The application provides a large-span under-hanging arc-shaped steel truss construction method, which comprises the following steps: firstly, a three-dimensional model is established and construction condition
simulation is performed to optimize structure design; then, an adjustable arc-shaped assembling jig frame is erected on the ground, arc-shaped main steel truss assembling is completed on the arc-shaped assembling jig frame, a boom, a conversion beam and an under-hanging structure are installed to form an integrated whole lifting unit; then, a hydraulic synchronous lifting
system is installed on the top of a bearing steel column to perform graded lifting and monitoring, and is fixed and installed after lifting in place; finally, graded unloading and structure monitoring are performed, and subsequent structure construction and completion acceptance are performed. The application adopts ground arc-shaped jig frame whole assembling, and the arc-shaped truss is formed at one time, so that linear precision is high, deviation is small, large-area full
scaffold is cancelled, materials are saved, space is released, multi-
specialty cross operation can be realized, high-altitude operation is greatly reduced,
safety risk is reduced, construction efficiency is improved, structure stress is ensured to be uniform, deformation is controllable, and construction quality is stable and reliable.