Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Modularized and integrative disassembling and installing methods for blast furnace

A modular, furnace body technology, applied in blast furnaces, blast furnace details, blast furnace parts and other directions, can solve problems such as difficult connection, single structure, limited construction plane, etc., to reduce use and operation time, improve economic benefits, The effect of solving logistics problems

Inactive Publication Date: 2011-08-10
SHANGHAI BAOYE CONSTR INDAL FURNACE ENG TECH
View PDF1 Cites 27 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The biggest disadvantages of this method are: large amount of online construction work, many high-altitude operations, difficult connection of various procedures, large interaction between cross-operations, high risk, many uncertain factors, many safety hazards, low efficiency, and large-scale construction. Heavy equipment is used for a long time, the construction period is long, and the construction plane is limited, which has a great impact on the logistics of the entire production site. It cannot meet the short-term construction period and safety needs of large-scale blast furnaces, and has become a bottleneck for enterprises to reduce costs and improve efficiency.
However, this invention is limited to the implementation of local steel structures such as blast furnace frames, water pump houses, and heat exchange stations, and fails to solve the problems of transportation roads, transportation vehicles, and hoisting, and it needs to be hoisted by a crane to assemble them into larger modules. The on-site implementation in the area is obviously limited by the lifting capacity of transport vehicles and cranes, so the scale is small and the structure is single, which is of little significance to the entire project
Therefore, there are many difficulties and risks as follows, whether it is the conventional disassembly and assembly of parts or the combination of small-scale modular construction and conventional parts for local steel structures: 1. Large amount of online engineering: structure, equipment The removal or installation of pipes and pipes reached tens of thousands of tons
2. High risk and low efficiency of high-altitude operation: especially the construction site of the furnace top system is in the range of +46.300m ~ +115.000m, with many uncertain factors and many potential safety hazards
4. Long construction period: Due to the large amount of engineering, low efficiency of high-altitude operations, and large mutual influence of cross-operations, the construction period for blast furnace overhaul or new project disassembly and assembly is long
5. The construction plane is limited, and the logistics organization is difficult: the large-scale components to be dismantled need to be placed on the ground for disassembly, and the components need to be assembled on site in advance, and the crane station is located on the main passage, and the operation time is long. Large impact on the site, difficult logistics and transportation coordination

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Modularized and integrative disassembling and installing methods for blast furnace
  • Modularized and integrative disassembling and installing methods for blast furnace
  • Modularized and integrative disassembling and installing methods for blast furnace

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0062] Now a blast furnace needs to be dismantled, using a modular and integrated dismantling method for blast furnaces, including dismantling the furnace roof system, dismantling the hot blast surrounding pipe, dismantling the first floor beams, and dismantling the casthouse platform and furnace body. The specific steps are:

[0063] When dismantling the furnace roof system, a modular and integrated dismantling method is adopted. The furnace roof system 1 is located above an elevation of 40m, including the old seven-story platform and above structures and equipment, and weighs about 2600t. figure 1 As shown, through the sliding truss 11 and supporting system 12 erected on the 180° side of the blast furnace, the entire furnace roof system 1 is slid from a high altitude to a lowered position with the sliding equipment 13, and the arrow in the figure indicates the sliding direction. like figure 2 As shown, the furnace roof system 1 is lowered to the ground as a whole with the h...

Embodiment 2

[0071] A blast furnace needs to be installed now, using a modular and integrated installation method for blast furnaces, including installation of the furnace roof system, installation of hot air surrounding pipes, installation and construction of the furnace body, construction of the first floor beam and platform in the casting yard, and construction of the finished product tank , the specific steps are:

[0072] The installation of the furnace roof system adopts a modular and integrated installation method, and the frame, gas riser pipe and ball joints, furnace roof equipment above the material tank, electrical instruments, furnace top small piping and hydraulic piping are assembled offline and reinforced into a whole furnace roof System 1, such as Figure 15As shown, the entire roof system 1 is slid onto the transport vehicle 15 with the sliding equipment 13, and the furnace roof system 1 is transported to the ground on the 180° side of the blast furnace with the transport ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the installation method field of smelting equipment of iron, in particular relates to modularized and integrative disassembling and installing methods for a blast furnace. The modularized and integrative disassembling method for the blast furnace comprises: disassembling a furnace top system, disassembling a hot wind surrounding pipe, disassembling a layer beam and casting house platform and disassembling a furnace body. The modularized and integrative disassembling method is characterized in that when the furnace top system, the hot wind surrounding pipe, the layer beam and casting house platform and the furnace body are dissembled, the modularized and integrative disassembling method is adopted. The modularized and integrative insulating method for the blast furnace comprises: installing the furnace top system, installing the hot wind surrounding pipe, carrying out furnace body construction, carrying out layer beam and casting house platform construction and carrying out finished product groove construction and is characterized in that when the furnace top system, the hot wind surrounding pipe, the furnace body, the layer beam and casting house platform and the finished product groove are installed, the modularized and integrative installing method is adopted. According to the invention, construction efficiency is high, safety is high, and production cost is reduced.

Description

technical field [0001] The invention relates to the field of installation methods for iron smelting equipment, in particular to a modular and integrated disassembly and installation method for blast furnaces. Background technique [0002] Large blast furnaces especially 4000m 3 For the overhaul or new construction of the upper-level blast furnace, the demolition or installation works amounted to tens of thousands of tons. The existing construction technology mainly adopts the conventional method of dismantling and installing by parts. The biggest disadvantages of this method are: large amount of online construction work, many high-altitude operations, difficult connection of various procedures, large interaction between cross-operations, high risk, many uncertain factors, many safety hazards, low efficiency, and large-scale construction. Heavy equipment is used for a long time, the construction period is long, and the construction plane is limited, which has a great impact ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): C21B7/00
Inventor 李树彬王雄胡毅许立新唐兵传李鹏陈荣林彭秀武蔡峰崔海军张福川张顺王涛
Owner SHANGHAI BAOYE CONSTR INDAL FURNACE ENG TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products