Intelligent linkage control system and method for multiple grouting and leaking stoppage construction devices

Through the intelligent linkage control system, the convolutional neural network and decision tree model are used to identify the hole seam types and material types, build quantitative models, and generate linkage control solutions, which solves the problems of high difficulty in manual handling and poor safety in construction environment, and realizes grouting blockage The efficiency, accuracy and economical effect of missed construction.

CN118933397AInactive Publication Date: 2024-11-12北京安禹建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411313170.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the existing grouting and leak plugging construction technology, it is difficult to manually carry grouting materials, long construction time, poor construction environment safety, high labor costs, and lack of intelligent sensors and identification technology to automatically identify the usage status and requirements of the slurry tube.

Method used

Provide an intelligent linkage control system with multiple grouting and leak-blocking construction devices, including information collection module, qualitative analysis module, quantitative analysis module, linkage control module and control feedback module, and hole joints are performed through convolutional neural network and decision tree model. Identify type and material type, build a material quantitative model, generate linkage control plans, realize linkage control of multiple devices, and optimize the construction process.

Benefits of technology

It improves the efficiency and accuracy of grouting and leak plugging construction, reduces construction risks, reduces material waste, improves the economic benefits and quality level of construction, and achieves efficient linkage control of complex cracks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933397A_ABST
    Figure CN118933397A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of mechanical control, in particular to an intelligent linkage control system and method for multiple grouting and leaking stoppage construction devices, and the system comprises an information collection module which is used for collecting grouting and leaking stoppage information; the qualitative analysis module is used for carrying out qualitative analysis on the aperture type and the grouting material type of the target area to obtain the aperture type and the grouting material type of the target area; the quantitative analysis module is used for constructing a material quantitative model, obtaining the required amount of each grouting material type and the output speed per hour of each grouting material type, and judging the solidification effectiveness of the grouting materials; the linkage control module is used for obtaining a linkage control scheme and carrying out linkage control on a plurality of grouting and leaking stoppage construction devices; and the control feedback module is used for judging the effectiveness of the linkage control scheme. Efficient linkage of the multiple grouting and leaking stoppage construction devices when the multiple grouting and leaking stoppage construction devices cope with complex cracks is achieved, and the linkage control efficiency of the multiple grouting and leaking stoppage construction devices is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mechanical control, and in particular to an intelligent linkage control system and method for multiple grouting and leak plugging construction devices. Background Art

[0002] After a long period of construction, buildings will begin to crack. After the buildings crack, the cracks need to be sealed, so a grouting sealing machine is needed. The grouting sealing machine is a project that injects grouting materials into the cracks in the foundation of the building, the fault fracture zone and the joints and cracks of the building itself. Grouting can improve the impermeability and integrity of the stratum or building being grouted.

[0003] Chinese Patent Publication No.: CN112942888B discloses a grouting machine and a construction method for grouting, plugging and waterproofing using the grouting machine, which relates to the field of leaking building construction. In order to solve the problem that the slurry outlet pipe is long and is usually stored together, when it is needed, the slurry outlet pipes are all spread out on the ground, which makes it inconvenient for construction workers to move. Therefore, there is a problem to be improved. It includes a machine body and a slurry outlet pipe located on the machine body, the slurry outlet pipe is connected to the machine body, a storage ring is provided on one side of the machine body, a connecting frame is provided on the inner side wall of the storage ring, and the side of the connecting frame away from the storage ring is connected to the machine body; a limiting ring is sleeved on the storage ring, one end of the limiting ring is connected to the connecting frame, the slurry outlet pipe is wound around the storage ring, and the slurry outlet pipe is located between the storage ring and the limiting ring; a plurality of limiting groups are provided on the limiting ring, and the slurry outlet pipe is embedded between adjacent limiting groups. It can be seen that the grouting machine and the construction method using the grouting machine for grouting, plugging and waterproofing have the following problems: different construction environments and grouting requirements require slurry pipes of different lengths and specifications, and the applicability of the design in different scenarios needs to be evaluated; after long-term use, the slurry pipe, storage ring and limit ring will accumulate dust and mud, affecting the use effect and life; there is a lack of intelligent sensors and recognition technology to automatically identify the use status and needs of the slurry pipe, and there is a lack of automatic adjustment of the tightness of the limit group and the lifting height of the lifting cylinder. Summary of the invention

[0004] To this end, the present invention provides an intelligent linkage control system and method for multiple grouting and plugging construction devices to overcome the problems in the prior art of difficulty in manually transporting grouting materials, long construction time, poor safety of the construction environment, and high labor costs.

[0005] To achieve the above-mentioned purpose, on the one hand, the present invention provides an intelligent linkage control system for multiple grouting and plugging construction devices, comprising:

[0006] Information collection module, used to collect grouting plugging information;

[0007] A qualitative analysis module is used to qualitatively analyze the hole and crack types and grouting material types in the target area according to the grouting plugging information, and obtain the hole and crack types and grouting material types in the target area;

[0008] The quantitative analysis module is used to build a material quantitative model, obtain the required amount of each type of grouting material and the output speed of each type of grouting material, and judge the curing effectiveness of the grouting material;

[0009] A linkage control module is used to input the grouting qualitative model and the material quantitative model into the linkage control module to obtain a linkage control scheme and to perform linkage control on multiple grouting and plugging construction devices;

[0010] The control feedback module is used to judge the effectiveness of the linkage control scheme, and to backtrack the abnormal steps in the linkage control scheme according to the judgment results to obtain the backtracking steps, which are then optimized by experts.

[0011] Furthermore, when the qualitative analysis module qualitatively characterizes the hole and crack types and grouting material types in the target area, the preset qualitative database is divided into a qualitative training set of 75% and a qualitative test set of 25%, and the qualitative training set is input into the convolutional neural network model for training to obtain a trained convolutional neural network model, and the qualitative test set is input into the convolutional neural network model to test the convolutional network neural model to obtain a qualitative accuracy rate Q, and the qualitative accuracy rate Q is compared with the preset qualitative accuracy rate Q0, and the training compliance of the convolutional neural network model is judged according to the comparison result, and the convolutional neural network model is output according to the judgment result, wherein:

[0012] When Q≥Q0, it is determined that the convolutional neural network model training has reached the standard, and the convolutional neural network model is output as a grouting qualitative model, and the output result is set to include the hole and crack type and grouting material type of the target area;

[0013] When Q < Q0, it is determined that the convolutional neural network model training does not meet the standards, and the convolutional neural network model parameters are iteratively optimized and repeatedly trained until the convolutional neural network model training meets the standards. The number of iterative optimization times T is compared with the preset number of iterative optimization times T0. According to the comparison results, it is determined whether additional information from experts is needed, and a terminal alarm is issued according to the judgment results, where:

[0014] When T≤T0, it is determined that no additional information from experts is needed and no terminal alarm is issued;

[0015] When T>T0, it is determined that additional information from experts is needed and a terminal alarm is issued.

[0016] Furthermore, when constructing the material quantitative model, the quantitative analysis module inputs the hole type, grouting material type and hole base material humidity of the target area into the decision tree model, trains the decision tree model according to the historical quantitative database and the simulated quantitative database, divides the historical quantitative database and the simulated quantitative database into 80% of the quantitative training set and 20% of the quantitative test set, inputs the quantitative training set into the decision tree model, and inputs the quantitative test set into the trained decision tree model to obtain the quantitative accuracy E, compares the quantitative accuracy E with the preset quantitative accuracy E0, judges the compliance of the decision tree model training according to the comparison result, and outputs the decision tree model according to the judgment result, wherein:

[0017] When E≥E0, the decision tree model training is judged to be up to standard, and the decision tree model is output as a material quantitative model, and the output results are set to include the required amount of each grouting material type and the output speed of each grouting material type;

[0018] When E<E0, it is determined that the training of the decision tree model does not meet the standard, the training of the decision tree model is repeated, and the parameters are optimized until the training of the decision tree model meets the standard, and the decision tree model is output as a material quantitative model.

[0019] Furthermore, the quantitative analysis module obtains the grouting material curing time Y according to the required amount of each grouting material type and the output speed of each grouting material type, compares the grouting material curing time Y with the preset grouting material curing time Y0, judges the curing effectiveness of the grouting material according to the comparison result, and judges the adjustment process of the material quantitative model output result according to the judgment result, wherein:

[0020] When Y≥Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is normal, and there is no need to adjust the analysis process of the material quantitative model output result;

[0021] When Y<Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is abnormal, and the analysis process of the output result of the material quantitative model needs to be adjusted.

[0022] Furthermore, when the quantitative analysis module analyzes the environmental index according to the building environment information, the environmental index A is compared with the preset environmental index A0, the environmental index is judged according to the comparison result, and the analysis process of the preset grouting material curing time is adjusted according to the judgment result, wherein:

[0023] When A>AO, the quantitative analysis module determines that the environmental index is abnormal and sets the correction coefficient The preset grouting material solidification time Y0 is adjusted according to the correction coefficient, the adjusted preset grouting material solidification time Y0 is Ya, and Ya=Y0×a is set;

[0024] When A≤AO, the quantitative analysis module determines that the environmental indicators are normal, and there is no need to adjust the analysis process of the material quantitative model output results;

[0025] Compare the required service life B with the preset required service life B0, and conduct environmental service analysis based on the comparison results, where:

[0026] When B>B0, the quantitative analysis module determines that the environmental service difficulty is large and sets the correction coefficient The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b;

[0027] When B≤B0, the quantitative analysis module determines that the environmental service difficulty is small, and there is no need to adjust the environmental indicator analysis process.

[0028] Furthermore, when the linkage control module performs linkage control on multiple grouting and plugging construction devices, the grouting qualitative model and the material quantitative model are input into the linkage control module, the output results of the grouting qualitative model and the material quantitative model are normalized, and the construction time is minimized and the grouting efficiency is maximized. The constraint conditions are input, and the initial population of the linkage control scheme is generated, and the fitness value M for minimizing the construction time and the fitness value N for maximizing the grouting efficiency are calculated, and the comprehensive fitness value X=0.4M+0.6N is set, and the comprehensive fitness value X is compared with the preset comprehensive fitness value X0, and the offspring population is judged according to the comparison result, wherein:

[0029] When X≥X0, the comprehensive fitness value is determined to be normal, and the offspring population is entered to perform gene mutation on the offspring population. When the preset number of schemes is reached, the iteration is stopped and the scheme with the highest fitness is selected as the linkage control scheme;

[0030] When X<X0, the comprehensive fitness value is judged to be abnormal and cannot enter the offspring population.

[0031] Furthermore, when judging the effectiveness of the linkage control scheme, the control feedback module obtains the actual usage amount V of each grouting material type during the grouting process according to the control feedback module, compares the difference △V between the actual usage amount V of each grouting material type and the required amount V0 of each grouting material type with the preset difference △V0, judges the effectiveness of the linkage control scheme according to the comparison result, and backtracks the abnormal steps in the linkage control scheme according to the judgment result, wherein:

[0032] When V≤V0, the control feedback module determines that the linkage control scheme is effective and normal, and there is no need to backtrack the abnormal steps in the linkage control scheme;

[0033] When V>V0, the control feedback module determines that the effectiveness of the linkage control scheme is abnormal, and it is necessary to backtrack the key steps in the linkage control scheme and mark them as backtracking steps;

[0034] The control feedback module compares the number of backtracking step marks G within a preset period with the preset number of backtracking step marks G0, judges the backtracking step state according to the comparison result, and adjusts the judgment result of the effectiveness of the linkage control scheme according to the judgment result, wherein:

[0035] When G≤G0, the control feedback module determines that the backtracking step is a normal step, and adjusts the judgment result of the effectiveness of the linkage control scheme to normal;

[0036] When G>G0, the control feedback module determines that the backtracking step is an abnormal step, and there is no need to adjust the judgment result of the effectiveness of the linkage control scheme, and pushes the backtracking step optimization window to the expert, who optimizes the backtracking step.

[0037] On the other hand, the present invention also provides a plurality of grouting and leak-proofing construction devices of an intelligent linkage control system for the plurality of grouting and leak-proofing construction devices, comprising:

[0038] An intelligent linkage control system, used for intelligent linkage control of the first grouting plugging machine, the second grouting plugging machine, the third grouting plugging machine and the fourth grouting plugging machine through remote communication;

[0039] The first grouting plugging machine is used to clean the leakage base surface and wash the seams before grouting, and the grouting material is contained as a cleaning material. The first grouting plugging machine is connected to the intelligent linkage control system;

[0040] The second grouting plugging machine is used to handle the leakage of grout during the grouting process and to close the grouting hole after the grouting is completed. The grouting material contained is an inorganic grouting material. The second grouting plugging machine is connected to the intelligent linkage control system;

[0041] The third grouting plugging machine is used to penetrate into cracks and pores during the grouting process to form a waterproof layer. The grouting material is an organic polymer grouting material, which is connected to the intelligent linkage control system;

[0042] The fourth grouting and plugging machine is used to provide density and strength of the grouting during the grouting process. The grouting material contained is a special functional grouting material. The fourth grouting and plugging machine is connected to the intelligent linkage control system.

[0043] Furthermore, the grouting plugging machine comprises:

[0044] A gearbox, used to control the output speed of the grouting material;

[0045] Pressure pumps, used to deliver grouting materials to the target area at high pressure;

[0046] A controller, used to receive instructions from the intelligent linkage control system and control the grouting plugging machine;

[0047] Power connection line, used to transmit power to the grouting plugging machine;

[0048] A driving electric drill for drilling holes in the target area;

[0049] The handle is used to provide a fulcrum when the user moves the grouting plugging machine;

[0050] The material storage barrel cover is used to provide a closed storage space for grouting materials;

[0051] Material storage bucket, used to store grouting materials;

[0052] Pressure gauge, used to display the grouting pressure value;

[0053] A switch valve is used to control the grouting amount and grouting speed when the high-pressure hose is grouting into the target area;

[0054] a nozzle for injecting grouting material into a target area;

[0055] The pressure sensor is used to feed back the grouting pressure value during the grouting process to the intelligent linkage control system;

[0056] High-pressure hose, used to transport the high-pressure grouting material generated by the grouting plugging machine from the pressure pump to the target area;

[0057] Valve control sensor, used to control the opening and closing of the switch valve;

[0058] Information collection sensor, used to collect grouting and plugging information;

[0059] Among them, a controller is installed on the left side of the inner cavity of the gearbox, a driving electric drill is installed on the left side of the top surface of the gearbox, a power connection line is connected to the top of the left side of the driving electric drill, a handle is vertically fixedly installed at the center of the top surface of the gearbox, a material storage bucket is installed on the right side of the top surface of the gearbox, and a material storage bucket cover is installed on the top of the material storage bucket, a pressure pump is installed on the right side of the inner cavity of the gearbox, a pressure gauge is connected to the right side of the pressure pump, a pressure sensor is installed at the bottom of the pressure gauge, a high-pressure hose is connected to the right side of the pressure gauge, a switch valve is installed on the high-pressure hose, a valve control sensor is installed at the bottom of the switch valve, a nozzle is connected to the top of the high-pressure hose, and an information acquisition sensor is installed at the bottom of the nozzle.

[0060] On the other hand, the present invention also provides a method for an intelligent linkage control system of multiple grouting and plugging construction devices, comprising:

[0061] Step S1, collecting grouting plugging information;

[0062] Step S2, qualitatively characterizing the hole and crack type and the grouting material type of the target area according to the grouting plugging information, and obtaining the hole and crack type and the grouting material type of the target area;

[0063] Step S3, constructing a material quantitative model, obtaining the required amount of each type of grouting material and the output speed of each type of grouting material, and judging the curing effectiveness of the grouting material;

[0064] Step S4, inputting the grouting qualitative model and the material quantitative model into the linkage control module, obtaining a linkage control scheme, and performing linkage control on multiple grouting and plugging construction devices;

[0065] Step S5, judging the effectiveness of the linkage control scheme, and backtracking the abnormal steps in the linkage control scheme according to the judgment result to obtain the backtracking steps, and the experts optimize the backtracking steps.

[0066] Compared with the prior art, the beneficial effect of the present invention lies in that the system is arranged at the control terminal of multiple grouting and plugging construction devices, and the multiple grouting and plugging construction processes are controlled in linkage, so as to realize the efficient linkage of multiple grouting and plugging construction devices in dealing with complex cracks, and improve the linkage control efficiency of multiple grouting and plugging construction devices. The system collects data and information related to grouting and plugging in real time through the information acquisition module, and provides a basis for subsequent analysis and construction. The system provides scientific and reasonable guidance for the grouting and plugging process through the qualitative analysis module, improves the accuracy and pertinence of the construction design, and reduces the construction risk. The system predicts the demand for different types of grouting materials under different geological and pore conditions through the quantitative analysis module, and ensures the accuracy and effectiveness of the grouting construction. The system realizes the unified coordination of the construction process through the linkage control module, avoids confusion and delays caused by the independent operation of each device, reduces material waste, and improves the economic benefits and construction efficiency of the construction. The system provides a strong guarantee for the smooth progress of the construction process through the control feedback module, and continuously improves the construction efficiency and quality level through timely adjustment and optimization mechanism. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] Figure 1 This is a schematic diagram of the structure of the intelligent linkage control system of multiple grouting and plugging construction devices in this embodiment;

[0068] Figure 2 This is a schematic diagram of the structure of multiple grouting and plugging construction devices in this embodiment;

[0069] Figure 3 It is a structural schematic diagram of the grouting plugging machine of this embodiment;

[0070] Figure 4It is a flow chart of the intelligent linkage control method of multiple grouting and plugging construction devices in this embodiment. DETAILED DESCRIPTION

[0071] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0072] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.

[0073] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0074] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0075] See also Figure 1 As shown, it is a structural schematic diagram of the intelligent linkage control system of multiple grouting and plugging construction devices in this embodiment, and the intelligent linkage control system of multiple grouting and plugging construction devices includes:

[0076] Information collection module, used to collect grouting plugging information;

[0077] A qualitative analysis module, used to qualitatively characterize the hole type and grouting material type of the target area according to the grouting plugging information, and obtain the hole type and grouting material type of the target area, wherein the qualitative analysis module is connected to the information acquisition module;

[0078] A quantitative analysis module is used to construct a material quantitative model, obtain the required amount of each grouting material type and the output speed of each grouting material type, and judge the curing effectiveness of the grouting material. The quantitative analysis module is connected to the qualitative analysis module;

[0079] A linkage control module is used to input the grouting qualitative model and the material quantitative model into the linkage control module to obtain a linkage control scheme, and to perform linkage control on multiple grouting and plugging construction devices. The linkage control module is connected to the quantitative analysis module;

[0080] The control feedback module is used to judge the effectiveness of the linkage control scheme, and to trace back the abnormal steps in the linkage control scheme according to the judgment result to obtain the traceback steps, and the experts optimize the traceback steps. The control feedback module is connected with the qualitative analysis module, the quantitative analysis module and the linkage control module.

[0081] Specifically, the system is arranged at the control terminal of multiple grouting and plugging construction devices, and performs linkage control on the construction processes of multiple grouting and plugging construction devices, so as to realize efficient linkage of multiple grouting and plugging construction devices in dealing with complex cracks, and improve the linkage control efficiency of multiple grouting and plugging construction devices. The system collects data and information related to grouting and plugging in real time through the information acquisition module, and provides a basis for subsequent analysis and construction. The system provides scientific and reasonable guidance for the grouting and plugging process through the qualitative analysis module, improves the accuracy and pertinence of the construction design, and reduces the construction risk. The system predicts the demand for different types of grouting materials under different geological and pore conditions through the quantitative analysis module, and ensures the accuracy and effectiveness of the grouting construction. The system realizes unified coordination of the construction process through the linkage control module, avoids confusion and delays caused by the independent operation of each device, reduces material waste, and improves the economic benefits and construction efficiency of the construction. The system provides a strong guarantee for the smooth progress of the construction process through the control feedback module, and continuously improves the construction efficiency and quality level through timely adjustment and optimization mechanisms.

[0082] It can be understood that the present embodiment does not limit the specific number of the multiple grouting and plugging construction devices. Relevant technical personnel in this field can freely set it according to actual needs, and it is only necessary to meet the grouting and plugging construction needs of the target area. For example, four grouting and plugging devices can be set, and the grouting and plugging information includes the 2D surface image of the pores, the pore size, the humidity of the pore base material, the pore 3D structure and the type of the pore base material. The present embodiment does not limit the collection method of the grouting and plugging information. Relevant technical personnel in this field can freely set it according to actual needs, and it is only necessary to meet the collection requirements of the grouting and plugging information. For example, a camera can be set on the surface of the grouting machine to collect the 2D surface image of the pores, and a moisture detector can be used to measure the humidity of the pore base material. The probe can be placed on the surface or inside of the pore base material, and after the instrument is stable, the humidity value is read and recorded. A focused electron-ion dual-beam scanning electron microscope is set on the surface of the grouting machine to obtain the 3D structure of the pores and cracks, and a scanning electron microscope is set on the surface of the grouting machine to obtain the type of pore base material. The 2D surface image of the pores and cracks refers to the plane image data obtained after the surface image of the pores and cracks that need to be plugged is collected. The pore size refers to the data obtained after the size of the pore gap is collected, including the data of the diameter, radius, width and depth. The humidity of the pore base material refers to the amount of water contained in the pore base material, including the water adsorbed on the surface of the pore base material and the water combined inside the pore base material. The 3D structure of the pores and cracks refers to the shape and size characteristics of the pores and cracks in three-dimensional space. The type of pore base material refers to the type of building materials with pores and cracks inside and on the surface of the building. The target area refers to the specific wall part that needs to be grouting reinforced and repaired in the construction project.

[0083] Specifically, the system collects grouting and leak-proofing information through an information collection module, so as to collect data and information related to grouting and leak-proofing in real time, providing a basis for subsequent analysis and construction.

[0084] Specifically, when the qualitative analysis module qualitatively characterizes the hole and crack types and grouting material types in the target area, the preset qualitative database is divided into a qualitative training set of 75% and a qualitative test set of 25%, and the qualitative training set is input into the convolutional neural network model for training to obtain a trained convolutional neural network model, and the qualitative test set is input into the convolutional neural network model to test the convolutional network neural model to obtain a qualitative accuracy rate Q, and the qualitative accuracy rate Q is compared with the preset qualitative accuracy rate Q0, and the training compliance of the convolutional neural network model is judged according to the comparison result, and the convolutional neural network model is output according to the judgment result, wherein:

[0085] When Q≥Q0, it is determined that the convolutional neural network model training has reached the standard, and the convolutional neural network model is output as a grouting qualitative model, and the output result is set to include the hole and crack type and grouting material type of the target area;

[0086] When Q < Q0, it is determined that the convolutional neural network model training does not meet the standards, and the convolutional neural network model parameters are iteratively optimized and repeatedly trained until the convolutional neural network model training meets the standards. The number of iterative optimization times T is compared with the preset number of iterative optimization times T0. According to the comparison results, it is determined whether additional information from experts is needed, and a terminal alarm is issued according to the judgment results, where:

[0087] When T≤T0, it is determined that no additional information from experts is needed and no terminal alarm is issued;

[0088] When T>T0, it is determined that additional information from experts is needed and a terminal alarm is issued.

[0089] Specifically, the target area refers to a specific wall part that needs to be grouting reinforced and repaired in a construction project. The preset qualitative database includes the types of hole types and the composition information of the grouting material. The composition information of the grouting material includes curing time, strength, water resistance and weather resistance. The qualitative training set refers to a data set used to train a convolutional neural network model. The qualitative test set refers to a data set used to evaluate the performance of a convolutional neural network model. The convolutional neural network model refers to a deep feedforward neural network used to process data with a grid structure. The qualitative accuracy Q refers to the proportion of the number of samples W correctly output by the convolutional neural network model to the total number of samples W0 in the qualitative test set, that is, Q=W / W0. The preset qualitative accuracy Q0 refers to a preset value for judging whether the training of the convolutional neural network model meets the standards. This embodiment does not limit the numerical value of the preset qualitative accuracy Q0. Relevant technicians in this field can freely set it according to actual needs, as long as the training of the convolutional neural network model meets the standards is met. The requirement for judging the situation can be met, such as the preset accuracy rate Q0=0.97 can be set, the number of iterative optimization times refers to the number of times the model parameters are repeatedly updated when training the model, the preset number of iterative optimization times refers to the number of times the optimization process is repeatedly executed in advance when training the model, such as setting T0=50 times, the expert supplementary information refers to the filling of the grouting plugging information supplement window by the expert, the qualitative analysis module obtains the material data filled in by the expert in the grouting plugging information supplement window, and inputs the material data into the grouting qualitative model to obtain the supplemented pore type and grouting material type, the grouting plugging information supplement window refers to the platform for further supplementing information during the output process of the grouting qualitative model, the material data includes the target area information and the cleanliness of the pores and seams, the present embodiment does not limit the terminal alarm method, the relevant technical personnel in this field can freely set it according to actual needs, and only need to meet the alarm demand for expert supplementary information, such as setting the display screen alarm to notify the expert of supplementary information.

[0090] Specifically, the system uses a qualitative analysis module to qualitatively characterize the hole and crack types and grouting material types in the target area based on the grouting plugging information, so as to provide scientific and reasonable guidance for the grouting plugging process, improve the accuracy and pertinence of the construction design, reduce construction risks, and improve project quality and efficiency.

[0091] Specifically, when constructing the material quantitative model, the quantitative analysis module inputs the pore type, grouting material type and pore base material humidity of the target area into the decision tree model, trains the decision tree model according to the historical quantitative database and the simulated quantitative database, divides the historical quantitative database and the simulated quantitative database into 80% quantitative training sets and 20% quantitative test sets, inputs the quantitative training sets into the decision tree model, and inputs the quantitative test sets into the trained decision tree model to obtain the quantitative accuracy E, compares the quantitative accuracy E with the preset quantitative accuracy E0, judges the compliance of the decision tree model training according to the comparison results, and outputs the decision tree model according to the judgment results, wherein:

[0092] When E≥E0, the decision tree model training is judged to be up to standard, and the decision tree model is output as a material quantitative model, and the output results are set to include the required amount of each grouting material type and the output speed of each grouting material type;

[0093] When E<E0, it is determined that the training of the decision tree model does not meet the standard, the training of the decision tree model is repeated, and the parameters are optimized until the training of the decision tree model meets the standard, and the decision tree model is output as a material quantitative model.

[0094] Specifically, the historical quantitative database refers to the storage and management of the required amount of each grouting material type and the output speed of each grouting material type in the past time, the simulated quantitative database refers to the storage and management of simulation data, and the simulation data refers to a data set for completing the missing information in the historical quantitative database. The decision tree model refers to a quantitative and regression method based on a tree structure, the quantitative training set refers to a data set used to train a decision tree model, and the quantitative test set refers to a data set used to evaluate the performance of the decision tree model. The quantitative accuracy E refers to the ratio of the number of samples R correctly quantified by the model to the total number of samples R0 in the quantitative test set, and E=R / R0 is set. The preset quantitative accuracy E0 refers to the preset accuracy used to reflect the training of the decision tree model. This embodiment does not limit the value of the preset quantitative accuracy. Relevant technical personnel in this field can freely set it according to actual needs, as long as the need to judge the training of the decision tree model meets the standards is met. For example, the preset quantitative accuracy E0 can be set to 0.99. The required amount of each grouting material type refers to the dosage required for each grouting material obtained according to the target area, and the output speed of each grouting material type refers to the flow rate of the grouting material during the grouting process.

[0095] Specifically, the quantitative analysis module obtains the grouting material curing time Y according to the required amount of each grouting material type and the output speed of each grouting material type, compares the grouting material curing time Y with the preset grouting material curing time Y0, judges the curing effectiveness of the grouting material according to the comparison result, and judges the adjustment process of the material quantitative model output result according to the judgment result, wherein:

[0096] When Y≥Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is normal, and there is no need to adjust the analysis process of the material quantitative model output result;

[0097] When Y<Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is abnormal, and the analysis process of the output results of the material quantitative model needs to be adjusted;

[0098] When the quantitative analysis module analyzes the environmental index according to the building environment information, the environmental index A is compared with the preset environmental index A0, the environmental index is judged according to the comparison result, and the analysis process of the preset grouting material curing time is adjusted according to the judgment result, wherein:

[0099] When A>AO, the quantitative analysis module determines that the environmental index is abnormal and sets the correction coefficient The preset grouting material solidification time Y0 is adjusted according to the correction coefficient, the adjusted preset grouting material solidification time Y0 is Ya, and Ya=Y0×a is set;

[0100] When A≤AO, the quantitative analysis module determines that the environmental indicators are normal, and there is no need to adjust the analysis process of the material quantitative model output results;

[0101] Compare the required service life B with the preset required service life B0, and conduct environmental service analysis based on the comparison results, where:

[0102] When B>B0, the quantitative analysis module determines that the environmental service difficulty is large and sets the correction coefficient The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b;

[0103] When B≤B0, the quantitative analysis module determines that the environmental service difficulty is small, and there is no need to adjust the environmental indicator analysis process.

[0104] Specifically, the grouting material solidification time refers to the time required for the grouting material to reach the specified strength and stable state after completing the slurry hydration reaction. The slurry hydration reaction refers to the process in which the components in the grouting material react chemically with water molecules after the grouting material is mixed with water to generate new compounds and change the structure of the original compounds, thereby changing the slurry performance. The preset grouting material solidification time refers to the time required for the grouting material to reach the specified strength and stable state from injection, which is preset according to the engineering requirements, the characteristics of the grouting material and the environmental conditions before the grouting process begins. For example, Y0=8 hours is set. This embodiment does not limit the adjustment process of the material quantitative model output result. Those skilled in the art can freely set it according to actual conditions, and only need to meet the adjustment requirements of the material quantitative model output result. For example, the parameters of the material quantitative model can be set to introduce characteristic solidification time. The building environment information refers to the natural environment information of the building where the grouting plugging construction is carried out. Artificial environmental information and information about the building itself, the natural environmental information refers to the temperature, humidity, wind speed and rainfall of the building where the grouting and leak-proofing construction is carried out, the artificial environmental information refers to the traffic flow and traffic facilities around the building where the grouting and leak-proofing construction is carried out, the information about the building itself refers to the structural form, bearing capacity and structural components of the building where the grouting and leak-proofing construction is carried out, the environmental index refers to the measurement level set for environmental factors to evaluate environmental quality, such as setting the environmental index A to high, medium and low levels, the preset environmental index refers to the expected goals and quantitative standards set for environmental indicators, such as setting the preset environmental index A0 to medium, the required service life refers to the time period that users expect the grouting and leak-proofing construction to meet its functional and safety requirements under normal use conditions, the preset required service life refers to the period during which the building after the grouting and leak-proofing construction maintains its use function under normal maintenance conditions, and the environmental service analysis refers to the analysis and evaluation of the performance of the building after the grouting and leak-proofing construction.

[0105] Specifically, the system constructs a material quantitative model through a quantitative analysis module, obtains the required amount of each type of grouting material and the output speed of each type of grouting material, and judges the curing effectiveness of the grouting material, so as to predict the demand for different types of grouting materials under different geological and pore conditions, ensure the accuracy and effectiveness of grouting construction, and when it is found that the curing effect is not good, the system will issue an alarm in time so that construction personnel can take corresponding measures to adjust and remedy.

[0106] Specifically, when the linkage control module performs linkage control on multiple grouting and plugging construction devices, the grouting qualitative model and the material quantitative model are input into the linkage control module, the output results of the grouting qualitative model and the material quantitative model are normalized, and the construction time is minimized and the grouting efficiency is maximized. The constraint conditions are input, the initial population of the linkage control scheme is generated, the fitness value M for minimizing the construction time and the fitness value N for maximizing the grouting efficiency are calculated, the comprehensive fitness value X=0.4M+0.6N is set, the comprehensive fitness value X is compared with the preset comprehensive fitness value X0, and the offspring population is judged according to the comparison result, wherein:

[0107] When X≥X0, the comprehensive fitness value is determined to be normal, and the offspring population is entered to perform gene mutation on the offspring population. When the preset number of schemes is reached, the iteration is stopped and the scheme with the highest fitness is selected as the linkage control scheme;

[0108] When X<X0, the comprehensive fitness value is judged to be abnormal and cannot enter the offspring population.

[0109] Specifically, the normalization processing refers to the fusion of the output data of the grouting qualitative model and the material quantitative model to ensure that data from different sources can be compared and analyzed under the same module. The minimization of construction time refers to the shortest total time of grouting and plugging construction through reasonable task allocation, construction scheduling and resource allocation under the premise of ensuring construction quality and safety. The maximization of grouting efficiency refers to the best grouting effect through optimizing grouting parameters, improving construction methods and improving construction equipment performance under the premise of ensuring grouting quality. The linkage control scheme refers to coordinating the working status and task allocation of each grouting and plugging machine to minimize the construction time and maximize the grouting efficiency. The fitness value of minimizing construction time refers to the fitness value used to measure the effect of the linkage control scheme in reducing construction time. The fitness value of maximizing grouting efficiency refers to the fitness value of the linkage control scheme in improving the grouting effect. The comprehensive fitness value refers to the fitness value of a single optimization target. The fitness value is obtained by weighted summation of weight coefficients. The preset comprehensive fitness value refers to the standard for measuring whether different linkage control schemes achieve the expected optimization effect. For example, X0=0.8 is set. The specific numerical value of the weight coefficient is not limited in this embodiment. Technical personnel in this field can freely set it according to actual conditions, and only need to meet the calculation requirements of the comprehensive fitness value. For example, the weight n1 of the fitness value M for minimizing construction time can be set to 0.4, and the weight n2 of the fitness value N for maximizing grouting efficiency can be set to 0.6. The offspring population refers to a new generation of individuals generated by comprehensive fitness selection of individuals in the initial population. The gene mutation refers to randomly selecting one or more genes in the offspring population for change. The specific numerical value of the preset number of schemes is not limited in this embodiment. Technical personnel in this field can freely set it according to actual conditions, and only need to meet the requirements for obtaining the comprehensive fitness value. For example, the preset number of schemes can be set to 80 times. The iteration refers to the process of generating a new population.

[0110] Specifically, the system inputs the grouting qualitative model and the material quantitative model into the linkage control module through the linkage control module, obtains the linkage control scheme, and performs linkage control on multiple grouting and plugging construction devices to facilitate the unified coordination of the construction process, avoid confusion and delays caused by independent operation of each device, reduce material waste, and improve the economic benefits and construction efficiency of the construction.

[0111] Specifically, when judging the effectiveness of the linkage control scheme, the control feedback module obtains the actual usage amount V of each grouting material type during the grouting process according to the control feedback module, compares the difference △V between the actual usage amount V of each grouting material type and the required amount V0 of each grouting material type with the preset difference △V0, judges the effectiveness of the linkage control scheme according to the comparison result, and backtracks the abnormal steps in the linkage control scheme according to the judgment result, wherein:

[0112] When V≤V0, the control feedback module determines that the linkage control scheme is effective and normal, and there is no need to backtrack the abnormal steps in the linkage control scheme;

[0113] When V>V0, the control feedback module determines that the effectiveness of the linkage control scheme is abnormal, and it is necessary to backtrack the key steps in the linkage control scheme and mark them as backtracking steps;

[0114] The control feedback module compares the number of backtracking step marks G within a preset period with the preset number of backtracking step marks G0, judges the backtracking step state according to the comparison result, and adjusts the judgment result of the effectiveness of the linkage control scheme according to the judgment result, wherein:

[0115] When G≤G0, the control feedback module determines that the backtracking step is a normal step, and adjusts the judgment result of the effectiveness of the linkage control scheme to normal;

[0116] When G>G0, the control feedback module determines that the backtracking step is an abnormal step, and there is no need to adjust the judgment result of the effectiveness of the linkage control scheme, and pushes the backtracking step optimization window to the expert, who optimizes the backtracking step.

[0117] Specifically, the actual usage of each type of grouting material refers to the actual usage of each type of grouting material during the construction process, and the preset difference refers to the allowable error value between the actual usage of each type of grouting material and the required amount of each type of grouting material during the construction process. For example, △V0=5kg is set. The backtracking of abnormal steps in the linkage control scheme refers to the reverse tracking and locating of the causes and processes of abnormal steps when the linkage control scheme has steps that do not meet expectations during operation. This embodiment does not limit the specific value of the preset period, and those skilled in the art can freely set it according to actual conditions, as long as the backtracking steps are satisfied. The periodic marking requirement of the marking times can be used, such as the preset period can be set to 3 days. The number of backtracking step marking times refers to the total number of times the steps in the linkage control scheme are marked during the backtracking process. The preset number of backtracking step marking times refers to the preset value of the number of backtracking step marking times within the preset period, such as G0 can be set to 3. The backtracking step optimization window refers to a platform for experts to optimize the backtracking steps. This embodiment does not limit the way experts optimize abnormal steps. Those skilled in the art can freely set it according to actual conditions, and only need to meet the optimization requirements for abnormal steps, such as setting exclusion to correct the material quantitative model.

[0118] Specifically, the system determines the effectiveness of the linkage control scheme through the control feedback module, so as to provide strong guarantees for the smooth progress of the construction process, and continuously improve the construction efficiency and quality level through timely adjustment and optimization mechanisms.

[0119] See also Figure 2 As shown, it is a schematic diagram of the structure of multiple grouting and plugging construction devices in this embodiment, and the multiple grouting and plugging construction devices include:

[0120] An intelligent linkage control system 16 is used to perform intelligent linkage control on the first grouting plugging machine 17, the second grouting plugging machine 18, the third grouting plugging machine 19 and the fourth grouting plugging machine 20 through remote communication;

[0121] The first grouting plugging machine 17 is used to clean the leakage base surface and the seams before grouting, and the grouting material is a cleaning material. The first grouting plugging machine 17 is connected to the intelligent linkage control system 16;

[0122] The second grouting plugging machine 18 is used to handle the leakage of grout during the grouting process and to close the grouting hole after the grouting is completed. The grouting material is an inorganic grouting material. The second grouting plugging machine 18 is connected to the intelligent linkage control system 16;

[0123] The third grouting plugging machine 19 is used to penetrate into cracks and pores during the grouting process to form a waterproof layer. The grouting material is an organic polymer grouting material, which is connected to the intelligent linkage control system 16;

[0124] The fourth grouting and plugging machine 20 is used to provide density and strength of the grouting during the grouting process. The grouting material contained is a special functional grouting material. The fourth grouting and plugging machine 20 is connected to the intelligent linkage control system 16.

[0125] Specifically, the remote communication refers to the technology of transmitting data from the intelligent linkage control system to the grouting plugging machine controller through the 5G network, the cleaning material includes clean water, the grouting hole refers to the hole set for injecting slurry, the inorganic grouting material includes single-liquid cement slurry, cement-water glass slurry and water glass, the organic polymer grouting material includes water-soluble polyurethane, acrylamide, epoxy resin and methyl methacrylate, the waterproof layer refers to a layer of barrier with waterproof function formed in cracks, pores and leakage sites during the grouting process, and the special functional grouting material includes a combination of natural minerals and artificial minerals with functional materials.

[0126] Specifically, the multiple grouting and plugging construction devices are applied to areas where water leaks and cracks occur in construction projects. A platform is set up in the construction area to place the multiple grouting and plugging construction devices. When the conditions for setting up the platform are not met, the multiple grouting and plugging construction devices are placed indoors, and the high-pressure grouting material generated by the grouting and plugging machine is transported from the pressure pump to the target area through a high-pressure hose. The intelligent linkage control system 16 sends a command to the controller of the first grouting and plugging machine 17 through remote communication. The first grouting and plugging machine 17 opens the valve switch and injects cleaning material into the grouting nozzle to clean the dust in the seam. After cleaning, the intelligent linkage control system 16 sends a command to the controller of the second grouting and plugging machine 18 through remote communication. The second grouting and plugging machine 18 opens the valve switch and seals the surface of the crack where water seeps with inorganic grouting material to prevent slurry from leaking during grouting. After the sealing is completed, the intelligent linkage control system 16 sends a command to the controller of the second grouting and plugging machine 18 through remote communication. The control system 16 sends a command to the controller of the third grouting and plugging machine 19 through remote communication, and the third grouting and plugging machine 19 opens the valve switch, and injects organic polymer grouting material into the grouting hole, maintains the pressure until the adjacent hole starts grouting, and grouting of other grouting holes is carried out in turn. If there are special requirements, the intelligent linkage control system 16 sends a command to the controller of the fourth grouting and plugging machine 20 through remote communication, and the fourth grouting and plugging machine 20 opens the valve switch, and injects the special function grouting material into the grouting hole through high pressure; after the grouting is completed, check whether there is water seepage at the leakage site 72 hours later. If there is no water seepage, the intelligent linkage control system 16 sends a command to the controller of the second grouting and plugging machine 18 through remote communication, and the second grouting and plugging machine 18 opens the valve switch, and brushes the inorganic grouting material on the construction surface to achieve the purpose of long-term waterproofing. The linkage control system controls multiple grouting and plugging machines to work together to improve construction efficiency.

[0127] See also Figure 3 As shown, it is a schematic diagram of the structure of the grouting plugging machine of this embodiment, and the grouting plugging machine comprises:

[0128] Gearbox 1, used to control the output speed of grouting material;

[0129] A pressure pump 2, used to deliver the grouting material to the target area in a high pressure form;

[0130] Controller 3, used to receive instructions from the intelligent linkage control system and control the grouting plugging machine;

[0131] A power connection line 4, used to transmit electric energy to the grouting and plugging machine;

[0132] driving an electric drill 5 for drilling holes in a target area;

[0133] A handle 6 is used to provide a fulcrum when the user moves the grouting plugging machine;

[0134] The material storage barrel cover 7 is used to provide a closed storage space for the grouting material;

[0135] A material storage bucket 8, used for storing grouting materials;

[0136] A pressure gauge 9, used to display the grouting pressure value;

[0137] The switch valve 10 is used to control the grouting amount and grouting speed when the high-pressure hose 13 is grouting into the target area;

[0138] A nozzle 11 is used to inject the grouting material into the target area;

[0139] The pressure sensor 12 is used to feed back the grouting pressure value during the grouting process to the intelligent linkage control system;

[0140] A high-pressure hose 13 is used to transport the high-pressure grouting material generated by the grouting plugging machine from the pressure pump to the target area;

[0141] A valve control sensor 14, used to control the opening and closing of the switch valve 10;

[0142] Information collection sensor 15, used to collect grouting plugging information;

[0143] Among them, a controller 3 is installed on the left side of the inner cavity of the gearbox 1, a driving electric drill 5 is installed on the left side of the top surface of the gearbox 1, and a power connection line 4 is connected to the top of the left side of the driving electric drill 5. A handle 6 is vertically fixedly installed at the center of the top surface of the gearbox 1, a material storage bucket 8 is installed on the right side of the top surface of the gearbox 1, and a material storage bucket cover 7 is installed on the top of the material storage bucket 8. A pressure pump 2 is installed on the right side of the inner cavity of the gearbox 1, a pressure gauge 9 is connected to the right side of the pressure pump 2, a pressure sensor 12 is installed at the bottom of the pressure gauge 9, a high-pressure hose 13 is connected to the right side of the pressure gauge 9, a switch valve 10 is installed on the high-pressure hose 13, a valve control sensor 14 is installed at the bottom of the switch valve 10, a nozzle 11 is connected to the top of the high-pressure hose 13, and an information acquisition sensor 15 is installed at the bottom of the nozzle 11.

[0144] Specifically, the grouting and plugging machine adjusts the speed and torque of the power output through the gearbox, extracts the grouting material from the material storage bucket through the pressure pump and conveys it to the target area under pressure, receives the operation instructions of the intelligent linkage control system through the controller and controls the coordinated work of various components, delivers the electric energy required for the grouting process through the power connection line, drives the electric drill to realize the drilling operation, and drives the pressure pump to perform the grouting operation, uses the handle to facilitate the user to carry and move the grouting and plugging machine, seals the material storage bucket through the material storage bucket cover to prevent the leakage and pollution of the grouting material, stores the grouting material through the material storage bucket, and displays the pressure gauge through the pressure gauge The working pressure of the grouting plugging machine is shown to facilitate observation of pressure changes. The grouting plugging machine controls the flow and opening and stopping of the grouting material through the switch valve to achieve precise grouting. The grouting plugging machine sprays the grouting material to the target area through the nozzle. The grouting plugging machine monitors the pressure change through the pressure sensor and transmits the signal to the controller to achieve automatic control. The grouting plugging machine connects the pressure pump and the nozzle through a high-pressure hose to transmit the grouting material to meet different grouting needs. The grouting plugging machine controls the opening and closing of the switch valve through the valve control sensor to achieve precise control of the flow of the grouting material. The grouting plugging machine collects the grouting plugging information through the information acquisition sensor, and transmits the grouting plugging information to the controller for subsequent analysis and processing.

[0145] Specifically, the target area refers to the specific wall part that needs to be reinforced and repaired by grouting in the construction project. The grouting pressure value refers to the pressure required to overcome the flow resistance of the grouting material and diffuse the slurry during grouting. The high-pressure grouting material refers to the material that uses high pressure to inject grouting materials into the gaps in the treated building structure to make up for and repair cracks, holes and defects in the building structure.

[0146] See also Figure 4 As shown, it is a flow chart of the intelligent linkage control method of multiple grouting and plugging construction devices in this embodiment, and the method includes:

[0147] Step S1, collecting grouting plugging information;

[0148] Step S2, qualitatively characterizing the hole and crack type and the grouting material type of the target area according to the grouting plugging information, and obtaining the hole and crack type and the grouting material type of the target area;

[0149] Step S3, constructing a material quantitative model, obtaining the required amount of each type of grouting material and the output speed of each type of grouting material, and judging the curing effectiveness of the grouting material;

[0150] Step S4, inputting the grouting qualitative model and the material quantitative model into the linkage control module, obtaining a linkage control scheme, and performing linkage control on multiple grouting and plugging construction devices;

[0151] Step S5, judging the effectiveness of the linkage control scheme, and backtracking the abnormal steps in the linkage control scheme according to the judgment result to obtain the backtracking steps, and the experts optimize the backtracking steps.

[0152] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.

Claims

1. An intelligent linkage control system for multiple grouting and plugging construction devices, characterized in that: include: Information collection module, used to collect grouting plugging information; A qualitative analysis module is used to qualitatively analyze the hole and crack types and grouting material types in the target area according to the grouting plugging information, and obtain the hole and crack types and grouting material types in the target area; The quantitative analysis module is used to build a material quantitative model, obtain the required amount of each type of grouting material and the output speed of each type of grouting material, and judge the curing effectiveness of the grouting material; A linkage control module is used to input the grouting qualitative model and the material quantitative model into the linkage control module to obtain a linkage control scheme and to perform linkage control on multiple grouting and plugging construction devices; The control feedback module is used to judge the effectiveness of the linkage control scheme, and to backtrack the abnormal steps in the linkage control scheme according to the judgment results to obtain the backtracking steps, which are then optimized by experts.

2. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 1 is characterized in that: When the qualitative analysis module qualitatively characterizes the hole and crack types and grouting material types in the target area, the preset qualitative database is divided into a qualitative training set of 75% and a qualitative test set of 25%, and the qualitative training set is input into the convolutional neural network model for training to obtain a trained convolutional neural network model, and the qualitative test set is input into the convolutional neural network model to test the convolutional network neural model to obtain a qualitative accuracy rate Q, and the qualitative accuracy rate Q is compared with the preset qualitative accuracy rate Q0, and the training compliance of the convolutional neural network model is judged according to the comparison result, and the convolutional neural network model is output according to the judgment result, wherein: When Q≥Q0, it is determined that the convolutional neural network model training has reached the standard, and the convolutional neural network model is output as a grouting qualitative model, and the output result is set to include the hole and crack type and grouting material type of the target area; When Q < Q0, it is determined that the convolutional neural network model training does not meet the standards, and the convolutional neural network model parameters are iteratively optimized and repeatedly trained until the convolutional neural network model training meets the standards. The number of iterative optimization times T is compared with the preset number of iterative optimization times T0. According to the comparison results, it is determined whether additional information from experts is needed, and a terminal alarm is issued according to the judgment results, where: When T≤T0, it is determined that no additional information from experts is needed and no terminal alarm is issued; When T>T0, it is determined that additional information from experts is needed and a terminal alarm is issued.

3. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 2 is characterized in that: When constructing the material quantitative model, the quantitative analysis module inputs the hole type, grouting material type and hole base material humidity of the target area into the decision tree model, trains the decision tree model according to the historical quantitative database and the simulated quantitative database, divides the historical quantitative database and the simulated quantitative database into 80% of quantitative training sets and 20% of quantitative test sets, inputs the quantitative training sets into the decision tree model, and inputs the quantitative test sets into the trained decision tree model to obtain the quantitative accuracy E, compares the quantitative accuracy E with the preset quantitative accuracy E0, judges the compliance of the decision tree model training according to the comparison result, and outputs the decision tree model according to the judgment result, wherein: When E≥E0, the decision tree model training is judged to be up to standard, and the decision tree model is output as a material quantitative model, and the output results are set to include the required amount of each grouting material type and the output speed of each grouting material type; When E<E0, it is determined that the training of the decision tree model does not meet the standard, the training of the decision tree model is repeated, and the parameters are optimized until the training of the decision tree model meets the standard, and the decision tree model is output as a material quantitative model.

4. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 3 is characterized in that: The quantitative analysis module obtains the grouting material curing time Y according to the required amount of each grouting material type and the output speed of each grouting material type, compares the grouting material curing time Y with the preset grouting material curing time Y0, judges the curing effectiveness of the grouting material according to the comparison result, and judges the adjustment process of the material quantitative model output result according to the judgment result, wherein: When Y≥Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is normal, and there is no need to adjust the analysis process of the material quantitative model output result; When Y<Y0, the quantitative analysis module determines that the curing effectiveness of the grouting material is abnormal, and the analysis process of the material quantitative model output result needs to be adjusted.

5. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 4 is characterized in that: When the quantitative analysis module analyzes the environmental index according to the building environment information, the environmental index A is compared with the preset environmental index A0, the environmental index is judged according to the comparison result, and the analysis process of the preset grouting material curing time is adjusted according to the judgment result, wherein: When A>AO, the quantitative analysis module determines that the environmental index is abnormal and sets the correction coefficient The preset grouting material solidification time Y0 is adjusted according to the correction coefficient, the adjusted preset grouting material solidification time Y0 is Ya, and Ya=Y0×a is set; When A≤AO, the quantitative analysis module determines that the environmental indicators are normal, and there is no need to adjust the analysis process of the material quantitative model output results; Compare the required service life B with the preset required service life B0, and conduct environmental service analysis based on the comparison results, where: When B>B0, the quantitative analysis module determines that the environmental service difficulty is large and sets the correction coefficient The preset environmental index A0 is adjusted according to the correction coefficient, and the adjusted environmental index is Aa, Aa = A0 × b; When B≤B0, the quantitative analysis module determines that the environmental service difficulty is small, and there is no need to adjust the environmental indicator analysis process.

6. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 5 is characterized in that: When the linkage control module performs linkage control on multiple grouting and plugging construction devices, the grouting qualitative model and the material quantitative model are input into the linkage control module, the output results of the grouting qualitative model and the material quantitative model are normalized, and the construction time is minimized and the grouting efficiency is maximized. The constraint conditions are input, the initial population of the linkage control scheme is generated, the fitness value M for minimizing the construction time and the fitness value N for maximizing the grouting efficiency are calculated, the comprehensive fitness value X=0.4M+0.6N is set, the comprehensive fitness value X is compared with the preset comprehensive fitness value X0, and the offspring population is judged according to the comparison result, wherein: When X≥X0, the comprehensive fitness value is determined to be normal, and the offspring population is entered to perform gene mutation on the offspring population. When the preset number of schemes is reached, the iteration is stopped and the scheme with the highest fitness is selected as the linkage control scheme; When X<X0, the comprehensive fitness value is judged to be abnormal and cannot enter the offspring population.

7. The intelligent linkage control system of multiple grouting and plugging construction devices according to claim 6 is characterized in that: When judging the effectiveness of the linkage control scheme, the control feedback module obtains the actual usage amount V of each grouting material type during the grouting process according to the control feedback module, compares the difference △V between the actual usage amount V of each grouting material type and the required amount V0 of each grouting material type with the preset difference △V0, judges the effectiveness of the linkage control scheme according to the comparison result, and backtracks the abnormal steps in the linkage control scheme according to the judgment result, wherein: When V≤V0, the control feedback module determines that the linkage control scheme is effective and normal, and there is no need to backtrack the abnormal steps in the linkage control scheme; When V>V0, the control feedback module determines that the effectiveness of the linkage control scheme is abnormal, and it is necessary to backtrack the key steps in the linkage control scheme and mark them as backtracking steps; The control feedback module compares the number of backtracking step marks G within a preset period with the preset number of backtracking step marks G0, judges the backtracking step state according to the comparison result, and adjusts the judgment result of the effectiveness of the linkage control scheme according to the judgment result, wherein: When G≤G0, the control feedback module determines that the backtracking step is a normal step, and adjusts the judgment result of the effectiveness of the linkage control scheme to normal; When G>G0, the control feedback module determines that the backtracking step is an abnormal step, and there is no need to adjust the judgment result of the effectiveness of the linkage control scheme, and pushes the backtracking step optimization window to the expert, who optimizes the backtracking step.

8. A multiple grouting and plugging construction device applied to the intelligent linkage control system of multiple grouting and plugging construction devices as claimed in claims 1 to 7, characterized in that: The multiple grouting and plugging construction devices include: An intelligent linkage control system, used for intelligent linkage control of the first grouting plugging machine, the second grouting plugging machine, the third grouting plugging machine and the fourth grouting plugging machine through remote communication; The first grouting plugging machine is used to clean the leakage base surface and wash the seams before grouting, and the grouting material is contained as a cleaning material. The first grouting plugging machine is connected to the intelligent linkage control system; The second grouting plugging machine is used to handle the leakage of grout during the grouting process and to close the grouting hole after the grouting is completed. The grouting material contained is an inorganic grouting material. The second grouting plugging machine is connected to the intelligent linkage control system; The third grouting plugging machine is used to penetrate into cracks and pores during the grouting process to form a waterproof layer. The grouting material is an organic polymer grouting material, which is connected to the intelligent linkage control system; The fourth grouting and plugging machine is used to provide density and strength of the grouting during the grouting process. The grouting material contained is a special functional grouting material. The fourth grouting and plugging machine is connected to the intelligent linkage control system.

9. The multiple grouting and leak-proofing construction devices of the intelligent linkage control system of multiple grouting and leak-proofing construction devices according to claim 8, characterized in that: The grouting plugging machine comprises: A gearbox, used to control the output speed of the grouting material; Pressure pumps, used to deliver grouting materials to the target area at high pressure; A controller, used to receive instructions from the intelligent linkage control system and control the grouting plugging machine; Power connection line, used to transmit power to the grouting plugging machine; A driving electric drill for drilling holes in the target area; The handle is used to provide a fulcrum when the user moves the grouting plugging machine; The material storage barrel cover is used to provide a closed storage space for grouting materials; Material storage bucket, used to store grouting materials; Pressure gauge, used to display the grouting pressure value; A switch valve is used to control the grouting amount and grouting speed when the high-pressure hose is grouting into the target area; a nozzle for injecting grouting material into a target area; The pressure sensor is used to feed back the grouting pressure value during the grouting process to the intelligent linkage control system; High-pressure hose, used to transport the high-pressure grouting material generated by the grouting plugging machine from the pressure pump to the target area; Valve control sensor, used to control the opening and closing of the switch valve; Information collection sensor, used to collect grouting and plugging information; Among them, a controller is installed on the left side of the inner cavity of the gearbox, a driving electric drill is installed on the left side of the top surface of the gearbox, a power connection line is connected to the top of the left side of the driving electric drill, a handle is vertically fixedly installed at the center of the top surface of the gearbox, a material storage bucket is installed on the right side of the top surface of the gearbox, and a material storage bucket cover is installed on the top of the material storage bucket, a pressure pump is installed on the right side of the inner cavity of the gearbox, a pressure gauge is connected to the right side of the pressure pump, a pressure sensor is installed at the bottom of the pressure gauge, a high-pressure hose is connected to the right side of the pressure gauge, a switch valve is installed on the high-pressure hose, a valve control sensor is installed at the bottom of the switch valve, a nozzle is connected to the top of the high-pressure hose, and an information acquisition sensor is installed at the bottom of the nozzle.

10. A method for an intelligent linkage control system applied to multiple grouting and plugging construction devices as described in claims 1-9, characterized in that: The method comprises: Step S1, collecting grouting plugging information; Step S2, qualitatively characterizing the hole and crack type and the grouting material type of the target area according to the grouting plugging information, and obtaining the hole and crack type and the grouting material type of the target area; Step S3, constructing a material quantitative model, obtaining the required amount of each type of grouting material and the output speed of each type of grouting material, and judging the curing effectiveness of the grouting material; Step S4, inputting the grouting qualitative model and the material quantitative model into the linkage control module, obtaining a linkage control scheme, and performing linkage control on multiple grouting and plugging construction devices; Step S5, judging the effectiveness of the linkage control scheme, and backtracking the abnormal steps in the linkage control scheme according to the judgment result to obtain the backtracking steps, and the experts optimize the backtracking steps.