the complex construction environment. The east side of the desulfurization tower is the original coke oven track, the west side is the chimney, and the east side is the built denitrification reactor. The site space is small, the construction period is short, and only the south side of the desulfurization tower can meet the hoisting requirements.
[0020] On this basis, in step S1-module decomposition: The desulfurization tower MK-1 module is the shell of the southwest side of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 28.6t. The desulfurization tower MK-2 module is the shell of the northwest side of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 23t. The desulfurization tower MK-3 module is the shell of the southeast side of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 28.6t. The desulfurization tower MK-4 module is the shell of the northwest side of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 23t. The desulfurization tower MK-5 module is the shell of the middle and west sides of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 28t. The desulfurization tower MK-6 module is the central and eastern shell of the desulfurization tower, with an installation elevation of +3.5m to 19.1m. The module is an integral prefabricated component with a hoisting weight of 28t. The MK-1, MK-2, MK-3, MK-4, MK-5 and MK-6 modules are all integral prefabricated components.
[0021] In the step S2-module prefabrication: (1) After the desulfurization tower wall panels are cut, their geometric dimensions and flatness must be strictly checked by technical personnel, and they must be marked and stored and fixed on a flat and uniform mold to strictly prevent deformation.
[0022] (2) When butt joints are used for the splicing of reinforcing ribs, a gasket should be added and the weld must be fully penetrated. Lap joints are not allowed. T-joints between radial ribs and latitudinal ribs should use double-sided continuous fillet welds, and double-sided intermittent welds should be used between reinforcing ribs and wall panels. The weld length and weld leg height must meet the requirements of the drawings.
[0023] (3) Layout and numbering of materials should be carried out in accordance with the process requirements to reserve welding shrinkage allowance during production and installation, as well as processing allowances such as cutting, planing and milling.
[0024] (4) The layout platform must be kept flat, and there must be no weld nodules or dirt on the surface of the steel plate.
[0025] (5) All steel components must be laid out in full size before production, and only after verification can they be cut and prefabricated.
[0026] (6) Before gas cutting, clean the rust and dirt on the surface of the steel cutting area, and clean the slag and spatter left by gas cutting after gas cutting. The cutting speed is uniform to prevent tempering. After cutting, there should be no obvious cracks, slag inclusions, delamination and edge defects greater than 1mm at the fracture.
[0027] When shipping the module: (1) Correct selection of transport vehicles and lifting machinery Based on the basic shape, geometric size requirements and weight of each module, road conditions and economic benefits, determine the appropriate transport vehicle and crane model, number ratio and optimal shipping method.
[0028] (2) Check the transport routes and roads in detail and organize the transport vehicle drivers and relevant technical personnel to inspect the transport routes along the way, the flatness and hardening of the road surface, the road slope, the maximum turning radius of the road, the presence of ground obstacles such as electric poles, and whether the clearance dimensions of the pipeline corridors on both sides meet the height requirements.
[0029] (3) The lifting and loading and unloading of modules must be directed by a dedicated person in the project department, using appropriate operating tools and strictly complying with the lifting technical rules to prevent the modules from mechanical vibration, impact, deformation, falling or other accidental damage during the lifting process.
[0030] (4) During transportation within the factory, the speed should not exceed 20 miles per hour. The transportation must be carried out by a licensed driver and escort personnel, and obvious markings must be set on the vehicle and modules.
[0031] In the step S3-module hoisting: 260T and 80T truck cranes are used for lifting. Special lifting equipment and fall chain groups are used to adopt multi-point upright lifting technology to complete the lifting of the structural module. During the module lifting process, a tail rope is set to ensure the stability of the module during the lifting process.
[0032] (1) Before lifting, confirm that the embedded bolts of the foundation have been completed and calibrated, and complete the process handover procedures with the installation professionals.
[0033] (2) The site meets the lifting requirements and has been leveled.
[0034] (3) The main truck crane of 260T lifts the module and stops lifting when it is 10-20cm away from the transport truck. Check the crane, foundation hoisting equipment, and module for any abnormalities.
[0035] (4) The main crane slowly lifts the module. When the bottom of the module exceeds the top of the foundation, the main arm begins to rotate westward to the position. During the rotation of the main arm, the direction of the module is controlled by a tail rope to avoid collision with the lifting main arm, equipment foundation, steel structure frame, and other structures.
[0036] (5) The fitter places the module on the foundation, aligns it, and then removes the hook from the crane to complete the installation of the module.
[0037] (6) When hoisting, the west side desulfurization tower module should be hoisted first, and then the east side desulfurization tower module should be installed. This can reduce the operating radius and hoisting height, and reduce the crane load.
[0038] (7) Install the wind rope in time after the module is in place.
[0039] (8) Finally, complete the uninstalled beams and auxiliary components.
[0040] In step S3-module hoisting, the force analysis of each module is as follows: Take module MK-1 as an example, which has the longest distance and the longest crane boom, for stress analysis.
[0041] Technical parameters of cranes used for equipment hoisting Equipment hoisting force analysis and calculation (1) Calculation of the maximum force on the main crane when the equipment is upright Performance parameters of 260T truck crane: when the crane reloading radius is 12m, the arm length is 38m, and the maximum rated weight is 34T.
[0042] The main arm crane is subjected to the greatest force when the equipment is kept in an upright state, and the maximum rated load P is: P=Q=(G+q1+q2)=(28.6+0.3+0.277)=29.177T.
[0043] G: --- Module net weight (28.6t); Q:---The maximum load that the crane can bear; q1:---Crane hook weight (0.3T); q2: --- Rope weight (0.277T); Crane load factor . Meet construction specifications and operational safety requirements.
[0044] (2) Calculation of maximum force during horizontal lifting of tail crane According to the principle of static equilibrium, the following equation is listed: F1+F2=G; F2×5=F1×5; The solution is: F1=F2=13.3t; Where: G——equipment weight, G=26.6t; The maximum force of the tail crane when starting to lift is: P2=(F2+g′)K1K2=(13.3+0.4)×1.1×1.1=16.577t g′——The total weight of the 260T truck crane hook weight of 0.15t and the machine rigging weight of 0.25t is 0.4t K1: dynamic load coefficient, take 1.1; K2: unbalance coefficient, take 1.1; According to the actual situation on site, the crane main arm is selected to be about 18m and the operating radius is about 10m. Checking the crane performance table, the QAY80 truck crane is selected with a lifting capacity of 19.2t.
[0045] Crane load factor . Meet the safety requirements of on-site construction and operation.
[0046] (3) Wire rope selection table Two L=16m steel wire ropes with two strands bent are selected as the main hoist ropes, and the angle between the two ropes is about 60°. Therefore, the load borne by a single steel wire rope is: P=Q / nsinα=26.6÷4×sin60=26600×10÷4×0.87=57855N=57.855KN.
[0047] P—Tension force on each wire rope (KN).
[0048] Q—The gravity of the lifting equipment (N).
[0049] n—the number of steel wire ropes used.
[0050] α—The angle between the wire rope and the plumb line.
[0051] According to the table, the steel wire rope is 30NAT6×37+1—1440ZZ391.9KN, and its single-wire force safety factor is: 391.9÷57.8=6.78, which meets the "7.2.2 Safety regulations for the use of steel wire ropes" in the "Petrochemical Large Equipment Hoisting Engineering Specifications" GB50798-2012.
[0052] In the step S3-module hoisting: (1) Install the MK-1, MK-2, MK-3, MK-4, MK-5, and MK-6 modules in place.
[0053] (2) After the above 6 modules are installed in place, install the bottom filling beam and bottom plate of the desulfurization tower. After the installation is completed, install the bottom steel funnel. The steel funnel is prefabricated as a whole.
[0054] (3) After the above installation is in place, complete the beams and wall panels between the modules (MK1 / 2 / 3 / 4) in the order of the modules, and at the same time complete the beams, wall panels and shutters between the modules (MK5, MK6) and the wall panels.
[0055] (4) After all the modules in the previous step are completed, the desulfurization tower top plate is hoisted as a whole. After the top plate is hoisted into place, a limit plate is set. After ensuring the accurate position, the extended part of the limit plate is spot welded to the vertical module. After all the circumferential seams of the top plate are welded, the limit block is removed and cleaned.
[0056] In the step S5-assembly welding: (1) Before assembly, the module must be inspected and qualified; the rust, burrs, dirt, etc. within 30 to 50 mm on each side of the connection contact surface and along the edge of the weld must be cleaned.
[0057] (2) The splicing of plates and profiles is carried out before assembly; the assembly of components is carried out after the parts are assembled, welded and corrected.
[0058] (3) More than 75% of the top contact surface is in close contact. Check with a 0.3mm feeler gauge and the inserted area is less than 25%. The edge gap shall not be greater than 0.8mm.
[0059] (4) The allowable deviation of the installation welding groove angle is ±5°, and the allowable deviation of the blunt edge is ±1mm.
[0060] (5) The main control items of the external dimensions of the assembled steel components shall comply with the requirements of the following table, and the other general control items shall comply with the requirements of the attached table.
[0061] Allowable deviation of main control items of steel component dimensions (mm) project Permissible deviation Distance from multi-section column milling plane to the first mounting hole ±1.0 Distance between the outermost mounting holes at both ends of the solid beam ±3.0 Cross-sectional geometry at component connections ±3.0 Web centerline offset at column-beam connection 2.0 Bending sagitta of compression member (rod) L / 1000, and should not be greater than 10.0 (6) Manual arc welding is adopted for welding. Welders must pass the examination and hold a certificate before they can work. They must weld in accordance with the welding process instruction manual. They are not allowed to weld freely or weld on the parent material outside the weld. The joints between layers of multi-layer welding are staggered. When welding, welding rods with peeling coating or rusty cores must not be used.
[0062] (7) Principles for selecting welding rods: J427 welding rods should be used for welding between Q235B.
[0063] (8) Before use, the welding rod should be baked according to the baking time and temperature specified in the product manual (J427 welding rod drying temperature is 150℃, and insulation is 1 hour); after the welding rod is dried, it should be placed in an insulation box at 100-150℃ and taken out for use at any time. It should be used up within 4 hours after being taken out, otherwise it should be baked again.
[0064] (9) When welding on assembled components, the parameters and welding sequence specified in the welding process should be strictly followed to control the deformation of the components after welding. To control welding deformation, anti-deformation measures can also be used. When multi-layer welding is used, the surface of the previous weld should be cleaned before welding.
[0065] (10) The welding sequence of component joints should be symmetrically expanded from the center to the surrounding areas in the plane, and the vertical sequence can be adopted to facilitate process coordination, facilitate construction, and ensure welding quality.
[0066] (11) The order of welding principles is as follows: try to use symmetrical welding methods to minimize welding deformation and shrinkage; weld the parts with large shrinkage first, and weld the parts with small shrinkage later; pay attention to slag removal during welding and thoroughly remove weld root defects; balance the heating during welding.
[0067] (12) For butt and fillet combination welds that require full penetration, such as T-joints, cross joints, and fillet joints, the weld leg size shall not be less than t / 4 (t is the thickness of the vertical steel plate).
[0068] (13) The corners of fillet welds should be welded continuously around the corners, and the starting and ending points of the arc should be greater than 10.0 mm from the end of the weld: For continuous welds without arc starting and lead-out plates at the end of fillet welds, the starting and ending points of the arc should be greater than 10.0 mm from the end of the weld, and the arc pit should be filled.
[0069] (14) Multi-layer welding should be performed continuously. Each weld should be cleaned and inspected promptly after completion, and defects should be removed before welding.
[0070] (15) For concave fillet welds, the transition between the weld metal and the base material shall be smooth; for concave fillet welds, no cut marks shall be left on the surface.
[0071] (16) The welding material type used for positioning welding should match the material of the weldment; the weld thickness should not exceed 2 / 3 of the designed weld thickness and should not be greater than 8mm; the weld length should not be less than 25mm; the positioning welding position should be arranged within the weld bead and welded by a certified welder.
[0072] (17) After welding is completed, the welder cleans the slag and spatter on the weld surface and checks the appearance quality of the weld.
[0073] (18) For carbon structural steel, weld flaw detection can only be carried out after the weld has cooled to ambient temperature, and for low alloy structural steel, 24 hours after welding is completed.
[0074] (19) When welding, ensure that the welding environment has good conditions. Welding shall not be carried out if any of the following conditions are found and there are no effective protective facilities: strong winds; after rain or on rainy days; humidity: relative humidity greater than 90%.
[0075] In the step S7—desulfurizing agent loading: (1) Before loading the desulfurizer, specialized technicians and related personnel shall enter the tower to inspect and confirm the internal components. Requirements for confirmation: 1) The shutters have been installed and fully welded around without any gaps. 2) The shutter grilles are intact and undamaged, correctly installed, and firmly crimped.
[0076] (2) Choose to load the desulfurizer when the weather is clear because the relative humidity in the air is low at this time. Do not load the desulfurizer on rainy days.
[0077] (3) The desulfurizer filling sequence shall be carried out according to the drawings. To ensure that the desulfurizer is less worn and broken during filling, a cloth bag is placed under the filling hopper with a length of 10-12 meters.
[0078] (4) To ensure the filling effect, first fill all the desulfurizers in one tower, and then fill multiple desulfurization tanks at the same time after adjusting and determining the final filling quantity in each desulfurization tank. The technicians must be present to guide during the filling.
[0079] (5) After filling, confirm that the material specifications of the distributor wire mesh are correct, and after it is firmly installed, add the formal gasket to seal the tower cover.
[0080] In the step S8—insulation material construction: (1) Insulation nails and bracket installation The hook nail supports must be welded by professionals and must be welded firmly. The longer supports must meet the expansion requirements. The insulation nails must be welded firmly, evenly spaced, consistent in length, and installed vertically. The spacing and length of the bracket legs must be even, and the spacing of the fixings must meet the design requirements. The insulation nails and brackets must be welded at the same time when the modules are prefabricated.
[0081] (2) Insulation layer installation The thickness of a single layer of the insulation layer shall not exceed 100mm. If it exceeds 100mm, it shall be constructed in layers, and the thickness of each layer shall be roughly equal. After the construction of the first layer of insulation cotton is completed and accepted, the second layer of insulation cotton shall be constructed. The seams between layers shall be pressed, and the construction shall be carried out layer by layer to meet the design thickness requirements. The single layer shall be staggered and the seams between layers shall be pressed. Self-locking pressure plates shall be added to the hooks and pressed tightly against the insulation layer. The exposed part of the hooks shall be bent upwards 90 degrees and embedded in the insulation layer. The surface shall be flat.
[0082] (3) Installation of protective layer When installing corrugated plates in the full length direction, try to use a whole corrugated plate, and must overlap the installation; for vertically installed corrugated plates, the blind rivets must be installed in the same position, in a straight line horizontally and vertically, with a deviation of no more than 2mm; the corrugated plates must retain sufficient expansion joints; the horizontal top corrugated plate is installed with a 1% water flow slope; use mechanical cutting when cutting the outer protective plate, and flame cutting is strictly prohibited.
[0083] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A modular construction method for a dry moving bed desulfurization tower, characterized in that: The steps include: S1—Module decomposition: According to the drawings, the desulfurization tower shell is decomposed into 6 modules, namely MK-1, MK-2, MK-3, MK-4, MK-5 and Mk-6. Among them, MK-1 to Mk-4 are "L"-shaped modules, and MK-5 and MK-6 are "well"-shaped modules; S2—Module prefabrication: Cut and prefabricate the MK-1, MK-2, MK-3, MK-4, MK-5, and MK-6 modules in sequence, and transport the modules to the construction site after prefabrication; S3—Module hoisting: hoist 6 modules in the order of Mk-1, MK-2, MK-3, MK-4, MK-5, and Mk-6; S4- Top plate hoisting: hoist the desulfurization tower top plate into place as a whole, set the limit plate, spot weld the extended part of the limit plate to the 6 modules, and remove the limit block after the top plate is fully welded; S5—Assembly welding: firstly, the plates and profiles are spliced. The components are assembled after the parts are assembled, welded and corrected. After welding, the slag and spatter on the weld surface are cleaned and the appearance quality of the weld is checked. S6—Module alignment and leveling: With the help of tools such as theodolite, magnetic plumb bob, and level ruler, ensure that the geometric dimensions, verticality, and horizontality of each installation part are within the allowable deviation range, and weld and fix them in time after confirming the level; S7—Desulfurization agent filling: The desulfurization agent filling sequence is carried out according to the drawings. The cloth bags are placed under the filling hopper. When filling the desulfurization agent, all the desulfurization agents of one tower are filled first. After adjusting and determining the final filling quantity in each desulfurization tank, multiple desulfurization tanks are filled at the same time. S8—Insulation material construction: first install the insulation nails and brackets, then install the insulation layer, and finally install the protective layer.
2. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S1-module decomposition: the Mk-1 module is the southwest shell of the desulfurization tower, the MK-2 module is the northwest shell, the MK-3 module is the southeast shell, the MK-4 module is the northwest shell, the MK-5 module is the middle-west shell, and the Mk-6 module is the middle-east shell, and the MK-1, MK-2, MK-3, MK-4, MK-5 and Mk-6 modules are all integral prefabricated parts.
3. A modular construction method for a dry mobile desulfurization tower according to claim 1, characterized in that: In the step S2-module prefabrication: (1) After the desulfurization tower wall panels are cut, the geometric dimensions and flatness must be strictly checked, marked, and stored and fixed on a flat and uniform mold to strictly prevent deformation; (2) When butt joints are used for the splicing of reinforcing ribs, a gasket should be added and the weld must be fully penetrated. Lap joints are not allowed. T-joints between radial ribs and latitudinal ribs should use double-sided continuous fillet welds, and double-sided intermittent welds should be used between reinforcing ribs and wall panels. The weld length and weld leg height must meet the requirements of the drawings. (3) Lofting and numbering materials should reserve welding shrinkage allowances during production and installation as well as machining allowances such as cutting, planing and milling according to process requirements; (4) The layout platform must be kept flat, and there must be no weld nodules or dirt on the steel plate surface; (5) All steel components must be laid out in full size before production, and only after verification can they be cut and prefabricated; (6) Before gas cutting, clean the rust and dirt on the surface of the steel cutting area, and clean the slag and spatter left by gas cutting after gas cutting; the cutting speed should be uniform to prevent tempering. After cutting, there should be no obvious cracks, slag inclusions, stratification and edge defects larger than 1mm at the fracture.
4. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S3-module hoisting: Special lifting equipment and chain hoisting group are used to adopt multi-point upright lifting technology to complete the lifting of structural modules. During the module lifting process, a tail rope is set to ensure the stability of the module during the lifting process; (1) Before lifting, confirm that the embedded bolts of the foundation have been completed and calibrated, and complete the process handover procedures with the installation professionals; (2) The site meets the lifting requirements and has been leveled; (3) The main truck crane lifts the module and stops lifting when it is 10-20cm away from the transport truck. Check the crane, foundation hoisting equipment, and module for any abnormalities. (4) The main crane slowly lifts the module, and when the bottom of the module exceeds the top of the foundation, the main arm begins to rotate westward to the position. During the rotation of the main arm, the direction of the module is controlled by a tail rope to avoid collision with the hoisting main arm, equipment foundation, steel structure frame, and other structures; (5) The fitter places the module on the foundation, aligns it, and then removes the hook from the crane to complete the installation of the module; (6) When hoisting, first hoist the desulfurization tower module on the west side, and then install the desulfurization tower module on the east side; (7) Install the wind rope in time after the module is in place; (8) Finally, complete the uninstalled beams and auxiliary components.
5. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S3-module hoisting: (1) After the MK-1, MK-2, MK-3, MK-4, MK-5 and MK-6 modules are installed in place, install the bottom filler beam and bottom plate of the desulfurization tower. After the installation is completed, install the bottom steel funnel. The steel funnel is prefabricated as a whole; (2) Complete the beams and wall panels between modules (MK1 / 2 / 3 / 4) in the order of modules, and complete the beams, wall panels and shutters between modules (MK5, MK6) and wall panels.
6. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S5-assembly welding: (1) Before assembly, the module must be inspected and qualified; the rust, burrs, dirt, etc. within 30 to 50 mm on each side of the connection contact surface and along the edge of the weld must be cleaned; (2) More than 75% of the top contact surface is in close contact. Check with a 0.3mm feeler gauge and the inserted area is less than 25%, and the edge gap shall not be greater than 0.8mm; (3) The allowable deviation of the installation welding groove angle is ±5°, and the allowable deviation of the blunt edge is ±1mm; (4) When welding, avoid welding on the parent material outside the weld bead, stagger the joints between layers of multi-layer welding, and avoid using welding rods with peeling coating or rusty core; (5) The welding sequence of component joints should be symmetrically expanded from the middle to the surrounding areas in the plane, and the vertical sequence can be adopted to facilitate process coordination, facilitate construction, and ensure welding quality; (6) The welding principle sequence is: try to use symmetrical welding method to minimize welding deformation and shrinkage; weld the part with large shrinkage first, and weld the part with small shrinkage later; During welding, attention should be paid to slag removal and thorough removal of weld root defects; the amount of heat during welding should be balanced; (7) For butt and fillet welds that require full penetration, such as T-joints, cross joints, and fillet joints, the weld leg size shall not be less than t / 4 (t is the thickness of the vertical steel plate); (8) The corners of fillet welds should be welded continuously around the corners, and the distance between the arc start and end points and the weld end should be greater than 10.0 mm; for continuous welds without arc starting and lead-out plates at the ends of fillet welds, the distance between the arc start and end points and the weld end should be greater than 10.0 mm, and the arc pit should be filled; (9) Multi-layer welding should be performed continuously. Each layer of weld should be cleaned and inspected in time after welding, and defects should be removed before welding. (10) For concave fillet welds, the transition between the weld metal and the base material shall be smooth; for concave fillet welds, no cut marks shall be left on the surface.
7. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S7—desulfurizing agent filling: (1) Before loading the desulfurizer, it is necessary to enter the tower to check and confirm the internal components: 1) The shutters have been installed and fully welded around the edges without any gaps; 2) The shutter grille is intact and undamaged, correctly installed, and firmly crimped; (2) After filling, confirm that the material specifications of the distributor wire mesh are correct, and after it is firmly installed, add the formal gasket to seal the tower cover.
8. A modular construction method for a dry moving bed desulfurization tower according to claim 1, characterized in that: In the step S8—insulation material construction: (1) Insulation nails and bracket installation The hook nails are welded firmly, the longer supports meet the expansion requirements, the insulation nails are welded firmly, the spacing is uniform, the length is consistent, and the installation is vertical. The spacing and length of the bracket legs are evenly distributed. The insulation nails and brackets are welded at the same time when the modules are prefabricated; (2) Insulation layer installation The insulation layer is constructed layer by layer, with staggered seams in single layers and pressed seams between layers. A self-locking pressure piece is added to the hook nails and pressed tightly against the insulation layer. The exposed part of the hook nail is bent upwards 90 degrees and embedded into the insulation layer. (3) Installation of protective layer When installing corrugated plates in the full length direction, use the entire corrugated plate and install them in overlapping positions. For corrugated plates installed vertically, the blind rivets must be installed in the same position, in a straight line horizontally and vertically, with a deviation of no more than 2mm. The corrugated plate retains sufficient expansion joints; When installing the horizontal top corrugated plate, leave a 1% water flow slope; use mechanical cutting when cutting the outer protective plate.