Installation control method of marine laser collimator
By machining the plane of the aiming device base and cutting off the allowance, combined with the installation of the limiting guide rail bracket, the problems of unstable installation and complicated operation of the laser aiming device were solved, and an efficient and low-cost installation method was achieved.
Patent Information
- Application Number
- CN202410888779.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In existing technologies, the installation and adjustment methods of laser aiming devices have a significant impact on their accuracy and stability, and are difficult and costly to operate.
By machining the target base and cutting off excess material, combined with the installation of the limit guide rail bracket, the precise positioning and fixation of the target base are ensured, thereby improving installation stability and accuracy.
It reduces the difficulty of operation, decreases adjustment time and cost, improves the installation stability and accuracy of the aiming device, and enhances its efficiency.
Smart Images

Figure CN118928691A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of shipbuilding, and in particular relates to an installation control method for a ship-used laser sight. Background Art
[0002] With the continuous development of laser technology, laser sights are widely used in shooting sports and military applications. As a new type of laser sight, marine laser sights have the advantages of high precision, low energy consumption and good stability. However, the installation and adjustment methods of laser sights have an important influence on the accuracy and stability of laser sights. Summary of the invention
[0003] The purpose of the present invention is to overcome the deficiencies in the above-mentioned prior art and to provide an installation control method for a marine laser sight. The present invention improves the stability of the sight installation and the accuracy of use by plane processing and excess cutting of the sight base.
[0004] In order to achieve the above invention purpose, the technical solution provided by the present invention is as follows:
[0005] A method for installing and controlling a marine laser sight, the method specifically comprising the following steps:
[0006] S1, positioning and installing the collimator base, cleaning the installation position of the collimator base, and polishing the installation position;
[0007] S2, installing the collimator base at a corresponding position and positioning the collimator base;
[0008] S3, after the positioning and installation of the collimator base is completed, the collimator base is cut to a certain extent, and after the cutting of the certain extent is completed, the collimator base is welded and fixed;
[0009] S4, after the installation and welding of the collimator base is completed, install the limit rail bracket, and install the limit rail bracket on the collimator platform or deck so that the upper plane of the limit rail bracket is parallel to the upper plane of the collimator base; the installation position of the limit rail bracket is directly behind the collimator;
[0010] S5, machining the plane of the collimator base, and installing the collimator after the machining is completed;
[0011] S6, install the collimator so that the bow and stern lines of the collimator are aligned with the bow and stern lines on the collimator base; after installation, check whether the horizontal state of the collimator and the parallelism of the center line meet the requirements;
[0012] S7, install the limit guide rail. Install the limit guide rail on the limit guide rail bracket. The limit guide rail and the limit guide rail bracket are connected by fixing bolts. When installing the fixing bolts, the fixing bolts on both sides of the limit guide rail are symmetrically installed and tightened. The installation of the limit guide rail is completed.
[0013] S8. After the installation of the limit rail is completed, return the sight to the zero position, and then install the navigation fixture on the limit rail to complete the overall installation of the sight.
[0014] Furthermore, the positioning of the collimator base specifically includes:
[0015] S21, when installing the sighting instrument base, the fore and aft markings of the sighting instrument base should be aligned with the center line of the deck;
[0016] S22, placing a level ruler on the plane of the collimator base, and placing the quadrant on the measuring plane of the level ruler, and adjusting the horizontality of the collimator base;
[0017] S23, measure the height distance from the sighting instrument base to the deck surface, and weld the sighting instrument base to fix it. After welding and fixing, use a hand grinder to cut and remove the temporary reinforcement inside the sighting instrument base.
[0018] Furthermore, the margin cutting of the collimator base is specifically as follows: the margin cutting of the collimator base is performed according to the measured height distance from the collimator base to the deck surface, so that the height of the collimator base meets the requirements.
[0019] Furthermore, after the collimator base is welded and fixed, no explosive work is allowed when removing the temporary reinforcement inside the collimator base.
[0020] Furthermore, the plane processing of the collimator base is specifically: using a processing machine tool to perform plane processing on the collimator base, and after the plane processing of the collimator base is completed, re-carving bow and stern cross lines on the plane of the collimator base.
[0021] Furthermore, the angle between the installation position of the limit guide rail, the center of the collimator base and the bow and stern centerline is 58°.
[0022] Based on the above technical solution, the installation control method of a marine laser sight in the present invention has achieved the following technical advantages through practical application:
[0023] 1. The installation control method of a marine laser sight of the present invention improves the stability of the installation and the accuracy of use of the sight by plane processing and excess cutting of the sight base. The implementation of the present invention can effectively reduce the user's operating difficulty, reduce adjustment time and cost, and improve use efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1The invention discloses a sighting instrument base installation structure diagram in an installation control method of a marine laser sighting instrument.
[0025] Figure 2 The utility model discloses a top view of installation of a laser sight for a ship in an installation control method of the laser sight for a ship of the present invention.
[0026] Figure 3 The invention discloses a side view of the installation of a laser sight for a ship in an installation control method of the laser sight. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is described below by the specific examples shown in the accompanying drawings. However, it should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0028] like Figure 1-3 As shown, the present invention belongs to an installation control method for a marine laser sight, which specifically comprises the following steps:
[0029] S1, positioning and installing the collimator base 1, cleaning the installation position of the collimator base 1, and polishing the installation position;
[0030] S2, installing the collimator base 1 at a corresponding position and positioning the collimator base 1;
[0031] S3, after the collimator base 1 is positioned and installed, the collimator base 1 is cut to a certain extent, and after the collimator base 1 is cut to a certain extent, the collimator base 1 is welded and fixed;
[0032] S4, after the welding of the collimator base 1 is completed, the limit rail bracket 6 is installed, and the limit rail bracket 6 is installed on the collimator 3 platform or deck, so that the upper plane of the limit rail bracket 6 is parallel to the upper plane of the collimator base 1; the installation position of the limit rail bracket 6 is directly behind the collimator 3;
[0033] S5, plane processing of the collimator base 1, and installation of the collimator 3 after the processing;
[0034] S6, install the collimator 3 so that the bow and stern lines of the collimator 3 are aligned with the bow and stern lines on the collimator base 1; after the installation is completed, check whether the horizontal state of the collimator 3 and the parallelism of the center line meet the requirements;
[0035] S7, install the limit guide rail 4, install the limit guide rail 4 on the limit guide rail bracket 6, the limit guide rail 4 and the limit guide rail bracket 6 are connected by fixing bolts, when the fixing bolts are installed, the fixing bolts on both sides of the limit guide rail 4 are symmetrically installed and tightened; complete the installation of the limit guide rail 4; after installation, it should be ensured that the buffer bumper of the limit guide rail 4 contacts the middle position of the sliding bumper block, and the sliding bumper block slides smoothly;
[0036] S8, after the installation of the limit guide rail 4 is completed, the sighting device 3 is returned to the zero position, and then the navigation fixture 2 is installed on the limit guide rail 4 to complete the overall installation of the sighting device 3.
[0037] After the installation of the navigation fixture 2 is completed, the cable laying and grounding of the sighting device 3 are also performed;
[0038] The cable connecting the sight 3 should have a certain margin. The safety grounding of the sight 3 should be connected to the permanent structure of the hull or a base welded to the hull. The grounding point should not be easily subject to mechanical damage and oil and water immersion. The grounding method and requirements should comply with relevant requirements.
[0039] By plane processing and excess cutting of the collimator base 1, the installation stability and use accuracy of the collimator 3 are improved. The implementation of the present invention can effectively reduce the user's operating difficulty, reduce adjustment time and cost, and improve use efficiency.
[0040] The positioning of the collimator base 1 specifically includes:
[0041] S21, when the collimator base 1 is installed, the fore and aft engraved lines of the collimator base 1 are aligned with the center line on the deck;
[0042] S22, placing a level ruler on the plane of the collimator base 1, and placing the quadrant on the measuring plane of the level ruler, and adjusting the levelness of the collimator base 1;
[0043] S23, measuring the height distance from the collimator base 1 to the deck surface, and welding the collimator base 1 to fix it. After welding and fixing, the temporary reinforcement inside the collimator base 1 is cut and removed by a hand grinder.
[0044] The margin cutting of the collimator base 1 specifically includes: margin cutting of the collimator base 1 according to the measured height distance from the collimator base 1 to the deck surface, so that the height of the collimator base 1 meets the requirements.
[0045] After the collimator base 1 is welded and fixed, no explosive work is allowed when removing the temporary reinforcement inside the collimator base 1 .
[0046] The plane processing of the collimator base 1 specifically includes: using a processing machine tool to perform plane processing on the collimator base 1 , and after the plane processing of the collimator base 1 is completed, re-carving bow and stern cross lines on the plane of the collimator base 1 .
[0047] The angle between the installation position of the limit guide rail 4 and the center of the collimator base 1 and the bow and stern centerline is 58°.
[0048] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.
Claims
1. A method for installing and controlling a marine laser sight, characterized in that: The method specifically comprises the following steps: S1, positioning and installing the collimator base, cleaning the installation position of the collimator base, and polishing the installation position; S2, installing the collimator base at a corresponding position and positioning the collimator base; S3, after the positioning and installation of the collimator base is completed, the collimator base is cut to a certain extent, and after the cutting of the certain extent is completed, the collimator base is welded and fixed; S4, after the installation and welding of the collimator base is completed, install the limit rail bracket, and install the limit rail bracket on the collimator platform or deck so that the upper plane of the limit rail bracket is parallel to the upper plane of the collimator base; the installation position of the limit rail bracket is directly behind the collimator; S5, machining the plane of the collimator base, and installing the collimator after the machining is completed; S6, install the collimator so that the bow and stern lines of the collimator are aligned with the bow and stern lines on the collimator base; after installation, check whether the horizontal state of the collimator and the parallelism of the center line meet the requirements; S7, install the limit guide rail. Install the limit guide rail on the limit guide rail bracket. The limit guide rail and the limit guide rail bracket are connected by fixing bolts. When installing the fixing bolts, the fixing bolts on both sides of the limit guide rail are symmetrically installed and tightened. The installation of the limit guide rail is completed. S8. After the installation of the limit rail is completed, return the sight to the zero position, and then install the navigation fixture on the limit rail to complete the overall installation of the sight.
2. The installation control method of a marine laser sight according to claim 1, characterized in that: The positioning of the collimator base specifically includes S21, when installing the sighting instrument base, the fore and aft markings of the sighting instrument base should be aligned with the center line of the deck; S22, placing a level ruler on the plane of the collimator base, and placing the quadrant on the measuring plane of the level ruler, and adjusting the horizontality of the collimator base; S23, measure the height distance from the sighting instrument base to the deck surface, and weld the sighting instrument base to fix it. After welding and fixing, use a hand grinder to cut and remove the temporary reinforcement inside the sighting instrument base.
3. The installation control method of a marine laser sight according to claim 2, characterized in that: The margin cutting of the collimator base specifically includes: performing margin cutting on the collimator base according to the measured height distance from the collimator base to the deck surface, so that the height of the collimator base meets the requirements.
4. The installation control method of a marine laser sight according to claim 2, characterized in that: After the collimator base is welded and fixed, no explosive work is allowed when removing the temporary reinforcement inside the collimator base.
5. The installation control method of a marine laser sight according to claim 1, characterized in that: The plane processing of the collimator base is specifically as follows: using a processing machine tool to perform plane processing on the collimator base, and after the plane processing of the collimator base is completed, the bow and stern cross lines are re-engraved on the plane of the collimator base.
6. The installation control method of a marine laser sight according to claim 1, characterized in that: The angle between the installation position of the limit guide rail, the center of the collimator base and the bow and stern centerline is 58°.
Citation Information
Patent Citations
Method for controlling the positioning and mounting accuracy of a base of a special equipment on a main section
CN108974250A
Method for controlling positioning and mounting precision of special equipment base on total section
CN109606542A
Line drawing and installation method of equipment base and line drawing tool
CN110102982A
Installation method of laser inertial platform
CN112519981A
Method for positional setting of constructional components of a ship's propulsion unit
EP0015654A1